Vous êtes sur la page 1sur 1

Version Revision Code Nº Issued Page

1 0 HVAC007C 1-Aug-07 1/1 PROJECT GOLDEN TOWER PHASE 4

ADRS PHNOM PENH, CAMBODIA


CONTRACTING DIVISION PIPE LEAKAGE TEST REPORT
No 8b, Down Town Road 7,P.O.Box 28,
Phnom Penh, Kingdom of Cambodia PAGE HT- CHW- 11

SYSTEM: Air Conditioning and Ventilation System Building Management System


Chilled Water Pipe System Fuel Oil Piping System
Plumbing, Sanitary and Sewer system Clean Agent Fire Suppression &
Detection System
SYSTEM SPECS SECTION: Chiller Water Pipe System

DRAWING REFERENCE: CK-GT-GL-M1-DPS-02.B

REFERENCE DOCUMENTS:

Type of Test:
Hydrostatic In-Service Pneumatic Gravity Test
Pressure Test Test Test

Equipment(s)/ Materials to be tested:


Installed Black steel pipe with mechanically
( Welded& Threaded joints )
Water pressure pump testing.

LOCATIONOffice Building 8th floor FLOOR High level GRIDLINE

TESTING AND COMMISSIONING PROCEDURE:

Seal the entire section to be test and pressurise the pipe section up to 1.5 times of pipe working pressure and maintain for 2 hours.

Design Parameters ( Specify ) Date: 6-Oct-08 Time


Working Pressure: 4bars Duration: 8hour
Test Pressure: 6bars Initial Reading: 6bars 8h00
Ambient Temp.: Final Reading: 6bars 16h00
Start / Finish
Remark:

On this date, the Undersigned have witness testing of piping system as above described and find the test to be:

Conforming Non-conforming / Test Required

INSPECTED BY: APPROVED BY: WITNESSED BY:

DATE: DATE: DATE: