Vous êtes sur la page 1sur 10

ARTICLE IN PRESS

Marine Policy 27 (2003) 339–348

International rules on decommissioning of offshore


installations: some observations
B.A. Hamzah*
26 Jalan 2/2, Taman TAR, Ampang, Selangor 68000, Malaysia

Abstract

This paper, which is concerned mainly with international law and practice on the decommissioning of offshore installations,
examines the various global and regional instruments, which attempt to regulate decommissioning. In considering the way forward,
particularly for Third World countries, it is concluded that there is a need for oil-producing countries to enact comprehensive
national legislation on this subject.
r 2003 Published by Elsevier Science Ltd.

Keywords: Abandonment; Decommissioning; International Environmental Law; Offshore installations

1. What is decommissioning? and it is more inclusive than the term abandonment


found in many treaties dealing with offshore installa-
One of the difficulties in dealing with offshore tions. Both terms were often used interchangeably
platform decommissioning is the absence of a definitive before the Brent Spar incident.
legal definition of what constitutes decommissioning. The process of decommissioning usually takes place
Indeed the word ‘‘decommissioning’’ is not even found after the offshore platform (in this case oil and gas
in major international legal documents on offshore platform) has been abandoned or ceased to be
platform decommissioning. productive or operative. When production of gas or
The term decommissioning does not appear in the oil from a field becomes uneconomical, a decision may
1958 Geneva Convention on the Continental Shelf; it is be made by the relevant regulatory agencies in conjunc-
missing from the 1982 United Nations Convention on tion with the operator of the platform to cease
Law of Sea (UNCLOS); it is also not defined in the 1989 production, abandon the field and decommission the
International Maritime Organization (IMO) Guidelines infrastructure. In Europe oil companies are legally
and Standards [1]. Nor is it defined in the 1992 required to submit to the Government, a decommission-
Convention for the Protection of the Marine Environ- ing plan, a few years (2–5, depending on countries)
ment of the North-East Atlantic (OSPAR) [2] and other before platform operations cease.
regional treaties that deal with marine pollution. In practice, decommissioning and abandonment tend
Although not defined, all the above-mentioned interna- to describe the same process. The process to initiate
tional treaties mention the need to abandon offshore platform decommissioning is usually undertaken by the
platforms no longer in use. operator of an oil or natural gas installation, often in
Evidently, the word decommissioning in respect of consultation with the regulatory agencies .The decision
offshore installations has a recent origin. It became a to decommission or not is usually the prerogative of the
concern to the international oil industry following the Government as in Europe and in the United States. In
1995 Brent Spar controversy; before that incident many the United Kingdom, the process includes plan, gain
would refer to the concept of removing an abandoned approval for and implement the approval from the
offshore platform as ‘abandonment’. As a concept, Department of Trade and Industry (DTI). Disposal or
decommissioning has a more comprehensive application reuse of an installation when it is no longer needed or
has ceased to produce oil or gas, as well as site
*Tel.: +603-4256-9528. rehabilitation are treated as part of the decommissioning
E-mail address: bahamzah@pd.jaring.my (B.A. Hamzah). process in the UK.

0308-597X/03/$ - see front matter r 2003 Published by Elsevier Science Ltd.


doi:10.1016/S0308-597X(03)00040-X
ARTICLE IN PRESS
340 B.A. Hamzah / Marine Policy 27 (2003) 339–348

