Vous êtes sur la page 1sur 220

School of Building Science & Technology

Quantity Surveying & Specifications


RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
1.01 Excavation for foundation up to 1.5 M depth
including sorting out and stacking of useful
materials, removing of grass or plants, and
Cu.m
disposing of the excavated stuff up to 50 M. lead.
In ordinary soil.

For 10 Cum

[A] Materials --- --- ---

[B] Labours
Skilled Nos. --- 150 ---
Unskilled Nos. 5 90 450.00
Total labour rate 450.00

[C] Water + electric @ 2% of A+B --- --- 9.00

[D] Tools, Equipments & plants @ 2% A+B --- --- 9.00

[E] Scaffolding @ 2% A+B --- --- ----

[F] Profit & overhead @ 15% of A+B+C+D --- --- 70.2

Total cost 538.20

Unit Rate 54

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
1.03 Filling available excavated earth (including rock) in
trenches, plinth, sides of foundations etc. in layers
not exceeding 20 cm. in depth consoladating each
Cu.m
deposited layer by ramming and watering.

For 10 Cum

[A] Materials --- --- ---

[B] Labours
Skilled Nos. --- 150 ---
Unskilled Nos. 2.6 90 234.00
Total labour rate 234.00

[C] Water + electric @ 2% of A+B --- --- 4.68

[D] Tools, Equipments & plants @ 2% A+B --- --- 4.68

[E] Scaffolding @ 2% A+B --- --- ----

[F] Profit & overhead @ 15% of A+B+C+D --- --- 36.5

Total cost 279.86

Unit Rate 28
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
1.04 Filling in plinth with sand under floors including
watering ramming, consolidating and dressing etc. Cu.m
comp.

For 10 Cum

[A] Materials --- --- ---

[B] Labours
Skilled Nos. --- 150 ---
Unskilled Nos. 2.5 90 225.00
Total labour rate 225.00

[C] Water + electric @ 2% of A+B --- --- 4.50

[D] Tools, Equipments & plants @ 2% A+B --- --- 4.50

[E] Scaffolding @ 2% A+B --- --- ----

[F] Profit & overhead @ 15% of A+B+C+D --- --- 35.1

Total cost 269.10

Unit Rate 27
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
1.02 Filling in excavated trenches with sand under
B.B.C.C. including watering ramming, Cu.m
consolidating and dressing etc. comp.

For 10 Cum

[A] Materials --- --- ---

[B] Labours
Skilled Nos. --- 150 ---
Unskilled Nos. 2 90 180.00
Total labour rate 180.00

[C] Water + electric @ 2% of A+B --- --- 3.60

[D] Tools, Equipments & plants @ 2% A+B --- --- 3.60

[E] Scaffolding @ 2% A+B --- --- ----

[F] Profit & overhead @ 15% of A+B+C+D --- --- 28.08

Total cost 215.28

Unit Rate 22

Checked by:
Date: Page No.
Remarks

Rs

Rs/Cum
Remarks

Rs

Rs/Cum
Remarks

Rs

Rs/Cum
Remarks

Rs

Rs/Cum
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount Remarks
No.
3.01 Brick work using common brunt clay building
bricks having crusing strength not less than 35
Kg/S.cm. in foundation and plinth in cement Cu.m
mortar 1:4 (1cement : 4 fine sand), Conventional

For 10 Cum

[A] Materials
Bricks Nos. 4314 2.10 9059.40
Cement Bags 12.14 200.00 2428.00
Sand cu.m. 2.74 142.00 389.08
Total material rate 11876.48

[B] Labours
Skilled Nos. 8.2 150.00 1230.00
Unskilled Nos. 18 90.00 1620.00
Total labour rate 2850.00

[C] Water + electric @ 2% of A+B --- --- 294.53

[D] Tools, Equipments & plants @ 2% A+B --- --- 294.53

[E] Scaffolding @ 2% A+B --- --- 294.53

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 2341.51

Total cost 17951.58 Rs

Unit Rate 1795 Rs/Cum

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculation for rate analysis for Brick work for 10 Cum

[A] Materials
1. Bricks
Total No= 10 / (0.24 X 0.125 X 0.085) = 3921.56
10% Wastage=3922 x 1.1= 4314 bricks

2. Cement
Wet Mortar = 10× [  0 . 24 ×0 . 125 ×0 . 085 −  0 . 23 ×0 . 115 ×0 . 075  ]
0 . 24×0 . 125 ×0 . 085
= 2.22 + 5% Wastage
= 2.33 cu.m.

Dry Mortar = 2.33 x 1.25 (25% Shrinkage Factor)


= 2.91 cu.m

Cement = 2. 91
=0. 4162 Wastage
7
0. 42
= =12. 41Bags
0. 0345

3. Sand
Sand 2. 9 1×6
=
7
= 2.49 + 10% Wastage
= 2.74 cu.m.

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount Remarks
No.
3.02 Brick work using common brunt clay building
bricks having crusing strength not less than 35
Kg/S.cm. for Ground floor in cement mortar 1:4 Cu.m
(1cement : 4 fine sand), Conventional

For 10 Cum

[A] Materials
Bricks Nos. 4314 2.10 9059.40
Cement Bags 12.14 200.00 2428.00
Sand cu.m. 2.74 142.00 389.08
Total material rate 11876.48

[B] Labours
Skilled Nos. 9.8 150.00 1470.00
Unskilled Nos. 21.3 90.00 1917.00
Total labour rate 3387.00

[C] Water + electric @ 2% of A+B --- --- 305.27

[D] Tools, Equipments & plants @ 2% A+B --- --- 305.27

[E] Scaffolding @ 2% A+B --- --- 305.27

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 2426.89

Total cost 18606.18 Rs

Unit Rate 1861 Rs/Cum

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount Remarks
No.
3.03 Half brick masonary in common brunt clay building
bricks having crushing strength not less than 35
Kg./Sq.cm. in cement mortar 1:3 (1 Cement : 3 Sq.m
coarse sand) in Ground floor., Conventional

For 10 Sqm

[A] Materials
Bricks Nos. 539 2.10 1131.90
Cement Bags 1.38 200.00 276.00
Sand cu.m. 0.20 142.00 28.40
Total material rate 1436.30

[B] Labours
Skilled Nos. 1.3 150.00 195.00
Unskilled Nos. 2.5 90.00 225.00
Total labour rate 420.00

[C] Water + electric @ 2% of A+B --- --- 37.13

[D] Tools, Equipments & plants @ 2% A+B --- --- 37.13

[E] Scaffolding @ 2% A+B --- --- 37.13

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 295.15

Total cost 2262.83 Rs

Unit Rate 226 Rs/Sqm

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculation for rate analysis for Brick work for 10 Sqm

[A] Materials
1. Bricks
Bricks = 0.24 x 0.085
= 0.0204
= 10 / 0.0204 = 490.20
= 490.20 + 10% Wastage
= 539 Bricks

2. Cement
Wet Mortar = [10 - (490 x 0.23 x 0.075)] x 0.115
= 0.18 + 5% Wastage
= 0.19 cu.m.
Dry Mortar = 0.19 x 1.25 (25% Shrinkage Factor)
= 0.24 cu.m.

Cement = 0.24 / 4
= 0.048 + 2% Wastage
= 1.38 Bags

3. Sand
Qty = 0.24 x 3 /4
= 0.18 + 10% Wastage
= 0.20 cu.m.

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount Remarks
No.
3.04 Brick work using common brunt clay building
bricks having crusing strength not less than 35
Kg/S.cm. for First floor in cement mortar 1:4 Cu.m
(1cement : 4 fine sand), Conventional

For 10 Cum

[A] Materials
Bricks Nos. 4314 2.10 9059.40
Cement Bags 12.14 200.00 2428.00
Sand cu.m. 2.74 142.00 389.08
Total material rate 11876.48

[B] Labours
Skilled Nos. 9.8 150.00 1470.00
Unskilled Nos. 21.3 90.00 1917.00
10% extre labour for rise 338.70
Total labour rate 3725.70

[C] Water + electric @ 2% of A+B --- --- 312.04

[D] Tools, Equipments & plants @ 2% A+B --- --- 312.04

[E] Scaffolding @ 2% A+B --- --- 312.04

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 2480.75

Total cost 19019.06 Rs

Unit Rate 1902 Rs/Cum

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount Remarks
No.
3.05 Half brick masonary in common brunt clay building
bricks having crushing strength not less than 35
Kg./Sq.cm. in cement mortar 1:3 (1 Cement : 3 Sq.m
coarse sand) in First floor., Conventional

For 10 Sqm

[A] Materials
Bricks Nos. 539 2.10 1131.90
Cement Bags 1.38 200.00 276.00
Sand cu.m. 0.20 142.00 28.40
Total material rate 1436.30

[B] Labours
Skilled Nos. 1.3 150.00 195.00
Unskilled Nos. 2.5 90.00 225.00
10% extra labour for rise 42.00
Total labour rate 462.00

[C] Water + electric @ 2% of A+B --- --- 37.97

[D] Tools, Equipments & plants @ 2% A+B --- --- 37.97

[E] Scaffolding @ 2% A+B --- --- 37.97

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 301.83

Total cost 2314.03 Rs

Unit Rate 231 Rs/Sqm

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount Remarks
No.
3.06 Brick work using common brunt clay building
bricks having crusing strength not less than 35
Kg/S.cm. for tarrace in cement mortar 1:4 Cu.m
(1cement : 4 fine sand), Conventional

For 10 Cum

[A] Materials
Bricks Nos. 4314 2.10 9059.40
Cement Bags 12.14 200.00 2428.00
Sand cu.m. 2.74 142.00 389.08
Total material rate 11876.48

[B] Labours
Skilled Nos. 9.8 150.00 1470.00
Unskilled Nos. 21.3 90.00 1917.00
20% extre labour for rise 677.40
Total labour rate 4064.40

[C] Water + electric @ 2% of A+B --- --- 318.82

[D] Tools, Equipments & plants @ 2% A+B --- --- 318.82

[E] Scaffolding @ 2% A+B --- --- 318.82

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 2534.6

Total cost 19431.93 Rs

Unit Rate 1943 Rs/Cum

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount Remarks
No.
3.07 Half brick masonary in common brunt clay building
bricks having crushing strength not less than 35
Kg./Sq.cm. in cement mortar 1:3 (1 Cement : 3
Sq.m
coarse sand) in Tarrace., Conventional

For 10 Sqm

[A] Materials
Bricks Nos. 539 2.10 1131.90
Cement Bags 1.38 200.00 276.00
Sand cu.m. 0.20 142.00 28.40
Total material rate 1436.30

[B] Labours
Skilled Nos. 1.3 150.00 195.00
Unskilled Nos. 2.5 90.00 225.00
20% extra labour for rise 84.00
Total labour rate 504.00

[C] Water + electric @ 2% of A+B --- --- 38.81

[D] Tools, Equipments & plants @ 2% A+B --- --- 38.81

[E] Scaffolding @ 2% A+B --- --- 38.81

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 308.51

Total cost 2365.23 Rs

Unit Rate 237 Rs/Sqm

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
2.01 Providing and laying brick bat cement concrete
1:5:10 (1 Cement : 5 Course sand : 10 hand
broken bricks) including ramming, curing complete Cu.m

For 10 Cum

[A] Materials
Cement Bags 36.31 200.00 7262.00
Sand Cum 5.14 142.00 729.88
Brick bats Cum 10.28 175.00 1799.00
Total material rate 9790.88

[B] Labours
Skilled Nos. 3.10 150.00 465.00
Unskilled Nos. 23.30 90.00 2097.00
Total labour rate 2562.00

[C] Water + electric @ 2% of A+B --- --- 247.06

[D] Tools, Equipments & plants @ 2% A+B --- --- 247.06

[E] Scaffolding @ 2% A+B --- --- ----

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1927.05

Total cost 14774.04

Unit Rate 1477

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculation for rate analysis for BBCC for 10 Cum

[A] Materials

1. Cement
Wet Mix = 10cu.m.

Dry Mix = 15.2 cu.m. (52% Shrinkage Factor)

Cement = 15.2 / 13
= 1.17 / 0.0345
= 35.60 Bags +2% Wastage
= 36.31 Bags

2. Sand
Qty = (15.2 x 4) / 13
= 4.67 + 10% Wastage
= 5.14 cu.m.

3. Brick bats
Brick bats = (15.2 x 8) / 13
= 9.35 + 10% Wastage
= 10.28 cu.m.

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
2.03 Providing and laying reinforced cement concrete
1:1.5:3 (1 Cement : 1.5 Course sand : 3 broken
stone aggregate 40 m.m nominal size) including
compcting and curing, excluding cost of form work Cu.m
and reinforcement complete in coping and plinth
beem

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 2.50 150.00 375.00
Unskilled Nos. 29.00 90.00 2610.00
Total labour rate 2985.00

[C] Water + electric @ 2% of A+B --- --- 457.58

[D] Tools, Equipments & plants @ 2% A+B --- --- 457.58


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 457.58

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3616.34

Total cost 28047.87

Unit Rate 2805

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculation for rate analysis for RCC for 10 Cum

[A] Materials

1. Cement
Wet Mix = 10cu.m.

Dry Mix = 15.2 cu.m. (52% Shrinkage Factor)


= 15.5 cu.m. (2% Wastage)

Cement = 15.5 / 5.5


= 2.82 + 2% Wastage
= 2.88 / 0.0345
= 81.35 bags

2. Sand
Qty = (15.5 x 1.5) / 5.5
= 4.23 + 10% Wastage
= 4.65 cu.m.

Coarse Aggregates = (15.5 x 3) / 5.5


= 8.46 cu.m.
= 10.28 cu.m.

