Académique Documents
Professionnel Documents
Culture Documents
Unit
171.00
225.00
Column Footing
FOOTING
Providing and laying in position reinforced cement concrete
of nominal mix 1:1.5:3(M20) grade with 20mm and down
size graded granite metal, machine mixed, concrete laid in
layers not exceeding 15 cms thick, vibrated for all works in
foundation plinth and ground floor level for roof slabs,
staircase, lintles, retaining walls, return walls, walls ( any
thickness ) including attached plasters, columns, piers,
abutments, pillars, posts, struts, buttresses, string or lacing
courses, parapets, coping, bed blocks, anchor blocks, plain
window cills, fillets etc., including cost of all materials,
labour, HOM of machinery, curing, complete as per
specifications.
CUM
15.67
5,800.00
Column Footing
CUM
43.87
7,200.00
CUM
9.94
7,500.00
CUM
22.24
4,100.00
Column Footing
2.0
3.0
PCC BED
Providing and laying in position plain cement concrete of
mix 1:4:8 using 40mm and down size graded granite metal
machine mixed, concrete laid in layers not exceeding 15
cms. thick, well compacted, in foundation and plinth,
including cost of all materials, labour, HOM of machinery,
curing complete as per specifications.
4.0
PEDASTAL
Providing and laying in position reinforced cement concrete
of nominal mix 1:1.5:3(M20) grade with 20mm and down
size graded granite metal, machine mixed, concrete laid in
layers not exceeding 15 cms thick, vibrated for all works in
foundation, column pedastel, plinth and ground floor level
for roof slabs, staircase, lintles, retaining walls, return walls,
walls ( any thickness )
including attached plasters,
columns, piers, abutments, pillars, posts, struts, buttresses,
string or lacing courses, parapets, coping, bed blocks,
anchor blocks, plain window cills, fillets etc., including cost
of all materials, labour, HOM of machinery,
curing,
complete as per specifications.
5.0
Laterite Soling
Providing Laterite Soling below the plinth beam with 1:6
6.0
ABSTRACT ESTIMATION
Qty
Rate
PLINTH BEAM
Page1
7.0
8.0
9.0
CUM
15.15
8,200.00
CUM
124.72
170.00
CUM
9.79
8,500.00
EARTH FILLING
Filling available excavated earth ( excluding rock ) in sides
of foundations upto plinth in layers not exceeding 20 cms.
in depth, compacting each deposited layer by ramming
after watering with lead upto 50 m. and lift upto 1.5 m.
including cost of all labour complete as per specifications.
RCC COLUMN
Providing and laying in position reinforced cement concrete
of nominal mix 1:1.5:3(M20) grade with 20mm and down
size graded granite metal, machine mixed, concrete laid in
layers not exceeding 15 cms thick, vibrated for all works in
foundation plinth and ground floor level for roof slabs,
staircase, lintles, retaining walls, return walls, walls ( any
thickness ) including attached plasters, columns, piers,
abutments, pillars, posts, struts, buttresses, string or lacing
courses, parapets, coping, bed blocks, anchor blocks, plain
window cills, fillets etc., including cost of all materials,
labour, HOM of machinery, curing, complete as per
specifications.
Ground floor
RCC BEAM
Providing and laying in position reinforced cement concrete
of nominal mix 1:1.5:3(M20) grade with 20mm and down
size graded granite metal, machine mixed, concrete laid in
layers not exceeding 15 cms thick, vibrated for all works in
foundation plinth and ground floor level for roof slabs,
staircase, lintles, retaining walls, return walls, walls ( any
thickness ) including attached plasters, columns, piers,
abutments, pillars, posts, struts, buttresses, string or lacing
courses, parapets, coping, bed blocks, anchor blocks, plain
window cills, fillets etc., including cost of all materials,
labour, HOM of machinery, curing, complete as per
specifications.
