Académique Documents
Professionnel Documents
Culture Documents
2010
SUBMITTED BY:
DEVESH SINGH
IIIrd B.TECH
MECHANICAL ENGINEERING
ROLL NO. 0704540015
H.B.T.I. KANPUR
1
ACKNOWLEDGEMENT
With profound respect and gratitude, I take the opportunity to convey my thanks to
complete the training here.
I do extend my heartfelt thanks to Ms. Rachna Singh Bahal for providing me this
opportunity to be a part of this esteemed organization.
I am extremely grateful to all the technical staff of BTPS / NTPC for their co-
operation and guidance that has helped me a lot during the course of training. I have learnt a
lot working under them and I will always be indebted of them for this value addition in me.
I would also like to thank the training incharge of H.B.T.I., Kanpur and all the faculty
members of Mechanical Engineering Department for their effort of constant co- operation,
which have been a significant factor in the accomplishment of my industrial training.
DEVESH SINGH
H.B.T.I., KANPUR
2
CERTIFICATE
Training Incharge
NTPC,
Badarpur, New Delhi
3
TRAINING AT BTPS
I was appointed to do 6 week training at this esteemed organization from 22nd June to 31st
July, 2010. I was assigned to visit various division of the plant, which were:
Boiler Maintenance Department (BMD I/II/III)
Plant Auxiliary Maintenance (PAM)
Turbine Maintenance Department (TAM)
Coal Handling Department (CHD/NCHP)
These 6 weeks training was a very educational adventure for me. It was really
amazing to see the plant by yourself and learn how electricity, which is one of our daily
requirements of life, is produced.
This report has been made by my experience at BTPS. The material in this report has
been gathered from my textbook, senior student reports and trainers manuals and power
journals provided by training department. The specification and principles are as learned by
me from the employees of each division of BTPS.
DEVESH SINGH
4
INDEX
ABOUT NTPC
ABOUT BTPS
RANKINE CYCLE
5
ABOUT NTPC
NTPC Limited is the largest thermal power generating company of India, Public Sector
Company. It was incorporated in the year 1975 to accelerate power development in the
country as a wholly owned company of the Government of India. At present, Government of
India holds 89.5% of the total equity shares of the company and the balance 10.5% is held by
FIIs, Domestic Banks, Public and others. Within a span of 31 years, NTPC has emerged as a
truly national power company, with power generating facilities in all the major regions of the
country.
NTPC's core business is engineering, construction and operation of power generating plants
and providing consultancy to power utilities in India and abroad.
The total installed capacity of the company is 31134 MW (including JVs) with 15 coal based
and 7 gas based stations, located across the country. In addition under JVs, 3 stations are coal
based & another station uses naphtha/LNG as fuel. By 2017, the power generation portfolio is
expected to have a diversified fuel mix with coal based capacity of around 53000 MW, 10000
MW through gas, 9000 MW through Hydro generation, about 2000 MW from nuclear
sources and around 1000 MW from Renewable Energy Sources (RES). NTPC has adopted a
multi-pronged growth strategy which includes capacity addition through green field projects,
expansion of existing stations, joint ventures, subsidiaries and takeover of stations.
6
NTPC has been operating its plants at high efficiency levels. Although the company has
18.79% of the total national capacity it contributes 28.60% of total power generation due to
its focus on high efficiency. NTPC’s share at 31 Mar 2001 of the total installed capacity of
the country was 24.51% and it generated 29.68% of the power of the country in 2008-09.
Every fourth home in India is lit by NTPC. 170.88BU of electricity was produced by its
stations in the financial year 2005-2006. The Net Profit after Tax on March 31, 2006 was
INR 58,202 million. Net Profit after Tax for the quarter ended June 30, 2006 was INR 15528
million, which is 18.65% more than for the same quarter in the previous financial year.
2005).
NTPC has set new benchmarks for the power industry both in the area of power plant
construction and operations. Its providing power at the cheapest average tariff in the country.
NTPC is committed to the environment, generating power at minimal environmental cost and
preserving the ecology in the vicinity of the plants. NTPC has undertaken massive a
forestation in the vicinity of its plants. Plantations have increased forest area and reduced
barren land. The massive a forestation by NTPC in and around its Ramagundam Power
station (2600 MW) have contributed reducing the temperature in the areas by about 3°c.
NTPC has also taken proactive steps for ash utilization. In 1991, it set up Ash Utilization
Division
A graphical overview
7
Technological Initiatives
Environment Management
All stations of NTPC are ISO 14001 certified.
Various groups to care of environmental issues.
The Environment Management Group.
Ash Utilization Division.
Afforestation Group.
8
Centre for Power Efficiency & Environment Protection.
Group on Clean Development Mechanism.
NTPC is the second largest owner of trees in the country after the Forest department.
JOURNEY OF NTPC
9
ABOUT BTPS
Badarpur thermal power station started working in 1973 with a single 95 mw unit. There
were 2 more units (95 MW each) installed in next 2 consecutive years. Now it has total five
units with total capacity of 720 MW. Ownership of BTPS was transferred to NTPC with
effect from 01.06.2006 through GOI’s Gazette Notification .Given below are the details of
unit with the year they are installed.
10
Coal to Steam
Coal from the coal wagons is unloaded in the coal handling plant. This Coal is transported up
to the raw coal bunkers with the help of belt conveyors. Coal is transported to Bowl mills by
Coal Feeders. The coal is pulverized in the Bowl Mill, where it is ground to powder form.
The mill consists of a round metallic table on which coal particles fall. This table is rotated
with the help of a motor. There are three large steel rollers, which are spaced 120 apart.
When there is no coal, these rollers do not rotate but when the coal is fed to the table it packs
up between roller and the table and ths forces the rollers to rotate. Coal is crushed by the
crushing action between the rollers and the rotating table. This crushed coal is taken away to
the furnace through coal pipes with the help of hot and cold air mixture from P.A. Fan.
P.A. Fan takes atmospheric air, a part of which is sent to Air-Preheaters for heating while a
part goes directly to the mill for temperature control. Atmospheric air from F.D. Fan is heated
in the air heaters and sent to the furnace as combustion air.
Water from the boiler feed pump passes through economizer and reaches the boiler drum.
Water from the drum passes through down comers and goes to the bottom ring header. Water
from the bottom ring header is divided to all the four sides of the furnace. Due to heat and
density difference, the water rises up in the water wall tubes. Water is partly converted to
steam as it rises up in the furnace. This steam and water mixture is again taken to thee boiler
drum where the steam is separated from water.
11
Water follows the same path while the steam is sent to superheaters for superheating. The
superheaters are located inside the furnace and the steam is superheated (540C) and finally it
goes to the turbine.
Flue gases from the furnace are extracted by induced draft fan, which maintains balance draft
in the furnace (-5 to –10 mm of wcl) with forced draft fan. These flue gases emit their heat
energy to various super heaters in the pent house and finally pass through air-preheaters and
12
goes to electrostatic precipitators where the ash particles are extracted. Electrostatic
Precipitator consists of metal plates, which are electrically charged. Ash particles are
attracted on to these plates, so that they do not pass through the chimney to pollute the
atmosphere. Regular mechanical hammer blows cause the accumulation of ash to fall to the
bottom of the precipitator where they are collected in a hopper for disposal.