3. Grit
Grit (33%) = 8.46 x 0.33
= 2.62 +5% Wastage
= 2.96 cu.m.

4. Kapchi
Kapchi = 8.46 x 0.67
= 5.64 + 5% Wastage
= 5.93 cu.m.

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.

Providing and laying reinforced cement


concrete in 1:1.5:3 (1-cement, 1.5-fine
agg. 3- coarse agg. 20mm down size)
for column including curing etc.
complete excluding formwork and
3.03 reinforcement below plinth lvl. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 3.90 150.00 585.00
Unskilled Nos. 39.40 90.00 3546.00
Total labour rate 4131.00

[C] Water + electric @ 2% of A+B --- --- 480.50

[D] Tools, Equipments & plants @ 2% A+B --- --- 480.50


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 480.50

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3846.94

Total cost 29493.23

Unit Rate 2949


Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.04

Providing and laying reinforced cement


concrete in 1:1.5:3 (1-cement, 1.5-fine
agg. 3- coarse agg. 20mm down size)
for coping and for plinth beam
including curing etc. complete
excluding formwork and reinforcement
for above plinth lvl. and below GF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 3.00 150.00 450.00
Unskilled Nos. 30.00 90.00 2700.00
Total labour rate 3150.00

[C] Water + electric @ 2% of A+B --- --- 460.88

[D] Tools, Equipments & plants @ 2% A+B --- --- 460.88


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 460.88

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3690.96

Total cost 28297.39

Unit Rate 2830


Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.

3.05
Providing and laying reinforced cement
concrete in 1:1.5:3 (1-cement, 1.5-fine
agg. 3- coarse agg 20mm down size)
for column including curing etc.
complete excluding formwork and
reinforcement for above plinth upto GF
slab. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 4.70 150.00 705.00
Unskilled Nos. 43.10 90.00 3879.00
Total labour rate 4584.00

[C] Water + electric @ 2% of A+B --- --- 489.56

[D] Tools, Equipments & plants @ 2% A+B --- --- 489.56


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 489.56

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3918.97

Total cost 30045.44

Unit Rate 3005


Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.

3.06
Providing and laying reinforced cement
concrete in 1:1.5:3(1-cement, 1.5-fine
agg. 3- coarse agg. 20mm down size)
for lintel bend and chajja slab
including curing etc. complete
excluding formwork and reinforcement
for above plinth and upto GF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 4.60 150.00 690.00
Unskilled Nos. 39.10 90.00 3519.00
Total labour rate 4209.00

[C] Water + electric @ 2% of A+B --- --- 482.06

[D] Tools, Equipments & plants @ 2% A+B --- --- 482.06


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 482.06

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3859.35

Total cost 29588.31


Unit Rate 2959

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.07
Providing and laying reinforced cement
concrete in 1:1.5:3 (1-cement, 1.5-fine
agg. 3- coarse agg. 20mm down size)
for beam including curing etc.
complete excluding formwork and
reinforcement for above plinth and
upto GF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 4.10 150.00 615.00
Unskilled Nos. 38.10 90.00 3429.00
Total labour rate 4044.00

[C] Water + electric @ 2% of A+B --- --- 478.76

[D] Tools, Equipments & plants @ 2% A+B --- --- 478.76


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 478.76

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3833.11

Total cost 29387.18


Unit Rate 2939

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.08
Providing and laying reinforced cement
concrete in 1:1.5:3 (1-cement, 1.5-fine
agg. 3- coarse agg. 20mm down size)
for stair case including curing etc.
complete excluding formwork and
reinforcement for above plinth and
below GF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 5.10 150.00 765.00
Unskilled Nos. 51.10 90.00 4599.00
Total labour rate 5364.00

[C] Water + electric @ 2% of A+B --- --- 505.16

[D] Tools, Equipments & plants @ 2% A+B --- --- 505.16


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 505.16

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 4042.99


Total cost 30996.26

Unit Rate 3100

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.09
Providing and laying reinforced cement
concrete in 1:1.5:3 (1-cement, 1.5-fine
agg. 3- coarse agg. 20mm down size)
for slab including curing etc. complete
excluding cost of formwork and
reinforcement for above plinth and
below GF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 5.00 150.00 750.00
Unskilled Nos. 30.10 90.00 2709.00
Total labour rate 3459.00

[C] Water + electric @ 2% of A+B --- --- 467.06

[D] Tools, Equipments & plants @ 2% A+B --- --- 467.06


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 467.06

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3740.1


Total cost 28674.06

Unit Rate 2867

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.10
Providing and laying BBCC in 1:4:8 (1-
cement, 4-fine agg. 8-brick bat)
including curing, ramming etc.
complete for above GF slab below FF
slab. Cum

For 10 Cum

[A] Materials
Cement Bags 36.31 200.00 7262.00
Sand Cum 5.14 142.00 729.88
Brick bats Cum 10.28 175.00 1799.00
Total material rate 9790.88

[B] Labours
Skilled Nos. 3.10 150.00 465.00
Unskilled Nos. 23.30 90.00 2097.00
10% extra for rise 256.20
Total labour rate 2818.20

[C] Water + electric @ 2% of A+B --- --- 252.18

[D] Tools, Equipments & plants @ 2% A+B --- --- 252.18

[E] Scaffolding @ 2% A+B --- --- 56.54

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 2290.05

Total cost 15460.03


Unit Rate 1546

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.11
Providing and sinder concrete in 1:2:4
for sunk slab filling including curing
etc. complete above GF slab below FF
slab. Cum

For 10 Cum

[A] Materials
Cement Bags 65.55 200.00 13110.00
Sand Cum 4.88 142.00 692.96
Sinder Cum 9.55 500.00 4775.00
Total material rate 18577.96

[B] Labours
Skilled Nos. 3.10 150.00 465.00
Unskilled Nos. 23.30 90.00 2097.00
10% extra for rise 256.20
Total labour rate 2818.20

[C] Water + electric @ 2% of A+B --- --- 427.92

[D] Tools, Equipments & plants @ 2% A+B --- --- 427.92

[E] Scaffolding @ 2% A+B --- --- 55.80

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3660.72

Total cost 25968.53


Unit Rate 2597

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculation for rate analysis for Sinder concerte for 10 Cum

[A] Materials

1. Cement
Wet Mix = 10cu.m.

Dry Mix = 15.2 cu.m. (52% Shrinkage Factor)

Cement = 15.2 / 7
= 2.21 / 0.0345
= 64.26 Bags +2% Wastage
= 65.55 Bags

2. Sand
Qty = (15.2 x 2) / 7
= 4.34 + 10% Wastage
= 4.88 cu.m.

3. Sinder
Brick bats = (15.2 x 4) / 7
= 8.68 + 10% Wastage
= 9.55 cu.m.
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.12

Providing and laying reinforced cement


concrete in 1:1.5:3 (1-cement, 1.5-fine
agg. 3- coarse agg 20mm down size)
for column including curing etc.
complete excluding formwork and
reinforcement for above GF slab &
upto FF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 4.70 150.00 705.00
Unskilled Nos. 43.10 90.00 3879.00
10% extra for rise 458.40
Total labour rate 5042.40

[C] Water + electric @ 2% of A+B --- --- 498.72

[D] Tools, Equipments & plants @ 2% A+B --- --- 498.72


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 498.72

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3991.86

Total cost 30604.23

Unit Rate 3060

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.

3.13
Providing and laying reinforced cement
concrete in 1:1.5:3 (1-cement, 1.5-fine
agg. 3- coarse agg. 20mm down size)
for lintel bend and chajja above
including curing etc. complete
excluding formwork and reinforcement
for above GF slab upto FF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 4.60 150.00 690.00
Unskilled Nos. 39.10 90.00 3519.00
10% extra for rise 420.90
Total labour rate 4629.90

[C] Water + electric @ 2% of A+B --- --- 490.47


[D] Tools, Equipments & plants @ 2% A+B --- --- 490.47
Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 490.47

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3926.27

Total cost 30101.39

Unit Rate 3010

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.

3.14
Providing and laying reinforced cement
concrete in 1:1.5:3 (1-cement, 1.5-fine
agg. 3- coarse agg. 20mm down size)
for stair case including curing etc.
complete excluding formwork and
reinforcement for above GF slab upto
FF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 5.10 150.00 765.00
Unskilled Nos. 51.10 90.00 4599.00
10 % extra for rise 536.40
Total labour rate 5900.40
[C] Water + electric @ 2% of A+B --- --- 515.88

[D] Tools, Equipments & plants @ 2% A+B --- --- 515.88


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 515.88

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 4128.28

Total cost 31650

Unit Rate 3165.01

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.15
Providing and laying reinforced cement
concrete in 1:1.5:3 (1-cement, 1.5-fine
agg. 3- coarse agg. 20mm down size)
for concrete fins including curing etc.
complete excluding formwork and
reinforcement for above GF slab upto
FF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 5.30 150.00 795.00
Unskilled Nos. 53.00 90.00 4770.00
10 % extra for rise 556.50
Total labour rate 6121.50

[C] Water + electric @ 2% of A+B --- --- 520.31

[D] Tools, Equipments & plants @ 2% A+B --- --- 520.31


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 520.31

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 4163.43

Total cost 31919.65

Unit Rate 3192

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.16
Providing and laying reinforced cement
concrete in 1:1.5:3 (1-cement, 1.5-fine
agg. 3- coarse agg. 20mm down size)
for beam including curing etc.
complete excluding formwork and
reinforcement for above GF slab and
upto FF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 4.10 150.00 615.00
Unskilled Nos. 38.10 90.00 3429.00
Total labour rate 4044.00

[C] Water + electric @ 2% of A+B --- --- 478.76

[D] Tools, Equipments & plants @ 2% A+B --- --- 478.76


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 478.76

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3833.11

Total cost 29387.18

Unit Rate 2939

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.17

Providing and laying reinforced cement


concrete in 1:1.5:3 (1-cement, 1.5-fine
agg. 3- coarse agg. 20mm down size)
for slab including curing etc. complete
excluding formwork and reinforcement
for above GF upto FF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 5.00 150.00 750.00
Unskilled Nos. 30.10 90.00 2709.00
Total labour rate 3459.00

