The time estimates in weeks for activities of a PERT Network are given below
Activity to tm tp
1-2 1 1 7
1-3 1 4 7
1-4 2 2 8
2-5 1 1 1
3-5 2 5 14
4-6 2 5 8
5-6 3 6 15
5. If the project due date is 19 weeks. What is the probability of not meeting the
due date?
Expect
ed
Time Varian
Duration (in weeks) (µ) Std. Dev. ce
Activity to tm tp ti σTi σ2
A 1,2 1 1 7 2 1 1
B 1,3 1 4 7 4 1 1
C 1,4 2 2 8 3 1 1
D 2,5 1 1 1 1 0 0
E 3,5 2 5 14 6 2 4
F 4,6 2 5 8 5 1 1
G 5,6 3 6 15 7 2 4
Note: The critical path is highlighted in red.