Académique Documents
Professionnel Documents
Culture Documents
PART : III
SECTION : A
26.06.09
15
DRP
PSK
RMP/PVS
09.12.08
15
DRP
PSK
RMP/
PVS
Rev No.
Issue Date
Pages
Description
Prepared
By
Checked
By
Approved
By
Jacobs
HPCL, Mumbai
LSTK
44LK 5100
Part - III
Section- A
Sheet 2 of 15
TABLE OF CONTENTS
1.0
PURPOSE
2.0
SCOPE
3.0
DEFINITIONS
4.0
SELECTION
5.0
RELATED DOCUMENTATION
6.0
7.0
8.0
SOFTWARE USED
9.0
DOCUMENT REQUIRED
10.0
ATTACHMENTS
10.1
10.2
Jacobs
HPCL, Mumbai
LSTK
44LK 5100
1.0
Part - III
Section- A
Sheet 3 of 15
PURPOSE
This design basis deals with the subject of Identification of Stress Critical pipelines and
preparation of Critical line list. This procedure also defines the minimum requirements for
performing stress analysis, design and location of spring, support and extent of system
analysis with the extent of documentation required for flexibility analysis
Purpose of piping stress analysis is to ensure:
2.0
SCOPE
This specification covers the supply of engineering services to perform a complete piping and
pipe support analysis for new and modified piping systems for HPCL Mumbai Refinery for its
DHT Project.
3.0
DEFINITIONS
3.1
3.2
3.3
DESIGN PRESSURE
Design Pressure refers to the Design Pressure of the line under review as indicated on the
Line List. Design Pressure is as defined in clause 301.2 of ASME B 31.3.
3.4
In general, unless there is a difference of more than 50 C between working temperature and
the design temperature, the design temperature should be taken as Flexibility temperature.If
0
the difference is higher than 50 C the stress analysis temperature is needed to be decided in
consultation with process Licensor/Group.
The temperature under Fire Condition are not considered for stress analysis except for flare
lines.
Ambient Temperature shall be considered as 21 0 C. the assumed piping installation
temperature. The displacement stress range from this installation temperature to the
minimum recorded ambient temperature of 120C being less than the same from installation
Jacobs
HPCL, Mumbai
LSTK
44LK 5100
Part - III
Section- A
Sheet 4 of 15
temperature to the maximum operating temperature of hot piping in most cases the later
governs as per clause 319.2.3 of ASME B 31.3.
4.0
METHOD OF ANALYSIS
A line is selected and listed as a Critical Line provided it falls under any one of the
categories defined in Attachment 10.1 and is intended to include the special
requirements of Piping Stress Engineer. It is hence defined as any line for which a
flexibility review is required or where pipe supporting is deemed to be critical and needs
review by a Stress Engineer.Hence all lines following outside the categorization are
deemed non critical which can be reviewed using nomographs manual calculation and/on
visual analysis.
All lines in this list essentially need a formal computer analysis with a trunion
calculation,Flange leakage calculation and nozzle load calculation as required,Very large
diameter (thin walled)pipes and ducts need special design consideration which should be
highlighted.
4.1
4.2
4.3
SPECIAL PIPING
Special piping forming part of reformer tubes, heater internal piping, etc. are treated as
proprietary piping and nozzle loading at the Interface connections are to be co-ordinated
with vendor.
4.4
Jacobs
HPCL, Mumbai
LSTK
44LK 5100
Part - III
Section- A
Sheet 5 of 15
5.0
RELATED DOCUMENTATION
5.1
5.2
6.0
6.1
b. Thermal Loads
Thermal loads due to operating / design / steam out / decoking or any other abnormal
condition.
Pipe supporting shall be preferably follow the basic span as given in Piping Design
Basis (Annexure D), except for flare line in offsite on trestles in which case the basic
span shall be restricted to max.18m. For sizes not covered in Piping Design Basis,
basic span shall be established based on project requirement. For piping on rack or
sleeper, as a minimum, providing resting support on every grid of pipe rack / sleepers
mandatory. Guides shall be provided on straight run of pipes at intervals as specified
in piping design basis (Annexure C), unless specifically becomes non-viable due to
flexibility problems.