13
Mechanical Power to Electrical Power
As the blades of turbine rotate, the shaft of the generator, which is coupled to tha of the
turbine, also rotates. It results in rotation of the coil of the generator, which causes induced
electricity to be produced.
On large turbines, it becomes economical to increase the cycle efficiency by using reheat,
which is a way of partially overcoming temperature limitations. By returning partially
expanded steam, to a reheat, the average temperature at which the heat is added, is increased
and, by expanding this reheated steam to the remaining stages of the turbine, the exhaust
14
wetness is considerably less than it would otherwise be conversely, if the maximum tolerable
wetness is allowed, the initial pressure of the steam can be appreciably increased.
Bleed Steam Extraction: For regenerative system, nos. of non-regulated extractions is taken
from HP, IP turbine.
Regenerative heating of the boiler feed water is widely used in modern power plants; the
effect being to increase the average temperature at which heat is added to the cycle, thus
improving the cycle efficiency.
RANKINE CYCLE
The Rankine cycle is a thermodynamic cycle which converts heat into work. The heat is
supplied externally to a closed loop, which usually uses water as the working fluid. This
cycle generates about 80% of all electric power used throughout the world, including
virtually all solar thermal, biomass, coal and nuclear power plants. It is named after William
John Macquorn Rankine, a Scottish polymath..
Description
Physical layout of the four main devices used in the Rankine cycle
15
A Rankine cycle describes a model of the operation of steam heat engines most commonly
found in power generation plants. Common heat sources for power plants using the Rankine
cycle are coal, natural gas, oil, and nuclear.
The Rankine cycle is sometimes referred to as a practical Carnot cycle as, when an efficient
turbine is used, the TS diagram will begin to resemble the Carnot cycle. The main difference
is that a pump is used to pressurize liquid instead of gas. This requires about 1/100th (1%) as
much energy as that compressing a gas in a compressor (as in the Carnot cycle).
The efficiency of a Rankine cycle is usually limited by the working fluid. Without the
pressure going super critical the temperature range the cycle can operate over is quite small,
turbine entry temperatures are typically 565°C (the creep limit of stainless steel) and
condenser temperatures are around 30°C. This gives a theoretical Carnot efficiency of around
63% compared with an actual efficiency of 42% for a modern coal-fired power station. This
low turbine entry temperature (compared with a gas turbine) is why the Rankine cycle is
often used as a bottoming cycle in combined cycle gas turbine power stations.
The working fluid in a Rankine cycle follows a closed loop and is re-used constantly. The
water vapor and entrained droplets often seen billowing from power stations is generated by
the cooling systems (not from the closed loop Rankine power cycle) and represents the waste
heat that could not be converted to useful work.
Note that cooling towers operate using the latent heat of vaporization of the cooling fluid.
The white billowing clouds that form in cooling tower operation are the result of water
droplets which are entrained in the cooling tower airflow; it is not, as commonly thought,
steam. While many substances could be used in the Rankine cycle, water is usually the fluid
of choice due to its favorable properties, such as nontoxic and unreactive chemistry,
abundance, and low cost, as well as its thermodynamic properties.
One of the principal advantages it holds over other cycles is that during the compression
stage relatively little work is required to drive the pump, due to the working fluid being in its
liquid phase at this point. By condensing the fluid to liquid, the work required by the pump
will only consume approximately 1% to 3% of the turbine power and so give a much higher
efficiency for a real cycle.
The benefit of this is lost somewhat due to the lower heat addition temperature. Gas turbines,
for instance, have turbine entry temperatures approaching 1500°C. Nonetheless, the
efficiencies of steam cycles and gas turbines are fairly well matched.
16
Processes of the Rankine cycle
Ts diagram of a typical Rankine cycle operating between pressures of 0.06bar and 50bar.
There are four processes in the Rankine cycle, each changing the state of the working fluid.
These states are identified by number in the diagram to the right
i. Process 1-2: The working fluid is pumped from low to high pressure, as the fluid is a
liquid at this stage the pump requires little input energy.
ii. Process 2-3: The high pressure liquid enters a boiler where it is heated at constant
pressure by an external heat source to become a dry saturated vapour.
iii. Process 3-4: The dry saturated vapor expands through a turbine, generating power.
This decreases the temperature and pressure of the vapor, and some condensation may
occur.
iv. Process 4-1: The wet vapor then enters a condenser where it is condensed at a
constant pressure and temperature to become a saturated liquid. The pressure and
temperature of the condenser is fixed by the temperature of the cooling coils as the
fluid is undergoing a phase-change.
In an ideal Rankine cycle the pump and turbine would be isentropic, i.e., the pump and
turbine would generate no entropy and hence maximize the net work output. Processes 1-2
and 3-4 would be represented by vertical lines on the Ts diagram and more closely resemble
that of the Carnot cycle.
The Rankine cycle shown here prevents the vapor ending up in the superheat region after the
expansion in the turbine, which reduces the energy removed by the condensers.
17
Real Rankine cycle (non-ideal) : Rankine cycle with superheat
In a real Rankine cycle, the compression by the pump and the expansion in the turbine are not
isentropic. In other words, these processes are non-reversible and entropy is increased during
the two processes. This somewhat increases the power required by the pump and decreases
the power generated by the turbine.
In particular the efficiency of the steam turbine will be limited by water droplet formation. As
the water condenses, water droplets hit the turbine blades at high speed causing pitting and
erosion, gradually decreasing the life of turbine blades and efficiency of the turbine. The
easiest way to overcome this problem is by superheating the steam. On the Ts diagram above,
state 3 is above a two phase region of steam and water so after expansion the steam will be
very wet. By superheating, state 3 will move to the right of the diagram and hence produce a
dryer steam after expansion.
18
Regenerative Rankine cycle
The regenerative Rankine cycle is so named because after emerging from the condenser
(possibly as a subcooled liquid) the working fluid is heated by steam tapped from the hot
portion of the cycle. On the diagram shown, the fluid at 2 is mixed with the fluid at 4 (both at
the same pressure) to end up with the saturated liquid at 7. The Regenerative Rankine cycle
(with minor variants) is commonly used in real power stations.
Another variation is where 'bleed steam' from between turbine stages is sent to feedwater
heaters to preheat the water on its way from the condenser to the boiler.
The boiler is a rectangular furnace about 50 ft (15 m) on a side and 130 ft (40 m) tall. Its
walls are made of a web of high pressure steel tubes about 2.3 inches (60 mm) in diameter.
Pulverized coal is air-blown into the furnace from fuel nozzles at the four corners and it
rapidly burns, forming a large fireball at the centre. The thermal radiation of the fireball heats
the water that circulates through the boiler tubes near the boiler perimeter. The water
circulation rate in the boiler is three to four times the throughput and is typically driven by
pumps. As the water in the boiler circulates it absorbs heat and changes into steam at 700 °F
(370 °C) and 3,200 psi (22.1MPa). It is separated from the water inside a drum at the top of
the furnace.
