QUANTITY AND RATE ANALYSIS

Sr. Amount
Particulars Length Breadth Total Area Rate
No. (Approx.)
(in Sq.m) (Rs./ Sq.m) Rs
A PLOT 154
1 Total Area 40.00 23.00 920.00
2 Lab Area 15.00 13.45 201.75
3 Service Area
Add 4.60 23.00 105.80
20.50 23.00 471.50
14.70 6.10 89.67
14.70 3.50 51.45
Total Service Area 718.42
Deductions
For Tank 6.00 1.50 9.00
5.00 5.00 25.00

4 Actual Service Area to be 684.42


considered

Flooring the Lab area (excluding the


B storage area) wit Acid Resistant
Tiles
Deductions for Lab Area 5.00 13.45 67.25

Actual Lab Area to be considered 134.50

flooring with acid resistant tiles - - 134.50 1076.00 144722.00

C Mezzanine Costing (Steel Structure) - - 8 MT 65000.00 520000.00

D Partitions - - LS 250000.00

E Insulation Cost - - 700 85.00 59500.00

F Storage at Mezanine Floor - - - - -

PCC in total service area for PLOT


G - - 1400.00 4000.00 5600000.00
154 & 155

Painting (waterproof cement paint)


H - - 685.00 33.00 22605.00
three coats

I Floor Plan for Lab (for Plot 154) - - - - Attached

J TOTAL COST - - - - 6596827.00


CONSTRUCTION FOR MEZZANINE FLOOR AND OTHER ACCESSORIES WORK

TOTAL AREA /
SR. NO. PARTICULARS UNIT RATE AMOUNT
QUANTITY

A Mezzanine floor at PLOT 154

1 For Steel Strucutre 12.00 MT 60000.00 720000.00

Ground Floor LAB Area (Internal


2
Work)

3 Brickwork 20.00 Cu.m 3500.00 70000.00

4 Partitions L.S. - - 250000.00

5 Acid Resistant Tiles 135.00 Sq.m 1100.00 148500.00

6 Insulation Cost 700.00 Sq.m 70.00 49000.00

Flooring Rubble Soling (including


7 1400.00 Sq.m 250000.00
PLOT 155)

8 Painting (including PLOT 155) 1500.00 Sq.m 33.00 49500.00

9 Multiple Racks L.S. - - 100000.00

10 Floor Plans Attached

11 Structural Painiting L.S. - - 350000.00

Water tank, drainage work,


12 windows, doors etc and other L.S. - - 150000.00
miscellaneous

Total Amount 2137000.00

For flooring with PCC in M10


11 1400.00 Sq.m 4000.00 5600000.00
concrete