Page2
Ground floor
10.0
11.0
12.0
13.0
14.0
RCC STAIRCASE
Providing and laying in position reinforced cement concrete
of nominal mix 1:1.5:3(M20) grade with 20mm and down
size graded granite metal, machine mixed, concrete laid in
layers not exceeding 15 cms thick, vibrated for all works in
foundation plinth and ground floor level for roof slabs,
Ground
floor
Staircase
staircase, lintles, retaining walls, return
walls,
walls
( any
thickness
including
attached plasters, columns, piers,
LATERITE)STONE
MASONRY
abutments,
pillars,
posts, struts,
or lacing
Providing
and
constructing
lateritebuttresses,
size stone string
masonry
courses, parapets,
coping, bed of
blocks,
anchor
blocks,
including
cost and conveyance
materials
curing
etc plain
window
fillets
etc., including
cost ofSTRUCTURE
all materials,
completecills,
as per
specification
FOR SUPER
labour,
HOM
of
machinery,
curing,
complete
as per
in CM 1:6
specifications.
Ground floor
SOLID BLOCK MASONRY
Providing and constructing non-load bearing wall with
cement concrete solid blocks with compressive strength not
less than 35 Kg/sqcm with cement mortar 1:4 ( Jamb,
closer blocks ) with blocks of size 40x15x20cms. (lxbxh)
Ground floor
LOCKER ROOM
RCC LOCKER ROOM Providing and laying in position
reinforced cement concrete of nominal mix 1:1.5:3(M20)
grade with 20mm and down size graded granite metal,
machine mixed, concrete laid in layers not exceeding 15
cms thick, vibrated for all works in foundation plinth and
ground floor level for roof slabs, staircase, lintles, retaining
walls, return walls, walls ( any thickness ) including
attached plasters, columns, piers, abutments, pillars, posts,
struts, buttresses, string or lacing courses, parapets,
coping, bed blocks, anchor blocks, plain window cills, fillets
etc., including cost of all materials, labour, HOM of
machinery, curing, complete as per specifications.
CUM
23.73
8,500.00
CUM
1.90
8,500.00
CUM
40.74
4,300.00
SQM
148.32
900.00
Cum
11.21
CUM
38.30
8,000.00
RCC SLAB
Providing and laying in position reinforced cement concrete
of nominal mix 1:1.5:3(M20) grade with 20mm and down
size graded granite metal, machine mixed, concrete laid in
layers not exceeding 15 cms thick, vibrated for all works in
foundation plinth and ground floor level for roof slabs,
staircase, lintles, retaining walls, return walls, walls ( any
thickness ) including attached plasters, columns, piers,
abutments, pillars, posts, struts, buttresses, string or lacing
courses, parapets, coping, bed blocks, anchor blocks, plain
window cills, fillets etc., including cost of all materials,
labour, HOM of machinery, curing, complete as per
specifications.
Ground floor
15.0
LINTEL RCC
Page3
8,500.00
16.0
17.0
18.0
19.0
20.0
Ground floor
CHEJJA (SUNSHADE) RCC - 3"
Providing and laying in position reinforced cement concrete
of nominal mix 1:1.5:3(M20) grade with 20mm and down
size graded granite metal, machine mixed, concrete laid in
layers not exceeding 15 cms thick, vibrated for all works in
foundation plinth and ground floor level for roof slabs,
staircase, lintles, retaining walls, return walls, walls ( any
thickness ) including attached plasters, columns,
Groundpiers,
floor
abutments,
pillars,
posts,
struts,
buttresses,
string
or lacing
WINDOW GRILLS
courses,
coping, weighing
bed blocks,
anchor blocks,
windows parapets,
and ventilators
18kg/sqm
using plain
M.S.
window
cills,
fillets
etc.,
including
cost
of
all
flats, or M.S. square rods, or combination of M.S.materials,
flats and
labour,
of per
machinery,
curing, drawing
completeincluding
as per
square HOM
rods as
approved design,
specifications.
cutting steel sections and welding the same to required
pattern with a coat of red lead primer, cost of materials,
fixtures, labour and HOM of machinery complete as per
Ground floor
specifications.
PLASTERING :INTERNAL
Providing 12mm thick cement plaster in single coat with
cement mortar 1:4, to ceiling including rounding off corners
wherever required smooth rendering, : Providing and
removing scaffolding, including cost of materials, labour,
curing complete as per specifications.
Ground floor
PLASTERING: CEILING
Providing 12mm thick cement plaster in single coat with
cement mortar 1:3, to ceiling including rounding off corners
wherever required smooth rendering, : Providing and
removing scaffolding, including cost of materials, labour,
curing complete as per specifications.
CUM
0.75
19,025.00
SQM
13.08
1,320.00
KG
345.15
85.00
SQM
619.70
300.00
SQM
284.09
300.00
SQM
267.28
325.00
PLASTERING: EXTERNAL
Providing 18mm thick cement plaster in single coat with
cement mortar 1:6, to brick masonry including rounding off
corners wherever required smooth rendering, : Providing
and removing scaffolding, including cost of materials,
labour, curing complete as per specifications.
Extra for providing and mixing waterproofing compound in
cement plaster work at one kg per bag or in the proportion
recommended by the manufacturers, for cement mortar 1:4,
18mm thick cost of materials complete as per
specifications.
Ground floor
21.0
Page4
23.0
SQM
307.68
200.00
SQM
307.68
1,300.00
SQM
SQm
903.79
255.58
120.00
175.00
SQM
80.25
1,900.00
SQM
27.27
1,880.00
FLOORING
Providing and fixing Special make glazed Vitrified tiles
(Granomite finish) of approved make, quality and colour of
size 600x600x10mm thick fixed on existing flooring with a
special roffe adhesive for flooring and skirting etc.,
complete including providing spears at required interval and
removing stains etc
Ground floor
INTERNAL & CEILING PAINTING
Providing and applying painting in two coats with Water
bond Distamper paint of approved brand on wall surface to
give an even approved shade after throughly brushing the
surface, free from mortar drops and other foreign matter
including preparing the surface even and sand paper
smooth, cost of materials, labour, complete as per
specifications(do with primer)
Same as internal&Ceiling plastering quantity
Ground floor
Out side painting
24.0
ROLLING SHUTTER
Providing and fixing pull and push type of rolling shutters of
approved make out of 18guage, 75mm wide cold rolled
steel laths of convex corrugation, with side guides and
bottom rail, with interlocking arrangements for steel laths by
means of alternate clips, suspension shaft with high tension
coil type springs 2 nos, mounted on specially designed pipe
shafts, with bracket plates, guide channels, ball bearing
arrangements for imnside and outside locking with push
and pulloperations complete including pulling hooks, four
numbers. Handles with all fitings and accessories, painted
with coat of red lead paint cost of materials, labour , HOM
of machinery compl;ete as [per specifications. Shutter size
for shop 3.0m 2.8m (variable to some extent as per site
condition).
Ground floor
25.0
WINDOW SHUTTERS
windows and ventilators weighing 18kg/sqm using M.S.
flats, or M.S. square rods, or combination of M.S. flats and
square rods as per approved design, drawing including
cutting steel sections and welding the same to required
pattern with a coat of red lead primer, cost of materials,
fixtures, labour and HOM of machinery complete as per
specifications.
Ground floor
26.0
STEEL
Page5
27.0
SHUTTERING
KSRB 4-6.2 Providing and removing centering , shuttering ,
strutting , propping etc. and removal of form work for flat
surface such as suspended floors , roofs , landings ,
balconies and likes thickness upto 20mm including cost of
all materials , labour complete as per specifications.
TON
13.10
SQM
910.73
50,000.00
500.00
Total
Add Electrification @ 7% of total cost
Add Plumbing & Sanitary (Lumpsum)
Grand Total
PUTTUR
31.05.2016
Page6
38,475.00
90,899.17
315,860.35
74,547.00
91,184.00
Page7
124,203.43
21,201.90
83,224.35
Page8
201,703.58
16,162.92
175,171.68
133,488.00
89,712.00
325,571.82
Page9
14,308.70
17,265.60
29,337.75
185,908.50
85,228.20
86,864.70
Page10
61,536.00
399,984.00
108,454.68
44,725.80
152,475.00
51,267.60
Page11
655,000.00
455,366.43
4,129,128.15
289,038.97
100,000.00
4,518,167.12
ENGINEER
Page12
NAME OF WORK : PROPOSED CONSTRUCTION OF COMMERCIAL BUILDING IN S.NO.24/2B & 24/8 OF KAVU VI
PUTTUR TALUK, DK DISTRICT.