19
Boiler Side of the Badarpur Thermal Power Station, New Delhi
The saturated steam is introduced into superheat pendant tubes that hang in the hottest part of
the combustion gases as they exit the furnace. Here the steam is superheated to 1,000 °F (540
°C) to prepare it for the turbine. The steam generating boiler has to produce steam at the high
purity, pressure and temperature required for the steam turbine that drives the electrical
generator.
The generator includes the economizer, the steam drum, the chemical dosing equipment, and
the furnace with its steam generating tubes and the superheater coils. Necessary safety valves
are located at suitable points to avoid excessive boiler pressure. The air and flue gas path
equipment include: forced draft (FD) fan, air preheater (APH), boiler furnace, induced draft
(ID) fan, fly ash collectors (electrostatic precipitator or baghouse) and the flue gas stack.
For units over about 210 MW capacity, redundancy of key components is provided by
installing duplicates of the FD fan, APH, fly ash collectors and ID fan with isolating dampers.
On some units of about 60 MW, two boilers per unit may instead be provided.
20
Schematic diagram of a coal-fired power plant steam generator
2. Steam Temperature:
i. Drum 341C
ii. Super heater outlet 540C
iii. Reheat inlet 332C
iv. Reheat outlet 540C
3. Steam Pressure:
i. Drum design 158. 20 kg/cm2
ii. Drum operating 149.70 kg/cm2
iii. Super heater outlet 137.00 kg/cm2
iv. Reheat inlet 26.35 kg/cm2
v. Reheat outlet 24.50 kg/cm2
21
4. Fuel Specifications
A) Coal
i. Fixed Carbon 38%
ii. Volatile Matter 26%
iii. Moisture 8.0%
iv. Ash 28%
v. Grindability 55HGI
vi. High Heat 4860 Kcal/Kg
vii. Coal size to Mill 20 mm
B) Oil
i. Low Heat value 10000 kcal/kg
ii. Sulphur 4.5% w/w
iii. Moisture 1% w/w
5. Heat Balance
i. Dry gas loss 4.63%
ii. Carbon loss 2%
iii. Radiation loss 0.26%
iv. Unaccounted loss 1.5%
v. H2 in air and H2O in fuel 4.9%
1. FURNACE
Furnace is primary part of boiler where the chemical energy of the fuel is converted to
thermal energy by combustion. Furnace is designed for efficient and complete
22
combustion. Major factors that assist for efficient combustion are amount of fuel
inside the furnace and turbulence, which causes rapid mixing between fuel and air. In
modern boilers, water furnaces are used.
2. BOILER DRUM
Drum is of fusion-welded design with welded hemispherical dished ends. It is
provided with stubs for welding all the connecting tubes, i.e. downcomers, risers,
pipes, saturated steam outlet. The function of steam drum internals is to separate the
water from the steam generated in the furnace walls and to reduce the dissolved solid
contents of the steam below the prescribed limit of 1 ppm and also take care of the
sudden change of steam demand for boiler.
The secondary stage of two opposite banks of closely spaced thin corrugated sheets,
which direct the steam and force the remaining entertained water against the
corrugated plates. Since the velocity is relatively low this water does not get picked
up again but runs down the plates and off the second stage of the two steam outlets.
From the secondary separators the steam flows upwards to the series of screen dryers,
extending in layers across the length of the drum. These screens perform the final
stage of the separation.
Once water inside the boiler or steam generator, the process of adding the latent heat
of vaporization or enthalpy is underway. The boiler transfers energy to the water by
the chemical reaction of burning some type of fuel.
The water enters the boiler through a section in the convection pass called the
economizer. From the economizer it passes to the steam drum. Once the water enters
the steam drum it goes down the down comers to the lower inlet water wall headers.
From the inlet headers the water rises through the water walls and is eventually turned
into steam due to the heat being generated by the burners located on the front and rear
water walls (typically). As the water is turned into steam/vapour in the water walls,
the steam/vapour once again enters the steam drum.
23
External View of an Industrial Boiler at BTPS, New Delhi
The steam/vapour is passed through a series of steam and water separators and then
dryers inside the steam drum. The steam separators and dryers remove the water
droplets from the steam and the cycle through the water walls is repeated. This
process is known as natural circulation.
The boiler furnace auxiliary equipment includes coal feed nozzles and igniter guns,
soot blowers, water lancing and observation ports (in the furnace walls) for
observation of the furnace interior. Furnace explosions due to any accumulation of
combustible gases after a tripout are avoided by flushing out such gases from the
combustion zone before igniting the coal.
The steam drum (as well as the superheater coils and headers) have air vents and
drains needed for initial start-up. The steam drum has an internal device that removes
moisture from the wet steam entering the drum from the steam generating tubes. The
dry steam then flows into the superheater coils. Geothermal plants need no boiler
since they use naturally occurring steam sources.
Heat exchangers may be used where the geothermal steam is very corrosive or
contains excessive suspended solids. Nuclear plants also boil water to raise steam,
either directly passing the working steam through the reactor or else using an
intermediate heat exchanger.
24
3. WATER WALLS
Water flows to the water walls from the boiler drum by natural circulation. The front
and the two side water walls constitute the main evaporation surface, absorbing the
bulk of radiant heat of the fuel burnt in the chamber. The front and rear walls are bent
at the lower ends to form a water-cooled slag hopper. The upper part of the chamber
is narrowed to achieve perfect mixing of combustion gases. The water wall tubes are
connected to headers at the top and bottom. The rear water wall tubes at the top are
grounded in four rows at a wider pitch forming g the grid tubes.
4. REHEATER
Reheater is used to raise the temperature of steam from which a part of energy has
been extracted in high–pressure turbine. This is another method of increasing the
cycle efficiency. Reheating requires additional equipment i.e. heating surface
connecting boiler and turbine pipe safety equipment like safety valve, non return
valves, isolating valves, high pressure feed pump, etc: Reheater is composed of two
sections namely the front and the rear pendant section, which is located above the
furnace arc between water-cooled, screen wall tubes and rear wall tubes.
Tubes of a reheater
5. SUPERHEATER
Whatever type of boiler is used, steam will leave the water at its surface and pass into
the steam space. Steam formed above the water surface in a shell boiler is always
saturated and become superheated in the boiler shell, as it is constantly. If superheated
steam is required, the saturated steam must pass through a superheater. This is simply
a heat exchanger where additional heat is added to the steam.
25
In water-tube boilers, the superheater may be an additional pendant suspended in the
furnace area where the hot gases will provide the degree of superheat required. In
other cases, for example in CHP schemes where the gas turbine exhaust gases are
relatively cool, a separately fired superheater may be needed to provide the additional
heat.
6. ECONOMIZER
The function of an economizer in a steam-generating unit is to absorb heat from the
flue gases and add as a sensible heat to the feed water before the water enters the
evaporation circuit of the boiler.