[C] Water + electric @ 2% of A+B --- --- 467.06

[D] Tools, Equipments & plants @ 2% A+B --- --- 467.06


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 467.06

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3740.1

Total cost 28674.06

Unit Rate 2867

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.18
Providing and laying BBCC in 1:4:8 (1-
cement, 4-fine agg. 8-brick bat)
including curing, ramming etc.
complete for above FF slab and upto
SF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 36.31 200.00 7262.00
Sand Cum 5.14 142.00 729.88
Brick bats Cum 10.28 175.00 1799.00
Total material rate 9790.88

[B] Labours
Skilled Nos. 3.10 150.00 465.00
Unskilled Nos. 23.30 90.00 2097.00
20% extra for rise 512.40
Total labour rate 3074.40

[C] Water + electric @ 2% of A+B --- --- 257.31

[D] Tools, Equipments & plants @ 2% A+B --- --- 257.31

[E] Scaffolding @ 2% A+B --- --- 257.31

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 2045.58

Total cost 15682.78

Unit Rate 1568

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.19
Providing and sinder concrete in 1:2:4
for sunk slab filling including curing
etc. complete above FF slab and upto
SF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 65.55 200.00 13110.00
Sand Cum 4.88 142.00 692.96
Sinder Cum 9.55 500.00 4775.00
Total material rate 18577.96

[B] Labours
Skilled Nos. 3.10 150.00 465.00
Unskilled Nos. 23.30 90.00 2097.00
20% extra for rise 512.40
Total labour rate 3074.40

[C] Water + electric @ 2% of A+B --- --- 433.05

[D] Tools, Equipments & plants @ 2% A+B --- --- 433.05

[E] Scaffolding @ 2% A+B --- --- 433.05

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3442.73

Total cost 26394.23

Unit Rate 2639

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.20

Providing and laying reinforced cement


concrete in 1:1.5:3 (1-cement, 1.5-fine
agg. 3- coarse agg 20mm down size)
for column including curing etc.
complete excluding formwork and
reinforcement for above FF slab and
upto SF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 4.70 150.00 705.00
Unskilled Nos. 43.10 90.00 3879.00
20% extra for rise 916.80
Total labour rate 5500.80

[C] Water + electric @ 2% of A+B --- --- 507.89

[D] Tools, Equipments & plants @ 2% A+B --- --- 507.89


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 507.89

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 4064.74

Total cost 31163.02

Unit Rate 3116

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.21

Providing and laying reinforced cement


concrete in 1:1.5:3 (1-cement, 1.5-fine
agg. 3- coarse agg.) for lintel bend and
chajja including curing etc. complete
excluding formwork and reinforcement
for above FF slab and upto SF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 4.60 150.00 690.00
Unskilled Nos. 39.10 90.00 3519.00
20% extra for rise 841.80
Total labour rate 5050.80

[C] Water + electric @ 2% of A+B --- --- 498.89

[D] Tools, Equipments & plants @ 2% A+B --- --- 498.89


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 498.89

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3993.19

Total cost 30614.47

Unit Rate 3061

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.22

Providing and laying reinforced cement


concrete in 1:1.5:3 (1-cement, 1.5-fine
agg. 3- coarse agg. 20mm down size)
for beam including curing etc.
complete excluding formwork and
reinforcement for above FF slab & upto
SF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 4.10 150.00 615.00
Unskilled Nos. 38.10 90.00 3429.00
20% extra for rise 808.80
Total labour rate 4852.80

[C] Water + electric @ 2% of A+B --- --- 494.93

[D] Tools, Equipments & plants @ 2% A+B --- --- 494.93


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 494.93

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3961.71

Total cost 30373.11

Unit Rate 3037

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.23

Providing and laying reinforced cement


concrete in 1:1.5:3 (1-cement, 1.5-fine
agg. 3- coarse agg. 20mm down size)
for slab including curing etc. complete
excluding formwork and reinforcement
for above FF slab upto SF slab. Cum

For 10 Cum

[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80

[B] Labours
Skilled Nos. 5.00 150.00 750.00
Unskilled Nos. 30.10 90.00 2709.00
20% extra for rise 691.80
Total labour rate 4150.80

[C] Water + electric @ 2% of A+B --- --- 480.89

[D] Tools, Equipments & plants @ 2% A+B --- --- 480.89


Mixer Machine (On Rent) 120.00
Needle Vibrator 60.00

[E] Scaffolding @ 2% A+B --- --- 480.89

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3850.09

Total cost 29517.37

Unit Rate 2952

Checked by:
Date: Page No.
Remarks

Rs

Rs/Cum
Remarks

For
10 Cum

Rs

Rs/Cum
Remarks

For
10 Cum

Rs

Rs/Cum
Remarks

For
10 Cum

Rs

Rs/Cum
Remarks

For
10 Cum

Rs

Rs/Cum
Remarks

For
10 Cum

Rs
Rs/Cum

Remarks

For
10 Cum

Rs
Rs/Cum

Remarks

For
10 Cum
Rs

Rs/Cum

Remarks

For
10 Cum
Rs

Rs/Cum

Remarks

Rs
Rs/Cum

Remarks

Rs
Rs/Cum
Remarks
For
10 Cum

Rs

Rs/Cum

Remarks
For
10 Cum

Rs

Rs/Cum

Remarks
For
10 Cum

Rs

Rs/Cum

Remarks
For
10 Cum

Rs

Rs/Cum

Remarks
For
10 Cum

Rs

Rs/Cum

Remarks
For
10 Cum

Rs

Rs/Cum

Remarks
Rs

Rs/Cum

Remarks
Rs

Rs/Cum

Remarks
For
10 Cum

Rs

Rs/Cum

Remarks
For
10 Cum

Rs

Rs/Cum

Remarks
For
10 Cum

Rs

Rs/Cum

Remarks
For
10 Cum

Rs

Rs/Cum
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
4.01 Providing and erecting formwork including
deshuttering etc. complete for plinth beam and Sq.m
coping below plinth upto 1.5m depth.

For 1.5 Sqm

[A] Materials
12mm ply wood BWR grade Sqm 1.8 485 58.20
(divided by 15 - no of repetitions)
Wooden battens Cum 0.04 12350 32.93
(divided by 15 - no of repetitions)
Nails kg 0.25 40 10
Binding wire kg 0.25 35 8.75
Deshuttering oil Lit 0.15 15 2.25
Total material rate 112.13

[B] Labours
Skilled 0.2 150 30
Unskilled 0.2 90 18
Total labour rate 48.00

[C] Water + electric @ 2% of A+B 0.00

[D] Tools, Equipments & plants @ 2% A+B 3.20

[E] Profit & overhead 24.50

Total cost 187.84

Unit Rate 125


Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
4.03 Providing and erecting formwork including
deshuttering etc. complete for padetal of column Sq.m
below plinth.

For 0.72 Sqm footing

[A] Materials
12mm ply wood BWR grade Sqm 0.8 485 25.87
(divided by 15 - no of repetitions)
Wooden battens Cum 0.02 12350 18.53
(divided by 15 - no of repetitions)
Nails kg 0.1 40 4
Binding wire kg 0.12 35 4.2
Deshuttering oil Lit 0.1 15 1.5
Total material rate 54.09

[B] Labours
Skilled 0.1 150 15
Unskilled 0.1 90 9
Total labour rate 24.00

[C] Water + electric @ 2% of A+B 0.00

[D] Tools, Equipments & plants @ 2% A+B 1.56

[E] Profit & overhead 11.95

Total cost 91.60

Unit Rate 127


Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculation for rate analysis for 0.72 Sqm footing

Materials
1. 12mm plywood
Length=2 x (1.2+1.2+0.03) =4.86 (here 0.3 is for thickness of ply for both sides)
Q=4.86 x 0.15=0.729 Sqm
Total =0.729+10% wastage=0.8 Sqm

2. Battens
Q=4.86 x 0.075 x 0.05=0.018 Cum
Q=4 x 0.5 x 0.050 x 0.025=0.0025 Cum
Total = 0.0205 + 10% wastage
= 0.0225
3. Nails
For first use for 10 Sqm= 5kg
For other 15 uses= 1 Kg / every use
Total weight= 20 Kg for 10 Sqm for 16 uses
Total weight per Sqm per use = 20/10 x 16 = 0.125 Kg / Sqm
Total weight for 0.72 Sqm=0.1 Kg

4. Binding Wire
Assume 0.1 kg

5. Deshuttering oil
Assume 0.1 Lit.
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
4.02 Providing and erecting formwork including
deshuttering etc. complete for column below Sq.m
plinth.

Rate analysis for 3.84 Sqm

[A] Materials
12mm ply wood BWR grade Sqm 4.38 485 141.62
(divided by 15 - no of repetitions)
Wooden battens Cum 0.06 12350 52.69
(divided by 15 - no of repetitions)
Props Nos. 6 50 15.00
(divided by 20 - no of repetitions)
Nails kg 0.38 40 15.2
Binding wire kg 0.4 35 14
Deshuttering oil Lit 0.25 15 3.75
Shakanja Nos. 4 40 3.2
Total material rate 242.26

[B] Labours
Skilled 0.96 150 144
Unskilled 0.77 90 69.3
Total labour rate 213.30

[C] Water + electric @ 2% of A+B 0.00

[D] Tools, Equipments & plants @ 2% A+B 9.11

[E] Profit & overhead 69.70

Total cost 534.38

Unit Rate 139


Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculations for rate analysis for 3.84 Sqm of column formwork

Materials
1. 12mm plywood
Q= 2 x 0.35 x 2.4 =1.68
Q=2 x (0.45 + 0.03) x 2.4=2.30 (here 0.3 is for thickness of ply for both sides)
Total =3.98+10% wastage=4.38

2. Battens
Vertical
Q=10 x 0.075 x 0.025 x 2.4=0.045
Horizontal
Q=2 x 3 x 0.075 x 0.025 x 0.50=0.0056
Q=2 x 3 x 0.075 x 0.025 x 0.35=0.0039
Q=2 x 4 x 0.25 x 0.075 x 0.025 =0.0038
(L=0.480-0.075-0.075-0.075=0.255)
Q=2 x 4 x 0.2 x 0.075 x 0.020 =0.0024
(L=0.350-0.075-0.075=0.2)
Total=0.0157
Total=0.061 + 5% wastage=0.064

3. Props
6 Nos.

4. Nails
For first use for 10 Sqm= 5kg
For other 15 uses= 1 Kg / every use
Total weight= 20 Kg for 10 Sqm for 16 uses
Total weight per Sqm per use = 20/10 x 16 = 0.125 Kg / Sqm
Total weight for 3.84 Sqm=0.48 Kg

5. Binding Wire
Assume 0.5 kg

6. Deshuttering oil
Assume 0.5 Lit.

7. Shakanja
Total 6 Nos.

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
4.04 Providing and erecting formwork including
deshuttering etc. complete for column above
Sq.m
plinth and upto Ground Floor slab.

Rate analysis for 3.84 Sqm

[A] Materials
12mm ply wood BWR grade Sqm 4.38 485 141.62
(divided by 15 - no of repetitions)
Wooden battens Cum 0.06 12350 52.69
(divided by 15 - no of repetitions)
Props Nos. 6 50 15.00
(divided by 20 - no of repetitions)
Nails kg 0.38 40 15.2
Binding wire kg 0.4 35 14
Deshuttering oil Lit 0.25 15 3.75
Shakanja Nos. 4 40 3.2
Total material rate 242.26

[B] Labours
Skilled 1 150 150
Unskilled 0.9 90 81
Total labour rate 231.00

[C] Water + electric @ 2% of A+B 0.00

[D] Tools, Equipments & plants @ 2% A+B 9.47

[E] Profit & overhead 72.41

Total cost 555.14

Unit Rate 145


Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
4.05 Providing and erecting formwork including
deshuttering etc. complete for lintel and chajja
Sq.m
above plinth and upto Ground Floor slab lvl.

