Vous êtes sur la page 1sur 71

New Rule for Steel

Erection
BY
Standardized Steel -Consultation
New Rule for Steel Erection. Retrieved September 9, 2008, from
standardizedsteel.com/db5/00437/standardizedsteel.com/

The Standard
On the web

GO
1

Do you want a short


lesson on how to navigate
through this program?
If you want to see wh
ich buttons to click
on to get through the
presentation, click
here

If youre confident
that you can
navigate through a
web-based
presentation on
your own, click on
the next button.
2

Navigational Symbols Used in


this Presentation
Return to the program, usually from additional information
Definitions, more information, FAQs, etc
Read the actual Standard on line
Back to the Outline

Next slide

Why the new rules??


OSHA studies of 673 fatalities among
ironworkers highlighted common
hazards
Deaths were largely preventable by
engineering & regulatory changes

= Outline
-703 -

Site layout, site specific erection plan & construct


ion sequence
-704 - Hoisting & rigging
-706 - Structural steel assembly details
-707 - Column anchorage
-708 - Beams & columns
-709 - Open web steel joists
-711 - Systems engineered metal buildings
-714 - Falling object protection
-716 - Fall protection
-717 - Training
5

Site layout, site-specific erection


plan & construction sequence
Controlling contractor
must provide written
notification that
concrete has attained
75% of design strength, or
Sufficient strength to
support the loads
6

Site layout, site-specific erection


plan & construction sequence
Controlling
contractor must
ensure that
adequate access
roads are provided
and maintained
Photo courtesy of National Ironworkers & Employers Apprenticeship
Training and Journeyman Upgrading Fund. All rights reserved.

Site layout, site-specific erection


plan & construction sequence
Controlling
contractor must
ensure that a suitable
space is provided for
storage of materials and
safe operation of
hoisting operations
8

Site layout, site-specific erection


plan & construction sequence
All hoisting
operations must be
preplanned to ensure
all working under
loads requirements
are met
9

Site layout, site-specific erection


plan & construction sequence
A site-specific erection
Example
plan may be developed to
provide alternate means
to protect employees
Appendix A contains
guidelines
App
A

Site layout, site-specific erection


plan & construction sequence
Steel erection must be
done under the
supervision of a
competent person who
is present at the
worksite.

TOC
1Next Section

Hoisting & Rigging


The new section
( 296-155-704) and
296-155-525 & -526
Both apply to
hoisting and rigging

Photo courtesy of National Ironworkers & Employers Apprenticeship


Training and Journeyman Upgrading Fund. All rights reserved.

Hoisting & Rigging


Crane pre-shift visual inspection
must be visually inspected by a
competent person
rule gives inspection minimums
deficiencies must be evaluated
immediately
equipment posing a hazard must be
placed out of service
operator has authority to stop and
refuse any loads until safety is
assured

Photo courtesy of National Ironworkers &


Employers Apprenticeship Training and
Journeyman Upgrading Fund. All rights reserved.

Hoisting & Rigging


A qualified rigger must inspect the
rigging prior to each shift

Photo courtesy of National Ironworkers & Employers


Apprenticeship Training and Journeyman Upgrading
Fund. All rights reserved.

Hoisting & Rigging


Working under loads
Routes for
suspended loads
must be
preplanned to
avoid
endangering
workers
1

Hoisting & Rigging


When working under loads
materials must be rigged to prevent
unintentional displacement
hooks must have self-closing safety
latches or equivalent
all loads must be rigged by a qualified
rigger
2

Hoisting & Rigging


Multiple lift rigging procedure
only when:
a multiple lift rigging
assembly is used
specifically within
manufacturers specifications
& limitations
maximum of 5 members
hoisted per lift
only beams & similar
structural members are lifted
only trained employees
involved

Photo courtesy of National Ironworkers & Employers Apprenticeship


Training and Journeyman Upgrading Fund. All rights reserved.

Hoisting & Rigging


Multiple lift rigging procedure
Bundles of decking
are NOT
appropriate for
multiple lift.
Even though metal
decking meets the
definition of structural
members

Hoisting & Rigging


Multiple lift rigging procedure
Components of the multiple lift rigging
assembly must be specifically designed
and assembled with a maximum
capacity for total assembly and for
each individual attachment point.
Based on manufacturers specifications
with a 5 to 1 safety factor on all
components
2

Hoisting & Rigging


Multiple lift rigging procedure
Total load must not exceed
rated capacity as specified in the
hoisting equipment load charts and
rigging capacity specified in the
rigging-rating charts

Hoisting & Rigging


Multiple lift rigging procedure

Controlled load
lowering must be
used whenever the
load is over the
connectors

TOC

Next
2 Section

Structural Steel Assembly


Structural stability maintained at all times
during the erection process

Multistory structures
have permanent floors
installed as the
erection of structural
members progresses
Within 8 floors of the
concrete, or
Photo courtesy of National Ironworkers & Employers
Apprenticeship Training and Journeyman Upgrading Fund.
All rights reserved.