Earlier economizer were introduced mainly to recover the heat available in the flue
gases that leaves the boiler and provision of this addition heating surface increases the
efficiency of steam generators. In the modern boilers used for power generation feed
water heaters were used to increase the efficiency of turbine unit and feed water
temperature.
An economizer
Use of economizer or air heater or both is decided by the total economy that will
result in flexibility in operation, maintenance and selection of firing system and other
related equipment. Modern medium and high capacity boilers are used both as
economizers and air heaters. In low capacity, air heaters may alone be selected.
26
Stop valves and non-return valves may be incorporated to keep circulation in
economizer into steam drum when there is fire in the furnace but not feed flow. Tube
elements composing the unit are built up into banks and these are connected to inlet
and outlet headers.
7. AIR PREHEATER
Air preheater absorbs waste heat from the flue gases and transfers this heat to
incoming cold air, by means of continuously rotating heat transfer element of
specially formed metal plates. Thousands of these high efficiency elements are spaced
and compactly arranged within 12 sections. Sloped compartments of a radially
divided cylindrical shell called the rotor. The housing surrounding the rotor is
provided with duct connecting both the ends and is adequately scaled by radial and
circumferential scaling.
An air preheater
Special sealing arrangements are provided in the provided in the air preheater to
prevent the leakage between the air and gas sides. Adjustable plates are also used to
help the sealing arrangements and prevent the leakage as expansion occurs. The air
preheater heating surface elements are provided with two types of cleaning devices,
soot blowers to clean normal devices and washing devices to clean the element when
soot blowing alone cannot keep the element clean.
27
8. PULVERIZER
A pulverizer is a mechanical device for the grinding of many types of materials. For
example, they are used to pulverize coal for combustion in the steam-generating
furnaces of the fossil fuel power plants.
A Pulverizer
Types of Pulverizer
28
An external view of a Coal Pulverizer
29
II. PLANT AUXILIARY MAINTENANCE
Theory of Circulation
Water must flow through the heat absorption surface of the boiler in order that it be
evaporated into steam. In drum type units (natural and controlled circulation), the water is
circulated from the drum through the generating circuits and then back to the drum where the
steam is separated and directed to the super heater. The water leaves the drum through the
down corners at a temperature slightly below the saturation temperature. The flow through
the furnace wall is at saturation temperature. Heat absorbed in water wall is latent heat of
vaporization creating a mixture of steam and water. The ratio of the weight of the water to the
weight of the steam in the mixture leaving the heat absorption surface is called circulation
ratio.
Water delivered to steam generator from feed water is at a temperature well below the
saturation value corresponding to that pressure. Entering first the economizer, it is heated to
about 30-40C below saturation temperature. From economizer the water enters the drum and
thus joins the circulation system. Water entering the drum flows through the down corner and
enters ring heater at the bottom. In the water walls, a part of the water is converted to steam
and the mixture flows back to the drum. In the drum, the steam is separated, and sent to
superheater for superheating and then sent to the high-pressure turbine. Remaining water
mixes with the incoming water from the economizer and the cycle is repeated.
As the pressure increases, the difference in density between water and steam reduces. Thus
the hydrostatic head available will not be able to overcome the frictional resistance for a flow
30
corresponding to the minimum requirement of cooling of water wall tubes. Therefore natural
circulation is limited to the boiler with drum operating pressure around 175 kg/ cm2.
The Hydraulic Ash handling system is used at the Badarpur Thermal Power Station.
The hydraulic system carried the ash with the flow of water with high velocity through a
channel and finally dumps into a sump. The hydraulic system is divided into a low velocity
31
and high velocity system. In the low velocity system the ash from the boilers falls into a
stream of water flowing into the sump. The ash is carried along with the water and they are
separated at the sump. In the high velocity system a jet of water is sprayed to quench the hot
ash. Two other jets force the ash into a trough in which they are washed away by the water
into the sump, where they are separated. The molten slag formed in the pulverized fuel
system can also be quenched and washed by using the high velocity system. The advantages
of this system are that its clean, large ash handling capacity, considerable distance can be
traversed, absence of working parts in contact with ash.
Fly ash is captured and removed from the flue gas by electrostatic precipitators or fabric bag
filters (or sometimes both) located at the outlet of the furnace and before the induced draft
fan. The fly ash is periodically removed from the collection hoppers below the precipitators
or bag filters. Generally, the fly ash is pneumatically transported to storage silos for
subsequent transport by trucks or railroad cars.
At the bottom of every boiler, a hopper has been provided for collection of the bottom ash
from the bottom of the furnace. This hopper is always filled with water to quench the ash and
clinkers falling down from the furnace. Some arrangement is included to crush the clinkers
and for conveying the crushed clinkers and bottom ash to a storage site.
As the types of boiler are not alike their working pressure and operating conditions vary and
so do the types and methods of water treatment. Water treatment plants used in thermal
power plants used in thermal power plants are designed to process the raw water to water
with a very low content of dissolved solids known as ‘demineralized water’. No doubt, this
plant has to be engineered very carefully keeping in view the type of raw water to the thermal
plant, its treatment costs and overall economics.
32
A water treatment plant
The type of demineralization process chosen for a power station depends on three main
factors:
Pretreatment section.
Demineralization section
Pretreatment Section
Pretreatment plant removes the suspended solids such as clay, silt, organic and inorganic
matter, plants and other microscopic organism. The turbidity may be taken as two types of
suspended solid in water; firstly, the separable solids and secondly the non-separable solids
(colloids). The coarse components, such as sand, silt, etc: can be removed from the water by
simple sedimentation. Finer particles, however, will not settle in any reasonable time and
must be flocculated to produce the large particles, which are settle able. Long term ability to
remain suspended in water is basically a function of both size and specific gravity.
33
Demineralization
This filter water is now used for demineralizing purpose and is fed to cation exchanger bed,
but enroute being first dechlorinated, which is either done by passing through activated
carbon filter or injecting along the flow of water, an equivalent amount of sodium sulphite
through some stroke pumps. The residual chlorine, which is maintained in clarification plant
to remove organic matter from raw water, is now detrimental to action resin and must be
eliminated before its entry to this bed.
A demineralization tank
A DM plant generally consists of cation, anion and mixed bed exchangers. The final water
from this process consists essentially of hydrogen ions and hydroxide ions which is the
chemical composition of pure water. The DM water, being very pure, becomes highly
corrosive once it absorbs oxygen from the atmosphere because of its very high affinity for
oxygen absorption. The capacity of the DM plant is dictated by the type and quantity of salts
in the raw water input. However, some storage is essential as the DM plant may be down for
maintenance. For this purpose, a storage tank is installed from which DM water is
continuously withdrawn for boiler make-up. The storage tank for DM water is made from
materials not affected by corrosive water, such as PVC. The piping and valves are generally
of stainless steel. Sometimes, a steam blanketing arrangement or stainless steel doughnut
float is provided on top of the water in the tank to avoid contact with atmospheric air. DM
34
water make-up is generally added at the steam space of the surface condenser (i.e., the
vacuum side). This arrangement not only sprays the water but also DM water gets deaerated,
with the dissolved gases being removed by the ejector of the condenser itself.
