Notes:

Phase 1 includes:
1.
Modification to existing subsurface drainage, Re: Civil.
2.
Modification to existing electrical services, Re: Electrical
Phasing Drawing.
3.
Modification to existing underground plumbing, Re:
Plumbing.
4.
Construction of new 3-story Classroom Wing N.
5.
Modification to existing walkway where new Classroom
Wing N ties into existing walkway.
6.
Construct upgrades to West Cafeteria wall to provide 2
hour-rated separation.
7.
Modification of existing walkways were buildings is
demolished and walkways remain.
8.
Removal of a section of existing parking lot at south side
of new Classroom Wing N.
9.
The work included in this phase is to be Substantially
Complete in 425 days.
Phase 2 includes:
1.
Abatement of Classroom Wing E (Not In Contract, work to
be performed under a separate contract by Owner). Allow
35 days for the abatement of Classroom Wing E.
2.
Full demolition of existing 2-story Classroom Wing E.
Demolition of Classroom Wing E must be completed
during Summer of 2016.
3.
Modifications required at first and second floors of
Buildings A and B where Classroom Wing E was
removed.
4.
Removal of trees in courtyard.
5.
Removal and salvage of "Garden of Angels" monument to
be reinstalled in Phase 5B of the project.
6.
Removal of sidewalks in courtyard.
7.
Modification of subsurface drainage, Re: Civil.

Additive
Alternate
No.1

FD

UP

Additive
Alternate
No. 2

"M" Wing
FDFDFDFDFDFDFD
FDFDFDFDFDFDFD

Modular
Building

"B" Wing
(Administration
/ Media)
Phase 3B - Addition to and
Renovation of Building "B"

"C"
Wing

60'

"J" Wing
(Home
Economics)

Phase 4 - Renovation of Building


"C" (Additive Alternate No. 3)

"F" Wing
Covered
Outdoor
Dining

Phase 5A - Demolish
Classroom Wing "F"

Seal

775 Days

New Canopy

60'

Additive Alternate 3 not taken

Phase 3B includes (Work in Phases 3A and 3B is concurrent):


1.
Abatement of Building B (Not In Contract, to be performed
by separate contract by Owner).
2.
As Additive Alternates No. 1 and No. 2, selective
demolition of areas of Building B (Administrative/Media).
3.
As Additive Alternates No. 1 and No. 2, renovation of
Building B (Administrative/Media).
4.
As Additive Alternate No. 1, addition to Building B
(Administrative/Media).
5.
As Additive Alternate No. 1, addition of new entrance to
school at Building B (Administrative/Media) including new
sidewalks and planters.
6.
The work included in this phase is to be Substantially
Complete in 775 days.
Phase 4 includes:
1.
Abatement of Building C (Not In Contract, to be performed
by separate contract by Owner).
2.
As Additive Alternate No. 3, selective demolition of
Building C and subsequent renovation of Building C. Also
included is an new canopy to the South of Building C.
3.
The work included in this phase is to be Substantially
Complete in 775 days.
Phase 5A includes:
1.
Abatement of Classroom Wing F (Not In Contract, work to
be performed under a separate contract by Owner). Allow
35 days for the abatement of Classroom Wing F.
2.
Complete demolition of Classroom F building and
foundation. Demolition of Classroom Wing F must be
completed during Summer of 2017.
3.
Modifications required at Building B where Classroom
Wing F was removed.
4.
Final site grading.
5.
Implementation of new landscaping.
Phase 5B includes:
1.
Construction of new pad for "Garden of Angels"
monument.
2.
Construction of new sidewalks in courtyard.
3.
The work included in this phase is to be Substantially
Complete in 850 days.
General Notes for All Phases:
1.
During all phases of work school will be fully operational
during regular school calendar year. The school
maintains use of some facilities during the summer break
for camps, etc. Safety of students, staff, and visitors is
very important. Fencing and barricades as required to
keep non-work personnel out of the construction site will
be Contractor's responsibility.
2.
Coordinate with Owner to move out of existing spaces
that are to be demolished or renovated prior to Contractor
needing to obtain that space to work if necessary.
3.
Reference instructions to bidders Article 11 Completion
Time for milestone time frames for each phase of work
listed above.

BPSB Project No. CM1211C

775 Days

Phase 3A - Construct
Classroom Wing "M"

DW

REF.

"H" Wing
(Girl's Gym)

Consultant

2801 Airline Drive, Bossier City, LA 71111

"E" Wing

850 Days

smbbarchitects.com

Phase 3A includes (Work in Phases 3A and 3B is concurrent):


1.
Additional electrical service work, Re: Electrical.
2.
Construction of new 3-story Classroom Wing M.
3.
New connections to subsurface drainage for new
courtyard.
4.
Upgrade of openings in East Building H (Girl's Gym) wall
to provide 2-hour rated separation.
5.
Modification of existing covered walkway for construction
of new Classroom Wing M.
6.
New covered walkway connection at East end of
Classroom Wing M.
7.
The work included in this phase is to be Substantially
Complete in 850 days.

"A" Wing
(Auditorium)

Phase 2 Demolish Classroom Wing "E"

O 318.221.1623
F 318.221.1626

Airline High School Classroom Wings

FD

"G" Wing
(Boy's Gym)

333 Texas Street


Suite 1200
Shreveport, LA 71101

Project No.

1303.03

Cafeteria
Issue

"N" Wing

January 15, 2015 Bid


Documents

"K" Wing (Shop)

Kitchen

"D" Wing

DW

REF.

UP

425 Days

Date

Phase 1 - Construct
Classroom Wing "N"

February 4,
2015

Sheet Title

Phasing Plan

Sheet No.

Phasing Plan
32'

North

A0.10