Construction schedule for the construction of Merta Road Project - Package I

Executed Balance
Sr. No. Description of Activity Unit BOQ Qty. Dec Jan feb Mar Apr May Jun
Qty. Qty.

1 Excavation Cum 107644 20000 87644 25000 25000 25000 12644

Construction of
2 Cum 62340 0 62340 15000 15000 15000 17340
Embankment

3 GSB Cum 51544 3500 48044 7500 7500 7500 7500 7500 7500 3044

4 WMM Cum 36179 0 36179 5500 5500 5500 5500 5500 5500 3179

5 BM Cum 1875 0 1875 300 300 300 300 300 375

6 DBM Cum 27792 0 27792 3000 3500 4500 4500 4500 4000 3792

6 Bituminious Concrete Cum 8920 0 8920 1500 1500 1500 1500 1500 1420

7 Pre Cast Kerb Mtr. 30000 0 30000 5000 5000 5000 5000 5000 5000

10 Concrete M-30 Cum 1446 0 1446 1446

11 PCC Cum 593 0 593 593


Construction schedule for the construction of Merta Road Project - Package II

Executed Balance
Sr. No. Description of Activity Unit BOQ Qty. Dec Jan feb Mar Apr May Jun
Qty. Qty.

1 Excavation Cum 64559 20000 44559 20000 25000

Construction of
2 Cum 174220 0 174220 15000 45000 45000 45000 24220
Embankment

3 GSB Cum 57641 0 57641 7000 8000 10000 10000 10000 10000 2641

4 WMM Cum 42829 0 42829 5500 5500 7000 7000 7000 7000 3829

5 BM Cum 981 0 981 300 300 300 81

6 DBM Cum 29060 0 29060 3000 4000 5000 5000 5000 5000 2060

7 Bituminious Concrete Cum 9959 0 9959 1500 1500 1500 2000 2000 1459

8 Pre Cast Kerb Mtr. 39500 0 39500 4500 5000 5000 5000 10000 10000

9 Concrete M-30 Cum 5800 0 5800 2000 2000 1800

10 PCC Cum 3000 0 3000 1000 1000 1000


Construction schedule for the construction of Merta Road Project - Package III

Description of Executed Balance


Sr. No. Unit BOQ Qty. Dec Jan feb Mar Apr May Jun July
Activity Qty. Qty.

1 Excavation Cum 309342 10000 299342 40000 60000 60000 60000 60000 19342

Construction of
2 Cum 48300 0 48300 10000 15000 15000 8300
Embankment

3 GSB Cum 47886 0 47886 7500 7500 7500 7500 7500 7500 2886

4 WMM Cum 44290 0 44290 6000 6000 6000 6000 6000 6000 8290

5 BM Cum 981 0 981 300 300 300 81

6 DBM Cum 24864 0 24864 2000 2000 4000 4000 4000 4000 4864

Bituminious
7 Cum 9970 0 9970 1500 1500 1500 1500 1500 2470
Concrete

8 Pre Cast Kerb Mtr. 32000 0 32000 4500 4500 4500 4500 4500 4500 5000

9 R R Masonry Cum 14940 0 14940 7500 7440

RCC Pipe for


10 Mtr. 532 0 532 200 200 132
culverts

11 Concrete M-30 Cum 5885 0 5885 1000 2000 2000 885

12 PCC Cum 3233 0 3233 1000 1000 1233