Lightning Protection System Installation Works

Inspection Checklist

Project Name

KHABAT THERMAL POWER


PLANT UNITS 1&2

Owner Name

Ministry of Electricity (MOE) of Kurdistan


Regional Government

Contractor

POSCO ENGINEERING &


CONSTRUCTION CO., LTD.

Main Subcontractor

GAMA POWER SYSTEMS


ENGINEERING & CONTRACTING INC.

Item Name / Item No Lightning Protection System


/ Description
Installation

Area / Unit
ITP No

KP-00+++-CQ712-B7702

Report No

ITP Item
Date

Drawing No

Rev.0

Approximate Date/Time of Pouring Concrete:


No.

ITEM DESCRIPTION

BKEM

Visual check of materials.

Check the installed down-conductor wire is visually proper.

Check that all dimensioning of down-conductor and clamps as per the approved
attached drawing are followed while implementation.

Check that all joints are properly fix as per the typical installation details attached with
the inspection checklist.

Check that connections are properly for the down-conductor connects the air terminals
to the grounding system.

Remarks / Comments

BKEM

GAMA

3rd Party / AI

POSCO

Name:

Name:

Name:

Name:

Date:

Date:

Date:

Date:

Sign:

Sign:

Sign:

Sign: