ROOT CAUSE INVESTIGATION REPORT

Subject: Work Stop at TCOT


Date: 17/02/2011
Equipment: Tank T-446
Prepared by: Abdull Rahim Abu Bakar

No Issue Description

HOTWORK PERMIT was not issued Fire hydrant hoses and fittings
1
by TCOT was not available at site

COLD WORK cannot be carried out:


1) Emergency
overflow roof to remove vapor seal
JHA and JobCard was not attached
2 Qty: 19 nos
to PTW
2) To
service and cleaning rim vent (6")

Qty: 1 point

Recovery plan

1) To purchase immediately fire hydrant and fittings


(Purchase date: 17/02/2011)

2) JSA and JobCard was issued and accepted by all work supervisor.
(Date: 17/02/2011)

Lesson Learnt

1) To avoid communication breakdown between BULER project team and site


workers.

2) To ready all related document prior to start any work.

3) To regularly educate all supervisors and workers about the work process flow,
(if applicable e.g EIS, SOE, MCS, JMS, drawings, work schedule, manpower and
equipment loading, JSA, repair procedure, consumable, MOS, parts, material and etc