Rate analysis for 2.99 Sqm

[A] Materials
12mm ply wood BWR grade Sqm 3.61 485.00 116.72
(divided by 15 - no of repetitions)
Wood Cum 0.02 12350.00 15.89
(divided by 15 - no of repetitions)
Props Nos. 3 50.00 7.50
(divided by 20 - no of repetitions)
Nails kg 0.5 40.00 20.00
Binding wire kg 0.5 35.00 17.50
Deshuttering oil Lit 0.4 15.00 6.00
Total material rate 183.61

[B] Labours
Skilled 0.80 150 120
Unskilled 0.69 90 62.1
Total labour rate 182.10

[C] Water + electric @ 2% of A+B 0.00

[D] Tools, Equipments & plants @ 2% A+B 7.31

[E] Profit & overhead 55.95

Total cost 428.98

Unit Rate 143


Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculations for rate analysis for 3.84 Sqm of column formwork

Materials
1. 12mm plywood
For sides 2 x 0.25 x 5=2.5 Sqm
For bottom = 1.3 x 0.23 = 0.3 Sqm
For bottom= 0.46 x 1.76 = 0.81 Sqm
Total = 3.61 Sqm

2. Wood
Qty = (5+ 0.46) x 2 x 0.025 x 0.050 =0.0136
Qty = 2 x 1.76 x 0.025 x 0.05=0.004
Total =0.0193
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
12.02 Providing and erecting formwork including
deshuttering etc. complete for Stair case from G.F. Sq.m
to F.F.

Rate analysis for 4.06 Sqm

[A] Materials
12mm ply wood BWR grade Sqm 4.59 485.00 148.41
(divided by 15 - no of repetitions)
Wood Cum 0.04 12350.00 30.46
(divided by 15 - no of repetitions)
Props Nos. 10 50.00 25.00
(divided by 20 - no of repetitions)
Nails kg 0.5 40.00 20.00
Binding wire kg 0.5 35.00 17.50
Deshuttering oil Lit 0.4 15.00 6.00
Total material rate 247.37

[B] Labours
Skilled 1.22 150 183
Unskilled 0.69 90 62.1
Total labour rate 245.10

[C] Water + electric @ 2% of A+B 0.00

[D] Tools, Equipments & plants @ 2% A+B 9.85

[E] Profit & overhead 75.35

Total cost 577.67


Unit Rate 142

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculations for rate analysis for 3.84 Sqm of column formwork

Materials
1. 12mm plywood
For Decking:
Inclined Length = 1.54 m
Q= 0.915 x 1.54 =1.41 Sqm
Landing = 0.915 x 0.665 m WAIST SLAB
OF FLIGHT 2
180
230

Q= 0.915 x 0.665 =0.84 Sqm PROJ ECTION


DUE TO WINDER
FLIGHT 1

For Risers:
Nos - 5 (0.180 x 0.915)
Q= 5 x 0.915 x 0.18 = 0.82 Sqm

For Strings: WAISTSLAB


15
40 665
LANDING
WINDER
(BRICK
MASONRY)
900

250

Flight Length = 1.54 m (.34 x 1.54) Nos. - 2


180

STEPS
1250

Q= 2 x 1.54 x 0.34 = 1.09 Sqm


Landing = 1.14 x 0.125 m (Sides - 2)
Q= 2 x 1.14 x 0.125 = 0.28 Sqm
For Winder Side a (0.915 x 0.23)
0.915+.030 = 0.945
Q= 0.945 x 0.23 = 0.22 Sqm
For Winder Side b (0.915 x 0.16)
Q= 0.915 x 0.18 = 0.16 Sqm
Total = 4.59 + 5% Wastage = 4.81 Sqm
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
4.06 Providing and erecting formwork including
deshuttering etc. complete for beam at Ground Sq.m
Floor slab.

For 1.98 Sqm beam formwork

[A] Materials
12mm ply wood BWR grade Sqm 1.68 485 54.22
(divided by 15 - no of repetitions)
Wooden battens Cum 0.07 12350 53.52
(divided by 15 - no of repetitions)
Props Nos 5 50 12.5
Nails kg 0.25 40 10
Binding wire kg 0.2 35 7
Deshuttering oil Lit 0.2 15 3
Shankaja Nos 5 40 4
Total material rate 140.24

[B] Labours
Skilled 0.59 150 88.5
Unskilled 0.4 90 36
Total labour rate 124.50

[C] Water + electric @ 2% of A+B 0.00

[D] Tools, Equipments & plants @ 2% A+B 5.29


[E] Profit & overhead 40.51

Total cost 310.54

Unit Rate 157

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculation for rate analysis for 1.98 Sqm beam formwork

Materials
1. 12mm plywood
Length=2 x (0.28+0.025) x 2.5=1.525 (here 0.025 is for thickness of ply for both sides)

Total =1.525+10% wastage=1.677 Sqm

2. Battens
Bottom=0.025 x 0.230 x2.5=0.0144 Cum
Sides=2 x 2 x 0.075 x 0.050 x 2.5=0.0375 Cum
Sides=2 x 6 x 0.130 x 0.050 x 0.025=0.00195 Cum
T head= 5 x 0.3 x 0.075 x 0.05=0.0056 Cum
Total = 0.0594 + 10% wastage
= 0.065 Cum

3. Props
Total Nos. 5

4. Nails
For first use for 10 Sqm= 5kg
For other 15 uses= 1 Kg / every use
Total weight= 20 Kg for 10 Sqm for 16 uses
Total weight per Sqm per use = 20/10 x 16 = 0.125 Kg / Sqm
Total weight for 1.975 Sqm=0.25
5. Binding Wire
Assume 0.2 kg

6. Deshuttering oil
Assume 0.2 Lit.

7. Shankaja
Total No 5

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
4.07 Providing and erecting formwork including
deshuttering etc. complete for Ground Floor slab. Sq.m

For 12.8 Sqm

[A] Materials
Shuttering plate Nos. 23.7 300 203.14
(divided by 35 - no of repetitions)
Wooden battens Cum 0.16 12350 130.09
(divided by 15 - no of repetitions)
Props Nos. 42 50 140.00
(divided by 15 - no of repetitions)
Nails kg 1.6 40 64
Binding wire kg 1.5 35 52.5
Deshuttering oil Lit 2 15 30
Total material rate 619.73

[B] Labours
Skilled 2.94 150 441
Unskilled 2.56 90 230.4
Total labour rate 671.40

[C] Water + electric @ 2% of A+B 0.00


[D] Tools, Equipments & plants @ 2% A+B 25.82

[E] Profit & overhead @ 15% of A+B+C+D 197.54

Total cost 1514.49

Unit Rate 118

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculation for 12.8 Sqm

[A] Materials
1. Shuttering plate
Area of 1 plate= 0.9 x 0.6=0.54 Sqm
No of Shuttering plates= 12.8/0.54 = 23.7 Nos

2. Battens
Total No= 4/0.9 = 5+1=6 Nos
Total volume= 6 x 3.2 x 0.1 x 0.075 = 0.144
Material wastage 10% = 0.144 x 1.1 = 0.158

3. Props
Total Nos.= 42 Nos

4. Nails
For first use for 10 Sqm= 5kg
For other 15 uses= 1 Kg / every use
Total weight= 20 Kg for 10 Sqm for 16 uses
Total weight per Sqm per use = 20/10 x 16 = 0.125 Kg / Sqm
Total weight for 12.8 Sqm=1.6 Kg

5. Binding Wire
Assume 1.5 Kg for 12.8 Sqm slab formwork
6. Deshuttering Oil
Assume 2 Lit. for 12.8 Sqm formwork

[B] Labours
Skilled 0.23 / Sqm
Unskilled 0.2/ Sqm
Total Skilled = 0.23 x 12.8= 2.94
Total Unskilled = 0.23 x 12.8= 2.54

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
4.08 Providing and erecting formwork including
deshuttering etc. complete for stub column of Sq.m
First Floor.

Rate analysis for 3.84 Sqm

[A] Materials
12mm ply wood BWR grade Sqm 4.38 485 141.62
(divided by 15 - no of repetitions)
Wooden battens Cum 0.06 12350 52.69
(divided by 15 - no of repetitions)
Props Nos. 6 50 15.00
(divided by 20 - no of repetitions)
Nails kg 0.38 40 15.2
Binding wire kg 0.4 35 14
Deshuttering oil Lit 0.25 15 3.75
Shakanja Nos. 4 40 3.2
Total material rate 242.26

[B] Labours
Skilled 1 150 150
Unskilled 0.9 90 81
10% extra for rise 23.1
Total labour rate 254.10

[C] Water + electric @ 2% of A+B 0.00

[D] Tools, Equipments & plants @ 2% A+B 9.93

[E] Profit & overhead 75.94

Total cost 582.23

Unit Rate 152

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
4.09 Providing and erecting formwork including
deshuttering etc. complete for lintel and chajja at Sq.m
First Floor Lintel Level.

Rate analysis for 2.99 Sqm

[A] Materials
12mm ply wood BWR grade Sqm 3.61 485.00 116.72
(divided by 15 - no of repetitions)
Wood Cum 0.02 12350.00 15.89
(divided by 15 - no of repetitions)
Props Nos. 3 50.00 7.50
(divided by 20 - no of repetitions)
Nails kg 0.5 40.00 20.00
Binding wire kg 0.5 35.00 17.50
Deshuttering oil Lit 0.4 15.00 6.00
Total material rate 183.61

[B] Labours
Skilled 0.80 150 120
Unskilled 0.69 90 62.1
10 % extra for rise 18.21
Total labour rate 200.31

[C] Water + electric @ 2% of A+B 0.00

[D] Tools, Equipments & plants @ 2% A+B 7.68

[E] Profit & overhead 58.74

Total cost 450.34

Unit Rate 151

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
4.14 Providing and erecting formwork including
deshuttering etc. complete for Sloping Roof at Sq.m
First Floor Lintel slab.

Rate analysis for 3.84 Sqm

[A] Materials
12mm ply wood BWR grade Sqm 4.38 485 141.62
(divided by 15 - no of repetitions)
Wooden battens Cum 0.06 12350 52.69
(divided by 15 - no of repetitions)
Props Nos. 6 50 15.00
(divided by 20 - no of repetitions)
Nails kg 0.38 40 15.2
Binding wire kg 0.4 35 14
Deshuttering oil Lit 0.25 15 3.75
Shakanja Nos. 4 40 3.2
Total material rate 242.26
[B] Labours
Skilled 1.2 150 180
Unskilled 1.1 90 99
10% extra for rise 27.9
Total labour rate 306.90

[C] Water + electric @ 2% of A+B 0.00

[D] Tools, Equipments & plants @ 2% A+B 10.98

[E] Profit & overhead 84.02

Total cost 644.17

Unit Rate 168

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
4.10 Providing and erecting formwork including
deshuttering etc. complete for beams First Floor
Sq.m
slab level.

For 1.98 Sqm beam formwork

[A] Materials
12mm ply wood BWR grade Sqm 1.68 485 54.22
(divided by 15 - no of repetitions)
Wooden battens Cum 0.07 12350 53.52
(divided by 15 - no of repetitions)
Props Nos 5 50 12.5
Nails kg 0.25 40 10
Binding wire kg 0.2 35 7
Deshuttering oil Lit 0.2 15 3
Shankaja Nos 5 40 4
Total material rate 140.24

[B] Labours
Skilled 0.59 150 88.5
Unskilled 0.4 90 36
10% extra for rise 12.45
Total labour rate 136.95

[C] Water + electric @ 2% of A+B 0.00

[D] Tools, Equipments & plants @ 2% A+B 5.54

[E] Profit & overhead 42.41

Total cost 325.14

Unit Rate 164

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
4.11 Providing and erecting formwork including
deshuttering etc. complete for First Floor slab. Sq.m

For 12.8 Sqm

[A] Materials
Shuttering plate Nos. 23.7 300 203.14
(divided by 35 - no of repetitions)
Wooden battens Cum 0.16 12350 130.09
(divided by 15 - no of repetitions)
Props Nos. 42 50 140.00
(divided by 15 - no of repetitions)
Nails kg 1.6 40 64
Binding wire kg 1.5 35 52.5
Deshuttering oil Lit 2 15 30
Total material rate 619.73

[B] Labours
Skilled 2.94 150 441
Unskilled 2.56 90 230.4
10% extra for rise 67.14
Total labour rate 738.54

[C] Water + electric @ 2% of A+B 0.00

[D] Tools, Equipments & plants @ 2% A+B 27.17

[E] Profit & overhead @ 15% of A+B+C+D 207.82

Total cost 1593.25

Unit Rate 124

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
4.12 Providing and erecting formwork including
deshuttering etc. complete for Lintel beams First Sq.m
Floor lintel level.