Among the legal community, the term abandonment mainly for the purpose of environmental assessment:
is widely used. The 1958 Geneva Convention on the cold phase, removal and disposal. Whatever it is, the
Continental Shelf, the 1982 UNCLOS, the 1989 IMO purpose of the decommissioning is to ensure a balanced
Guidelines, and the 1992 OSPAR refer to abandonment and complete process.
as the process of dismantling and disposal of the unused For ease of understanding, the implementation
platform. process can be further divided into three practical
According to AM Forte, the confusion is an phases:
‘‘unfortunate choice’’, and the word ‘‘decommissioning’’ * A first phase consists of rendering the redundant
is a preferable term to describe the process and
structure hydrocarbon and chemical free by, where
procedures associated with disposal of installations, as
appropriate, abandoning the wells, removing con-
well as site rehabilitation after they are no longer
ductors/risers, flushing and cleaning the process/
needed [3].
utility systems, ensuring all the vessels and pipe work
In the UK, Norway and Holland, an environmental
are gas and oil free and preparing the components for
impact assessment (EIA) is mandatory before an
the lifting/removal operations.
abandoned platform is decommissioned. The EIA is a * A second phase involves the deconstruction and
process for anticipating the effects on the environment
removal of the installation and associated compo-
caused by a development. The objective of the EIA is to
nents.
incorporate environmental considerations into the * A third phase involves site restoration and regular
project planning and design stages, to ensure best
monitoring and inspection of the site.
environmental practice is followed. The EIA process
also provides for an early airing of the concerns of The scope of decommissioning will depend on the
stakeholders, which must be adequately addressed. type of installation and what options are foreseen for the
Through an EIA it is possible to ensure that planned redundant installation, or whether deferral of final
activities are in line with company policy and legislative decommissioning is possible. Anyhow, irrespective of
requirements. the option for decommissioning, the licensee or operator
The process of decommissioning an installation is must submit well in advance a decommissioning plan to
long and tedious. Getting the approval from the relevant the relevant authorities once a decision has been made
authority for every step of the operation can be quite a to abandon a platform. The operator must furnish
challenge. In the UK the process can take between 3 and adequate information, which has to include the neces-
6 years; but in countries where the legal framework and sary, technical, safety, environmental, fishing, naviga-
technical experience is still undeveloped, the process tion and financial information to the authorities. In the
may take much longer. UK it is the Government through the DTI that has a
In the UK, the procedure for platform decommission- final say on platform decommissioning, often in
ing is spelt out in detail in The Guidelines Notes for consultation with all the stakeholders as well as the
Industry: Decommissioning of Offshore Installations operator.
and Pipelines under the Petroleum Act 1988 [4]. There seems to be a fine line between decommission-
The DTI’s Offshore Decommissioning Unit in ing and dumping. According to the London Dumping
Aberdeen is responsible for coordinating the considera- Convention, 1972 [5] dumping is defined as any
tion and approval of decommissioning programmes for deliberate disposal at sea of wastes or other matter
installations and pipelines in the UK. The Unit acts as a from vessels, aircraft, platforms or other man made
one-stop-shop whenever possible and will consult with structures at sea. It also includes the deliberate disposal
the other Government Departments and Agencies which at sea of vessels, aircraft, platforms or other man-made
have an interest in the consideration of decommission- structures at sea. The 1996 Protocol to the London
ing proposals. There may, however, be occasions when Dumping Convention [6] expanded the definition of
the DTI will ask the Operator to make direct contact dumping to include any storage of wastes or other matter
with a particular Government Department, for example, in the seabed and the subsoil thereof from vessels, aircraft,
with the Ministry of Agriculture, Fisheries and Food platforms or other man-made structures at sea; and any
(MAFF) on an aspect which may have specific implica- abandonment or toppling at site of platforms or other
tions for fisheries. man-made structures, for the sole purpose of deliberate
The decommissioning process differs between coun- disposal. The 1996 Protocol, however, is more flexible. It
tries and does not necessarily follow the phases adopted allows for the disposal of platforms and man-made
by the UK’s DTI. For example, the proposed PETRO- structures at sea so long as licensed by the national
NAS PMU Guidelines (Malaysia) have identified four authorities.
phases: pre-decommissioning, implementation, post de- Article 5 of Annex III of OSPAR equates the whole or
commissioning and field review. Another approach is to partial non-removal of disused offshore installations to
divide the decommissioning process into three phases dumping, tolerated only if a permit has been issued by
ARTICLE IN PRESS
B.A. Hamzah / Marine Policy 27 (2003) 339–348 341

the competent national authorities, again on a-case-by- disposal has been implemented in accordance with the
case basis. Indeed, this policy becomes the corner stone terms of the decommissioning programmes.
for OSPAR. Similarly, the Baltic Convention [7], Reg. 8 What became very obvious in the UK decommission-
of Annex V1 on the prevention of pollution from ing experience was the need for transparency in
offshore activities, obliges the contracting parties to balancing stakeholders’ interest and that nothing should
ensure that all abandoned offshore units are essentially be taken for granted. In the case of the Brent Spar, the
removed and brought ashore under the responsibility of failure to deal effectively with pressure from the
the owner. Anything left behind (i.e., partial removal) Greenpeace movement had significant financial conse-
would be considered dumping. quences for Royal Dutch Shell. The company’s initial
Based on the practice in the UK, in evolving a policy estimates to decommission the Brent Spar was only 10
on platform decommissioning, Third World oil-produ- million pounds sterling; but by the time the floating
cing countries can benefit from the following conclu- storage facility was finally decommissioned in 1995 it
sions: cost Shell 60 million pounds sterling. Although the
Firstly, the Government, in this case the DTI, plays company recouped its reputation, as Greenpeace did
an important role in regulating and facilitating the admit it went overboard with its scientific calculations,
process of platform decommissioning undertaken by the the damage had been done.
operator. The Government enacts the relevant legisla-
tion and maintains close liaison with the external parties
and monitors the entire process. In the UK the 2. Issues
Government provides tax breaks to the operator. In
Norway, the Government pays the oil operator for Worldwide, there are close to 7000 oil and gas
undertaking the decommissioning activities. installations/platforms; some 4000 in the Gulf of
Secondly, the process for decommissioning is long Mexico, and over 1000 in South East Asian waters.
and tedious. Each platform is unique and no generic The rest are off Japan, Europe, Latin America and the
solution applies. The options for disposal have to be Middle East. Many of them have been in service for
carefully analysed and they should be as transparent as more than 15 years; some are over 20 years old. Many
possible for the stakeholders to support. In the case of have been abandoned, waiting to be decommissioned.
the Brent Spar, the Greenpeace movement was able to One can imagine the amount of steel structure and
mobilize support from the civil society against deep sea concrete to be removed from the bottom of the sea,
dumping although Royal Dutch Shell had received the some permitted to be left in situ.
blessing of the UK Government to dispose of the Brent Of course, it costs money to decommission an
Spar in the deeper part of the North Sea, as it was safe installation. As an example, as has been seen, in 1995
to the environment and shipping. It was not a question it cost Shell sixty million pounds sterling to decommis-
of failure in planning or technical incompetence, but it sion the Brent Spar. The total cost to remove all
was a failure of misjudgement on the part of Shell to offshore installations in the North Sea alone would be
underestimate the pressure from Greenpeace. colossal. The cost to remove all the offshore installations
In the DTI Guidelines, due mention is made of the in the world, which potentially will be abandoned as the
need to comply with international agreements and fields mature, can only be imagined.
obligations, consultation with the stakeholders, as well In Malaysia alone a study has conservatively esti-
as the need to effectively monitor the various phases in mated it will cost PETRONAS, the national oil
the decommissioning process. While the onus is on the company, some 8 billion Malaysian ringgit (approxi-
operator to undertake the task, a suitable monitoring mately US$2 billion) to remove some two hundred plus
regime must be in place and specified in the decom- installations in offshore Malaysia [8].
missioning programme. A legal framework to govern every aspect of platform
The DTI requires that the operator submit in- decommissioning has been put into place in Europe
spection reports on a regular basis, including proposals through various treaty mechanisms. The two most
for any maintenance and remedial work that may important treaties dealing with platform decommission-
be required. The reports should also be published ing are the Convention for the Prevention of Marine
by appropriate means. In the case of the UK, Pollution by Dumping from Ships and Aircraft, 1972
OSPAR requires that the operator submit a satisfactory (the Oslo Convention) [9] and the OSPAR Convention
EIA and monitoring regime before permission for which, upon its entry into force in 1998, largely replaced
decommissioning could be given. The DTI also the Oslo Convention. These regional treaties were
requires that a post-disposal report is submitted intended to complement the international treaties on
indicating how the disposal operation was carried marine environment, most prominently the 1972 Lon-
out, any immediate consequences of the disposal don Convention on the Prevention of Marine Pollution
that have been observed and confirmation that the by Dumping of Wastes and other Matters and its 1996
ARTICLE IN PRESS
342 B.A. Hamzah / Marine Policy 27 (2003) 339–348

