Equipment Costsfor Course Project

ECE-05590SP – Transmission System Planning and Impact Studies


Fall 2010
Prices for Year 2010 Escalate at 5% to 2025

Single Circuit O/H Transmission Line, 69 kV @ <3 SIL $50,000/mile

Single Circuit O/H Transmission Line, 138 kV @ <3 SIL $160,000/mile

Single Circuit O/H Transmission Line, 345 kV @ <3 SIL $860,000/mile

Double Circuit O/H Transmission Line, 69 kV @ <3 SIL $90,000/mile

Double Circuit O/H Transmission Line, 138 kV @ <3 SIL $288,000/mile

Double Circuit O/H Transmission Line, 345 kV @ <3 SIL $1,5000,000/mile

Single Circuit U/G Transmission Line, 69 kV @ <3 SIL, <50 miles $500,000/mile

Single Circuit U/G Transmission Line, 138 kV @ <3 SIL <40 miles $1,600,000/mile

Single Circuit U/G Transmission Line, 345 kV @ <3 SIL <30 miles $12,000,000/mile

Sub Single Line Bay Position Radial (Less than 5) @69kV $200,000/line

Sub Single Line Bay Position Ring (Less than 6) @69kV $270,000/line

Sub Single Line Bay Position Breaker-and-a-Half @69kV $450,000/line

Sub Single Line Bay Position Radial (Less than 5) @138kV $400,000/line

Sub Single Line Bay Position Ring (Less than 6) @138kV $540,000/line

Sub Single Line Bay Position Breaker-and-a-Half @138kV $900,000/line

Sub Single Line Bay Position Radial (Less than 5) @345kV $500,000/line

Sub Single Line Bay Position Ring (Less than 6) @345kV $675,000/line

Sub Single Line Bay Position Breaker-and-a-Half @345kV $1,100,000/line


Three Phase Transformer, Phase Shift +/- 15 degrees $46/kVA

Three Phase Transformer, w/o Phase Shift $21/kVA


Fixed Shunt Capacitors $100/kVAr

Fixed Shunt Reactors $100/kVAr

Series Capacitors $15,000/kVAr


Regardless of Voltage

SVC $350/kVAr

StatCOM $450/kVAr

Generator technology changes per size, that is why it increases!


Generator 650 MW @ 0.9PF $900/kW
Generator 350 MW @ 0.9PF $700/kW
Generator 250 MW @ 0.9PF $600/kW
Generator 150 MW @ 0.9PF $500/kW
Generator 50 MW @ 0.9PF $400/kW

You are limited to replacing only, no upgrades (although this would be a great way to go)

All required or customary items are included in the costs: All Land, Transformers have LTCs regardless of
phase shifting, substations have control houses, batteries, protective relaying access, etc.

The official mile when not listed is the result of the impedance IN OHMS as shown in the load flow impedance
listing.