Structural Steel Assembly


Structural stability maintained at all times
during the erection process

Multistory structures have permanent


floors installed as the erection of structural
members progresses
Within 8 floors of the concrete, or

no more than 4 floors (or 48) of


unfinished bolting or welding above
secured floor
2

Structural Steel Assembly


Walking/working surfaces

Elimination of
tripping hazards:
no shear connectors or
other similar devices
until after
walking/working
surface has been
installed.
Photo courtesy of National Ironworkers & Employers
Apprenticeship Training and Journeyman Upgrading Fund.
All rights reserved.

Structural Steel Assembly


Walking/working surfaces

After July 18, 2006: workers


prohibited from walking on surface of
structural steel coated with paint or
other coating not slip resistant

Structural Steel Assembly


Plumbing up

When deemed necessary


by a competent person:
Plumbing up
equipment must be
installed in conjunction
with the steel erection
process to ensure
stability of the
structure.
Photo courtesy of National Ironworkers & Employers
Apprenticeship Training and Journeyman Upgrading
Fund. All rights reserved.

Structural Steel Assembly


Plumbing up

When necessary, plumbing up


equipment must be in place and
properly installed before the
structure is loaded with
construction material
3

Structural Steel Assembly


Plumbing up

Plumbing up equipment must


be removed only with the
approval of a competent
person
3

Structural Steel Assembly


Metal decking

Hoisting, landing &


placing of metal
decking bundles
provisions to prevent
displacement of
decking during
handling/storage
Photo courtesy of National Ironworkers & Employers
Apprenticeship Training and Journeyman Upgrading Fund.
All rights reserved.

Structural Steel Assembly


Metal decking

Roof & floor holes and openings Must


be installed as described:
Para 706(4)(b)

Photo courtesy of National Ironworkers & Employers Apprenticeship


Training and Journeyman Upgrading Fund. All rights reserved.

Structural Steel Assembly


Metal decking

Covering roof and floor openings

Photo courtesy of National Ironworkers & Employers Apprenticeship Training and Journeyman Upgrading Fund. All rights reserved.

Structural Steel Assembly


Metal decking

Decking gaps around


columns
where there are gaps
between columns, the
falling objects hazards
must be eliminated
Photo courtesy of National Ironworkers & Employers
Apprenticeship Training and Journeyman Upgrading
Fund. All rights reserved.

Structural Steel Assembly


Metal decking

During installation,
metal decking must
be laid tightly &
immediately secured
to prevent movement

Structural Steel Assembly


Metal decking

During installation,
metal decking
panels must be
placed to ensure
full support by
structural members
3

Structural Steel Assembly


Metal decking

Derrick floors
must be fully
decked or planked
& connections
completed

Structural Steel Assembly


Metal decking

Temporary loads
placed on derrick
floors must be
distributed over the
underlying support
to prevent local
overloading

TOC

Next
4 Section

Column anchorage
Insufficient column
anchorage is a
primary cause of
column failure and
a large contributor
to fatalities among
ironworkers!

Photo courtesy of National Ironworkers & Employers Apprenticeship


Training and Journeyman Upgrading Fund. All rights reserved.

Column anchorage
Erection Stability

All columns must


be anchored by a
minimum of four
anchor bolts
Photo courtesy of National Ironworkers & Employers Apprenticeship
Training and Journeyman Upgrading Fund. All rights reserved.

Column anchorage
Erection Stability

All columns must be


anchored by a minimum of
four anchor bolts

all anchor rod


assemblies must meet
strength criteria
listed in the rule
4

Column anchorage
Erection Stability

Columns must be
set on level, finished
floors
Pre-grouted leveling
plates
leveling nuts, or
shim packs

Photo courtesy of National Ironworkers & Employers Apprenticeship


Training and Journeyman Upgrading Fund. All rights reserved.

Column anchorage
Erection Stability

All columns must be


evaluated by a competent
person to determine if
guying or bracing is
needed.
If guying or bracing is
needed, it must be installed

Photo courtesy of National Ironworkers & Employers


Apprenticeship Training and Journeyman Upgrading Fund.
All rights reserved.

Column anchorage
Anchor rods (bolts)

Anchor rods/bolts must not be


repaired, replaced or field modified
without approval of the project
structural engineer of record

Column anchorage
Anchor rods (bolts)

Controlling contractor must provide


written notification to the steel erector
if there has been any repair,
replacement or modification of the
anchor rods/bolts
TOC

Next
4 Section

Beams & Columns


Final placing of solid web structural
members

The load must not be released until


members are secured with at least 2
bolts per connection

Beams & Columns


Final placing of solid web structural
members
The load must not be released until members are
secured with at least 2 bolts per connection

Bolts must be
Same size and strength shown in the
erection drawings
Drawn up wrench tight, or equivalent
specified
5

Beams & Columns


Final placing of solid web structural
members

A competent person must determine if


more than 2 bolts are needed

Beams & Columns


Diagonal bracing

Solid web
structural
members used as
diagonal bracing
must be secured
by at least one
bolt per
connection
Wrench tight or
equivalent

Beams & Columns

Double connections at columns and/or


beam webs over a column

When making connections


sharing common connection
holes, at least one bolt with
its wrench-tight nut must
remain connected to the
first member
Diagram

Photo courtesy of National Ironworkers & Employers


Apprenticeship Training and Journeyman Upgrading Fund.
All rights reserved.