Protocols, as well as the International Convention for operators/contractors, the ownership of about-to-be
the Prevention of Pollution from Ships, 1973, as decommissioned structures was conveniently transferred
modified by the Protocol of 1978 [10] (MARPOL 73/ to the state Oil Company or to the host government.
78). But such a legal framework is still absent in Third The oil operators can no longer be held responsible for
World countries; not a single oil producing state in the any decommissioning work after the ownership of the
Third World has comprehensive national legislation on platforms changes hands.
platform abandonment. It is a well-established practice that oil companies
The current interest in decommissioning preceded the operating in Third World countries are reluctant to
controversial Brent Spar. There are at least four primary dismantle and dispose of disused platforms they had
reasons rekindling interest in this topic. Firstly, the installed. To overcome this discrepancy many oil-
maturing of a large number of offshore oil and gas fields producing countries (e.g. Malaysia and Indonesia) in
worldwide has raised the question of accountability, the Third World are now considering legislation to
third party liability and good practices in the oil provide for a platform abandonment regime. Such a
industry. Secondly, the issue of cost became an legal regime would of course incorporate a variety of
important concern to both the oil industry and oil- legal rules under international law, national law and, of
producing states. The cost of removing and disposing of course, contract law.
all the unused platforms is expected to be high. For more than a decade now the oil and gas industry
Removing the large structures in the deep sea can be has been aware of a problem looming on the horizon:
costly. The question of who should bear the cost of how to manage the costs of decommissioning the
platform decommissioning became a hot topic in thousands of offshore oil and gas platforms all over
Europe and elsewhere. Thirdly, accompanying the the world? Within the last decade or so there has been a
unfinished debate of who should pay to remove the heightened concern over environmental issues with the
unused platforms was the growing global concern for a industry being the target for those concerned about
more responsible marine environment management greenhouse gas emissions. The need to be extra cautious
regime. Coastal states came under pressure to adopt a with issues relating to ocean governance, in particular,
more responsible approach to ocean governance, the role of the industry in managing the fragile marine
including taking steps to remove unused offshore environment, has made ocean dumping an awkwardly
platforms. Fourthly, concern for the freedom of sensitive issue. At the same time, knowledge of
navigation and, its corollary navigational safety has economic, legal as well technical aspects of platform
inspired the IMO to develop guidelines on removal of decommissioning has grown considerably over the
offshore platforms. years, with the industry gaining invaluable experience
For the above reasons and, no doubt, for other from their decommissioning projects in the shallow Gulf
reasons too, a consensus of opinion emerged by the of Mexico waters and in the deeper depths of the North
middle of 1980s on the need to establish a legal Sea.
framework to deal with this topic. With the introduction Many oil-producing developed states have specific
of basic international standards on the continental shelf, laws and legislation dealing with platform decommis-
some coastal states have demanded more teeth in sioning. In these countries, the legal framework is drawn
dealing with this matter. National legislation to deal up by the relevant Government agencies in consultation
with platform decommissioning was introduced as in the with the oil industry. The legal framework would define
UK and USA. clearly the scope of functions and responsibility for the
The earlier legislation in most Third World countries removal as well as disposal of unused platforms due for
was found to contain nothing more than elementary decommissioning. In the developed world this legal
requirements for the contractors or operators to plug framework is put into place prior to oil exploration and
wells once abandoned. The national legislation often rightly so, as decommissioning forms an integral part of
imposed standards that were weak and unenforceable, oil production and thus it should dovetail nicely into the
such as ‘‘good oil field practices’’ and ‘‘normal oil field process. This is also done to ensure fairness, predict-
practices’’. The early oil contracts did not spell out ability and a sense of certainty. But the Third World is
details on decommissioning with regard to substantive only about to venture into platform decommissioning.
issues like funding, responsibility and who should pay This comes at a very awkward time: the resources are
for what, i.e., allocation of costs between oil companies running out and the states are not able to raise new fund
and host states. In the absence of negotiated contractual to undertake the costly task. The truth is, most
obligations, the burden is on the latter as the platforms developing states never plan for decommissioning
are stuck to their seabed. purposes including earmarking of funds.
For countries-mainly Third World countries-with In the Third World, the burden of platform de-
state oil companies a worse scenario has appeared. In commissioning remains with the Government or
the absence of specific contractual obligations with the the responsibility of the national oil companies. In
ARTICLE IN PRESS
B.A. Hamzah / Marine Policy 27 (2003) 339–348 343