Jacobs
HPCL, Mumbai
LSTK
44LK 5100
Part - III
Section- A
Sheet 6 of 15
Additional supports, guides, anchors, special supports like spring supports and sway
braces shall be provided based on detailed analysis of piping system to restrict the
forces on nozzles of critical equipments like pumps, compressors, turbines,
exchangers, fin-fan coolers etc.
A permanent support, either resting or spring support shall be provided for lines which
do not need any supporting otherwise but require supporting during maintenance.
Pads will be provided at pipe supports, for all sizes and services of lines irrespective of
whether shoes are required or not.
Adequate care shall be taken for small bore(1 inch NB and below) branch from
piping. For all lines in 600# and above classes - lines having two phase flow and lines
having pulsating flow such as discharge of reciprocating compressors and
reciprocating pumps, all small bore branches (vents, drain, orifice traps, pressure /
temperature tapings, sample connections), PSV / TSV inlets etc., shall be provided
with 2 number stiffeners at 90 Deg to each other from main pipe to impart adequate
stiffness to the branch connection. The stiffeners shall be made from 6 mm thick flats
of material equivalent to the pipe material. Irrespective rating, the stiffeners shall be
provided for all orifice taps, all small bore tapings from PSV inlet / outlet lines and all
small bore tapings from control valve manifolds.
For pulsating flow lines, detailed thermal and vibration analysis by analog study shall
be done to decide on location of anchor supports and guides etc.
In case of two phase with slug flow lines, piping design shall be checked by dynamic
analysis to prevent vibrations.
Piping support design shall be such that deflection in piping systems due to sustained
loads shall not exceed 15mm, between two adjacent supports.
Long trunion type of supports (more than 0.5m) is to be avoided. In case long trunion
support is unavoidable, trunion height shall be restricted to 0.5m and balance height to
be made up by providing extended structure.
In case of heaters having the provision for steam-air decoking, the main lines and
decoking lines should not be in hanging position when not in operation.
Piping passing through technological structure or passing near the concrete column
etc. should have adequate space or gap considering insulation, to avoid restriction of
line movement during thermal expansion.
High density PUF block shall be considered for cold piping supports. Wooden blocks
may be used for load taking supports on vertical lines or as anchor supports.
All pipe supports shall be so designed that there is no undue tension on equipment
flanges.
6.2
6.2.1
Piping stress analysis shall follow ASME B31.3 and shall complete to prevent over
stressing of pipe during operating conditions with wind and seismic loadings. During
sustained, occasional (wind and seismic) & thermal expansion loading on piping, the
material allowable stresses shall be as per ASME B 31.3 for ASTM materials. For DIN
material specifications the allowable stress values shall be calculated as per ASME B 31.3
clause 302.3.2(d), wherein yield strength and ultimate strength values at temperature shall
be taken from DIN material standards. For DIN material specifications, the other material
properties viz. elastic modulus, density, coefficient of thermal expansion shall be taken
Jacobs
HPCL, Mumbai
LSTK
44LK 5100
Part - III
Section- A
Sheet 7 of 15
Analysis shall include, but not be limited to the following; thermal, dead weight, internal
pressure, wind and seismic, and a combination of these based on ASME B 31.3.
6.2.3
(Y is vertical)
X-Direction
Z-Direction
Y-Direction (Vert.)
0.21g
0.21g
0.15g
0.3g
0.09g
0.15g
0.09g
0.3g
015g
Wind analysis shall follow ASCE-7 using a basic wind velocity of 160 km/h. At a minimum,
wind loading shall be applied to all components in two (2) perpendicular horizontal
directions at elevation 10 m and above. Shape factor for piping shall be considered as 0.7.
ASCE-7 Exposure category C [kz = 0.85 for z <4.6 m & kz= (0.10044* z)^0.2105 for z >=
4.6 m up to 274m] & gust factor of value 1.5 shall be considered for taking care of effect of
height and topography. Wind and seismic loading will not occur simultaneously.
