Vous êtes sur la page 1sur 2

MANUELA CORPORATION

IN HOUSE ESTIMATE
Building Administration Department

RENOVATION OF APARTELLE 18

OPTION 1- Includes total re-tiling from ground to 3rd floor(job out) OPTION 2 -Retained existing flooring at 2nd and 3rd floor(in-house)

ITEM DESCRIPTION QUANTITY UNIT AMOUNT QUANTITY UNIT AMOUNT REMARKS

m^2 /GAL pesos/m^2 pesos m^2 pesos/m^2 pesos

GROUND FLOOR
Preparation and Chipping works for tiles installation (ground
1 floor) 45 800.00 36,000.00 45 650.00 29,250.00

.40 x .40 Homogenous tiles 45 45

2 Painting works for ceiling , walls and column (grd floor) 18 800.00 14,400.00 18 550.00 9,900.00

3 Lightings 3 1,000.00 3 1,000.00

Sub total 50,400.00 39,150.00

SECOND FLOOR
Preparation and Chipping works for tiles installation (2nd
1 floor) 73 800.00 58,400.00 73 160.00 11,680.00 USING RUBBERIZED PAINT
.40 x .40 Homogenous tiles 73 73
Painting works for ceiling, walls, column , doors and cabinets
2 (2nd floor) 20 800.00 16,000.00 20 550.00 11,000.00

3 Lightings 6 1,000.00 6 1,000.00

Sub total 74,400.00 22,680.00

THIRD FLOOR

1 Preparation and Chipping works for tiles (ground floor) 85 800.00 68,000.00 85 160.00 13,600.00 USING RUBBERIZED PAINT
.40 x .40 Homogenous tiles 85 85
Painting works for ceiling ,walls,column and cabinets(3rd
2 floor) 24 800.00 19,200.00 24 550.00 13,200.00

3 Lightings 8 1,000.00 8,000.00 8 1,000.00

Sub total 95,200.00 26,800.00

OTHERS

Other materials needed : wires, c.o. plastic moulding, door knobs


and other consumables lot 10,000.00 10,000.00 lot 10,000.00 10,000.00

NOTES/OPTIONS:
- AIRCON IS NOT INCLUDED

OPTIONS:
- REPAINTING OF 2ND &3RD FLOORING IS ALSO AN ALTERNATIVE

FOR TOTAL IMPROVEMENT INSTEAD OF RE-TILING

- FLOORING PAINTING WORKS (2ND&3RD FLR) = 25,280 PESOS


- TILING WORKS (2ND&3RD) ,option 1 = 126, 400 PESOS

- USING VINLY TILES FROM GROUND TO 3RD FLOOR = 95,420 PESOS


TOTAL ESTIMATED COST ### 98,630.00