Académique Documents
Professionnel Documents
Culture Documents
K.Shashidhar
Hitech College of Engineering & Technology,
Hyderabad, Andhra Pradesh, INDIA
Email: shashi_kb4u@yahoo.com
Cell contact: 09848909049
Abstract - Electric utilities in India are facing the pressure of consumption is 381,359.5 Million Unit. Ideally, losses in an
reducing costs and improving the quality and reliability of electric system should be around 3 to 6%. Voltage stability
supply. It is not sufficient to analyze how a particular portion problem generally arises in over loaded systems. The
of the network may be modified to improve its performance collapses are – low voltage profiles, heavy reactive power
today: it is a matter of determining what would be the optimal
flows, inadequate reactive support, and heavily loaded
solution when allowance has also to be made for the
uncertainties in the prediction of the future scenario of systems. To reduce the losses and to improve the system
customer demand. The utilities do not follow any accurate efficiency, a policy has been made [2].
mathematical procedure in installing Distribution If a new 11KV/415V Transformer is to be designed and
Transformer. Moreover in many cases they are not placed in connected to an existing network, several possible solutions
the required position due to socio-political and economical are studied. These solutions may include various connection
reasons which will result in losses. Since the Distribution form schemes of the substation and several feasible locations,
a large part of the network, a small amount of loss at each while the principal scheme is defined with a limited number
transformer leads to a great variation in total. To address this of possibilities. Many a times with the utilities, due to large
problem care should be taken to minimize the power loss while
number of possible sites, an economical comparison may
commissioning a transformer. Apart from estimating the
power loss the voltage regulation should also be considered for overlook the optimal technical solution. The final decision is
finding the optimal location of a Transformer. In this paper a usually influenced by additional factors such as topography;
mathematical analysis is made to find the optimal location of a land ownership, environmental considerations etc. But if the
Transformer based upon the minimum peak power loss and location of the Transformer is arbitrary the result can be a
minimum voltage regulation. Here three different cases are bad voltage profile. In both the cases we have extra losses
analyzed considering the present load and forecasting the resulting in a less efficient and unnecessary higher cost
future load demand and thus obtaining four to five optimal electrical system installation [1].
locations at which the distribution transformer can be placed.
A comparative study is also made to have a choice between One such attempt is made in this paper by estimating the
increasing the rating of the over rated transformer or finding
location of the distribution transformer taking into
the optimal location for a new transformer.
consideration of the present and future possible load
Keywords: power loss, voltage regulation, transformer losses, demand. The various possible technical locations are tried
transformer banking. out to obtain an optimal position which can be later
compared with the economical issues in placing the
transformer. In this paper the reduction of total power loss is
I. INTRODUCTION compared by both finding the optimal location for an
additional transformer and replacing the over loaded
Although Considerable Research has been carried out in transformer with higher rating transformer. Three different
distribution, there are yet few areas in the distribution possible cases are considered and analyzed to reduce the
network which are to be concentrated in order to reduce the losses and improve the voltage regulation. The three
losses to the maximum extent possible and to increase the different cases are as follows:
power quality. In developed countries, the amount of power
loss is not greater than 10%.However, in developing Case 1: In a locality, the power demand is increasing at a
countries, the percentage of active power losses is around considerable rate without any change in the network. To
20%; therefore, utilities in the electric sector are currently meet the load demand and also to reduce the line losses
interested in reducing it in order to be more competitive, either an additional transformer can be placed or the over
since the electricity prices in deregulated markets are related loaded transformer can be replaced by a higher rating
to the system losses [3]. In India, there are forty power transformer.
distribution companies in various states and Union Case 2: The load network (layout) is increasing in different
Territories supplying power. As on March, 2005 the total directions. To cater the new load demand and to reduce the
transformer capacity of the distribution utilities is 330,829 line losses, either a higher transformer rating is replaced
MVA and total distribution line length of the forty with the over loaded transformer or an additional
distribution utilities is 6,081,878 km. Total electricity
transformer can be placed within the same locality at some Pi is the real power at node i and
other different place. Qi is the reactive power at node i
Case 3: Considering the load demand is increased in and
around the transformer location. Study has to be carried out The total active and reactive power loss is given by
either to increase the transformer rating or install an
additional transformer. The better approach is followed to
reduce the line losses.
(3)
The above cases are analyzed in two steps
1. The location at which the minimum peak power
loss is obtained (4)
2. The location corresponding to minimum voltage
regulation is obtained. The voltage regulation is calculated by using the formula
But in the network, since the buses 6-9 forms the main From the above two scenarios it is better to place a new
line, it can be considered as better location to place a new Transformer at some optimal location instead of increasing
transformer. This analysis was also supported by observing the transformer rating, taking into consideration of all the
the voltage profile at all the transformers. Now to obtain the Geographical constraints and political issues.
exact location at which the transformer is to be placed, the
Case 2: Due to urbanization there can be a change in the Distance From Power Loss
S.No
physical layout of the load network i.e the distance of the bus 6 (KW)
tail end load from the transformer is increased, which leads 1 0.05 149.6
to increase in line losses. In this case the transformer should 2 0.08 109.53
cater the increased load demand and line losses. Replacing 3 0.09 89.24
the transformer with higher rating will not reduce the line 4 0.1 63.36
losses. But if an additional transformer is placed at an 5 0.15 60.23
optimal location within the network the total power losses 6 0.2 56.41
are reduced. 7 0.3 109.74
8 0.4 103.78
Considering in the same Karapa Distribution Network of
Table 6: Power loss when a transformer is moved in unit distances
Figure 1, the line length is increased between the buses 10
between the Buses for an extended network
and 11 by 100 meters as shown in Figure 2.
From the above table it is observed that the optimal location
to place a transformer is at 200m from Bus 6. If at any case
it is not possible to place the Distribution transformer then
the next optimal location is selected.
.
REFERENCES