6.2.5
Analysis of all nozzles loading on vessels within the piping boundaries is covered in this
specification. Nozzle analysis shall follow the guidelines of ASME Section VIII, Division 1,
and WRC 297 & 107 (latest editions). Nozzle stresses shall fall within the allowable as per
ASME.
6.2.6
All forces on connections to equipment shall not exceed maximum allowable as specified
by equipment vendor.
6.2.7
Pipe supports loads shall be based on the maximum loads determined by the piping
analysis. JE shall evaluate all pipe support loading including friction forces due to thermal
expansion using good engineering judgement. Adjustments shall be made to the piping
system and model such that the pipe supports loads are within a reasonable uniformity
throughout the piping system.
6.2.8
Various Load cases built in Caesar II to check stress in piping system are listed below.
Jacobs
HPCL, Mumbai
LSTK
44LK 5100
Part - III
Section- A
Sheet 8 of 15
Load Case
Type
Remarks
1)
2)
3)
4)
WW+HP
W+T1+P1
W+T2+P1
W+T1+P1+U1
HYD
OPE
OPE
OPE
5)
W+T1+P1+U2
OPE
6)
W+T1+P1+U3
OPE
7)
W+T1+P1-U1
OPE
8)
W+T1+P1-U2
OPE
9)
W+T1+P1-U3
OPE
10)
11)
12)
13)
14)
15)
16)
17)
18)
19)
20)
21)
22)
23)
24)
25)
26)
27)
28)
29)
30)
31)
W+T1+P1+WIN1
W+T1+P1+WIN3
W+P1
W+P2
L2-L12
L3-L12
L4-L2
L5-L2
L6-L2
L7-L2
L8-L2
L9-L2
L10-L2
L11-L2
L12+L16
L12+L17
L12+L18
L12+L19
L12+L20
L12+L21
L12+L22
L12+L23
OPE
OPE
SUS
SUS
EXP
EXP
OCC
OCC
OCC
OCC
OCC
OCC
OCC
OCC
OCC
OCC
OCC
OCC
OCC
OCC
OCC
OCC
W Dead Weight
WW Water Weight
P2-Design Pressure
T2-Design Temperature
U - Uniform Load
Jacobs
HPCL, Mumbai
LSTK
44LK 5100
Part - III
Section- A
Sheet 9 of 15
L2 Load Case
SUS, EXP, OCC, HYD, OPE Various load types, viz., sustained, expansion, occasional, hydro test,
operating etc.
6.2.9
7.0
The general guideline for stress analysis of Jacketed lines are as follows :
a.
b.
Provide Spider (or spacer) at every 10 (3 m) and locate approx. 4 (100 mm) from elbow.
Connect core to jacket by connect node and anchor.
c.
piping
8.0
Nozzle Loadings
Wind Analysis
ASCE 7 98
SOFTWARE USED
COADEs piping stress analysis software Caesar II, Version 5.0 or above shall be used
for Pipe stress analysis. Pipe thickness & material allowable stress values will be
manually fed as input.
9.0
DOCUMENT REQUIREMENT
9.1
A written report shall be submitted on the piping and equipment analysis. The report shall
include all pertinent information that shall include but not be limited to the following :
Location and type of pipe supports with loads and movements.
Location of expansion joints and movements.
Vertical and horizontal loads including moments at all support points.
Vertical and horizontal loads including moments on all equipment and vessel
connections.
Caesar II analysis report, which shall include as a minimum, restraint forces,
movements and stresses for all load cases. For flange connection, loaded with high
bending moments and/or tensile forces in piping or at equipment connections, Caesar
II flange leakage report will be provided. For piping analyzed, if subjected to hydro test,
hydro test load case will be made in Caesar II to check for loading under hydro test &
the requirement of any additional temporary supports for hydro test.
Detailed nodal model used for the stress analysis
All assumptions and limitations applied to the analysis.
9.2
All dimensions and analysis shall be performed using metric and SI units.
9.3
Jacobs
HPCL, Mumbai
LSTK
44LK 5100
Part - III
Section- A
Sheet 10 of 15
Support loads (anchors, guides or rest) only they are above limit (The limit is
defined in the beginning of the project in consultation with civil)
Design and maximum operating conditions
Coordinate axis system considered for inputs
Dimensional details for piping designer to locate supports in piping model/layout.