developed countries the oil industry accepts the respon- competent organisation (i.e., the International Maritime
sibility of removing and disposing of their installations Organisation). The mandate of the IMO covers naviga-
that are no longer in use. In the Third World, the oil tional safety and marine environment. The resulting
industry takes very little interest in the decommissioning Guidelines and Standards produced by the IMO in 1989
of oil and gas platforms, citing the absence of national set out a minimum for states to adopt.
legislation on this matter. It is only lately that many However, the debate on platform decommissioning
production-sharing agreements in the third world, for has triggered an examination by some oil-producing
example, are designed with decommissioning in mind. states of their exposure to risk in this area. For those
Even then, the oil industry will still look at the fine print states with production sharing agreements, it came as a
or look for loopholes to escape responsibility and, in the surprise to discover that the transfer of title to
process, avoid cost and liability. Where they agree to installations that had seemed so important to them
undertake decommissioning, as in the case of Malaysia, implied a transfer of liability for decommissioning and
the national oil company absorbs the costs; oil the attendant bills. While states agreed some legislation
companies are allowed to claim their expenses through on this was required, their approach differed depending
the mechanism of cost recovery. on a variety of factors. Most importantly, power
In Malaysia under the current production-sharing relationships and the size of their reserves dictate the
contract, the oil industry can even recover their attractiveness or lack of it for investment. The oil
contribution to a special fund (managed by Petronas) industry will always be guided by profit margins.
on platform decommissioning. While the post 1998 Public international law regulates policy on removal
production-sharing contracts (PSC) in Malaysia do and disposal of oil and gas installations at sea. None-
contain a provision for the contractor to decommission theless, states do enjoy a certain amount of discretion in
unused platforms, it lacks details and does not oblige the designing and implementing national legislation on
PSC contractors to remove and dispose of any offshore installations. This freedom is closely tied to
abandoned installation. their international obligations. This should be taken to
Many oil production agreements stipulate a require- imply that the current international law concerning
ment to plug wells and undertake unspecified measures abandonment, removal and disposal of offshore instal-
as appropriate to good oil field practices or industry lations has not been cast in stone. It is very likely that in
practices in oil field operations before abandoning an oil future attitudes may change with regard to platform
field. What constitutes best practices is often determined decommissioning. The development of new technology
by the oil industry and they tend to vary between will have an impact on attitudes and usually the law will
companies and locations. Those considered best prac- adjust accordingly to reflect the change in attitude.
tices in European waters, for example, are not necessa- United Kingdom and United States were two
rily transferred to other parts of the world. dominant maritime powers in the 1950s pushing for an
The oil industry always claims their operations are international treaty on platform abandonment under
governed by the agreements they sign. Very often these the pretext of freedom of navigation. The real motive is
agreements do not spell out the best practices except to of course maritime security. In the years leading to the
state a general phrase in the agreement such as 1958 Convention on the Continental Shelf, it was the
‘‘appropriate oil field good measures’’. Such phrase is United Kingdom, with firm support from the United
intended to be ambiguous and an escape hatch. The States, that initiated the debate on this issue; first at the
general phrase means in law nothing, although it International Law Commission and later in the corri-
provides clients a certain comfort level. dors of the United Nations.
As more platforms began to mature world wide, the In the 1950s the United Kingdom had not yet become
oil industry began to put increasing pressure on the an oil producing state. But the UK retained direct
international community to develop international rules interest in Royal Dutch/Shell and British Petroleum.
and guidelines before some oil producing states started Besides the fields in Brunei and in the Netherlands, the
drawing up unilateral legislation that could undermine remaining productive oil fields owned and operated by
their activities. Some states took up the call from the the two British companies in the 1950s were in Middle
industry and began a process of consultation between East. The success in Brunei waters and in the Gulf of
like-minded parties. The result was the 1958 Geneva Mexico inspired some naval planners in the UK and
Convention on the Continental Shelf, which, among USA to undertake some preventive measures to protect
other important provisions, has a special provision their freedom of navigation doctrine. Article 5.5 of the
obligating state parties to remove in entirety all offshore 1958 Geneva Convention on the Continental Shelf was
installations. intended to protect the maritime security interests of
UNCLOS contains more flexible provisions. In both nations. By insisting that all abandoned platforms
particular, it allows for partial removal. UNCLOS has be completely removed, the US and Great Britain could
also widened the scope by enlisting the help of a enjoy the freedom of navigation.
ARTICLE IN PRESS
344 B.A. Hamzah / Marine Policy 27 (2003) 339–348

