Académique Documents
Professionnel Documents
Culture Documents
TITLE HERE
(Including Cover)
PROJECT NAME
DOCUMENT NO.
For Information
TITLE
For Review
OWNER
01.09.2015
Rev.
No.
DATE
Purpose
For Approval
For Construction
As-Built
First Issue
DESCRIPTION
PREPARED
CHECKED
REVIEWED
APPROVED
Owner
POSCO ENGINEERING
& CONSTRUCTION CO., LTD.
Main Subcontractor
Method Statement
for Electrical Works Cable tray and ladder Installation
works
Doc. No
KP-00+++-CY712B7105
Rev. No.
Page
A
2 of 8
1.1
This method statement is written for the purpose of establishing method and procedures for the Installation of Cable
Tray and G.I Trunking System for the building MEP services.
1.2
1.3
Division: INSTALLATION
Specific safety measures have to follow as applicable, and all the safety measures are covered separately in the project
safety plan.
Method Statement
for Electrical Works Cable tray and ladder Installation
works
Doc. No
KP-00+++-CY712B7105
Rev. No.
Page
1.5
A
3 of 8
5. Operation
1. Materials: Materials used will be as per the material submittal approved by the engineer and routing
as well and sizes will be as per the approved drawings in co-ordination with other services.
2. Storage / Protection: Cable Trays, Trunking and Accessories shall be unloaded with care to avoid
any damages. If they are shipped in packs or pallets, each pack of pallet shall be lifted individually
with suitable lifting equipment. Every precaution shall be taken to preserve their cleanliness before
installation.
1.6
Method Statement
for Electrical Works Cable tray and ladder Installation
works
Doc. No
KP-00+++-CY712B7105
Rev. No.
Page
A
4 of 8
6. All routes are chosen to allow ease of access to all cables when installed. All horizontal cables are to
be set around all vertical rising services as necessary. Ensure sufficient clearance from soffit for
every installation.
7. Earth continuity conductors shall be provided across gaps in all Cable Tray / Trunking runs and
bolted connections.
8. Support shall be by means of steel brackets installed at intervals necessary to provide a rigid fixing
and to ensure that deflection does not exceed 5mm mid span of support when fully loaded.
Treatment of cut edges as per cut edges to be included. Supports for Tray / Trunking (spacing) shall
be as per standard practice and manufacturer's recommendations.
9. Additional support shall be provided where the Cable Tray / Trunking changes direction or cables
drop out of the cable tray. Dome headed bolts, nuts and washers of finish suitable to the tray shall be
used between trays.
10. Suspension sets comprise threaded M10 zinc or cadmium plated hanger rods together with nuts and
locking washers, supports channel hold down clips all of which shall have a galvanized finish. Any
cut ends supports, rods, etc, must be corrosion protected by use of galvanized or equal. No
extended rods to be left.
11. The cable tray shall be installed with a 40mm minimum space between the structure and the tray.
12. All cable shall be securely fixed to the tray, work and the complete installation must be carried out in
a neat and workmanlike manner without crossovers.
13. Cables on face-up horizontally fixed tray must be secured by use of the tie wraps where not in view.
If cables are bunched or single cables greater than 25sq mm are installed, cleats or metal straps
shall be used.
Method Statement
for Electrical Works Cable tray and ladder Installation
works
Doc. No
KP-00+++-CY712B7105
Rev. No.
Page
1.7
A
5 of 8
7. Responsibilities
1. Project Manager:
1. To ensure that all the preparation and application works are carried out according to the
Contract Specification.
2. To ensure that the progressing of works is carried out according to the planned program and
as per the approved method statement.
3. To ensure that all equipment and material required executing the work are available
according to the planned Construction Programme.
4. To co-ordinate with the Main Contractor, MEP co-coordinator and Safety Officer for a safe
and proper execution of the works.
2. Site Engineer:
1. To ensure that the works are carried out according to the Contract Specifications approved
method statement.
2. To provide all necessary information and distribute responsibilities to his construction team.
3. To monitor the progress of work in relation with the work program and to report to the Project
Manager.
Method Statement
for Electrical Works Cable tray and ladder Installation
works
Doc. No
KP-00+++-CY712B7105
Rev. No.
Page
A
6 of 8
4. To co-ordinate with the safety officer and to ensure that the works are carried out in safe
practicing methods.
3. Foreman:
1. The foreman will carryout his duties by maintaining continuous coordination with the site
engineer on daily basis, and ensure proper distribution of the workforce in the required and
planned locations.
2. To ensure that his assistant foreman/ charge hands are aware of the job requirements and
they have enough information to carry out their duties properly.
3. To ensure in consultation with the site engineer that the manpower involved in the works are
moving as agreed and planned for the work.
4. To ensure that the daily work is progressing as planned and advise the Site Engineer of any
requirement for the additional resources.
5. To control disposal of waste materials according to the instructions received from the site
engineer.
6. To ensure full coordination with the safety officer to maintain safe working and proper house
keeping of the site, following the approved safety measures and further ensure that all his
working team are aware of the same to prevent accident and losses.
7. To inform the site engineer and of the areas ready for inspection.
8. Distribution and the control of materials shall be monitored by foreman and storekeeper.
4. Safety Engineer:
1. Ensure the implementation of all the safety measures in accordance with the HSE plan and
everybody aware of it for it's proper implementation.
2. Ensure all the implemented safety measures are adequate to maintain the safe working on
the site.
3. Inspect all the site activities and train the persons to prevent accidents and its proper
reporting to the project manager and the client.
4. Ensure that the site is maintained clean and tidy.
Doc. No
Method Statement
for Electrical Works Cable tray and ladder Installation
works
KP-00+++-CY712B7105
Rev. No.
Page
1.8
7 of 8
8. Manpower Required
9. Inspection And Test Plan Format For Installation Of Cable Tray Or Trunking
ITP
Inspection
Clause
Description
No
Type of
Inspection
Reference
Document
Design
and Review
of Design
Drawings
Documents
Drawings
Material
Approval
Check
Installation of
Visual
Cable Tray /
Trunking
Visual
Request
for
Measurement Approved
inspection of
Instrument,
Drawings
works
Earth Test
Approved
Review
of
Drawing,
Documents
Specification
Approved
Method
Statement
Testing Requirement/
Acceptance Criteria
Drawing
No obstructions Level,
Approved Drawings
Routes
Method
Method Statement
for Electrical Works Cable tray and ladder Installation
works
Doc. No
KP-00+++-CY712B7105
Rev. No.
Page
1.10
A
8 of 8
The equipments that will be engaged for Installation of Cable Trays and Trunking works will be as follows:
1. Wire cutters
2. Hacksaw
3. Measuring tape
4. Drill machine
5. Wooden hammer
6. Flat file
7. Screw drivers
8. Open and box spanners
9. Base Cutter
1.12
Strictly followed as per the manufacturer's Health and Safety recommendations for handling and use of the materials.
Ensure all involved personnel shall be aware of the same.
1.13
This method Statement should be read in conjunction with the below referenced documentations:
ITP for Cable Tray and Trunking
1.14
14. Distribution
Copies of this method statement have also been issued to the following for information/ action/ comments:
Project Manager
Site Engineer
Foremen