For 1.98 Sqm beam formwork

[A] Materials
12mm ply wood BWR grade Sqm 1.68 485 54.22
(divided by 15 - no of repetitions)
Wooden battens Cum 0.07 12350 53.52
(divided by 15 - no of repetitions)
Props Nos 5 50 12.5
Nails kg 0.25 40 10
Binding wire kg 0.2 35 7
Deshuttering oil Lit 0.2 15 3
Shankaja Nos 5 40 4
Total material rate 140.24
[B] Labours
Skilled 0.5 150 75
Unskilled 0.3 90 27
10% extra for rise 10.2
Total labour rate 112.20

[C] Water + electric @ 2% of A+B 0.00

[D] Tools, Equipments & plants @ 2% A+B 5.05

[E] Profit & overhead 38.62

Total cost 296.11

Unit Rate 150

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
4.13 Providing and erecting formwork including
deshuttering etc. complete for First Floor Lintel Sq.m
slab.

For 12.8 Sqm

[A] Materials
Shuttering plate Nos. 23.7 300 203.14
(divided by 35 - no of repetitions)
Wooden battens Cum 0.16 12350 130.09
(divided by 15 - no of repetitions)
Props Nos. 42 50 140.00
(divided by 15 - no of repetitions)
Nails kg 1.6 40 64
Binding wire kg 1.5 35 52.5
Deshuttering oil Lit 2 15 30
Total material rate 619.73
[B] Labours
Skilled 2.5 150 375
Unskilled 2 90 180
10% extra for rise 55.5
Total labour rate 610.50

[C] Water + electric @ 2% of A+B 0.00

[D] Tools, Equipments & plants @ 2% A+B 24.60

[E] Profit & overhead @ 15% of A+B+C+D 188.23

Total cost 1443.06

Unit Rate 113

Checked by:
Date: Page No.
Remarks

Rs/Sqm
Remarks

Rs/Sqm
es)
Remarks

Rs/Sqm
Remarks

Rs/Sqm
Remarks

Rs/Sqm
Remarks
Rs/Sqm
Remarks
Rs/Sqm

oth sides)
Remarks
Rs

Rs / Sqm
Remarks
Rs/Sqm

Remarks
Rs/Sqm

Remarks
Rs/Sqm

Remarks
Rs/Sqm

Remarks
Rs

Rs / Sqm

Remarks
Rs/Sqm

Remarks
Rs

Rs / Sqm
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount Remarks
No.
5.01 Providing, fabricating & erecting tor steel ( yield
strength 4250 kg/cm2 ) bars for RCC work
Including binding, bending and placing in position
etc. complete. for below plinth level. (coping, Kg.
footing, plinth beam, column)

For 100 Kg

[A] Materials
Reinforcement Bars kgs. 102.00 33.00 3366.00
Binding wire (@ 1.3kg/ 100kgs.) kgs. 13.00 35.00 455.00
Total material rate 3821.00

[B] Labours
Skilled 1 150 150
Unskilled 1 90 90
Total labour rate 240.00

[C] Water + electric @ 2% of A+B --- --- 0.00

[D] Tools, Equipments & plants @ 2% A+B --- --- 81.22

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 621.33

Total cost 4763.55 Rs

Unit Rate 48 Rs / Kg

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount Remarks
No.
5.02 Providing, fabricating & erecting mild steel ( yield
strength 2600 kg/cm2 )bars for RCC work
Including binding, bending and placing in position
Kg.
etc. complete for below plinth level. (coping,
footing, plinth beam, column)

For 100 Kg

[A] Materials
Reinforcement Bars kgs. 102.00 31.00 3162.00
Binding wire (@ 1.3kg/ 100kgs.) kgs. 13.00 35.00 455.00
Total material rate 3617.00

[B] Labours
Skilled 1 150 150
Unskilled 1 90 90
Total labour rate 240.00

[C] Water + electric @ 2% of A+B --- --- 0.00

[D] Tools, Equipments & plants @ 2% A+B --- --- 77.14

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 590.12

Total cost 4524.26 Rs

Unit Rate 45 Rs / Kg
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount Remarks
No.
5.03 Providing, fabricating & erecting tor steel ( yield
strength 4250 kg/cm2 ) bars for RCC work
Including binding, bending and placing in position
Kg.
etc. complete. for Ground Floor slab level.
(beam, slab, stub column)

For 100 Kg

[A] Materials
Reinforcement Bars kgs. 102.00 33.00 3366.00
Binding wire (@ 1.3kg/ 100kgs.) kgs. 13.00 35.00 455.00
Total material rate 3821.00

[B] Labours
Skilled 1 150 150
Unskilled 1 90 90
Total labour rate 240.00

[C] Water + electric @ 2% of A+B --- --- 0.00

[D] Tools, Equipments & plants @ 2% A+B --- --- 81.22

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 621.33

Total cost 4763.55 Rs

Unit Rate 48 Rs / Kg
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount Remarks
No.
5.04 Providing, fabricating & erecting mild steel ( yield
strength 2600 kg/cm2 )bars for RCC work
Including binding, bending and placing in position
etc. complete for Ground Floor slab level. Kg.
(beam, slab, stub column)

For 100 Kg

[A] Materials
Reinforcement Bars kgs. 102.00 31.00 3162.00
Binding wire (@ 1.3kg/ 100kgs.) kgs. 13.00 35.00 455.00
Total material rate 3617.00

[B] Labours
Skilled 1 150 150
Unskilled 1 90 90
Total labour rate 240.00

[C] Water + electric @ 2% of A+B --- --- 0.00

[D] Tools, Equipments & plants @ 2% A+B --- --- 77.14

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 590.12

Total cost 4524.26 Rs

Unit Rate 45 Rs / Kg
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount Remarks
No.
5.05 Providing, fabricating & erecting tor steel ( yield
strength 4250 kg/cm2 ) bars for RCC work
Including binding, bending and placing in position
Kg.
etc. complete. for First Floor slab level. (beam,
slab, stub column)

For 100 Kg

[A] Materials
Reinforcement Bars kgs. 102.00 33.00 3366.00
Binding wire (@ 1.3kg/ 100kgs.) kgs. 13.00 35.00 455.00
Total material rate 3821.00

[B] Labours
Skilled 1 150 150
Unskilled 1 90 90
10% extra for rise 24
Total labour rate 264.00

[C] Water + electric @ 2% of A+B --- --- 0.00

[D] Tools, Equipments & plants @ 2% A+B --- --- 81.70

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 625.01

Total cost 4791.71 Rs

Unit Rate 48 Rs / Kg
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount Remarks
No.
5.06 Providing, fabricating & erecting mild steel ( yield
strength 2600 kg/cm2 )bars for RCC work
Including binding, bending and placing in position
Kg.
etc. complete for First Floor slab level. (beam,
slab, stub column)

For 100 Kg

[A] Materials
Reinforcement Bars kgs. 102.00 31.00 3162.00
Binding wire (@ 1.3kg/ 100kgs.) kgs. 13.00 35.00 455.00
Total material rate 3617.00

[B] Labours
Skilled 1 150 150
Unskilled 1 90 90
10% extra for rise 24
Total labour rate 264.00

[C] Water + electric @ 2% of A+B --- --- 0.00

[D] Tools, Equipments & plants @ 2% A+B --- --- 72.82

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 557.07

Total cost 4270.89 Rs

Unit Rate 43 Rs / Kg

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.01 Proving and laying 20 mm thick double coat Mala
finished cement plaster consisty of 10mm thick
cement plaster each in two coats on fair sides of
Brick walls for interior plastering in C.M. 1:3 (1 Sq.m
cement : 3 sand) including Mala finishing etc.
complete for

For 100 Sqm

[A] Materials
Cement Bags 16.94 160.00 2710.40
Sand Cum 2.29 110.00 251.90
Total material rate 2962.30

[B] Labours
Skilled 8.50 150 1275
Unskilled 28.00 90 2520
Total labour rate 3795.00

[C] Water + electric @ 2% of A+B --- --- 135.15

[D] Tools, Equipments & plants @ 2% A+B --- --- 135.15

[E] Scaffolding @ 2% A+B --- --- 135.15

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1074.41

Total cost 8237.15

Unit Rate 82

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculations for rate analysis of 100 Sqm

[A] Materials
1st Coat (1:4)
Wet Mortar = 100 x 0.012
= 1.20 + 10% Wastage
= 1.32 cu.m.
Dry Mortar = 1.32 x 1.25 (25% Shrinkage)
= 1.65 cu.m.

Cement = 1.65 / 5
= 0.33 + 2% Wastage
= 0.34 / 0.345
= 9.60 Bags

Sand = (1.65 x 4) / 5
= 1.32 + 10% Wastage
= 1.45 cu.m.

2nd Coat (1:3)


Wet Mortar = 100 x 0.008
= 0.80 + 10% Wastage
= 0.82 cu.m.
Dry Mortar = 0.82 x 1.25 (25% Shrinkage)
= 1.02 cu.m.

Cement = 1.02 / 4
= 0.255 + 2% Wastage
= 0.26 / 0.345
= 7.34 Bags

Sand = (1.02 x 3) / 4
= 0.765 + 10% Wastage
= 0.84 cu.m.
For Third coat = 10 Kg
Total weight=30.7 Kg + 10% wastage
Total qty = 33.77 Kg
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.02 Proving and laying 20 mm thick double coat Mala
finished cement plaster consisty of 10mm thick
cement plaster each in two coats on ceiling, soffit
of beam of concrete for interior plastering in C.M. Sq.m
1:3 (1 cement : 3 sand) including Mala finishing
etc. co

For 100 Sqm

[A] Materials
Cement Bags 7.07 160.00 1131.20
Sand Cum 1.08 110.00 118.80
Total material rate 1250.00

[B] Labours
Skilled 4.00 150 600
Unskilled 20.00 90 1800
Total labour rate 2400.00

[C] Water + electric @ 2% of A+B --- --- 73.00

[D] Tools, Equipments & plants @ 2% A+B --- --- 73.00

[E] Scaffolding @ 2% A+B --- --- 73.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 580.35

Total cost 4449.35

Unit Rate 44
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculations for rate analysis of 100 Sqm

[A] Materials
Proportion 1:4
Wet Mortar = 100 x 0.010
= 1.00 + 10% Wastage
= 1.1 cu.m.
Dry Mortar = 1.1 x 1.25 (25% Shrinkage)
= 1.23 Cum

Cement = 1.45 / 5
= 0.24 + 2% Wastage
= 0.244 / 0.345
= 7.07 Bags

Sand = (1.65 x 4) / 5
= 0.98 + 10% Wastage
= 1.08 Cum
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.03 Providing & applying 20mm thick double coat sand
face external plaster consisry of 10mm thick
plaster each in two coats, first coat in CM 1:4
(1cement : 4sand), second coat in CM 1:2 (1cemnt Sq.m
: 2sand) on fair sides of Brick wall including
scaffolding, curi

For 100 Sqm

[A] Materials
Cement Bags 15.68 160.00 2508.80
Sand Cum 2.35 110.00 258.50
Total material rate 2767.30

[B] Labours
Skilled 9.50 150 1425
Unskilled 30.00 90 2700
Total labour rate 4125.00

[C] Water + electric @ 2% of A+B --- --- 137.85

[D] Tools, Equipments & plants @ 2% A+B --- --- 137.85

[E] Scaffolding @ 2% A+B --- --- 137.85

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1095.88

Total cost 8401.71

Unit Rate 84
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculations for rate analysis of 100 Sqm

[A] Materials
1st Coat (1:4)
Wet Mortar = 100 x 0.012
= 1.20 + 10% Wastage
= 1.32 cu.m.
Dry Mortar = 1.32 x 1.25 (25% Shrinkage)
= 1.65 cu.m.

