Vous êtes sur la page 1sur 17

Operations Research  Unit 11 

Unit 11  Project Scheduling and PERT­CPM 

Structure 

11.1.     Introduction 
11.2.      Basic difference between PERT and CPM 
11.2.1  PERT 
11.2.2  CPM 
11.2.3  Project scheduling by PERT­CPM 
11.3.     PERT / CPM network components and precedence relationship 
11.3.1  Critical Path Calculations 
11.3.2  Determination of the Critical Path 
11.3.3  Determination of Floats 
11.4.  Project Management – PERT 
11.5.     Summary 
Terminal Questions 
Answers to SAQs and TQs 

11.1.  Introduction 
A project such as construction of a bridge, highway, power plant, repair and maintenance of an oil 
refinery  or  an  air  plane  design,  development  and  marketing  a  new  product,  research  and 
development etc., may be defined as a collection of inter­related activities (or tasks) which must 
be completed in a specified time according to a specified sequence and require resources such 
as personnel, money, materials, facilities etc. 

The growing complexities of today’s projects had demanded more systematic and more effective 
planning  techniques  with  the  objective  of  optimizing  the  efficiency  of  executing  the  project. 
Efficiency here implies effecting the utmost reduction in the time required to complete the project 
while accounting for the economic feasibility of using available resources. 

Project management has evolved as a new field with the development of two analytic techniques 
for planning, scheduling and controlling projects. These are the Critical Path Method (CPM) and 
the  Project  Evaluation  and  Review  Technique  (PERT).  PERT  and  CPM  are  basically  time­ 
oriented methods in the sense that they both lead to the determination of a time schedule.

Sikkim Manipal University  182 
Operations Research  Unit 11 

Learning Objectives: 

After studying this unit, you should be able to understand the following 

1.  What is a project? 

2.  What is project management? 

3.  Application of PERT / CPM method to network analysis 

11.2.  Basic difference between PERT and CPM 
Though  there  are  no  essential  differences  between  PERT  and  CPM  as  both  of  them  share  in 
common  the  determination  of  a  critical  path  and  are  based  on  the  network  representation  of 
activities and their scheduling that determines the most critical activities to be controlled so as to 
meet the completion date of the project. 

11.2.1  PERT 
1.  Since PERT was developed in connection with an R and D work, therefore it had to cope with 
the uncertainties which are associated with R and D activities. In PERT, total project duration 
is regarded as a random variable and therefore associated probabilities are calculated so as 
to characterise it. 
2.  It is an event­oriented network because in the analysis of network emphasis is given an important 
stages  of  completion  of  task    rather  than  the  activities  required  to  be  performed  to  reach  to  a 
particular event or task. 
3.  PERT is normally used for projects involving activities of non­repetitive nature in which time 
estimates are uncertain. 
4.  It helps in pinpointing critical areas in a project so that necessary adjustment can be made to 
meet the scheduled completion date of the project. 

11.2.2  CPM 
1.  Since  CPM  was  developed  in  connection  with  a  construction  project  which  consisted  of 
routine tasks whose resources requirement and duration was known with certainty, therefore 
it is basically deterministic. 
2.  CPM is suitable for establishing a trade­off for optimum balancing between schedule time and 
cost of the project. 
3.  CPM is used for projects involving activities of repetitive nature.

Sikkim Manipal University  183 
Operations Research  Unit 11 

11.2.3 Project scheduling by PERT­CPM 
It consists of three basic phases: planning, scheduling and controlling. 
1.  Project Planning: The various steps involved during this phase are given below: 
i)  Identify various activities (task or work elements) to be performed in the project. 
ii)  Determining requirement of resources such as men, materials, machines etc., for carrying 
out  activities listed above. 
iii)  Estimating costs  and times for various activities. 
iv)  Specifying the inter­relationship among various activities. 
v)  Developing  a  network  diagram  showing  the  sequential  inter­relationships  between  the 
various activities. 

