Executed Balance
Sr. No. Description of Activity Unit BOQ Qty. Dec Jan feb Mar Apr May Jun
Qty. Qty.
Construction of
2 Cum 62340 0 62340 15000 15000 15000 17340
Embankment
3 GSB Cum 51544 3500 48044 7500 7500 7500 7500 7500 7500 3044
4 WMM Cum 36179 0 36179 5500 5500 5500 5500 5500 5500 3179
6 DBM Cum 27792 0 27792 3000 3500 4500 4500 4500 4000 3792
6 Bituminious Concrete Cum 8920 0 8920 1500 1500 1500 1500 1500 1420
7 Pre Cast Kerb Mtr. 30000 0 30000 5000 5000 5000 5000 5000 5000
Executed Balance
Sr. No. Description of Activity Unit BOQ Qty. Dec Jan feb Mar Apr May Jun
Qty. Qty.
Construction of
2 Cum 174220 0 174220 15000 45000 45000 45000 24220
Embankment
3 GSB Cum 57641 0 57641 7000 8000 10000 10000 10000 10000 2641
4 WMM Cum 42829 0 42829 5500 5500 7000 7000 7000 7000 3829
6 DBM Cum 29060 0 29060 3000 4000 5000 5000 5000 5000 2060
7 Bituminious Concrete Cum 9959 0 9959 1500 1500 1500 2000 2000 1459
8 Pre Cast Kerb Mtr. 39500 0 39500 4500 5000 5000 5000 10000 10000
1 Excavation Cum 309342 10000 299342 40000 60000 60000 60000 60000 19342
Construction of
2 Cum 48300 0 48300 10000 15000 15000 8300
Embankment
3 GSB Cum 47886 0 47886 7500 7500 7500 7500 7500 7500 2886
4 WMM Cum 44290 0 44290 6000 6000 6000 6000 6000 6000 8290
6 DBM Cum 24864 0 24864 2000 2000 4000 4000 4000 4000 4864
Bituminious
7 Cum 9970 0 9970 1500 1500 1500 1500 1500 2470
Concrete
8 Pre Cast Kerb Mtr. 32000 0 32000 4500 4500 4500 4500 4500 4500 5000