3. Check list as per JE work instructions.
4. Following outputs
Load Cases
Restraint summary
Spring hanger report, if any
5. Stress critical line list extract for the lines analysed
6. Piping material specifications
7. Equipment drawings with allowable loads, if available
8. PID
Jacobs
HPCL, Mumbai
LSTK
44LK 5100
Part - III
Section- A
Sheet 11 of 15
ATTACHMENT 10.1
CRITERIA FOR IDENTIFING CRITICAL LINES.
SR
NO
Temperature
T, Degree C
Pipe
Diameter
D,Inch
NB
Piping
Material
All
D>2
All
All
D>3
All
3
4
5
T < (-) 45
T > 200
T > 100
All
All
All
T > 65
D>3
D>3
D > 16
(see note
3)
D>3
7
8A
T > 65
T < (-) 29
D>2
D>3
NonMetallic
All
All
8B
9
T > 65
DeltaT > 27
(Note 2)
T > 65
D>3
D>2
All
All
D>4
All
T < (-) 29
D>4
All
T < (-) 40
All
D>4
All
Metallic
T > 80
D>4
Metallic
T < (-) 29
D>8
Metallic
T > 70
D>8
Metallic
All
All
D> 2
D> 2
All
All
10
A
10
B
11
12
A
12
B
12
C
12
D
13
14
All Services.
Note :
1. Load sensitive equipment include fired heaters,boilers / steam generators, Reformers,lined
vessels with lining of brittle material,non-ferrous equipment,Graphite heat exchangers,plate &
frame heat exchanger,Spiral Heat Exchangers,Equipment on load Cells etc.
2. Also include lines connected to nozzles having differential settlement / Thermal displacement
more than 12 mm.
3. Delta T refers to the differential temperature between the process piping and jacket.
4. Very large diameter pipes (dia / thickness >100)and ducts need to be designed using finite
element analysis methods.
5. Category M Fluids involve toxic and harmful fluids which are identified by process.These
services are lethal and hence critical.They need mandatory flange leakage calculations. To get
the loads at flanges,a computerised stress analysis is required.
6. For critical lines in seismic prone, plants refer Attachment 10.2 for categorisation.
Jacobs
HPCL, Mumbai
LSTK
44LK 5100
Part - III
Section- A
Sheet 12 of 15
ATTACHMENT 10.2
Categorization for Seismic analysis
Definition: Plant Piping located in earthquake prone areas of the country will experience accelerations
imparted through foundations, structures and various equipment. Criticai piping {toxic, flammable, high
pressure, high temperature, emergency) which must remain leak;tight or operable (deliver, control or
shutoff flow) during or following the event, have nozzle loads within vendor's set limits, have minimum
sway to avoid impact or interference with adjacent equipment / pipes / structures need seismic analysis to
determine the effects.
Based on Indian code IS 1893-2002, areas falling under Zones IV and V are categorized as "Severe"
while Zones II and III are prone to earthquakes of "Moderate" or "Low" intensity. The IS 1893-2002
guidelines for BUILDINGS to be seismically designed are as beiow;
For regular buildings, if the building height is greater than 40 m in Zones IV and V or greater than
90 m in Zone II and III
;
For irregular buildings, if height is more than 12 m in Zones IV and V and more than 40 m in
Zones II and III,
Method: Process Plants normally fall within the irregular building category and hence the piping and
equipment are to be analysed accordingly. To get realistic results, it is essential that seismic analysis for
piping be carried out using the Dynamic analysis method viz. Time History method or Modal Response
Spectrum method. Piping connected to tail columns/vessels, chimneys and any slender structure should
preferably be analysed using dynamic analysis. Long-run piping on tall slender structures (such as flare
piping on trestles) should be analysed using composite analysis. For toxic/lethal piping systems, the
seismic anchor movements also need to be imposed during the dynamic analysis. However for
simplification's sake wherever dynamic analysis is not mandatory by the client or the response
spectra cannot be derived from data available, seismic design can be done using the Equivalent
Static (static coefficient) method.