4. DRAUGHT SYSTEM
i. Natural Draught
ii. Induced Draught
iii. Forced Draught
iv. Balanced Draught
In natural draft units the pressure differentials are obtained have constructing tail chimneys so
that vacuum is created in the furnace. Due to small pressure difference, air is admitted into
the furnace.
In this system, the air is admitted to natural pressure difference and the flue gases are taken
out by means of Induced Draught (I.D.) fans and the furnace is maintained under vacuum.
35
An induced draught system
A set of forced draught (F.D.) fans is made use of for supplying air to the furnace and so the
furnace is pressurized. The flue gases are taken out due to the pressure difference between the
furnace and the atmosphere.
Here a set of Induced and Forced Draft Fans are utilized in maintaining a vacuum in the
furnace. Normally all the power stations utilize this draft system.
36
5. INDUSTRIAL FANS
ID Fan
The induced Draft Fans are generally of Axial-Impulse Type. Impeller nominal diameter is of
the order of 2500 mm. The fan consists of the following sub-assemblies:
Suction Chamber
Inlet Vane Control
Impeller
Outlet Guide Vane Assembly
An ID fan
FD Fan
The fan, normally of the same type as ID Fan, consists of the following components:
Silencer
Inlet Bend
Fan Housing
Impeller with blades and setting mechanism
An FD fan
37
The centrifugal and setting forces of the blades are taken up by the blade bearings. The blade
shafts are placed in combined radial and axial anti-friction bearings, which are sealed off to
the outside. The angle of incidence of the blades may be adjusted during operation. The
characteristic pressure volume curves of the fan may be changed in a large range without
essentially modifying the efficiency. The fan can then be easily adapted to changing
operating conditions.
The rotor is accommodated in cylindrical roller bearings and an inclined ball bearing at the
drive side absorbs the axial thrust.
Lubrication and cooling these bearings is assured by a combined oil level and circulating
lubrication system.
PA Fan if flange-mounted design, single stage suction, NDFV type, backward curved bladed
radial fan operating on the principle of energy transformation due to centrifugal forces. Some
amount of the velocity energy is converted to pressure energy in the spiral casing. The fan is
driven at a constant speed and varying the angle of the inlet vane control controls the flow.
The special feature of the fan is that is provided with inlet guide vane control with a positive
and precise link mechanism.
It is robust in construction for higher peripheral speed so as to have unit sizes. Fan can
develop high pressures at low and medium volumes and can handle hot-air laden with dust
particles.
38
6. COMPRESSOR HOUSE
Instrument air is required for operating various dampers, burner tilting, devices, diaphragm
valves, etc: in the 210 MW units. Station air meets the general requirement of the power
station such as light oil atomizing air, for cleaning filters and for various maintenance works.
The control air compressors and station air compressors have been housed separately with
separate receivers and supply headers and their tapping.
A compressor house
Control air compressors have been installed for supplying moisture free dry air required for
instrument used. The output from the compressors is fed to air receivers via return valves.
From the receiver air passed through the dryers to the main instrument airline, which runs
along with the boiler house and turbine house of 210 MW units. Adequate numbers of
tapping have been provided all over the area.
Air-Drying Unit
Air contains moisture which tends to condense, and causes trouble in operation of various
devices by compressed air. Therefore drying of air is accepted widely in case of instrument
air. Air drying unit consists of dual absorption towers with embedded heaters for reactivation.
The absorption towers are adequately filled with specially selected silica gel and activated
alumina while one tower is drying the air.
39
An air drying unit
The station air compressor is generally a slow speed horizontal double acting double stage
type and is arranged for belt drive. The cylinder heads and barrel are enclosed in a jacket,
whih extends around the valve also. The intercooler is provided between the low and high
pressure cylinder which cools the air between tag and collects the moisture that condenses.
Air from L.P. cylinder enters at one end of the intercooler and goes to the opposite end
wherefrom it is discharged to the high-pressure cylinder; cooling water flows through the nest
of the tubes and cools the air. A safety valve is set at rated pressure.
40
Two selector switches one with positions auto load/unload and another with positions auto
start/stop, non-stop have been provided on the control panel of the compressor. In auto start-
stop position, the compressor will start.
TURBINE CLASSIFICATION:
1. Impulse turbine:
In impulse turbine steam expands in fixed nozzles. The high velocity steam from
nozzles does work on moving blades, which causes the shaft to rotate. The essential
features of impulse turbine are that all pressure drops occur at nozzles and not on
blades.
2. Reaction turbine:
In this type of turbine pressure is reduced at both fixed and moving blades. Both
fixed and moving blades act like nozzles. Work done by the impulse effect of steam
due to reverse the direction of high velocity steam. The expansion of steam takes
place on moving blades.
41
COMPOUNDING:
Several problems occur if energy of steam is converted in single step and so compounding is
done. Following are the type of compounded turbine:
i. Velocity Compounded Turbine:
Like simple turbine it has only one set of nozzles and entire steam pressure drop
takes place there. The kinetic energy of steam fully on the nozzles is utilized in
moving blades. The role of fixed blades is to change the direction of steam jet and
too guide it.
ii. Pressure Compounded Turbine:
This is basically a number of single impulse turbines in series or on the same
shaft. The exhaust of first turbine enters the nozzles of next turbine. The total
pressure drop of steam does not tae on first nozzle ring but divided equally on all
of them.
iii. Pressure Velocity Compounded Turbine:
It is just the combination of the two compounding and has the advantages of
allowing bigger pressure drops in each stage and so fewer stages are necessary.
Here for given pressure drop the turbine will be shorter length but diameter will be
increased.
MAIN TURBINE:
The 210MW turbine is a cylinder tandem compounded type machine comprising of H.P. and
I.P and L.P cylinders. The H.P. turbine comprises of 12 stages the I.P turbine has 11 stages
and the L.P has four stages of double flow. The H.P and I.P. turbine rotor are rigidly
compounded and the I.P. and L.P rotor by lens type semi flexible coupling. All the 3 rotors
are aligned on five bearings of which the bearing number is combined with thrust bearing.
The main superheated steam branches off into two streams from the boiler and passes through
the emergency stop valve and control valve before entering the governing wheel chamber of
the H.P. Turbine. After expanding in the 12 stages in the H.P. turbine then steam is returned
in the boiler for reheating.
The reheated steam from boiler enters I.P. turbine via the interceptor valves and control
valves and after expanding enters the L.P stage via 2 numbers of cross over pipes.
In the L.P. stage the steam expands in axially opposed direction to counteract the thrust and
enters the condenser placed directly below the L.P. turbine. The cooling water flowing
42
through the condenser tubes condenses the steam and the condensate the collected in the hot
well of the condenser.
The condensate collected the pumped by means of 3x50% duty condensate pumps through
L.P heaters to deaerator from where the boiler feed pump delivers the water to the boiler
through H.P. heaters thus forming a closed cycle.
STEAM TURBINE
A steam turbine is a mechanical device that extracts thermal energy from pressurized steam
and converts it into useful mechanical work.