2.  Scheduling: Once the planning phase is over, scheduling of the project, is when each of the 
activities required to be performed, is taken up. The various steps involved during this phase 
are listed below: 
1.  Estimating the durations of activities, taking into considerations the resources required for 
these execution in most economic manner. 
2.  Based on these time estimates, preparing a time chart showing the start and finish times 
for  each  activity,  and  hence  calculation  of  total  project  duration  by  applying  network 
analysis  techniques  such  as forward   (backward)  pass  and  floats  calculation; identifying 
the  critical  path;  carrying  out    resource  smoothing  (or  levelling)  exercise    for  critical  or 
scarce  resources  including  re­costing  of  the  schedule  taking  into  account  resource 
constraints. 

3.  Project Control: Project control  refers to revaluating actual progress against the plan. If 


significant differences are observed then                 re­scheduling must be done to update 
and revise the uncompleted part of the project. 

Self Assessment Questions 1 

Verify whether the following statements are True or False 

1.  Project consists of interrelated activities. 

2.  Project activities are to be completed in a specified time according to specified sequence. 

3.  PERT and CPM identifies non critical activities. 

4.  PERT is activity oriented network.

Sikkim Manipal University  184 
Operations Research  Unit 11 

5.  CPM is used for projects that are repetitive in nature. 

11.3  PERT/CPM Network Components And Precedence Relationship 


PERT/CPM networks consists of two major components as discussed below: 

a)  Events:  An  event  represents  a point in  time  that  signifies  the  completion  of  some  activities 
and  the  beginning  of  new  ones.  The  beginning  and  end  points  of  an  activity  are  thus 
described  by  2  events  usually  known  as  the  Tail  and  head  events.  Events  are  commonly 
represented  by  circles  (nodes)  in  the  network  diagram.  They  do  not  consume  time  and 
Resource 

b)  Activities: Activities of the network represent project operations or task to be conducted.  An 
arrow  is  commonly  used  to  represent  an  activity,  with  its  head  indicating  the  direction  of 
progress  in  the  project.    Activities  originating  from  a  certain  event  cannot  start  until  the 
activities  terminating  at  the  same  event  have  been  completed.  They  consume  time  and 
Resource. 

Events in the network diagram are identified by numbers. Numbers are given to events such that 
arrow head number must be greater than arrow tail number. 

Activities are identified by the numbers  of their starting (tail) event and  ending (head) event. An 


arrow (i .J) extended between two events, the tail event i represents the start  of the activity and 
the head event  J represents the completion of the activity as shown in Fig. 9.1: 

Activity

i  J 

Starting event  Completion Event 

Fig. 9.1 

Sikkim Manipal University  185 
Operations Research  Unit 11 

Figure 9.2 shows another  example, where activities (1, 3) and (2, 3) must be completed before 
activity (3, 4) can  start. 


3  4

Fig. 9.2 

The rules for constructing the arrow diagram are as follows: 
1.  Each activity is represented  by one and only one arrow in the network. 

2.  No two activities can be identified by the same head and tail events. 

3.  To ensure the correct precedence  relationship in the arrow diagram, the following questions 
must be answered as every activity is added to the network: 
a)  What activities must be completed immediately before these activity can start ? 

b)  What activities must follow this activity ? 
c)  What activity must occur concurrently with this activity ? 

This  rule  is  self­explanatory.  It  actually  allows  for  checking  (and  rechecking)  the  precedence 
relationships as one progresses in the development of the network. 

Example 1: Construct the arrow diagram comprising activities A, B, C …….. and L such that the 
following relationships are satisfied: 
1)  A, B and C the first activities of the project, can start simultaneously. 
2)  A and B precede D. 
3)  B precedes E, F and H. 
4)  F and C precede G. 
5)  E and H precede I and J. 
6)  C, D, F and J precede K. 
7)  K precedes L. 
8)  I, G and L are the terminal activities of the project. 