Cement = 1.65 / 5
= 0.33 + 2% Wastage
= 0.34 / 0.345
= 9.60 Bags

Sand = (1.65 x 4) / 5
= 1.32 + 10% Wastage
= 1.45 cu.m.

2nd Coat (1:4)


Wet Mortar = 100 x 0.008
= 0.80 + 10% Wastage
= 0.82 cu.m.
Dry Mortar = 0.82 x 1.25 (25% Shrinkage)
= 1.02 cu.m.

Cement = 1.02 / 5
= 0.204 + 2% Wastage
= 0.21 / 0.345
= 6.08 Bags

Sand = (1.02 x 4) / 5
= 0.816 + 10% Wastage
= 0.90 cu.m.
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.10 Proving and laying 20 mm thick double coat Mala
finished cement plaster consisty of 10mm thick
cement plaster each in two coats on over head
water tank plastering in C.M. 1:3 (1 cement : 3 Sq.m
sand) including Mala finishing etc. complete for
Tarrace.

For 100 Sqm

[A] Materials
Cement Bags 16.94 160.00 2710.40
Sand Cum 2.29 110.00 251.90
Total material rate 2962.30

[B] Labours
Skilled 8.50 150 1275
Unskilled 28.00 90 2520
10% extra for rise 379.5
Total labour rate 4174.50

[C] Water + electric @ 2% of A+B --- --- 142.74

[D] Tools, Equipments & plants @ 2% A+B --- --- 142.74

[E] Scaffolding @ 2% A+B --- --- 142.74

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1134.75

Total cost 8699.76

Unit Rate 87
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.06 Proving and laying 20 mm thick double coat Mala
finished cement plaster consisty of 10mm thick
cement plaster each in two coats on ceiling, soffit
of beam of concrete for interior plastering in
C.M. 1:3 (1 cement : 3 sand) including Mala Sq.m
finishing etc. complete for First Floor.

For 100 Sqm

[A] Materials
Cement Bags 16.94 160.00 2710.40
Sand Cum 2.29 110.00 251.90
Water proofing agent @ 100ml/bag Lit 1.69 100.00 169.00
Total material rate 3131.30

[B] Labours
Skilled 8.00 150 1200
Unskilled 28.00 90 2520
10 % extra for rise 37.2
Total labour rate 3757.20

[C] Water + electric @ 2% of A+B --- --- 137.77

[D] Tools, Equipments & plants @ 2% A+B --- --- 137.77

[E] Scaffolding @ 2% A+B --- --- 137.77

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1095.27

Total cost 8397.08

Unit Rate 84
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.04 Providing & applying 20mm thick double coat sand
face external plaster consisry of 10mm thick
plaster each in two coats, first coat in CM 1:4
(1cement : 4sand), second coat in CM 1:2 (1cemnt Sq.m
: 2sand) on fair sides of Concrete slab including
scaffolding, c

For 100 Sqm

[A] Materials
Cement Bags 15.68 160.00 2508.80
Sand Cum 2.35 110.00 258.50
Total material rate 2767.30

[B] Labours
Skilled 9.50 150 1425
Unskilled 30.00 90 2700
10% extra for lift 412.5
Total labour rate 4537.50

[C] Water + electric @ 2% of A+B --- --- 146.10

[D] Tools, Equipments & plants @ 2% A+B --- --- 146.10

[E] Scaffolding @ 2% A+B --- --- 146.10

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1161.46

Total cost 8904.55

Unit Rate 89
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.05 Proving and laying 20 mm thick double coat Mala
finished cement plaster consisty of 10mm thick
cement plaster each in two coats on fair sides of
Brick walls for interior plastering in C.M. 1:3 (1 Sq.m
cement : 3 sand) including Mala finishing etc.
complete for First Floor.

For 100 Sqm

[A] Materials
Cement Bags 16.94 160.00 2710.40
Sand Cum 2.29 110.00 251.90
Total material rate 2962.30

[B] Labours
Skilled 8.50 150 1275
Unskilled 28.00 90 2520
20% extra for rise 759
Total labour rate 4554.00

[C] Water + electric @ 2% of A+B --- --- 150.33

[D] Tools, Equipments & plants @ 2% A+B --- --- 150.33

[E] Scaffolding @ 2% A+B --- --- 150.33

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1195.09

Total cost 9162.37

Unit Rate 92
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.09 Providing & applying 20mm thick double coat
sand face external plaster consisry of 10mm thick
plaster each in two coats, first coat in CM 1:4
(1cement : 4sand), second coat in CM 1:2 (1cemnt
: 2sand) on both sides of Brick wall including Sq.m
scaffolding, curing etc. complete for at Tarrace
level.

For 100 Sqm

[A] Materials
Cement Bags 7.07 160.00 1131.20
Sand Cum 1.08 110.00 118.80
Total material rate 1250.00

[B] Labours
Skilled 4.00 150 600
Unskilled 20.00 90 1800
20% extra for rise 480
Total labour rate 2880.00

[C] Water + electric @ 2% of A+B --- --- 82.60

[D] Tools, Equipments & plants @ 2% A+B --- --- 82.60

[E] Scaffolding @ 2% A+B --- --- 82.60

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 656.67

Total cost 5034.47


Unit Rate 50

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.07 Providing & applying 20mm thick double coat
sand face external plaster consisry of 10mm thick
plaster each in two coats, first coat in CM 1:4
(1cement : 4sand), second coat in CM 1:2 (1cemnt
Sq.m
: 2sand) on fair sides of Brick wall including
scaffolding, curing etc. complete for at First Floor
level.

For 100 Sqm

[A] Materials
Cement Bags 15.68 160.00 2508.80
Sand Cum 2.35 110.00 258.50
Total material rate 2767.30

[B] Labours
Skilled 9.50 150 1425
Unskilled 30.00 90 2700
20% extra for lift 825
Total labour rate 4950.00

[C] Water + electric @ 2% of A+B --- --- 154.35

[D] Tools, Equipments & plants @ 2% A+B --- --- 154.35

[E] Scaffolding @ 2% A+B --- --- 154.35

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1227.05


Total cost 9407.39

Unit Rate 94

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.08 Providing & applying 20mm thick double coat
sand face external plaster consisry of 10mm thick
plaster each in two coats, first coat in CM 1:4
(1cement : 4sand), second coat in CM 1:2 (1cemnt
: 2sand) on fair sides of Concrete slab including Sq.m
scaffolding, curing etc. complete for at First Floor
level.

For 100 Sqm

[A] Materials
Cement Bags 15.68 160.00 2508.80
Sand Cum 2.35 110.00 258.50
Total material rate 2767.30

[B] Labours
Skilled 9.50 150 1425
Unskilled 30.00 90 2700
30% extra for lift 1237.5
Total labour rate 5362.50

[C] Water + electric @ 2% of A+B --- --- 162.60

[D] Tools, Equipments & plants @ 2% A+B --- --- 162.60

[E] Scaffolding @ 2% A+B --- --- 162.60


[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1292.64

Total cost 9910.23

Unit Rate 99

Checked by:
Date: Page No.
Remarks

Rs

Rs / Sqm
Remarks

Rs

Rs / Sqm
Remarks

Rs

Rs / Sqm
Remarks

Rs

Rs / Sqm
Remarks

Rs

Rs / Sqm
Remarks

Rs

Rs / Sqm
Remarks

Rs

Rs / Sqm
Remarks

Rs
Rs / Sqm

Remarks
Rs

Rs / Sqm

Remarks
Rs

Rs / Sqm
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
10.01 Providing and fixing frame of C P sag and
glassed window including hardware, finishing etc. Sq.m
complete at Ground Floor level.

For 1.78 Sqm

[A] Materials
Teak Wood Cum 0.07 20000.00 1340.00
Glass Sqm 1.23 300.00 369.00
Beading Rmt 3.47 21.00 72.79
Bars Kg 10.85 32.00 347.20
Hardware
Handles Nos. 2.00 15.00 30.00
Hook & Eye Nos. 4.00 7.00 28.00
Butt Hinges Nos. 4.00 9.00 36.00
Stopper Nos. 4.00 10.00 40.00
Holdfast Nos. 4.00 3.00 12.00
Nails + Fevicol (2% of Hardware) 2.92
Total material rate 2277.91

[B] Labours
Skilled 2.31 150 346.5
Unskilled 0.71 90 63.9
Fixing 40
Total labour rate 450.40

[C] Water + electric @ 2% of A+B --- --- 54.57

[D] Tools, Equipments & plants @ 2% A+B --- --- 54.57

[E] Scaffolding @ 2% A+B --- --- 54.57

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 433.80

Total cost 3325.81

Unit Rate 1868

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculations for rate analysis of 1.92 Sqm

[A] Materials

For Shutter:
1. Wood(30 mm):
Style (Nos. - 4)
Q= 4 x 0.03 x 0.075 x 1.3 = 0.0117 Cum
Rails (Nos. - 4)
Q= 4 x 0.03 x 0.075 x 0.685 = 0.00616 Cum
For Frame: (125 x 65)
Length = 1.37+1.37+1.3+1.3 = 5.34
Q= 0.125 x 0.065 x 5.34 = 0.0433 Cum
Total = 0.06116Cum
1520

Total = 0.06116 + 10% Wastage = 0.0672 685


535

HORNS
RAILS
HOLDFAST

GLAZING

2. Glass (6 mm):
1300
1150

FRAME
BEADING

Q= 2 x 0.535 x 1.15 = 1.23 Sqm

3. Beading: (0.685 + 1.15)


Q= 2 x 2 x 0.685 x 1.15 = 3.466 Cum
Total = 0.0024 + 5% Wastage = 0.0036
4. For steel bar (Nos. - 9)
Q= 9 x 0.88 x 1.37 = 10.85 Kg
Total = 10.85 + 5% Wastage = 16.275
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
10.02 Providing and fixing frame of C P sag and flushed
door including hardware, finishing etc. complete at Sq.m
Ground Floor level.

For 1.92 Sqm

[A] Materials
BlockBoard Sqm 1.92 550.00 1056.00
6mm Plywood Sqm 3.84 260.00 998.40
Wood Cum 0.04 20000.00 878.00
Hardware
Handles Nos. 2.00 20.00 40.00
Tower Bolts Nos. 1.00 15.00 15.00
Butt Hinges Nos. 3.00 11.00 33.00
Aldrop Nos. 1.00 15.00 15.00
Holdfast Nos. 6.00 3.00 18.00
Nails + Fevicol (2% of Hardware) 2.42
Total material rate 3055.82

[B] Labours
Skilled 2.49 150 373.5
Unskilled 0.77 90 69.12
Fixing 40
Total labour rate 482.62

[C] Water + electric @ 2% of A+B --- --- 70.77

[D] Tools, Equipments & plants @ 2% A+B --- --- 70.77

[E] Scaffolding @ 2% A+B --- --- 70.77

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 562.61

Total cost 4313.36

Unit Rate 2247


Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculations for rate analysis of 1.92 Sqm

[A] Materials

For Shutter:
1. Block Board (25 mm):
Q= 0.915 x 2.1 = 1.92 Sqm
Total = 1.92 + 5% Wastage = 0.096

2. Plywood (6 mm): 915

Q= 2 x 0.915 x 2.1 = 3.84 Sqm HORNS

Total = 3.84 + 5% Wastage = 4.03 HO LDFAS T

W O ODE N FR AME
2100

3. Wood (5 mm): L= 6.03


Q= 2 x 0.040 x 6.03 x 0.005 = 0.0024 Cum
Total = 0.0024 + 5% Wastage = 0.0036

For Frame: (125 x 65)


3. Wood
Length = 2.1+2.1+0.915 =5.115
Q= 0.125 x 0.065 x 5.115 = 0.0415 Cum
Total = 0.0415 + 5% Wastage = 0.0436
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
10.05 Providing and fixing frame of C P sag and
glassed window including hardware, finishing etc. Sq.m
complete at First Floor level.