From a mechanical point of view, the turbine is ideal, because the propelling force is applied
directly to the rotating element of the machine and has not as in the reciprocating engine to be
transmitted through a system of connecting links, which are necessary to transform a
reciprocating motion into rotary motion. Hence since the steam turbine possesses for its
moving parts rotating elements only if the manufacture is good and the machine is correctly
designed, it ought to be free from out of balance forces.
If the load on a turbine is kept constant the torque developed at the coupling is also constant.
A generator at a steady load offers a constant torque. Therefore, a turbine is suitable for
driving a generator, particularly as they are both high-speed machines.
A further advantage of the turbine is the absence of internal lubrication. This means that the
exhaust steam is not contaminated with oil vapour and can be condensed and fed back to the
boilers without passing through the filters. It also means that turbine is considerable saving in
lubricating oil when compared with a reciprocating steam engine of equal power.
A final advantage of the steam turbine and a very important one is the fact that a turbine can
develop many time the power compared to a reciprocating engine whether steam or oil.
OPERATING PRINCIPLES
A steam turbines two main parts are the cylinder and the rotor. The cylinder (stator) is a steel
or cast iron housing usually divided at the horizontal centerline. Its halves are bolted together
for easy access. The cylinder contains fixed blades, vanes and nozzles that direct steam into
the moving blades carried by the rotor. Each fixed blade set is mounted in diaphragms located
in front of each disc on the rotor, or directly in the casing. A disc and diaphragm pair a
turbine stage. Steam turbines can have many stages. A rotor is a rotating shaft that carries the
moving blades on the outer edges of either discs or drums. The blades rotate as the rotor
43
revolves. The rotor of a large steam turbine consists of large, intermediate and low-pressure
sections.
In a multiple-stage turbine, steam at a high pressure and high temperature enters the first row
of fixed blades or nozzles through an inlet valve/valves. As the steam passes through the
fixed blades or nozzles, it expands and its velocity increases. The high velocity jet of stream
strikes the first set of moving blades. The kinetic energy of the steam changes into
mechanical energy, causing the shaft to rotate. The steam that enters the next set of fixed
blades strikes the next row of moving blades.
44
As the steam flows through the turbine, its pressure and temperature decreases while its
volume increases. The decrease in pressure and temperature occurs as the steam transmits
energy to the shaft and performs work. After passing through the last turbine stage, the steam
exhausts into the condenser or process steam system.
The kinetic energy of the steam changes into mechanical energy through the impact (impulse)
or reaction of the steam against the blades. An impulse turbine uses the impact force of the
steam jet on the blades to turn the shaft. Steam expands as it passes through thee nozzles,
where its pressure drops and its velocity increases. As the steam flows through the moving
blades, its pressure remains the same, but its velocity decreases. The steam does not expand
as it flows through the moving blades.
STEAM CYCLE
The thermal (steam) power plant uses a dual (vapor+liquid) phase cycle. It is a closed cycle
to enable the working fluid (water) to be used again and again. The cycle used is ‘Rankine
cycle’ modified to include superheating of steam, regenerative feed water heating and
reheating of steam.
MAIN TURBINE
The 210 MW turbine is a tandem compounded type machine comprising of H.P. and I.P.
cylinders. The H.P. turbines comprise of 12 stages, I.P. turbine has 11 stages and the L.P.
turbine has 4 stages of double flow.
45
The H.P. and I.P. turbine rotors are rigidly compounded and the L.P. motor by the lens type
semi flexible coupling. All the three rotors are aligned on five bearings of which the bearing
no. 2 is combined with the thrust bearing
The main superheated steam branches off into two streams from the boiler and passes through
the emergency stop valve and control valve before entering the governing wheel chamber of
the H.P. turbine. After expanding in the 12 stages in the H.P. turbine the steam is returned in
boiler for reheating.
The reheated steam for the boiler enters the I.P> turbine via the interceptor valves and control
valves and after expanding enters the L.P. turbine stage via 2 nos of cross-over pipes.
In the L.P. stage the steam expands in axially opposite direction to counteract the trust and
enters the condensers placed below the L.P. turbine. The cooling water flowing throughout
the condenser tubes condenses the steam and the condensate collected in the hot well of the
condenser.
The condensate collected is pumped by means of 3*50% duty condensate pumps through
L.P. heaters to deaerator from where the boiler feed pump delivers the water to boiler through
H.P. heaters thus forming a close cycle.
46
TURBINE CYCLE
Fresh steam from the boiler is supplied to the turbine through the emergency stop valve.
From the stop valves steam is supplied to control valves situated in H.P. cylinders on the
front bearing end. After expansion through 12 stages at the H.P. cylinder, steam flows back to
the boiler for reheating steam and reheated steam from the boiler cover to the intermediate
pressure turbine through two interceptor valves and four control valves mounted on I.P.
turbine.
After flowing through I.P. turbine steam enters the middle part of the L.P. turbine through
cross-over pipes. In L.P. turbine the exhaust steam condenses in the surface condensers
welded directly to the exhaust part of L.P. turbine.
The selection of extraction points and cold reheat pressure has been done with a view to
achieve a high efficiency. These are two extractors from H.P. turbine, four from I.P. turbine
and one from L.P. turbine. Steam at 1.10 and 1.03 g/sq. cm. Abs is supplied for the gland
sealing. Steam for this purpose is obtained from deaerator through a collection where
pressure of steam is regulated.
47
From the condenser, condensate is pumped with the help of 3*50% capacity condensate
pumps to deaerator through the low-pressure regenerative equipments.
Feed water is pumped from deaerator to the boiler through the H.P. heaters by means of
3*50% capacity feed pumps connected before the H.P. heaters.
TURBINE COMPONENTS
Casing.
Rotor.
Blades.
Sealing system.
Stop & control valves.
Couplings and bearings.
Barring gear.
48
TURBINE CASINGS
HP Turbine Casings:
Outer casing: a barrel-type without axial or radial flange.
Barrel-type casing suitable for quick startup and loading.
The inner casing- cylindrically, axially split.
The inner casing is attached in the horizontal and vertical planes in the barrel casing
so that it can freely expand radially in all the directions and axially from a fixed point
(HP- inlet side).
IP Turbine Casing:
The casing of the IP turbine is split horizontally and is of double-shell construction.
Both are axially split and a double flow inner casing is supported in the outer casing
and carries the guide blades.
Provides opposed double flow in the two blade sections and compensates axial thrust.
Steam after reheating enters the inner casing from Top & Bottom.
LP Turbine Casing:
The LP turbine casing consists of a double flow unit and has a triple shell welded
casing.
The shells are axially split and of rigid welded construction.
The inner shell taking the first rows of guide blades is attached kinematically in the
middle shell.
Independent of the outer shell, the middle shell, is supported at four points on
longitudinal beams.
Steam admitted to the LP turbine from the IP turbine flows into the inner casing from
both sides.
ROTORS
HP Rotor:
The HP rotor is machined from a single Cr-Mo-V steel forging with integral discs.
In all the moving wheels, balancing holes are machined to reduce the pressure
difference across them, which results in reduction of axial thrust.