The offshore installations installed in the 1950s were While states are permitted to extract oil and gas on
relatively small and could be easily removed. None was the continental shelf, the Convention provides that such
actually in deep or treacherous water. Similarly the exploration and exploitation must not result in unjustifi-
onshore installations in Texas, for example, were small able interference with the rights of other states (Article
pumping units and they were easily decommissioned 5(1)). The construction as well as the operation of the
after they had become redundant. The small Texas installations is governed by this general rule (Article
installations were used as benchmarks for the 1958 5(2)). A safety zone of 500 m around the installation is
Convention on the Continental Shelf. Few then thought provided for in Articles 5(2) and 5(3). The critical
the new generation of offshore installations would be provision, however, is Article 5(5), which reads:
huge infrastructures, complete with landing pads for
Any installations which are abandoned or disused
helicopters, hospitals, accommodation facilities, fire-
must be entirely removed.
walls, etc. Anchored to the seabed these structures are
not easily removed. Removing them could be a financial This article makes it mandatory for state parties (57 of
nightmare. Retaining them in situ could result in them, including Malaysia) to remove all the offshore
residual or third party liability as well as a source of installations. This is how the concept of total removal of
marine pollution. offshore installations first gained currency in public
The debate on offshore installations must also be seen international law.
in the context of the 1945 Truman Declaration on the Missing from the Convention are issues pertaining to
Continental Shelf. Intended to demonstrate that the disposal requirements. The treaty is also silent on how
continental shelf was an extension of the landmass, the to deal with pipelines. It would appear that the pipelines
declaration gave the US the right to exploit all natural are to be treated differently from the installations.
resources on its continental shelf. Oil was one of the
resources over which the United States wanted to have
exclusive jurisdiction, and at the same time to deny other 4. 1982 UN Law of the Sea Convention (UNCLOS)
powers the opportunity to exploit it.
UNCLOS is a very comprehensive international
treaty on ocean governance. It covers most legal aspects
3. The 1958 Geneva Convention of ocean space and its uses. They include navigation,
overflight rights, resource exploitation and exploration,
The 1958 Geneva Convention on the Continental conservation of marine resources, shipping, marine
Shelf, building upon the Truman Declaration, included environment, shipping and many other aspects of ocean
the following elements: governance. The provisions dealing with the disposal
and removal of offshore installations must be appre-
* The continental shelf extends to a depth of 200 m or,
ciated in this context. The major concerns for ocean
beyond that limit, to where the depth of the super-
governance have lately revolved around the need to
jacent waters admits of the exploitation of the natural
develop a sustainable marine environment regime and to
resources of the submarine areas.
facilitate navigational safety. These two factors, cost
* The rights are exclusive to the extent that if the
and the availability of new technology for platform
coastal states does not explore the continental shelf or
removal, have triggered the need to develop a more
exploit its resources no one may undertake these
flexible legal framework on platform decommissioning
activities without the express consent of the coastal
acceptable to the oil industry and the coastal states.
state.
UNCLOS entered into force on 16 November 1994.
* The exploration of the continental shelf should not
On paper there seems to be a conflict of obligations
interfere with navigation, fishing or the conservation
between article 5.5 of the 1958 Geneva Convention on
of living resources.
the Continental Shelf and article 60.3 of 1982 UNCLOS.
* Methods for delimiting the continental shelf bound-
But in reality, if the Government so wishes, it can
aries.
renounce its obligations under the former treaty as most
* Provision of a 500 m safety zone around the installa-
of the provisions have been incorporated into UN-
tions.
CLOS. Until the Government does so, the obligations
* Any installation which is abandoned or disused must
remain.
be entirely removed.
Article 60.3 of UNCLOS reads:
The 1958 Geneva Convention on the Continental (3) Due notice must be given of the construction of
Shelf sets the tone in public international law on the such artificial islands, installations or structures, and
removal of offshore installations. This Convention spells permanent means for giving warning of their presence
out clearly the obligations of states with regard to their must be maintained. Any installations or structures
responsibilities and duties on the continental shelf. which are abandoned or disused shall be removed to
ARTICLE IN PRESS
B.A. Hamzah / Marine Policy 27 (2003) 339–348 345