MEASUREMENT SHEET
Sl.No.
Work Description
Measurement
No.s
Qty.
Unit
1.80
1.80
1.80
1.80
1.80
1.80
1.80
39.98
12.47
49.90
37.42
15.72
6.71
9.67
171.87
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
1.67
1.75
1.75
1.75
2.05
1.75
2.21
3.00
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
3.33
1.04
4.16
3.12
1.31
0.56
0.81
1.35
15.67
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
1.67
1.75
1.75
1.75
2.05
1.75
2.21
3.00
0.40
0.40
0.40
0.48
0.55
0.48
0.60
0.15
8.88
2.77
11.09
9.98
4.80
1.77
3.22
1.35
43.87
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
0.53
0.53
0.53
0.53
0.68
0.68
0.68
2.20
2.20
2.20
2.20
2.20
2.20
2.20
2.45
0.70
2.80
1.75
1.35
0.45
0.45
9.94
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
22.24
Cum
6.34
0.61
3.60
1.07
1.91
1.62
15.15
Cum
Cum
Cum
Cum
Cum
Cum
Cum
7
1.90
2
1.98
8
1.98
6
1.98
2
2.13
1
2.13
1
2.43
Total Excavation
1.67
1.75
1.75
1.75
2.05
1.75
2.21
7
1.90
2
1.98
8
1.98
6
1.98
2
2.13
1
2.13
1
2.43
1
3.00
Total PCC Bed
PCC Bed
Footing T1
Footing T2
Footing T3
Footing T4
Footing T5
Footing T6
Footing T7
Bank Locker Room
3 Footing
Footing T1
7
1.90
Footing T2
2
1.98
Footing T3
8
1.98
Footing T4
6
1.98
Footing T5
2
2.13
Footing T6
1
2.13
Footing T7
1
2.43
Bank Locker Room
1
3.00
Total Footing Concreting
4 Pedastal
Footing T1
7
0.30
Footing T2
2
0.30
Footing T3
8
0.30
Footing T4
5
0.30
Footing T5
3
0.30
Footing T6
1
0.30
Footing T7
1
0.30
Total Pedastal Concreting
Laterite Soling below the
5.0 plinth beam
1.0
174.0
0.23
0.7
6 Plinth Beam
Beam 1
1
61.28
Beam 2
1
5.86
Beam 3
1
52.13
Beam 4
1
10.36
Beam 5
1
18.44
Bank Locker Beam
4
3.00
Total Plinth Concreting
7
0.23
0.23
0.23
0.23
0.23
0.30
0.45
0.45
0.30
0.45
0.45
0.45
Footing T1
Footing T2
Footing T3
Footing T4
Footing T5
Footing T6
Footing T7
Bank Locker Room
TOTAL
Deduct
Footing
Concrete
Deduct Pedastal
TOTAL
7
2
8
6
2
1
1
1
1.90
1.98
1.98
1.98
2.13
2.13
2.43
3.00
1.67
1.75
1.75
1.75
2.05
1.75
2.21
3.00
1.80
1.80
1.80
1.80
1.80
1.80
1.80
0.70
39.98
12.47
49.90
37.42
15.72
6.71
9.67
6.30
178.17
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
20
35.63
Cum
10
17.82
Cum
124.72
Cum
8 RCC Column
Footing T1
7
0.45
Footing T2
2
0.45
Footing T3
8
0.45
Footing T4
5
0.45
Footing T5
3
0.60
Footing T6
1
0.60
Footing T7
1
0.60
Total RCC Column Qty.
0.23
0.23
0.23
0.23
0.23
0.23
0.23
3.30
3.30
3.30
3.30
3.30
3.30
3.30
2.39
0.68
2.73
1.71
1.37
0.46
0.46
9.79
cum
cum
cum
cum
cum
cum
cum
Cum
Beam 1
1
28.96
Beam1
1
3.04
Beam 2
1
20.57
Beam 2
1
3.04
Beam 3
1
37.42
Beam 3A
3
1.20
Beam 4
1
6.09
Beam 4A
1
1.20
Beam 5
2
6.00
Beam 5A
2
1.20
Beam 6
3
5.64
Beam 6
2
6.09
Beam 6A
5
1.20
Bem 7
2
6.09
Beam 8
2
3.73
Beam 9
1
20.35
Total RCC Beam Qty.
0.23
0.30
0.23
0.30
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.43
0.43
0.43
0.43
0.57
0.43
0.57
0.43
0.57
0.43
0.57
0.57
0.43
0.73
0.58
0.58
2.83
0.39
2.01
0.39
4.93
0.35
0.80
0.12
1.57
0.23
2.22
1.60
0.59
2.03
0.99
2.69
23.73
cum
cum
cum
cum
cum
cum
cum
cum
cum
cum
cum
cum
cum
cum
cum
cum
cum
0.23
1.80
0.30
0.90
0.23
0.13
0.15
0.15
0.10
0.34
0.73
0.74
1.90
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
3.00
3.00
3.00
3.00
3.00
1.35
1.20
1.35
1.35
0.30
13.11
26.59
5.58
2.10
1.68
-1.24
-2.32
-1.86
-0.56
-0.06
RCC Beam
10 RCC Staircase
Beam
Landing Slab
Steps
Waist Slab
11 Laterite Stone Masonry
Walls
Walls
Walls
Walls
Walls
Less Window W1
Less Window W2
Less Window W3
Less Window W4
Less Ventilator
1
1.80
1
1.50
18
0.90
2
2.74
Total RCC Qty.
1
2
1
1
1
2
7
4
1
2
19.00
19.27
8.09
3.04
2.43
2.00
1.20
1.50
1.80
0.45
Less Bank RS
1
2.10
Less RS
1
1.20
Total Laterite Masonry Qty.
12 Solid Block Masonry
Walls
4
4.15
Walls
1
6.15
Walls
1
4.95
Walls
1
2.50
Walls
1
6.00
Walls
1
6.00
Walls
1
1.80
Walls
1
1.20
Toilet wall
1
2.00
Less Doors
2
0.75
Less Doors
1
0.90
Total Solid Block Masonry Qty.
13 RCC for Locker Room
Walls
2
3.65
Walls
1
3.00
Walls
1
3.00
Less Door
1
1.20
Total RCC Qty.
14 RCC for Slab
Slab 1
1
6.09
Slab 1A
1
3.23
Slab 2
1
6.09
Slab 2A
1
2.66
Slab 3
1
6.09
Slab 3A
1
3.65
Slab 4
1
6.09
Slab 4A
1
2.36
Slab 5
1
6.09
Slab 5A
1
2.97
Slab 6
1
4.64
Slab 6A
1
1.82
Slab 7
1
4.64
Slab 8
1
4.64
Slab 9
1
4.64
Slab 10
1
4.87
Slab 11
1
3.00
Slab 12
1
3.00
Slab 12A
1
3.20
Slab 13
1
6.09
Slab 13A
1
3.00
Slab 14
1
6.09
Slab 14A
1
3.30
Slab 15
1
6.09
Slab 15A
1
3.58
Slab Projection
2
8.17
Slab Projection
2
19.40
Total RCC Qty.
