CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

PROYECTO
LOCALIDAD
DISTRITO
PROVINCIA

: CONST. DEL SIST. DE RIEGO TECNIFICADO HUGICHCAPUQUIO-HUACAMALCO JISSE JANJAILLO DIST. DE JANJAILLO, PROV. DE JAUJA-JUNIN
: JANJAILLO
PERIODO DE EJEC.
: JANJAILLO
FECHA
: JUNIN
: JAUJA
DEPARTAMENTO

DESCRIPCION

MESES
TERCER MES

PRES.

PRIMER MES

SEGUNDO MES

CUARTO MES

2,185.59
1.00

REFACCION DE CAPTACION

1,092.80

1,092.80

17,724.57
2.00

LINEA DE CONDUCCION (620 ML)

4,431.14

4,431.14

4,431.14

4,431.14

1,489.97

1,489.97

1,489.97

1,489.97

1,489.97

1,489.97

1,358.28

1,358.28

1,358.28

1,358.28

1,100.76

1,100.76

720.78

720.78

8,939.82
3.00

LINEA DE DISTRIBUCION (755 ML)


8,149.69

4.00

CAJA HIDRANTE (20 UND)

1,358.28

1,358.28

720.78

720.78

332.41

332.41

2,201.52
5.00

CAJA DE VALVULA DE CONTROL I (02 UND)


2,883.10

6.00

CAJA DE VALVULA DE CONTROL II (05 UND)


664.81

7.00

CAJA DE VALVULA DE PURGA (02 UND)


1,186.51

8.00

IMPACTO AMBIENTAL

COSTO DIRECTO
AVANCE MENS. (%)
AVANCE ACUM. (%)

43,935.61

593.26

593.26

1,092.80

5,523.94

5,921.11

5,921.11

7,279.39

2,848.25

4,669.79

4,669.79

2,411.46

3,004.72

593.26

0.00

PROGRAMADO

2.49%

12.57%

13.48%

13.48%

16.57%

6.48%

10.63%

10.63%

5.49%

6.84%

1.35%

0.00%

EJECUTADO

2.49%

12.57%

13.48%

13.48%

16.57%

6.48%

10.63%

10.63%

5.49%

6.84%

1.35%

0.00%

PROGRAMADO

2.49%

12.57%

13.48%

13.48%

16.57%

6.48%

10.63%

10.63%

5.49%

6.84%

1.35%

0.00%

EJECUTADO

2.49%

15.06%

28.54%

42.01%

58.58%

65.06%

75.69%

86.32%

91.81%

98.65%

100.00%

100.00%

: 3.0 MESES
: DIC. - 2010