ensure safety of navigation, taking into account the oil industry to treat installations in the deep water
any generally accepted international standards estab- differently from those in shallow water.
lished in this regard by the competent international The International Maritime Organization (IMO) was
organization. Such removal shall also have due regard very quick to assert its competence in this respect even
to fishing, the protection of the marine environment and though the UK and the major maritime powers had not
the rights and duties of other States. Appropriate ratified the document. There are several reasons why the
publicity shall be given to the depth, position and IMO did this. First, it wants to make sure that
dimensions of any installations or structures not entirely abandoned installations do not impede international
removed. navigation, particularly those in strategic straits and
Article 60(3) is not a stand-alone provision. It must be that the unused installations do not pollute the sea.
read along with other provisions in UNCLOS, in Navigational safety and clean sea matters are within
particular Articles 80,208 and 210. Article 80 applies IMO’s jurisdiction. Second, the explanation can be
to artificial islands, installations and structures on the found in the nature of power politics at the IMO, an
continental shelf. Article 208 of UNCLOS requires organization under the control of the major maritime
coastal states to adopt laws and regulations to prevent, powers, which make freedom of navigation their war
reduce and control pollution of the marine environment cry. Third, to ensure coastal states comply with these
arising from or in connection with seabed activities obligations through another multilateral institution
subject to their jurisdiction and from artificial islands, under their control, as the industrial world has some
installations and structures under their jurisdiction, reservations with UNCLOS.
pursuant to articles 60 and 80. Such regulations and Under UNCLOS coastal states have more flexibility
standards must not be less effective than international as long as they comply with the international standards
rules, standards, recommended practices and proce- established for this purpose. The snag is IMO Resolu-
dures. Article 210 deals with pollution from dumping. tions are not binding on state parties. However, the
Coastal states are permitted to legislate on what can be industrial world has argued that in this case the IMO
dumped at sea. It is imperative that the national resolutions are specific and since this is tied to
legislation is not less effective than established interna- UNCLOS, the Resolution is binding when the UN-
tional rules and standards. CLOS Convention enters into force. This is to force
Since the oceans are treated as one sea, certain control compliance through the back door. Clearly, on this
mechanisms have been established towards a more matter the industrial world had relied on power politics.
integrated ocean management. States are encouraged In other respects the UNCLOS provisions on plat-
to establish global standards to prevent, reduce and form decommissioning are quite similar to those of the
control such pollution. In general sea dumping is 1958 Geneva Convention. There is no provision for site
discouraged; in Europe it is banned following the Brent rehabilitation under UNCLOS. Oil and gas pipelines are
Spar episode. The policy of banning in Europe may also omitted. Surely the industry was familiar with the
soon gain global acceptance. The 1996 Protocols to the situation. It is possible that the matter is kept silent
1972 London Convention are slowly moving in that simply because the industry does not want to be
direction. responsible for what looks to be a very delicate post-
Of course, in terms of scope, Article 60 applies mutatis removal matter or feels that the state should be
mutandis to artificial islands, installations and structures responsible for that. Anyhow, site rehabilitation is
on the continental shelf, according to Article 80. It has now considered an important dimension of decommis-
been argued that Article 60 is very ambiguous. While it sioning. Periodical site monitoring could be a costly
envisages removal of abandoned and unused platforms, affair.
it subjects itself to lesser international standards. Under
the 1958 Convention, the language is very clear: nothing
less than total removal, i.e., to be removed entirely. 5. The IMO guidelines
Under UNCLOS, it is only removal and the word
‘‘entirely’’ is omitted. The backtracking can be attrib- The IMO adopted a Resolution in 1989 on Guidelines
uted to several factors. First, the installations are getting and Standards for the Removal of Offshore Installations
very big, very cumbersome to remove in entirety. and Structures on the Continental Shelf and in the
Second, the reluctance on the part of the oil industry Exclusive Economic Zone. By virtue of these guidelines,
to fully participate in this exercise of total removal, state parties are obliged to remove all abandoned and
mainly for reasons of cost. Third, a change of heart in disused offshore installations on any continental shelf or
the position of the United Kingdom, the major in any exclusive economic zone except where non-
champion of both resolutions. Part of the UK’s about- removal or partial removal is consistent with the guide-
turn decision has to do with the discovery of oil/gas in lines. By the same token, states are permitted to impose
the deeper part of the North Sea and the pressure from more stringent regulations than provided for in the
ARTICLE IN PRESS
346 B.A. Hamzah / Marine Policy 27 (2003) 339–348