15 Lintel RCC
W1
1
2.30
W2
6
1.50
W3
4
1.80
W4
1
2.10
V
2
0.60
0.23
0.23
3.00
3.00
-1.45
-0.83
40.74
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
2.10
2.10
2.10
54.78
20.30
16.34
8.25
19.80
19.80
5.94
3.96
4.20
-3.15
-1.89
148.32
0.30
0.30
0.30
2.10
3.00
3.00
3.00
0.30
6.57
2.70
2.70
-0.76
11.21
3.23
1.20
2.66
1.20
3.65
1.20
2.36
1.20
1.20
1.20
2.36
1.20
2.97
2.97
4.95
3.65
3.00
2.43
1.37
3.00
1.20
3.30
1.20
3.58
1.20
0.90
0.23
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
0.13
2.46
0.50
2.11
0.41
2.89
0.57
1.87
0.37
0.95
0.46
1.42
0.28
1.79
1.79
2.99
2.31
1.17
0.95
0.57
2.38
0.47
2.61
0.51
2.83
0.56
1.91
1.16
38.30
0.23
0.23
0.23
0.23
0.23
0.15
0.15
0.15
0.15
0.15
0.08
0.31
0.25
0.07
0.04
Cum
Cum
0.75
Cum
1.38
5.40
4.32
1.26
0.72
0.90
13.08
Sq mt
5.40
10.08
8.10
2.70
0.27
26.55
345.15
Sq mt
Sq mt
Sq mt
Sq mt
Sq mt
Sq mt
kg
55.97
19.80
10.89
39.60
43.23
21.45
25.08
32.34
32.14
5.94
31.68
9.90
63.36
9.90
8.25
19.80
31.68
16.50
18.81
39.60
15.35
19.80
29.70
7.92
16.50
19.80
5.04
3.15
653.18
5.40
10.08
6.48
2.43
0.27
3.78
3.15
1.89
33.48
619.70
m2
16 Chejja (Sunshade)
W1
W2
W3
W4
V
Exit Door
1
6
4
1
2
1
2.30
1.50
1.80
2.10
0.60
1.50
0.60
0.60
0.60
0.60
0.60
0.60
17 Window Grill
Window W1
2
2.00
Window W2
7
1.20
Window W3
4
1.50
Window W4
1
2.00
Ventilator
2
0.45
Total Window Grills Qty.
Total Window Grills Weight @13kg/sqm
18 Plastering - Internal
Bank
1
16.96
Bank
1
6.00
Loacker room
1
3.30
Locker Room
1
12.00
Manager Cabin
1
13.10
Canteen
1
6.50
Canteen
1
7.60
canten
2
4.90
Staircase room
2
4.87
Stair Cas Room
1
1.80
Medical
2
4.80
Meicaal
1
3.00
Office
4
4.80
Office
1
3.00
Office
1
2.50
Salon
1
6.00
Salon
2
4.80
Salon
2
2.50
Toilet
1
5.70
Clinic
2
6.00
Clinic
1
4.65
Super Market
1
6.00
Bank Toilet
5
1.80
Bank Toilet
2
1.20
Stationary
2
2.5
Atm
2
3.00
Extra toilet
2
1.20
2
0.75
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
3.30
2.10
2.10
Less W1
Less W2
Less 3
Less 4
Ventilators
RS
D
D1
1.35
1.20
1.35
1.35
0.30
2.10
2.10
2.10
2
7
4
1
2
1
2
1
2.00
1.20
1.20
1.80
0.45
1.80
0.75
0.90
1.35
1.20
1.35
1.35
0.30
19 Plastering - Ceiling
Bank
Bank Toilet
Bank Stationary
Atm
Loacker room
Manager Cabin
Canteen
Staircase room
Medical
Office
Office
Salon
Toilet
Clinic
Super Market
Corridor
Corridor
Stair Case
Landing slab
Total Ceiling Plastering Area
20 Plastering - External
Front Walls
Back Walls
Corridor Wall
Projection Slab
Projection Slab
Total Plastering Area
21 Flooring
Bank
Manager Cabin
Locker Room
Canteen
Staircase room