The seismic accelerations, response spectra and anchor movement values are to be obtained from the
Civil Group.
For seismic analysis, earthquake loadings shall not be considered to act simultaneously with wind. Also it
is to be noted that cross-country pipelines, buried piping & piping for nuclear installations will need
rigorous analysis and the selection criteria below does not apply. Refer LWI 220 for explanatory
techniques for seismic design of piping systems (under development)
Selection: With due considerations to fluid criticality and intended operation, in order to assess maximum
impact it is recommended that only critical piping with higher sizes (i.e. higher mass and/or at higher
elevations which in turn reflects as higher force) be seismicaiiy computer analysed. Since not explicit in
Indian codes, following guidelines are a conservative selection.
All critical piping systems aboveground with a weight (self+fluid+insuiation) greater than 410
kg/m (corresponds to a 24" STD schedule water filled pipe).
All critical piping systems above ground with any portion routed at a height (height as per the
above IS 1893 building categorization) with a weight greater than 210 kg/m (corresponds to a 16"
STD schedule water filled pipe). Give due consideration to piping connected to tall equipment &
piping routed on tall slender structures.
All emergency service critical piping systems above ground with any portion routed at or
greater than 25m with a weight greater than 110 kg/m (corresponds to a 10" STD schedule
water filled pipe).
Smaller critical lines (3" to 10") routed above 10 m elevation need to be seismically analysed
provided the wind load does not govern.
Jacobs
HPCL, Mumbai
LSTK
44LK 5100
Part - III
Section- A
Sheet 13 of 15
Piping < 410 kg/m and below 10m elevation and non-critical piping can be considered as nonseismic critical. Such systems shall be made rigid overall preferably by having every 2Fld / 3rd
support (appx 12m) as a seismic lateral restraint (guide) and every straight run (> 3 times
standard supporting span) with a longitudinal (axial) restraint. Equivalent Static Analysis needs to
be done only if peak spectral acceleration / static seismic coefficient is > 0.3 g, max
Branch lines can be decoupled from the run lines if Irun > 25 leaned where I = moment of inertia.
These guidelines are indicated graphically on Sht 2 of 2 of this attachment.
Jacobs
HPCL, Mumbai
LSTK
44LK 5100
Part - III
Section- A
Sheet 14 of 15
ATTACHMENT 10.2
Notes :
1. For site specific Zoning as per IS 1893, refer Project Initiation Checklist in Project
Procedure
2. If Dynamic Analysis is not mandatory by the client or the response spectra cannot be
derived from data available, Equivalent Static Analysis can be done. However, if
Equivalent Static Analysis yields uneconomical results, Dynamic Analysis methods
may be adopted to achieve realistic results.
3. Piping in this category are non-seismic critical. Systems shall be made rigid overall
preferably by having every 2nd / 3rd support (appx 12m) as a seismic lateral restraint
(guide) and every straight run {> 3 times standard supporting span) with a longitudinal
(axial) restraint. Equivalent Static Analysis needs to be done only if peak spectral
acceleration / static seismic coefficient is > 0.3 g, max component weight is > 200kg and
pipe centerline is > 1m.
4. A Tall equipment (tower.etc) located at grade is analogous to a Building (RCC or steel
frame structure). Piping connected to be categorized accordingly.
5. Piping on tall slender structures (such as flare piping on trestles) should undergo
composite analysis.
Jacobs
HPCL, Mumbai
LSTK
44LK 5100
Part - III
Section- A
Sheet 15 of 15
6. Emergency services are isolation/relief systems which reduce the potential of a major
hazardous accident such as emergency process control, emergency pressure relief,
emergency venting / blowdown, emergency shutdown, emergency purging / cooling, etc
classified as safety critical by Process.
: 300 #
Client
BASIC MATERIAL
: CARBON STEEL
Project - Location
: DHT MUMBAI
SPECIAL REQUIREMENT
:-
PMC
CORR. ALLOWANCE
REVISION
:1
: 44LK-5100-00/L.02/0101/A4
PIPE CLASS
B5Y
Page 1 of 5
TEMP
PRESS
0
52.11
38
52.11
50
51.09
65
50.48
70
49.66
SERVICE
SEA COOLING WATER SUPPLY & RETURN
NOTES
1
USE BUTTERFLY VALVES INSTEAD OF GATE VALVES FROM 10" ONWARDS IN WATER SERVICE AND UP TO 700C.