49
First stage has integral shrouds while other rows have shroudings, riveted to the
blades are periphery.
IP Rotor:
The IP rotor has seven discs integrally forged with rotor while last four discs are
shrunk fit.
The shaft is made of high creep resisting Cr-Mo-V steel forging while the shrunk fit
discs are machined from high strength nickel steel forgings.
Except the last two wheels, all other wheels have shrouding riveted at the tip of the
blades. To adjust the frequency of thee moving blades, lashing wires have been
provided in some stages.
LP Rotor:
The LP rotor consists of shrunk fit discs in a shaft.
The shaft is a forging of Cr-Mo-V steel while the discs are of high strength nickel
steel forgings.
Blades are secured to the respective discs by riveted fork root fastening.
In all the stages lashing wires are provided to adjust the frequency of blades. In the
last two rows, satellite strips are provided at the leading edges of the blades to protect
them against wet-steam erosion.
BLADES
Most costly element of the turbine.
Blades fixed in stationary part are called guide blades/ nozzles and those fitted in
moving part are called rotating/working blades.
Blades have three main parts:
o Aerofoil: working part.
o Root.
o Shrouds.
Shroud are used to prevent steam leakage and guide steam to next set of moving
blades.
50
VACUUM SYSTEM
This comprises of:
Condenser: 2 for 200 MW unit at the exhaust of LP turbine.
Ejectors: One starting and two main ejectors connected to the condenser locared near
the turbine.
C.W. Pumps: Normally two per unit of 50% capacity.
CONDENSER
There are two condensers entered to the two exhausters of the L.P. turbine. These are surface-
type condensers with two pass arrangement. Cooling water pumped into each condenser by a
vertical C.W. pump through the inlet pipe.
Water enters the inlet chamber of the front water box, passes horizontally through brass tubes
to the water tubes to the water box at the other end, takes a turn, passes through the upper
cluster of tubes and reaches the outlet chamber in the front water box. From these, cooling
water leaves the condenser through the outlet pipe and discharge into the discharge duct.
Steam exhausted from the LP turbine washes the outside of the condenser tubes, losing its
latent heat to the cooling water and is connected with water in the steam side of the
condenser. This condensate collects in the hot well, welded to the bottom of the condensers.
51
EJECTORS
There are two 100% capacity ejectors of the steam eject type. The purpose of the ejector is to
evacuate air and other non-condensating gases from the condensers and thus maintain the
vacuum in the condensers.
The ejector has three compartments. Steam is supplied generally at a pressure of 4.5 to 5
kg /cm2 to the three nozzles in the three compartments. Steam expands in the nozzle thus
giving a high-velocity eject which creates a low-pressure zone in the throat of the eject. Since
the nozzle box of the ejector is connected to the air pipe from the condenser, the air and
pressure zone. The working steam which has expanded in volume comes into contact with the
cluster of tube bundles through which condensate is flowing and gets condensed thus after
aiding the formation of vacuum. The non-condensing gases of air are further sucked with the
next stage of the ejector by the second nozzle. The process repeats itself in the third stage also
and finally the steam-air mixture is exhausted into the atmosphere through the outlet.
CONDENSATE SYSTEM
This contains the following
i. Condensate Pumps: 3 per unit of 50% capacity each located near condenser hot well.
ii. LP Heater: Normally 4 in number with no.1 located at the upper part of the
condenser and nos. 2,3 & 4 around 4m level.
iii. Deaerator; one per unit located around 181 M’ level in CD bay.
Condensate Pumps
The function of these pumps is to pump out the condensate to the desecrator through ejectors,
gland steam cooler and LP heaters. These pumps have four stages and since the suction is at a
negative pressure, special arrangements have been made for providing sealing. The pump is
generally rated for 160 m3/ hr at a pressure of 13.2 kg/ cm2 .
L.P. Heaters
Turbine has been provided with non-controlled extractions, which are utilized for heating the
condensate, from turbine bleed steam. There are 410 W pressure heaters in which the last
four extractions are used. L.P. Heater-1 has two parts LPH-1A and LPH-1B located in the
upper parts of the condenser A and condenser B, respectively. These are of horizontal type
with shell and tube construction. L.P.H. 2,3 and 4 are of similar construction and they are
52
mounted in a row of 5m level. They are of vertical construction with brass tubes the ends of
which are expanded into tube plate. The condensate flows in the ‘U’ tubes in four passes and
extraction steam washes the outside of the tubes. Condensate passes through these four L.P.
heaters in succession. These heaters are equipped with necessary safety valves in the steam
space level indicator for visual level indication of heating steam condensate pressure vacuum
gauges for measurement of steam pressure, etc:
Deaerator
The presence of certain gases, principally oxygen, carbon dioxide and ammonia, dissolved in
water is generally considered harmful because of their corrosive attack on metals, particularly
at elevated temperatures. One of the most important factors in the prevention of internal
corrosion in modern boilers and associated plant therefore, is that the boiler feed water should
be free as far as possible from all dissolved gases especially oxygen. This is achieved by
embodying into the boiler feed system a deaerating unit, whose function is to remove the
dissolved gases from the feed water by mechanical means. Particularly the unit must reduce
the oxygen content of the feed water to a lower value as far as possible, depending upon the
individual circumstances. Residual oxygen content in condensate at the outlet of deaerating
plant usually specified are 0.005/ litre or less.
A Deaerator
53
PRINCIPAL OF DEAERATION
It is based on following two laws.
Henry’s Law
Solubility
The Deaerator comprises of two chambers:
Deaerating column
Feed storage tank
Deaerating column is a spray cum tray type cylindrical vessel of horizontal construction
with dished ends welded to it. The tray stack is designed to ensure maximum contact time as
well as optimum scrubbing of condensate to achieve efficient deaeration. The deaeration
column is mounted on the feed storage tank, which in turn is supported on rollers at the two
ends and a fixed support at the centre. The feed storage tank is fabricated from boiler quality
steel plates. Manholes are provided on deaerating column as well as on feed storage tank for
inspection and maintenance.
The condensate is admitted at the top of the deaerating column flows downwards through the
spray valves and trays. The trays are designed to expose to the maximum water surfaces for
efficient scrubbing to affect the liberation of the associated gases steam enters from the
underneath of the trays and flows in counter direction of condensate. While flowing upwards
through the trays, scrubbing and heating is done. Thus the liberated gases move upwards
alongwith the steam. Steam gets condensed above the trays and in turn heats the condensate.
Liberated gases escapes to atmosphere from the orifice opening meant for it. This opening is
provided with a number of dlflectors to minimize the loss of steam.
54
Boiler Feed Pump
This pump is horizontal and of barrel design driven by an Electric Motor through a hydraulic
coupling. All the bearings of pump and motor are forced lubricated by a suitable oil
lubricating system with adequate protection to trip the pump if the lubrication oil pressure
falls below a preset value.
The high pressure boiler feed pump is a very expensive machine which calls for a very
careful operation and skilled maintenance. Operating staff must be able to find out the causes
of defect at the very beginning, which can be easily removed without endangering the
operator of the power plant and also without the expensive dismantling of the high pressure
feed pump.