Guidelines. In a sense, the Guidelines have set only the of no less than 55 m above the structure to facilitate
minimum standards. navigation. Coastal states are also required to ensure
There are two sections to the IMO Guidelines: that any residue from the left-over installations do not
Guidelines and Standards. The ‘‘Guidelines’’ provide cause or result in a hazard to navigation. At the same
for a case-by-case decision on whether to remove the time, coastal states have an obligation under the IMO
abandoned installation or not with emphasis on the Resolution to ensure that navigational aids are in place
following: and maintained on those installations that have been
abandoned and that those installations not removed in
* Any potential deterioration of the material and its
entirety be marked on charts. States are also required to
impact on navigation and marine environment and
ensure that the legal title to the installations which have
other uses of the sea.
not been fully removed remain unambiguous and that
* The costs, technical feasibility and risks of injury to
the liability for future damages are clearly established.
personnel associated with removal of the installation
The IMO Guidelines and Standards also make
or structure.
specific mention of converting abandoned platforms
* New uses for the platforms or other reasonable
for use as artificial reefs. But states are required to make
justification for allowing the platform or parts of it to
sure that the reefs are away from the customary traffic
remain on the seabed.
lanes and be consistent with the IMO Guidelines and
Where it pertains to the safety of navigation, the other established standards for the maintenance of
emphasis is on the proximity of the abandoned navigational safety standards.
installations to sea-lanes or whether they are located in There is also an environmental provision in the IMO
an approach to or in straits used for international Guidelines for compliance. Paragraph 3.3 states that the
navigation or in archipelagic waters. In other words, means of removing the installations should not cause a
there exists a general requirement to remove disused or significant adverse effect on living resources. Some
abandoned platforms in straits, access to ports or in authorities exclude the use of explosives. What consti-
navigational routes. The determination of any potential tutes adverse environmental effects is not spelt out but
effect on the marine environment should be based on left to the discretion of the coastal state.
scientific evidence. The overriding concerns of IMO Guidelines are
Under the sub-heading ‘‘Standards’’, complete re- navigational safety and marine pollution. Nonetheless
moval is required of all installations standing in less there is a notable absence of any environmental impact
than 75 m of water and weighing less than 4000 ton in air assessment as a standard procedure to be adopted.
(excluding deck and superstructure), and all installations Presumably this is left to the discretion of coastal states.
placed on the seabed after 1998 standing in less than 100 The purpose of the IMO Guidelines is to provide a set of
metres of water and weighing less than 4000 ton. The minimum standards and leave the coastal states with
exceptions are those installations that have been wide discretionary powers on how to move forward.
assigned for new uses if permitted to remain partially It should be noted that the OSPAR regime applicable
or wholly in place or where the entire removal is not in the North Sea is more stringent than the standards
technically feasible or would involve an extreme cost or imposed in IMO Guidelines. For example, OSPAR does
an extreme risk to the personnel and environment. The not permit deep sea dumping.
Standards further require that no installations should be
placed on the continental shelf or in the EEZ after 1
January 1998 unless the design and construction is such 6. International law concerning the disposal of offshore
that it makes it feasible to remove the installation in its installations
entirety.
Existing installations in water depths of greater than Decommissioning is a complex process involving
75 m or weighing less than 4000 ton can be wholly or removal and disposal. But the law seems silent on the
partially left in place, provided they do not cause latter. Neither the 1958 Geneva Convention nor
unjustifiable interference with other users of the sea. UNCLOS has any reference to platform disposal.
Installations, which are in straits used for international However, it is possible to identify some trends based
navigation or located in approaches to ports or in on recent practices in platform decommissioning in
customary deep-draft lanes and IMO adopted routing Europe and also to examine some of the treaty
systems, must be removed. Any installation in the Straits provisions. One treaty that deals with some aspects of
of Malacca, for example, would be subject to this rule. platform disposal is the London Convention, 1972, also
Where installations or structures remain above water known as the London Dumping Convention. According
they should be adequately maintained to prevent to this Convention, abandonment in situ and toppling of
structural failure. In the case of partial removal, the offshore platforms are considered as dumping and thus
coastal states must ensure an unobstructed water depth subject to regulation by this Convention. In relation to a
ARTICLE IN PRESS
B.A. Hamzah / Marine Policy 27 (2003) 339–348 347

toppled platform being converted to form an artificial also not permitted. The LC Protocol puts emphasis
reef, it was decided that it would still fall within the on the precautionary principle and the ‘‘polluter
competence of the Convention. But in this case, a pays’’ concept. The LC Protocol gives plenty of
coastal state can exercise its discretion: to allow rig-to- room to coastal states with regard to sea dumping,
reef conversion or not, so long as the reef would be only exhorting states to be very responsible and to
consistent with the aims of the Convention. The USA allow dumping only when states really believe that it
welcomes rig-to-reef policy but Germany believes such will not harm the sea. And, when data is insufficient to
policy prescription leaves too much discretion to coastal determine its harmful impact, to refrain from it. In other
states. words if states have doubt that by leaving an abandoned
But the Dumping Convention is silent on pipelines structure in situ it could lead to some form of marine
that have been abandoned. Is there a need to remove pollution, then it should not be allowed.
pipelines or can they just be buried/trenched, consider- In Europe, for example, there are very stringent rules
ing that the process of natural sedimentation would on sea dumping following the Brent Spar episode in
anyhow bury the pipelines? If they are to be removed, 1995. As a matter of principle, sea dumping of
what criteria should apply, considering the engineering abandoned platforms is not permitted unless it is
and economic practicality of the project and other consistent with general practice. Annex III of OSPAR
concerns including sustainable environmental manage- is concerned with the prevention and elimination of
ment? pollution from offshore sources. Articles 5–8 are directly
The Dumping Convention operates by means of a applicable to the abandonment of offshore installations.
licensing system, which distinguishes materials accord- Article 5 reiterates the need for a permit before
ing to three classifications. There are those that may not dumping. But it states that no permit is to be issued if
be dumped at all (Annex I), those that may be dumped if the disused offshore installations, including disused
a license is granted by the state after consultation with offshore pipelines, contain substances which may result
other members of the Convention (Annex II) and those in hazards to human health, harm to living resources
that require a special permit from the national authority and marine ecosystems, damage to amenities or inter-
(Annex III). Applicants for a permit have to submit ference with other legitimate uses of the sea. States are
environmental impact assessments in advance. required to consult other contracting parties before any
This regime has been supplemented by a protocol to permit is given.
the Convention, which, once ratified, will supersede it. In short, the practice in Europe is moving towards
This is the London Convention Protocol of 1996. The banning deep-sea dumping of offshore platforms.
protocol made sweeping changes to the concept of sea Although some states in the EC have their own
dumping .The main changes to the original convention preferences and differences in opinions, they have been
are in the areas of definitions, dumping provisions and kept muted. This is because, according to one document,
modern environmental principles. Among the defini- the disposal of decommissioned offshore installations in
tional changes introduced in the LC Protocols are those EC areas is a matter where the EC can exercise
concerning the ‘‘sea’’ and ‘‘platform’’. The term sea competence.
includes seabed and subsoil as well as the water column. Such regional mechanisms/regimes do not exist
By this definition disused platforms left on the seabed in South East Asia although this region has a large
are included within the Convention’s scope. Toppled share of offshore installations. As the old fields begin
structures and platforms left in situ will constitute to mature, many installations installed for the primary
dumping. The Convention does not define pollution but purpose of oil production are no longer productive
the LC Protocol defines it as anything that is introduced and slated for decommissioning. Presently there are
into the sea as a result of human activity that leads to or some one thousand offshore installations in South
is likely to lead to deleterious impact on living resources East Asian waters that one day will have to be
and marine ecosystems. decommissioned.
The system of licensing is also modified. The Protocol
has done away with the three categories of items that
cannot be dumped and replaced them with one list of all 7. 1958 Convention and UNCLOS
waste and other materials that may be dumped. These
are mainly inert or naturally occurring substances. What is the relationship between the removal
Although the Protocol does not specify that abandoned requirements in the 1958 Convention, UNCLOS and
platforms cannot be dumped at sea, it imposes an the IMO Guidelines? It is evident that there is a
obligation on the operator of the platform not to discrepancy between the provisions. In the 1958 Con-
dispose of any item that may result in harm to the vention, the emphasis is on total removal. But in
environment. Dumping anything in the sea for which UNCLOS, the requirements are more flexible although
there is insufficient data to predict likely outcomes is as a general rule it still insists on removal. Both treaties
ARTICLE IN PRESS
348 B.A. Hamzah / Marine Policy 27 (2003) 339–348