DESIGN PRESSURE FOR BUTTERFLY VALVES IS LIMITED UPTO 10 BAR.
BUTTERFLY VALVES FOR THE SPEC ARE PN10 RATED WITH A MAXIMUM PRESSURE OF 10.2 KG/CM2G
ALL BLIND FLANGES, FIG 8 FLANGES AND SPACER & BLINDS SHALL BE FRE-LINED FOR THE WETTED PORTIONS.
BLIND FLANGES AND SPACER & BLINDS SPECIFIED TO MANUFACTURER'S STANDARD SHALL BE DESIGNED FOR 700C AND 6.6 KG/CM2G TO SUIT 150#,
FF, 125 AARH, AWWA C207 CL.D FLANGES.
FOR U/G STEEL PIPES, PIPE WALL THK.SHALL BE CALCULATED AS PER SERVICE REQUIREMENT BY USING APPLICABLE CODES AS
B 31.3 / 31.4, AWWA-M-11 AND API RP-1102 AND HIGHER OF THREE THK.
ALL PIPING COMPONENTS EXCEPT VALVES AND STRAINERS FOR SIZES 3" & ABOVE SHALL BE CEMENT LINED AT SITE.
VALVES AND Y-TYPE STRAINERS FOR SIZES 3" & ABOVE SHALL BE INTERNALLY FRE-LINED EXCEPT THE TRIMS.
FORGINGS ARE ACCEPTABLE INSTEAD OF PLATE MATERIAL FOR BLIND FLANGES AND SPACER & BLINDS.
10
FOR SIZES >24", SPACER & BLIND SHALL BE DESIGNED BY THE MANUFACTURER AS PER ASME B 31.3
11
FOR SIZES ABOVE 30", TEMPERATURE AND PRESSURE RATINGS SHALL BE 700C & 6.6 KG/M2G RESPECTIVELY.
12
13
CORROSION ALLOWANCE SHALL BE 3.00MM FOR SIZES UP TO 2" AND NIL FOR SIZES 3" AND ABOVE.
SPECIAL NOTES
ITEM
SIZE
DESCRIPTION
MAINTAINENCE
JOINTS
ALL
FLANGED
PIPE JOINTS
0.5" TO 1.5"
SW COUPLING
2" TO 2.5"
BUTT WELDED
FLANGED
ON LINES 1.5"
AS PER P & ID
ON LINES 2"
ON LINES 1.5"
AS PER P & ID
ON LINES 2"
TEMP. CONN.
1.5"
FLANGED
PRESS. CONN.
0.75"
DRAINS
VENTS
A. CODE
: 300 #
Client
BASIC MATERIAL
: CARBON STEEL
SPECIAL REQUIREMENT : -
PIPE CLASS
PMC
B5Y
CORR. ALLOWANCE
REVISION
:1
: 44LK-5100-00/L.02/0101/A4
Page 2 of 5
BRANCH CONNECTIONS
44
42
40
36
34
T
32
30
T R
28
T R R
26
T R R R
24
R R R R
20
T R
R R R R
18
T R R
R R R R
16
T R R R
R R R R
14
T R R R R
R R R R
12
T R R R R R
R R R R
10
T R R R R R R
R R R R
T R R R R R R R
R R R R
R R R R R R R R
R R R R
5
T
4
3
R R R R R R R R
R R R R
2
T
P P P P P P P P
P P P P
P P P P P P P P
P P P P
P P P P P P P P
P P P P
T T
P P P P P P P P
P P P P
T T T
P P P P P P P P
P P P P
RUN PIPE NB
CODE
DESCRIPTION
SADDLE FUSED JT
TEES
H. COUPLING
WELDOLETS
PIPE TO PIPE
INSTRUMENT TEE
REINFORCED
REFER NOTES
SOCKOLETS
SWEEPOLET
THREADOLET
44
42
40
36
34
32
30
28
26
24
22
20
18
16
14
12
10
BRANCH PIPE NB
22
: 300 #
Client
BASIC MATERIAL
: CARBON STEEL
SPECIAL REQUIREMENT : -
CORR. ALLOWANCE
REVISION
:1
Input
Id.