Sikkim Manipal University  186 
Operations Research  Unit 11 

Fig. 9.3 

The  dummy  activities  D1  and  D2  are  used  (dotted  lines)  to  establish  correct  precedence 
relationships. D3  is used to identify activities E and H with unique end events.  The events of the 
project are numbered such that their ascending order indicates the direction of the progress in the 
project. 
Note: A dummy activity in a project network analysis has zero duration. 

11.3.1.  Critical Path Calculations 
The  application  of  PERT/CPM  should  ultimately  yield  a  schedule  specifying  the  start  and 
completion time of each activity.  The arrow diagram is the first step towards achieving that goal. 
The  start  and  completion  times  are  calculated  directly  on  the  arrow  diagrams  using  simple 
arithmetic.  The end result is to classify the activities as critical or non critical.  An activity is said 
to be critical if a delay in the start of the course makes a delay in the completion time of the entire 
project.    A  non­critical  activity  is  such  that  the  time  between  its  earliest  start  and  its  latest 
completion time is longer than its actual duration. A non­critical activity is said to have a slack or 
float time. 

11.3.2.  Determination of the Critical Path 
A critical path defines a chain of critical activities that connects the start and end  events of the 
arrow diagram.  In other words, the critical path identifies all the critical activities of the project. 

The  critical  path  calculations  include  two  phases.  The  first  phase  is  called  the  Forward  Pass 
where  all  calculations  begin  from  the  start  node  and  move  to  the  end  node.  At  each  node  a 
number is computed representing the earliest occurrence time of the corresponding event. These 

Sikkim Manipal University  187 
Operations Research  Unit 11 

numbers are shown in squares   . In forward pass we note the number of heads joining the event. 
We  take  the  maximum  earliest  timing  through  these  heads.The  second  phase  called  the 
Backwards  Pass,  begins  calculations from  the  “end”  node  and  moves  to  the  “start”  node.  The 
number computed at each node is shown in a triangle D near end point which represent the latest 
occurrence time of the corresponding event. Consider the forward pass In backward pass we see 
the number of tails and take minimum value through these tails. 

Let ESi  be the earliest start time of all the activities emanating from event i, i.e. ESi  represents 


the  earliest  occurrence  time  of  event  i,  if  i  =  1  is  the  “start”  event  then  conventionally,  for  the 
critical  path  calculations, ESi  =  0  ,  Let  Dij  be  the  duration  of  the  activity (i,  j).  Then  the forward 
pass calculations are given by the formula: 

ES i  = maxi  {ESi+Dij}, for all defined (i, j) activities with ESi=0.  Thus in order  to compute EsJ  for 


event j, Esi  for the tail events of all the incoming activities (i,  j) must be computed first. 

With the computation of all ESj, the forward pass calculations are completed.  The backward pass 
starts from  the  “end” event.  The  objective of  this  phase  to calculate LCi,  the latest completion 
time for all the activities coming into the event i.  Thus if i = n is the end event LCn  = ESn  initiates 
the backward pass. 

In general for any node i, LCi  = min {LCj­Dij} for all defined activities are calculated, which ends 
the calculation of backward pass. 

The critical path activities can now be identified by using the results of the forward and backward 
passes.  An activity (i, j) lies on the critical path if it satisfies the following conditions. 
A)  ESI  = LCi 
B)  ESJ  = LCJ 
C)  ESJ­ESI  = LCJ­LCI  = DiJ 

These conditions actually indicate that there is no float or slack time  between the earliest stand 
and the latest start of the activity. Thus the activity must critical.  In the arrow diagram these are 
characterised by numbers in     and D are the same at each of the head and tail events and the 
difference between the number in   (or D) at the head event and the number in     (or D) at the tail 
event in equal to the duration of the Activity. 

Thus we will get a critical path, which is chain of connected activities, which spans the network 
form start to end.