Exception

Beams & Columns


Column splices

Each column splice


must be designed to
resist a minimum
eccentric gravity
load of 300#
Photo courtesy of National Ironworkers & Employers
Apprenticeship Training and Journeyman Upgrading
Fund. All rights reserved.

Beams & Columns


Perimeter columns

Must extend a minimum


of 48 above the
finished floor to permit
installation of perimeter
safety cables prior to
erection of the next tier
Photo courtesy of National Ironworkers & Employers
Apprenticeship Training and Journeyman Upgrading
Fund. All rights reserved.

Beams & Columns


Perimeter columns

Must have holes


or other devices
for attaching
perimeter cables
TOC

Next
6 Section

Open Web Steel Joists


Open web
steel joists must
be secured
before releasing
the load.
Photo courtesy of National Ironworkers & Employers Apprenticeship
Training and Journeyman Upgrading Fund. All rights reserved.

Open Web Steel Joists


Landing and placing loads
No bundle of decking may
be placed on steel joists
until all bridging has been
installed and anchored and
all joist bearing ends
attached,
UNLESS
Photo courtesy of National Ironworkers & Employers Apprenticeship
Training and Journeyman Upgrading Fund. All rights reserved.

Systems-Engineered Metal
Buildings
Package Building

Before releasing hoisting equipment:


Columns
minimum 4 bolts at base

Rigid frames
50% of the bolts
or as specified by manufacturer

TOC

Next
6 Section

Falling Object Protection


All materials,
equipment, & tools
which are not in use
while aloft must be
secured against
accidental
displacement
6

Falling Object Protection


The controlling contractor must bar
other construction processes from
below steel erection unless overhead
protection for the employees below is
provided
TOC
Next
6 Section

Fall Protection
Must be in accordance
with 296-155,
Part C-1 &
Part K

TOC

Next
6 Section

Training
Fall hazard training
Special training in multiple lift
rigging procedure

TOC

End

Photos courtesy of Pacific Northwest Ironworkers and


Employers Apprenticeship and Training Committee -86
Very special thanks to Douglas Smith and Kevin
McGee
And thanks also to Jerry Rowland, Corona Steel and
Ironworkers Local #86
6

Navigational Symbols Used in


this Presentation
Return to the program, usually from additional information
Definitions, more information, FAQs, etc
Read the actual Standard on line
Back to the Outline

Next slide

links back to
this page

-703 - Site layout, site specific erection plan &

construction sequence
-704 - Hoisting & rigging
-706 - Structural steel assembly details
-707 - Column anchorage
Each line
Hyperlinks to the
-708 - Beams & columns
module listed
-709 - Open web steel joists
-711 - Systems engineered metal buildings
-714 - Falling object protection
-716 - Fall protection
-717 - Training
7

Behind the scenes how things are


arranged:

You get back


and forth from
the Outline

Section
-703

Outline

Section
-704

Section
-705
7

Links to other information


Steel erection must be
done under the
supervision of a
competent person who
is present at the
worksite.

Clicking here or
else on the i
will link you to
the definition

NEXT: Going from the presentation to web pages


to read or print out the actual Standard
Going to the Web to
read the actual
Standard is easy:
to go forward, use the
hyperlink provided
to go back, use the
back arrow

Whats a Hyperlink?
Whats a Back Arrow?

This is how the program


looks behind the scenes
7

Navigation Part II
The diagram of how things can be linked
Section
-703

Course
List

Section 703
on the Web

Section
-704

Section 704
on the Web

Section
-705

Section 705
on the Web

Other Web
Page if you want

And another
Web Page

Clicking here would


hyperlink to the web
page

Clicking here
would return to
the Presentation

Navigation Part II
Section
-704
Section 704
on the Web

Outline
Another way of moving
back to the presentation
Just close the web
page
7

Clicking here would


hyperlink to the web page

Clicking here
would close
the Web
page; return
to the
Presentation
7

Ready to start??
Not really.
Id like to go through
this navigation thing
one more time.

YES! Run it!

Hyperlink
An item (word, icon, button, etc) that will take
you to another location (page in the document,
web page, other program, etc)

Hyperlinks are identified by the fact


that when your cursor passes over
them, it changes from an arrow to a
hand.
Sometimes theyre even underlined

This is a Back
Arrow

Vous aimerez peut-être aussi