Medical
Office
Office
Salon
Toilet
Toilet wall
Clinic
Super Market
Bank Toilet
Wall
Stationery
ATM
Corridor
Corridor
Extra toilet
Total Flooring Area
22 Painting Internal
Bank
Bank
Loacker room
Locker Room
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
1
2
1
2
1
1
2
2
6.00
1.20
1.80
3.00
3.00
3.00
7.60
4.80
4.80
4.80
4.80
4.80
1.20
6.00
6.00
12.95
13.56
2.00
1.80
19.50
18.54
20.00
7.77
19.50
8.50
1.80
2.50
1.80
3.00
2.50
4.80
1.80
3.00
3.00
2.50
2.50
1.50
4.50
6.00
0.90
0.90
0.90
1.50
3.30
3.00
3.00
0.90
0.23
51.00
2.16
4.50
5.40
9.00
7.50
36.48
8.64
14.40
14.40
12.00
12.00
1.80
27.00
36.00
23.31
12.20
3.60
2.70
284.09
m2
128.70
55.62
60.00
13.99
8.97
267.28
m2
1
1
1
1
1
6.00
2.50
3.00
7.60
4.80
8.50
3.00
3.00
4.80
1.80
51.00
7.50
9.00
36.48
8.64
1
1
1
1
1
1
1
1
1
1
1
1
2
1
2
2
4.80
4.80
4.80
4.80
1.20
4.20
4.00
6.00
1.20
6.00
2.50
3.00
14.25
13.95
1.20
0.75
3.00
3.00
2.50
2.50
1.50
2.10
6.00
6.00
1.80
1.50
1.80
1.80
0.90
1.20
2.10
2.10
14.40
14.40
12.00
12.00
1.80
8.82
24.00
36.00
2.16
9.00
4.50
5.40
25.65
16.74
5.04
3.15
307.68
1
1
1
1
16.96
6.00
3.30
12.00
3.00
3.00
3.00
3.00
50.88
18.00
9.90
36.00
m2
Manager Cabin
Canteen
Canteen
canten
Staircase room
Stair Cas Room
Medical
Meicaal
Office
Office
Office
Salon
Salon
Salon
Toilet
Clinic
Clinic
Super Market
Bank Toilet
Bank Toilet
Stationary
Atm
Extra toilet
1
1
1
2
2
1
2
1
4
1
1
1
2
2
1
2
1
1
5
2
2
2
2
2
13.10
6.50
7.60
4.90
4.87
1.80
4.80
3.00
4.80
3.00
2.50
6.00
4.80
2.50
5.70
6.00
4.65
6.00
1.80
1.20
2.5
3.00
1.20
0.75
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
3.00
2.10
2.10
Less W1
Less W2
Less 3
Less 4
Ventilators
RS
D
D1
2
7
4
1
2
1
2
1
2.00
1.20
1.20
1.80
0.45
1.80
0.75
0.90
1.35
1.20
1.35
1.35
0.30
2.10
2.10
2.10
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
1
2
1
6.00
1.20
1.80
3.00
3.00
3.00
7.60
4.80
4.80
4.80
4.80
4.80
1.20
6.00
6.00
12.95
13.56
2.00
1.80
8.50
1.80
2.50
1.80
3.00
2.50
4.80
1.80
3.00
3.00
2.50
2.50
1.50
4.50
6.00
0.90
0.90
0.90
1.50
39.30
19.50
22.80
29.40
29.22
5.40
28.80
9.00
57.60
9.00
7.50
18.00
28.80
15.00
17.10
36.00
13.95
18.00
27.00
7.20
15.00
18.00
5.04
3.15
594.54
5.40
10.08
6.48
2.43
0.27
3.78
3.15
1.89
33.48
561.06
51.00
2.16
4.50
5.40
9.00
7.50
36.48
8.64
14.40
14.40
12.00
12.00
1.80
27.00
36.00
23.31
12.20
3.60
2.70
284.09
m2
m2
Front Walls
Back Walls
Corridor Wall
Projection Slab
Projection Slab
Total Painting Area
25 Centering&Shuttering
Plinth Beam Sides
2
1
1
2
2
Beam 1
Beam 2
Beam 3
19.50
18.54
20.00
7.77
19.50