For 1.78 Sqm

[A] Materials
Teak Wood Cum 0.07 20000.00 1340.00
Glass Sqm 1.23 300.00 369.00
Beading Rmt 3.47 21.00 72.79
Bars Kg 10.85 32.00 347.20
Hardware
Handles Nos. 2.00 15.00 30.00
Hook & Eye Nos. 4.00 7.00 28.00
Butt Hinges Nos. 4.00 9.00 36.00
Stopper Nos. 4.00 10.00 40.00
Holdfast Nos. 4.00 3.00 12.00
Nails + Fevicol (2% of Hardware) 2.92
Total material rate 2277.91

[B] Labours
Skilled 2.31 150 346.5
Unskilled 0.71 90 63.9
Fixing 60
Total labour rate 470.40

[C] Water + electric @ 2% of A+B --- --- 54.97

[D] Tools, Equipments & plants @ 2% A+B --- --- 54.97

[E] Scaffolding @ 2% A+B --- --- 54.97

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 436.98

Total cost 3350.19


Unit Rate 1882

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
10.06 Providing and fixing frame of C P sag and
flushed door including hardware, finishing etc. Sq.m
complete at First Floor level.

For 1.92 Sqm

[A] Materials
BlockBoard Sqm 1.92 550.00 1056.00
6mm Plywood Sqm 3.84 260.00 998.40
Wood Cum 0.04 20000.00 878.00
Hardware
Handles Nos. 2.00 20.00 40.00
Tower Bolts Nos. 1.00 15.00 15.00
Butt Hinges Nos. 3.00 11.00 33.00
Aldrop Nos. 1.00 15.00 15.00
Holdfast Nos. 6.00 3.00 18.00
Nails + Fevicol (2% of Hardware) 2.42
Total material rate 3055.82

[B] Labours
Skilled 2.49 150 373.5
Unskilled 0.77 90 69.12
Fixing 60
Total labour rate 502.62

[C] Water + electric @ 2% of A+B --- --- 71.17

[D] Tools, Equipments & plants @ 2% A+B --- --- 71.17

[E] Scaffolding @ 2% A+B --- --- 71.17

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 565.79

Total cost 4337.74

Unit Rate 2259


Checked by:
Date: Page No.
Remarks

Rs

Rs / Sqm
Remarks

Rs

Rs / Sqm
Remarks

Rs
Rs / Sqm

Remarks

Rs

Rs / Sqm
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.01

Providing and laying marble flooring


with bed mortar 1:8 (1 cement, 8sand)
including cutting finishing, filling up of
joints, polishing etc. complete for
above plinth lvl. below GF slab. Sqm

For 100 Sqm

[A] Materials
Cement (OPC) Bags 26.00 160.00 4160.00
Sand Cum 5.88 110.00 646.80
White Cement Bags 6.00 550.00 3300.00
Marble (With Polishing) Sqm 105.00 970.00 101850.00
Total material rate 109956.80

[B] Labours
Skilled 5.20 150 780
Unskilled 9.80 90 882
Total labour rate 1662.00

[C] Water + electric @ 2% of A+B --- --- 2232.38

[D] Tools, Equipments & plants @ 2% A+B --- --- 2232.38

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 17412.53

Total cost 133496.08

Unit Rate 1335


Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculations for rate analysis of 100 Sqm

[A] Materials
Marble = 100 sq.m. + 5% Wastage
= 105 sq.m.

Wet Mortar = 100 x 0.05


= 5 cu.m.
Dry Mortar = 5 cu.m. x 1.25 (Shrinkage Factor 25%)
= 6.25 cu.m.

Cement = 6.25 / 7
= 0.89 + 2% Wastage
= 0.90 / 0.0345
= 26 Bags

Sand = 6.25 x 6 / 7
= 5.35 + 10% Wastage
= 5.88 cu.m.

White Cement = 3 kg. per sq.m.


= 3 x 100
= 300 kgs.
= 3 Bags.
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.02
Providing and laying marble skirting of
75mm including cutting finishing,
filling up of joints, polishing etc.
complete. For above plinth lvl. below
GF slab. Rmt

For 100 Rmt

[A] Materials
Cement (OPC) Bags 2.21 160.00 353.60
Sand Cum 0.08 110.00 8.80
White Cement Bags 0.47 550.00 258.50
Marble (With Polishing) Sqm 7.88 970.00 7643.60
Total material rate 8264.50

[B] Labours
Skilled 4.00 150 600
Unskilled 4.00 90 360
Total labour rate 960.00

[C] Water + electric @ 2% of A+B --- --- 184.49

[D] Tools, Equipments & plants @ 2% A+B --- --- 184.49

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1439.02

Total cost 11032.50

Unit Rate 110


Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculations for rate analysis of 100 Sqm

[A] Materials
Marble = 100 x 0.075
= 7.5 sq.m. + 5% Wastage
= 7.88 sq.m.
Wet Mortar = 100 x 0.075 x 0.015
= 0.1125 cu.m. + 5% Wastage
= 0.12 cu.m.

Dry Mortar = 0.12 x 1.25 (Shrinkage Factor 25%)


= 0.15 cu.m.

Cement = 0.15 / 2 = 0.075 + 2% Wastage


= 2.21 Bags

Sand = 0.15 / 2 = 0.075 + 10% Wastage


= 0.08 cu.m.

White Cement = 3 kgs. per sq.m.


= 3 x 7.88 = 23.64kgs.
= 0.47 bags
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.03
Providing and laying of glazed tiles for
floor in bathroom terrace etc. including
cutting finishing, filling up of joints etc.
complete. for above plinth lvl. below
GF slab. Sqm

For 100 Sqm

[A] Materials
Cement (OPC) Bags 26.00 160.00 4160.00
Sand Cum 5.88 110.00 646.80
Glazed Tiles Sqm 105.00 375.00 39375.00
White cement Bags 0.50 550.00 275.00
Colouring pigment Kg 1.00 75.00 75.00
Total material rate 44531.80

[B] Labours
Skilled 4.70 150 705
Unskilled 9.10 90 819
Total labour rate 1524.00

[C] Water + electric @ 2% of A+B --- --- 921.12

[D] Tools, Equipments & plants @ 2% A+B --- --- 921.12

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 7184.70

Total cost 55082.74

Unit Rate 551


Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.04

Providing and laying of glazed tiles for


vertical surface in bathroom, kitchen
etc. including cutting finishing, filling
up of joints etc. complete. for above
plinth lvl. below GF slab. Sqm

For 100 Sqm

[A] Materials
Cement (OPC) Bags 18.49 160.00 2958.40
Sand Cum 0.69 110.00 75.90
Glazed Tiles Sqm 105.00 375.00 39375.00
White cement Bags 0.50 550.00 275.00
Colouring pigment Kg 1.00 75.00 75.00
Total material rate 42759.30

[B] Labours
Skilled 5.00 150 750
Unskilled 10.00 90 900
Total labour rate 1650.00

[C] Water + electric @ 2% of A+B --- --- 888.19

[D] Tools, Equipments & plants @ 2% A+B --- --- 888.19

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 6927.85

Total cost 53113.52

Unit Rate 531


Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.05
Providing and laying marble flooring
for steps with bed mortar 1:8 (1
cement, 8sand) including cutting
finishing, filling up of joints, polishing
etc. complete for above plinth lvl.
below GF slab. Sqm

For 100 Sqm

[A] Materials
Cement (OPC) Bags 26.00 160.00 4160.00
Sand Cum 5.88 110.00 646.80
White Cement Bags 5.00 550.00 2750.00
Marble (With Polishing) Sqm 105.00 970.00 101850.00
Total material rate 109406.80

[B] Labours
Skilled 6.20 150 930
Unskilled 11.00 90 990
Total labour rate 1920.00

[C] Water + electric @ 2% of A+B --- --- 2226.54

[D] Tools, Equipments & plants @ 2% A+B --- --- 2226.54

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 17366.98

Total cost 133146.85


Unit Rate 1331

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.06
Providing and laying marble skirting
75mm for steps with including cutting
finishing, filling up of joints, polishing
etc. complete for above plinth lvl.
below GF slab. Nos.

For 100 Nos

[A] Materials
Cement (OPC) Bags 1.00 160.00 160.00
Sand Cum 0.10 110.00 11.00
White Cement Bags 0.25 550.00 137.50
Marble (With Polishing) Sqm 2.50 970.00 2425.00
Total material rate 2733.50

[B] Labours
Skilled 2.00 150 300
Unskilled 2.00 90 180
Total labour rate 480.00

[C] Water + electric @ 2% of A+B --- --- 64.27

[D] Tools, Equipments & plants @ 2% A+B --- --- 64.27

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 501.31

Total cost 3843.35


Unit Rate 38

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.08

Providing and laying marble flooring


with bed mortar 1:8 (1 cement, 8sand)
including cutting finishing, filling up of
joints, polishing etc. complete for
above GF slab below FF slab. Sqm

For 100 Sqm

[A] Materials
Cement (OPC) Bags 26.00 160.00 4160.00
Sand Cum 5.88 110.00 646.80
White Cement Bags 5.00 550.00 2750.00
Marble (With Polishing) Sqm 105.00 970.00 101850.00
Total material rate 109406.80

[B] Labours
Skilled 5.20 150 780
Unskilled 9.80 90 882
10% extra for rise 166.2
Total labour rate 1828.20

[C] Water + electric @ 2% of A+B --- --- 2224.70

[D] Tools, Equipments & plants @ 2% A+B --- --- 2224.70

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 17352.66


Total cost 133037.06

Unit Rate 1330

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.09
Providing and laying marble skirting of
75mm including cutting finishing,
filling up of joints, polishing etc.
complete for above GF slab below FF
slab. Rmt

For 100 Rmt

[A] Materials
Cement (OPC) Bags 2.21 160.00 353.60
Sand Cum 0.08 110.00 8.80
White Cement Bags 0.47 550.00 258.50
Marble (With Polishing) Sqm 7.88 970.00 7643.60
Total material rate 8264.50

[B] Labours
Skilled 4.00 150 600
Unskilled 4.00 90 360
10% extra for rise 96
Total labour rate 1056.00

[C] Water + electric @ 2% of A+B --- --- 186.41

[D] Tools, Equipments & plants @ 2% A+B --- --- 186.41

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1454.00


Total cost 11147.32

Unit Rate 111

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.10
Providing and laying of glazed tiles for
floor in bathroom terrace etc. including
cutting finishing, filling up of joints etc.
complete. for above GF slab below FF
slab. Sqm

For 100 Sqm

[A] Materials
Cement (OPC) Bags 26.00 160.00 4160.00
Sand Cum 5.88 110.00 646.80
Glazed Tiles Sqm 105.00 375.00 39375.00
Colouring pigment Kg 1.00 75.00 75.00
Total material rate 44256.80

[B] Labours
Skilled 4.70 150 705
Unskilled 9.10 90 819
10% extra for rise 152.4
Total labour rate 1676.40

[C] Water + electric @ 2% of A+B --- --- 918.66

[D] Tools, Equipments & plants @ 2% A+B --- --- 918.66

[E] Scaffolding @ 2% A+B --- --- 0.00


[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 7165.58

Total cost 54936.11

Unit Rate 549

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.11

Providing and laying of glazed tiles for


skirting 75mm in bathroom terrace etc.
including cutting finishing, filling up of
joints etc. complete. for above GF slab
below FF slab. Rmt

For 100 Rmt

[A] Materials
Cement (OPC) Bags 2.21 160.00 353.60
Sand Cum 0.08 110.00 8.80
White Cement Bags 0.47 550.00 258.50
Glazed tiles Sqm 7.88 375.00 2955.00
Total material rate 3575.90

[B] Labours
Skilled 4.00 150 600
Unskilled 4.00 90 360
10% extra for rise 96
Total labour rate 1056.00

[C] Water + electric @ 2% of A+B --- --- 92.64

[D] Tools, Equipments & plants @ 2% A+B --- --- 92.64


[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 722.58

Total cost 5539.75

Unit Rate 55

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.12

Providing and laying of glazed tiles for


vertical surface in bathroom, kitchen
etc. including cutting finishing, filling
up of joints etc. complete for above GF
slab below FF slab. Sqm