are prima facie binding on the contracting parties. This The cost of removing the installations is very high
author has maintained elsewhere that despite claims by especially for those who have not made any financial
some that the treaty provisions have not become arrangement to cover platform-decommissioning ex-
customary international law, the position is not very penses. It is more acute for the developing oil producing
clear. One can make a case, however, that the provisions countries with declining revenue to manage the mature
have provided strong evidence of state practice but they oilfields. What needs to be done? Can they leave the
have not attained the status of customary international installations in the sea, as they have no financial means
law. Moreover, the 1989 IMO Guidelines and Standards to remove them? In the absence of customary interna-
document is legally not binding. tional law, how would states handle the concerns of
residual liability? Would leaving the installations at sea
compromise the other legitimate users of the sea? In the
8. The way forward long run, could abandoned platforms be a source of
marine pollution and pose a danger to international
There is need to re-examine the practicality of the navigation?
current legal regime on offshore platform decommis- One quick way out of the legal dilemma is for oil
sioning especially as they affect Third World countries. producing countries to enact comprehensive national
In the absence of a well-defined international legal legislation on platform decommissioning covering every
regime, the Third world countries could adopt an easy aspect of the decommissioning process discussed above.
way out by leaving the abandoned platforms or toppling The 1989 IMO Guidelines could be used as the
them in situ. In the long run this policy could pose minimum standards for determining weight of jacket
danger to marine pollution and international naviga- and water depth in removal options; it does not address
tion. This problem is less acute in Europe and America all other relevant issues.
where national legislation is well developed. Moreover, Third World countries, especially the oil producing
in the developed countries the states are in a better states, should also take a more assertive approach on
position to deal with the oil industry. This is not so in offshore decommissioning. Enacting national legislation
the Third World that depends on foreign oil companies. on offshore installations decommissioning would be a
The dependence limits their flexibility. way forward.
There is need to clearly define decommissioning
in international law. Currently, the term is not
defined though it is used interchangeably with aban- References
donment. Most treaties talk of abandonment when in
reality the intention is to refer to the process of [1] IMO Assembly Resolution A 672(16), adopted 19 October 1989.
decommissioning. [2] 32 International Legal Materials (ILM), 1993. p. 1072.
Even the installations are not defined and as such not [3] Forte ADM. Legal aspects of decommissioning. In: Norman DG,
Neilson J, editors. Decommissioning of Offshore Structures.
governed by any international norm. For example, the New York: Springer; 1998.
extensive pipelines at the bottom of the sea are not [4] The guidelines notes for industry: decommissioning of offshore
covered in the IMO Guidelines and OSPAR, the two installations and pipelines under the Petroleum Act 1988.
legal regimes on platform decommissioning. Should not London: HMSO, 1999.
the pipelines’ removal also be subject to some interna- [5] 11 International Legal Materials, 1972. p. 1294.
[6] 36 International Legal Materials, 1997. p. 7.
tional legal regime? If so, who should initiate the [7] Convention on the Protection of the Marine Environment
process? Is the IMO the competent organization? What of the Baltic Sea Area, 1992, Law of the Sea Bulletin, No. 22,
criteria should be used for pipelines? 1993. p. 54.
OSPAR is a regional treaty and applicable only in [8] Platform Abandonment Master Study, PETRONAS, 1997 (not
Europe. The 1989 IMO Guidelines are binding on state published).
[9] 11 International Legal Materials, 1972. p. 262.
parties. This makes compliance difficult. Besides not all [10] MARPOL 73/78. Consolidated Edition, IMO Sales No.
oil producing countries are party to UNCLOS and IMO-520E, 1991; and MARPOL 73/78, Amendments to Annex
IMO. I, IMO Sales No. IMO-520E, 1992.

Vous aimerez peut-être aussi