Item
Type
Page
of 5
PIPE3CLASS
: 44LK-5100-00/L.02/0101/A4
Lower
Size
(Inch)
Upper
Size
(Inch)
Sch/
Thk
Description
B5Y
Commodity
Code
Pipe Group
PIP
PIPE
00.500
00.750
S160
B36.10
PE, SEAMLESS
PIP
PIPE
01.000
01.500
XS
B36.10
PE, SEAMLESS
PIP
PIPE
02.000
02.000
XS
B36.10
BE, SEAMLESS
PIP
PIPE
03.000
06.000
STD
B36.10
BE, SEAMLESS
PIP
PIPE
08.000
10.000
10.00
IS-3589
IS-3589 GR.330
BE, WELDED
PIP
PIPE
12.000
14.000
12.00
IS-3589
IS-3589 GR.330
BE, WELDED
PIP
PIPE
16.000
18.000
14.00
IS-3589
IS-3589 GR.330
BE, WELDED
PIP
PIPE
20.000
20.000
14.00
IS-3589
IS-3589 GR.330
BE, WELDED
PIP
PIPE
24.000
48.000
CALC
IS-3589
IS-3589 GR.330
BE, WELDED
NIP
NIPPLE
00.500
00.750
B36.10
PBE, SEAMLESS
NIP
NIPPLE
01.000
01.500
B36.10
PBE, SEAMLESS
1
1
1
1
1
1
1
Flange Group
FLG
FLNG.SW
00.500
01.500
B-16.5
ASTM A 105
FLG
FLNG.SO
02.000
24.000
B-16.5
ASTM A 105
ASTM A 105
FLG
FLNG.SO
26.000
48.000
AWWAC207 CL.D
FLB
FLNG.BLIND
00.500
24.000
B-16.5
FLB
FLNG.BLIND
26.000
48.000
FEF
FLNG.FIG.8
00.500
08.000
FEF
10.000
24.000
FEF
26.000
48.000
AWWAC207 CL.D
ASME
B-16.48
ASME
B-16.48
MNF'STD
Fitting Group
ELB90
ELBOW. 90
00.500
00.750
B-16.11
ASTM A 105
SW, 6000
ELB90
ELBOW. 90
01.000
01.500
B-16.11
ASTM A 105
SW, 3000
ELB90
ELBOW. 90
02.000
02.000
B-16.9
BW, 1.5D
ELB90
ELBOW. 90
03.000
06.000
B-16.9
BW, 1.5D
ELB90
ELBOW. 90
08.000
48.000
ELB45
ELBOW. 45
00.500
00.750
B-16.9
BW, 1.5D
B-16.11
ASTM A 105
SW, 6000
ELB45
ELBOW. 45
01.000
01.500
ELB45
ELBOW. 45
02.000
02.000
B-16.11
ASTM A 105
SW, 3000
B-16.9
BW, 1.5D
ELB45
ELBOW. 45
03.000
06.000
B-16.9
BW, 1.5D
ELB45
ELBOW. 45
08.000
48.000
B-16.9
BW, 1.5D
TEQ
T.EQUAL
00.500
TEQ
T.EQUAL
01.000
00.750
B-16.11
ASTM A 105
SW, 6000
01.500
B-16.11
ASTM A 105
SW, 3000
TEQ
T.EQUAL
02.000
02.000
B-16.9
BW
TEQ
T.EQUAL
03.000
06.000
B-16.9
BW
TEQ
T.EQUAL
08.000
48.000
B-16.9
BW
TRED
TRED
T.RED
00.500
00.750
B-16.11
ASTM A 105
SW, 6000
T.RED
01.000
01.500
B-16.11
ASTM A 105
SW, 3000
TRED
T.RED
02.000
02.000
B-16.9
BW
M,M
Note
No
: 300 #
Client
BASIC MATERIAL
: CARBON STEEL
SPECIAL REQUIREMENT : -
CORR. ALLOWANCE
REVISION
:1
: 44LK-5100-00/L.02/0101/A4
Lower
Size
(Inch)
Upper
Size
(Inch)
Sch/
Thk
Description
T.RED
03.000
06.000
M,M
B-16.9
BW
TRED
T.RED
08.000
48.000
M,M
B-16.9
BW
REDC
REDUC.CONC
02.000
02.000
M,M
B-16.9
BW
Input
Id.
