Plan for Movement to 5th floor - STG Part

Task to be complete Duration Start Date End Date Remarks


STG
Pre Migration
1 Get Reliance leased line connectivity established (1 MBS) 4 Days 18-Apr-11 21-Apr-11
2 Airtel components to be ready for connectivity at new site 3 Days 18-Apr-11 20-Apr-11
3 Preparing new firewall & configure for testing purpose 1 Day 12-Apr-11 13-Apr-11
4 Cable testing by network vendor 1 Day
5 Identify 5 systems & move to new site for testing purpose 1 Day 20-Apr-11 21-Apr-11
6 Project wise bay allocation Half Day 15-Apr-11 15-Apr-11
7 Shifting Reliance 4 MBS line to new site 4 Hours 23-Apr-11 23-Apr-11

On Migration Day
1 Move the active components to new site 3 Hours 23-Apr-11 23-Apr-11
2 Setup the active components on new site 4 Hours 23-Apr-11 23-Apr-11
3 Move servers to new site 2 Hours 23-Apr-11 23-Apr-11
4 Shifting Airtel 4 MBS line to new site 4 Hours 24-Apr-11 24-Apr-11
5 Move Desktops, Printers to new site & setup 1 Day 24-Apr-11 24-Apr-11

Post Migration
1 Centrex voice line to be estabilished 3 Days 25-Apr-11 27-Apr-11

Project Wise Pre migration Process - STG


INDIUM
1 Testing the Lifemed, Refills Applications 1 Hour 22-Apr-11 22-Apr-11
2 Testing the Guardian, Tampa Applications 1 Hour 22-Apr-11 22-Apr-11
3 Testing the Procare, Reliance Applications 1 Hour 22-Apr-11 22-Apr-11

THAMES
1 Testing the Thames citrix application 1 Hour 22-Apr-11 22-Apr-11

HARMONY
1 Testing Alcatel-lucent applictaions using alcate laptop with RSA 1 Hour 23-Apr-11 23-Apr-11

Note
1 We can't test the Zalaris citrix connection untill the Airtel connectivity shifted to new site.
2 We can't test the OTES Remote Desktop connection untill the Reliance line shifted to new site
3 We can't test the Rotech E-forums application untill the Reliance line shifted to new site
4 Gamma project don't have any specific application to run test.
5 IT , Business Development, Finance, HR Teams don't have any specific applications to test.