For 100 Sqm

[A] Materials
Cement (OPC) Bags 18.49 160.00 2958.40
Sand Cum 0.69 110.00 75.90
Glazed Tiles Sqm 105.00 375.00 39375.00
White cement Bags 0.50 550.00 275.00
Colouring pigment Kg 1.00 75.00 75.00
Total material rate 42759.30

[B] Labours
Skilled 5.00 150 750
Unskilled 10.00 90 900
10% extra for rise 165
Total labour rate 1815.00

[C] Water + electric @ 2% of A+B --- --- 891.49


[D] Tools, Equipments & plants @ 2% A+B --- --- 891.49

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 6953.59

Total cost 53310.86

Unit Rate 533

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.13
Providing and laying marble flooring
for steps with bed mortar 1:8 (1
cement, 8sand) including cutting
finishing, filling up of joints, polishing
etc. complete for above GF slab below
FF slab. Sqm

For 100 Sqm

[A] Materials
Cement (OPC) Bags 26.00 160.00 4160.00
Sand Cum 5.88 110.00 646.80
White Cement Bags 5.00 550.00 2750.00
Marble (With Polishing) Sqm 105.00 970.00 101850.00
Total material rate 109406.80

[B] Labours
Skilled 6.20 150 930
Unskilled 11.00 90 990
10% extra for rise 192
Total labour rate 2112.00
[C] Water + electric @ 2% of A+B --- --- 2230.38

[D] Tools, Equipments & plants @ 2% A+B --- --- 2230.38

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 17396.93

Total cost 133376.48

Unit Rate 1334

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.14
Providing and laying marble skirting
75mm for steps with including cutting
finishing, filling up of joints, polishing
etc. complete for above GF slab below
FF slab. Nos.

For 100 Nos

[A] Materials
Cement (OPC) Bags 1.00 160.00 160.00
Sand Cum 0.10 110.00 11.00
White Cement Bags 0.25 550.00 137.50
Marble (With Polishing) Sqm 2.50 970.00 2425.00
Total material rate 2733.50

[B] Labours
Skilled 2.00 150 300
Unskilled 2.00 90 180
10% extra for rise 48
Total labour rate 528.00
[C] Water + electric @ 2% of A+B --- --- 65.23

[D] Tools, Equipments & plants @ 2% A+B --- --- 65.23

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 508.79

Total cost 3900.75

Unit Rate 39

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.15

Providing and laying marble flooring


with bed mortar 1:8 (1 cement, 8sand)
including cutting finishing, filling up of
joints, polishing etc. complete for
above FF slab below SF slab. Sqm

For 100 Sqm

[A] Materials
Cement (OPC) Bags 26.00 160.00 4160.00
Sand Cum 5.88 110.00 646.80
White Cement Bags 5.00 550.00 2750.00
Marble (With Polishing) Sqm 105.00 970.00 101850.00
Total material rate 109406.80

[B] Labours
Skilled 5.20 150 780
Unskilled 9.80 90 882
20% extra for rise 332.4
Total labour rate 1994.40

[C] Water + electric @ 2% of A+B --- --- 2228.02

[D] Tools, Equipments & plants @ 2% A+B --- --- 2228.02

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 17378.59

Total cost 133235.84

Unit Rate 1332

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.16
Providing and laying marble skirting of
75mm including cutting finishing,
filling up of joints, polishing etc.
complete for above FF slab below SF
slab. Rmt

For 100 Rmt

[A] Materials
Cement (OPC) Bags 2.21 160.00 353.60
Sand Cum 0.08 110.00 8.80
White Cement Bags 0.47 550.00 258.50
Marble (With Polishing) Sqm 7.88 970.00 7643.60
Total material rate 8264.50

[B] Labours
Skilled 4.00 150 600
Unskilled 4.00 90 360
20% extra for rise 192
Total labour rate 1152.00

[C] Water + electric @ 2% of A+B --- --- 188.33

[D] Tools, Equipments & plants @ 2% A+B --- --- 188.33

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1468.97

Total cost 11262.13

Unit Rate 113

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.17
Providing and laying of glazed tiles for
floor in bathroom terrace etc. including
cutting finishing, filling up of joints etc.
complete. for above FF slab below SF
slab. Sqm

For 100 Sqm

[A] Materials
Cement (OPC) Bags 26.00 160.00 4160.00
Sand Cum 5.88 110.00 646.80
Glazed Tiles Sqm 105.00 375.00 39375.00
Colouring pigment Kg 1.00 75.00 75.00
Total material rate 44256.80

[B] Labours
Skilled 4.70 150 705
Unskilled 9.10 90 819
20% extra for rise 304.8
Total labour rate 1828.80

[C] Water + electric @ 2% of A+B --- --- 921.71

[D] Tools, Equipments & plants @ 2% A+B --- --- 921.71

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 7189.35

Total cost 55118.38

Unit Rate 551

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.

6.18
Providing and laying of glazed tiles for
vertical surface in bathroom, kitchen
etc. including cutting finishing, filling
up of joints etc. complete for above FF
slab below SF slab. Sqm

For 100 Sqm

[A] Materials
Cement (OPC) Bags 18.49 160.00 2958.40
Sand Cum 0.69 110.00 75.90
Glazed Tiles Sqm 105.00 375.00 39375.00
White cement Bags 0.50 550.00 275.00
Colouring pigment Kg 1.00 75.00 75.00
Total material rate 42759.30

[B] Labours
Skilled 5.00 150 750
Unskilled 10.00 90 900
20% extra for rise 330
Total labour rate 1980.00

[C] Water + electric @ 2% of A+B --- --- 894.79

[D] Tools, Equipments & plants @ 2% A+B --- --- 894.79

[E] Scaffolding @ 2% A+B --- --- 0.00

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 6979.33

Total cost 53508.20

Unit Rate 535

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
3.19
Providing and laying china mosaic
including cutting finishing, filling up of
joints etc. complete for above FF slab
below SF slab. Sqm

For 100 Sqm

[A] Materials
China Mosaic Sqm 100.00 64.56 6456.00
Cement Bags 18.45 160.00 2952.00
Sand Cum 2.75 100.00 275.00
White Cement Bags 5.00 550.00 2750.00
Total material rate 12433.00
[B] Labours
Skilled 10.00 150 1500
Unskilled 30.00 90 2700
20% extra for rise 84
Total labour rate 4284.00

[C] Water + electric @ 2% of A+B --- --- 334.34

[D] Tools, Equipments & plants @ 2% A+B --- --- 334.34

[E] Scaffolding @ 2% A+B --- --- 334.34

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 2658.00

Total cost 20378.02

Unit Rate 204

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculations for rate analysis of 100 Sqm

[A] Materials
1. China mosaic
Qty 100 Sqm

2.Cement
Quantity of mortar required: 100 Sqm x 0.025m
Wet volume: 2.5 Cum
Dry volume: 2.5x1.25 (25%-shrinkage factor)
: 3.12cu.m.

CEMENT = 1x3.12
(4+1) x0.0345
=18.09 bags + 2% wastage
=18.45 bags

3. Sand
Sand: 1x3.12x4/5=2.75

4. White Cement
2.5 Kg / Sqm
=100 x 2.5=2500 Kg = 5 Bags

Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
6.21
Providing and laying china mosaic
including cutting, finishing, filling up of
joints etc. complete for above SF slab
below TF slab. Sqm

For 100 Sqm

[A] Materials
China Mosaic Sqm 100.00 64.56 6456.00
Cement Bags 18.45 160.00 2952.00
Sand Cum 2.75 100.00 275.00
White Cement Bags 5.00 550.00 2750.00
Total material rate 12433.00

[B] Labours
Skilled 10.00 150 1500
Unskilled 30.00 90 2700
20% extra for rise 84
Total labour rate 4284.00

[C] Water + electric @ 2% of A+B --- --- 334.34

[D] Tools, Equipments & plants @ 2% A+B --- --- 334.34

[E] Scaffolding @ 2% A+B --- --- 334.34

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 2658.00

Total cost 20378.02

Unit Rate 204

Checked by:
Date: Page No.
Remarks

Rs

Rs / Sqm
Remarks

Rs

Rs / Rmt
Remarks

Rs

Rs / Sqm
Remarks

Rs

Rs / Sqm
Remarks

Rs
Rs / Sqm

Remarks

Rs
Rs / Nos

Remarks
Rs

Rs / Sqm

Remarks
Rs

Rs / Rmt

Remarks
Rs

Rs / Sqm

Remarks
Rs

Rs / Rmt

Remarks
Rs

Rs / Sqm

Remarks
Rs

Rs / Sqm

Remarks
Rs

Rs / Nos

Remarks
Rs

Rs / Sqm

Remarks
Rs

Rs / Rmt

Remarks
Rs

Rs / Sqm

Remarks
Rs

Rs / Sqm

Remarks
Rs

Rs / Sqm
Remarks
Rs

Rs / Sqm
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
11.01 Providing and applying 3 coats of white wash on
newly plastered internal surface including finishing Sq.m
etc. complete at Ground Floor level.

For 100 Sqm

[A] Materials
Slaked lime Kg 30.8 5 154.00
Glue Kg 0.08 150 12.00
Ultramarine blue Kg 0.09 70 6.30
Sodium chloride Kg 4.01 5 20.05
Cement kg 33.77 11 371.47
Brush etc @ 10% 56.38
Total material rate 620.20

[B] Labours
Skilled 2.7 150 405
Unskilled 1.14 90 102.6
Total labour rate 507.60

[C] Water + electric @ 2% of A+B --- --- 0.00

[D] Tools, Equipments & plants @ 2% A+B --- --- 22.56

[E] Scaffolding @ 2% A+B --- --- 22.56

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 175.94

Total cost 1348.85

Unit Rate 13
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404

Calculations for rate analysis of 100 Sqm

[A] Materials
1. Slaked lime
For first coat =12 Kg
For second coat = 8 Kg
For Third coat = 8 Kg
Total weight=28 Kg + wastage
Total qty = 30.8 Kg

2. Glue
For first coat =0.03 Kg
For second coat = 0.02 Kg
For Third coat = 0.02 Kg
Total weight=0.07 Kg + 10% wastage
Total qty = 0.077 Kg

3. Ultramarin blue
For first coat =0.04 Kg
For second coat = 0.02 Kg
For Third coat = 0.02 Kg
Total weight=0.08 Kg + 10% wastage
Total qty = 0.088 Kg

4. Sodium Chloride
For first coat =1.55 Kg
For second coat = 1.05 Kg
For Third coat = 1.05 Kg
Total weight=3.65 Kg + 10% wastage
Total qty = 4.01 Kg

5. Cement
For first coat =10.7 Kg
For second coat = 10 Kg
For Third coat = 10 Kg
Total weight=30.7 Kg + 10% wastage
Total qty = 33.77 Kg
Checked by:
Date: Page No.
School of Building Science & Technology
Quantity Surveying & Specifications
RATE ANALYSIS
Name of the Project: Vrajnandan Bunglows Student Name: Japan Shah
Code No: 2404
Item
Item Description Unit Quantity Rate Amount
No.
11.02 Providing and applying 2 coats of semi-acrylic
paint on newly plastered external surface including
finishing etc. complete at Ground Floor level. Sq.m

For 100 Sqm

[A] Materials
Cement Paint Kg 42 25 1050.00
Brush sand etc. @ 10% 105.00
Total material rate 1155.00

[B] Labours
Skilled 5.5 150 825
Unskilled 4 90 360
Total labour rate 1185.00

[C] Water + electric @ 2% of A+B --- --- 0.00

[D] Tools, Equipments & plants @ 2% A+B --- --- 46.80

[E] Scaffolding @ 2% A+B --- --- 46.80

[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 365.04

Total cost 2798.64

Unit Rate 28
Checked by:
Date: Page No.
Remarks

Rs

Rs / Sqm
Remarks

Rs

Rs / Sqm

Vous aimerez peut-être aussi