100x75 ti mber 0.09 m3 @ 96297 = 8666.73
plastic plug 4 nr @ 10 = 40
100 brass screw 4 nr @ 12 = 48
75x38mm timber 0.86 m2 @ 1200 = 1032
total Material 9786.73 9786.73
Labour
sepcial skill labour 6 days @ 1400 = 8400.00
skill labour 0.5 days @ 1200 600.00
Unskill 3 days @ 700 = 2100.00
Plant
tools allow 3% of labour cost 0.03 333.00
Material
3mm thk glass panes 0.84 m2 @ 950 = 798.00
12x12mm beadi ng 9.14 m @ 15 137.10
brass panel oins 48 nr @ 66 3168.00
Material
butt hinges 3 nr @ 120 = 360.00
19 mm screw 24 nr @ 10 = 240.00
Material
casement stays 4 nr @ 110 = 440.00
12 mm screw 16 nr @ 12 = 192.00
Labour
sepcial skill labour 0.25 days @ 1400 = 350.00
Plant
tools allow 3% of labour cost 0.03 15.75
Material
barrel bolt 100mm 1 nr @ 46 = 46.00
12 mm brass screw 8 nr @ 8 = 64.00
Labour
sepcial skill labour 0.06 days @ 1400 = 84.00
Material
casement fastner s 6 nr @ 78 = 468.00
12 mm brass screw 24 nr @ 8 = 192.00
Labour
sepcial skill labour 0.06 days @ 1400 = 84.00
Plant
tools allow 3% of labour cost 0.03 3.78
Material
draw rings 6 nr @ 67 = 402.00
12 mm brass screw 12 nr @ 8 = 96.00
Labour
sepcial skill labour 0.13 days @ 1400 = 182.00
Material
varnish 1 nr @ 365 = 365.00
Labour
sepcial skill labour 0.54 days @ 1400 = 756.00
Plant
75mm brush 1/3 0.333 nr @ 160 53.33
tools allow 3% of labour cost 0.03 34.02