Item
Type
Page
of 5
PIPE4CLASS
B5Y
Commodity
Code
Fitting Group
TRED
REDC
REDUC.CONC
03.000
06.000
M,M
B-16.9
BW
REDC
REDUC.CONC
08.000
48.000
M,M
MNF'STD
IS-3589 GR.330
BW
REDE
REDUC.ECC
02.000
02.000
M,M
B-16.9
BW
REDE
REDUC.ECC
03.000
06.000
M,M
B-16.9
BW
REDE
REDUC.ECC
08.000
48.000
M,M
MNF'STD
IS-3589 GR.330
BW
SWGC
SWAGE.CONC
00.500
03.000
M,M
BS-3799
ASTM A 105
PBE
M,M
SWGE
SWAGE.ECC
00.500
03.000
BS-3799
ASTM A 105
PBE
CAP
CAP
00.500
00.750
B-16.11
ASTM A 105
SW, 6000
CAP
CAP
01.000
01.500
B-16.11
ASTM A 105
SW, 3000
CAP
CAP
02.000
02.000
B-16.9
BW
CAP
CAP
03.000
06.000
B-16.9
BW
CAP
CAP
08.000
48.000
B-16.9
BW
CPLF
CPLNG.FULL
00.500
00.750
B-16.11
ASTM A 105
SW, 6000
CPLF
CPLNG.FULL
01.000
01.500
B-16.11
ASTM A 105
SW, 3000
CPLH
CPLNG.HALF
00.500
00.750
B-16.11
ASTM A 105
SW, 6000
CPLH
CPLNG.HALF
01.000
01.500
B-16.11
ASTM A 105
SW, 3000
Valves Group
GAV
VLV.GATE
00.500
01.500
IS:778 CL.2
GAV
VLV.GATE
02.000
24.000
API-600
GAV
VLV.GLOBE
00.500
01.500
IS:778 CL.2
GAV
VLV.GLOBE
02.000
16.000
BS-1873
CHV
VLV.CHECK
00.500
01.500
IS:778 CL.2
CHV
VLV.CHECK
02.000
24.000
BS-1868
CHV
VLV.CHECK
26.000
48.000
API-594
BFV
VLV.BTRFLY
03.000
24.000
API-609/
BS-5155
BFV
VLV.BTRFLY
26.000
48.000
BS-5155
Note
No
: 300 #
Client
BASIC MATERIAL
: CARBON STEEL
SPECIAL REQUIREMENT : -
CORR. ALLOWANCE
REVISION
:1
Input
Id.
Item
Type
Lower
Size
(Inch)
Upper
Size
(Inch)
Page
of 5
PIPE5CLASS
Sch/
Thk
: 44LK-5100-00/L.02/0101/A4
Description
Bolt Group
BOM
BOLT.M/C
00.500
16.000
B-18.2
BOS
BOLT.STUD
18.000
48.000
B-18.2
BOLT:A193 GR.B7,GALV
NUT: A194 GR.2H, GALV
Gasket Group
GAS
GASKET
00.500
24.000
B-16.21ANSI B
16.5
Buna-N (Nitrile)
GAS
GASKET
26.000
48.000
AWWAC207 CL.D
Buna-N (Nitrile)
Trap/Strainer Group
TSR
STRNR.TEMP
03.000
24.000
MNF'STD
B:A285 GALV,
INT: SS 304
PSR
STRNR.PERM
03.000
24.000
MNF'STD
FLANGED, Y-TYPE,
300, FF/125AARH
B5Y
Commodity
Code
Note
No