Function
The water with the given operating temperature should flow continuously to the pump under
a certain minimum pressure. It passes through the suction branch into the intake spiral and
from there; it is directed to the first impeller. After leaving the impeller it passes through the
distributing passages of the diffuser and thereby gets a certain pressure rise and at the same
time it flows over to the guide vanes to the inlet of the next impeller. This will repeat from
one stage to the other till it passes through the last impeller and the end diffuser. Thus the
feed water reaching into the discharge space develops the necessary operating pressure.
Booster Pump
Each boiler feed pump is provided with a booster pump in its suction line which is driven by
the main motor of the boiler feed pump. One of the major damages which may occur to a
boiler feed pump is from cavitation or vapor bounding at the pump suction due to suction
failure. Cavitation will occur when the suction pressure of the pump at the pump section is
equal or very near to the vapor pressure of the liquid to be pumped at a particular feed water
temperature. By the use of booster pump in the main pump suction line, always there will be
positive suction pressure which will remove the possibility of cavitation. Therefore all the
feed pumps are provided with a main shaft driven booster pump in its suction line for
obtaining a definite positive suction pressure.
55
Lubricating Pressure
All the bearings of boiler feed pump, pump motor and hydraulic coupling are force
lubricated. The feed pump consists of two radial sleeve bearings and one thrust bearing. The
thrust bearing is located at the free end of the pump.
An HP heater
56
IV. MAINTENANCE PLANNING DEPARTMENT
PREDICTIVE MAINTENANCE
The art of predictive maintenance is to monitor the machine with the appropriate
technologies, frequently enough to detect the anticipated failure modes.
Increased uptime
Decreased unexpected breakdowns
Reduced Maintenance Costs
Maintenance is performed and it is planned
Improved Plant Safety
The sign may be change in sound level, vibration, pressure, temperature etc.
Change in the performance
Metal particles in the lubricant
Change in motor current etc.
PROACTIVE MAINTENANCE
Also known by different names including “Precision Maintenance” and “Reliability based
Maintenance”. The motto here is “Fix it once & Fix it Right”
57
KNOWLEDGE BASED MAINTENANCE
TECHNOLOGIES USED
58
Hardening of Joints of rotor bars and end ring
THERMOGRAPHY
IRT camera has been very useful tools in predictive maintenance for detecting hot
spots in electrical & switchyard equipment.
The thermal scanning survey in switchyard & other identified areas is done to monitor
the healthiness of electrical equipment.
ACCOUSTIC ANALYSIS
59
V. COAL HANDLING DEPARTMENT
As coal is the prime fuel for thermal power plant, adequate emphasis should be given for its
proper handling and storage. Also it is equally important to have a sustained flow of this fuel
to maintain uninterrupted power generation. Coal is used as the fuel because of the following
advantages.
Advantages of coal as fuel:
Abundantly available in India
Low Cost
Technology for power generation well developed.
Easy to handle, transport, store and use.
60
COAL CYCLE
61
Simple loading arrangement at a single point avoids the need for a big marshalling
yard with cumbersome operational system.
The high speed load outstation consists of one or two loading sites depending upon the coal
requirement of the linked power station. The handling capacity of the loading site is such that
it fills at least one big rake of wagon and in some cases, two rakes.
Coal transportation
62
The Coal Handling System
The storage facilities at the stockyards have been provided only for crushed coal. The coal
handling system is designed to provide 100% standby for all equipments and conveyors.
The 200 mm coal as received at the track hopper is fed to the crusher house for crushing.
Crusher of 50% capacity is provided and these are preferred to two crushers of 100%
capacity because of increased reliability and possible higher availability. A series of parallel
conveyors are designed thereafter to carry crushed coal directly to the boiler bunkers or to
divert it to the stockyard.
To feed coal into bunkers, mobile trippers have been provided over bunkers on conveyors,
coal mil & therefore the bunker conveyors of 200 MW units of the earlier projects are
provided between boiler and turbo-generator building. However for better mill maintenance,
accessibility, and to reduce coal dust nuisance; the turbine plant area, coal mills, bunker
conveyors are now being placed between boiler and electrostatic precipitator.
63
Coal Handling Division of BTPS, New Delhi
i. Pulley
They are made of mild steel. Rubber lagging is provided to decrease the friction factor
in between the belt and pulley.
ii. Scrapper
Conveyors are provided with scrappers at the discharge pulley in order to clean the
carrying side of the belt built up material on idler rolls. Care should be taken to ensure
that the scrapper is held against the belt with the pressure sufficient to remove
material without causing damage to the belt due to excessive force exerted by the
wiper.the following categories of scrapper are common in use:
Steel blade scrapper
Rubber/fabric blade scrapper
Nylon brush scrapper
Compressed air blast scrapper.
64
iii. Idlers
These essentially consist of rolls made out of seamless steel tube enclosed fully at
each end and fitted with stationary shaft, anti-friction bearings and seals. They support
the belt and enable it to travel freely without much frictional losses and also keep the
belt properly trained.
Idler
iv. Conveyor Belt
The conveyor belt consists of layers or piles of fabric duck, impregnated with rubber
and protected by a rubber cover on both sides and edges. The fabric duck supplies the
strngth to withstand the tension created in carrying the load while the cover protects
the fabric carcass. Heat resistant belting is always recommended for handling
materials at a temperature over 66C.
65
Coal Storage Area of the Badarpur Thermal Power Station, New Delhi
v. Vibrating Screen
The function of vibrating screen is to send the coal of having size less than 20 mm to
the crusher. The screen is operated by four v-belts connected to motor.
vi. Crusher
The role of crusher is to crush the coal from 200 mm to 20 mm size of coal received
from the vibrating screen. This is accomplished by means of granulators of ring type.
There are about 37 crushing elevations; each elevation has 4 granulators-2 of plain
type and 2 of tooth type, arranged alternately.
The granulators are made of manganese steel because of their work hardening
property. The coal enters the top of the crusher and is crushed between rotating
granulators and fluid case path. The crushed coal through a chute falls on belt feeder.
Normally these crushers have a capacity round 600 tonnes/ hr.
66
A Crusher
vii. Magnetic separators
This is an electromagnet placed above the conveyor to attract magnetic materials.
Over this magnet there is one conveyor to transfer these materials to chute provided
for dumping at ground level. Because of this, continuous removal is possible. It can
remove any ferrous impurity from 10 gms to 50 kg.
67
viii. Vibrating Feeder
It is used to feed the coal on the underground conveyor belt from where coal goes to
bunker. Coal from the stockyard with the help of bulldozer is taken to the vibrating
feeder via reclaim hopper and underground conveyor belts. A tripper is provided in
the conveyor to stack the material at desired location on either side or along the
conveyor with the help of chute or chute fitted with the tripper itself. The tripper is
provided with wheels, which move on rails parallel to conveyor.
These trippers are of three types mainly:
Motorized tripper
Bell-Propelled Manually operated Tripper.
Winch driven tripper
68