3.00
3.00
3.00
0.90
0.23
117.00
55.62
60.00
13.99
8.97
255.58
m2
m2
m2
m2
61.28
2.00
0.45
55.15
5.86
2.00
0.45
5.27
m2
52.13
2.00
0.30
31.28
m2
Beam 4
10.36
2.00
0.45
9.32
m2
Beam 5
18.44
2.00
0.45
16.60
3.00
2.00
0.45
10.80
128.4 m2
Column Pedastal
Column (.45*.23)
Column ((06*.23)
23.0
4.0
1.7
2.0
2.20
2.20
1.0
1.0
84.00
17.25
101.2 m2
Columns
Column (0.45*.23)
Column ((06*.23)
23.0
4.0
1.4
1.7
3.3
3.3
1.0
1.0
106.26
22.44
128.7 m2
Beam Bottoms
Beam 1
Beam 2
Beam 3
Beam 3A
Beam 4
Beam 4A
Beam 5
Beam 5A
Beam 6
Beam 6A
Bem 7
Beam 8
Beam 9
1
1
1
3
1
1
2
2
1
5
2
1
1
28.19
28.65
37.19
1.20
5.88
1.20
6.00
1.20
6.00
1.20
6.00
7.45
17.22
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
Beam 1
Beam 2
Beam 3
Beam 3A
Beam 4
Beam 4A
Beam 5
Beam 5A
Beam 6
Beam 6A
Bem 7
Beam 8
Beam 9
1
1
1
3
1
1
2
2
1
5
2
1
1
28.19
28.65
37.19
1.20
5.88
1.20
6.00
1.20
6.00
1.20
6.00
7.45
17.22
0.30
0.30
0.45
0.30
0.45
0.30
0.45
0.30
0.45
0.30
0.60
0.45
0.45
Slab 1
6.09
3.23
6.48
6.59
8.55
0.83
1.35
0.28
2.76
0.55
1.38
1.38
2.76
1.71
3.96
38.6
Beam Sides
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
16.91
17.19
33.47
2.16
5.29
0.72
10.80
1.44
5.40
3.60
14.40
6.71
15.50
133.6
Slab
19.7
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
SqM
Slab 1A
Slab 2
Slab 2A
Slab 3
Slab 3A
Slab 4
Slab 4A
Slab 5
Slab 5A
Slab 6
Slab 6A
Slab 7
Slab 8
Slab 9
Slab 10
Slab 11
Slab 12
Slab 12A
Slab 13
Slab 13A
Slab 14
Slab 14A
Slab 15
Slab 15A
Slab Projection
Slab Projection
Slab Side
Bank Locker Room
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
2
1
8
3.23
6.09
2.66
6.09
3.65
6.09
2.36
6.09
2.97
4.64
1.82
4.64
4.64
4.64
4.87
3.00
3.00
3.20
6.09
3.00
6.09
3.30
6.09
3.58
8.17
19.40
102.35
3.00
1.20
2.66
1.20
3.65
1.20
2.36
1.20
1.20
1.20
2.36
1.20
2.97
2.97
4.95
3.65
3.00
2.43
1.37
3.00
1.20
3.30
1.20
3.58
1.20
0.90
0.23
0.13
3.00
TOTAL
Total Shuttering
26 Window Shutters
Window W1
2
2.00
Window W2
7
1.20
Window W3
4
1.50
Window W4
1
1.80
Total Window Shutters Qty.
27 Rolling Shutter
Bank
1
1.80
Canteen
1
1.50
Medical
1
3.00
Office
1
3.00
Office
1
2.50
Salon
1
2.50
Clinic
1
4.00
Super Market
1
6.00
1
6.00
ATM
1
1.80
Total RS Area
1.35
1.35
1.35
1.35
2.50
2.50
2.50
2.50
2.50
2.50
2.50
2.50
2.50
2.50
3.9
16.2
3.2
22.2
4.4
14.4
2.8
7.3
3.6
11.0
2.2
13.8
13.8
23.0
17.8
9.0
7.3
4.4
18.3
3.6
20.1
4.0
21.8
4.3
14.7
8.9
12.8
72.0
380.2
910.7
SqM
SqM
5.40
11.34
8.10
2.43
27.27
Sq mt
Sq mt
Sq mt
Sq mt
Sq mt
4.50
3.75
7.50
7.50
6.25
6.25
10.00
15.00
15.00
4.50
80.25
Sq mt
Unit