Sikkim Manipal University  188 
Operations Research  Unit 11 

Example  2:  Consider  a  network  which  stands  from  node  1  and  terminate  at  node  6,  the  time 
required to perform each activity is indicated on the arrows. 

Fig. 9.4 

Let us start with forward pass with ESi  = 0. 
Since there is only one incoming activity (1, 2) to event 2 with D12  = 3. 
ES2  = ES1+ DS2  = 0+3=3. 

Let us consider the end 3, since there only one incoming activity (2, 3) to event 3, with D23  = 3. 
ES3  = ES2+ D23  = 3+3 = 6. 
To obtain ES4, since there are two activities A (3, 4) and (2,4 ) to the event  4 with D24  = 2 and D34 
= 0. 
ES4= maxi=2, 3  { ESi  + De4} 
= max { ES2  +D24, ES3  + D34} 
= max {3+2, 6+0} = 6 
Similary ES5  = 13 and ES6  = 19 
Which completed first phase. 
In the second phase we have 
LC6= 19 = ES6 
LC5  = 19­6 = 13 
LC4= minJ = 5, 6  {LCJ  – D4J}  = 6 
LC3  = 6, LC2  = 3 and LC1  = 0

\ activities (1, 2), (2, 3) (3, 4) (4, 5) (5, 6) are critical and (2, 4) (4, 6),          (3, 6), are non­critical.

Sikkim Manipal University  189 
Operations Research  Unit 11 

Thus the activities (1, 2) (2, 3 ) (3, 4) (4, 5) and (5, 6) define the critical path which is the shortest 
possible time to complete the project. 

11.3.3.  Determination of Floats 
Following  the  determination  of  the  critical  path,  the  floats  for  the  non­critical  activities  must  be 
computed.  Note  that  for  the  critical  activities  this  float  is  zero.    Before  showing  how  floats  are 
determined, it is necessary to define two new times that are associated with each activity.  There 
are Latest Start (LS) and the Earliest Completion (EC) times, which are defined activity (i, J) by 
LSeJ= LCJ  – DiJ 
and ECeJ  = ESi  + DiJ 

There are two important types of floats namely, Total Float (TF) and Free Float (FF).  The total 
float TFiJ  for activity (i, J) is the difference between the maximum time available to perform the 
activity (= LCJ  – ESi)  and its duration (= DiJ  ) 

That is, 

TFiJ  = LCJ – ESI  – DiJ  = LCJ  – ECiJ  = LS iJ  – ESi 

The free float is defined by assuming that all the activities start as early as possible.  In this case 
FFiJ  for activity (i, J) is the excess of available time  (= ESi  – ESi) over its deviation (= DiJ  ); 
that is,  FFiJ  = ESi  – ESi  = DiJ  . 

Note  that  only for  a  critical activity  must  have  zero  total float.  The free float  must also  be  zero 
when  the  total  float  is  zero.    The  converse  is  not  true,  that  is  in  the  sense  that  a  non­critical 
activity may have zero free floats. 

Let us consider the example taken before the critical path calculations together with the floats for 
the non­critical activities can be summarized in the convenient form shown in the following table:

Sikkim Manipal University  190 
Operations Research  Unit 11 

Earliest  Latest 
Activit  Table  Free 
Duration  Start  Completio  Start  Completio 
y  Float  Float 
DiJ  ES n  LS n
(i J)  i  ij  TFiJ  FFiJ 
ECiJ  DLCJ 
(1, 2)  3  0  3  0  3  0* 0 
(2, 3)  3  3  6  3  6  0*  0 
(2, 4)  2  3  5  4  6  1  1 
(3, 4)  0  6  6  6  6  0*  0 
(3, 5)  3  6  9  10  13  4  4 
(3, 6)  2  6  8  17  19  11  11 
(4, 5)  7  6  13  6  13  0*  0 
(4, 6)  5  6  11  14  19  8  8 
(5, 6)  6  13  19  13  19  0*  0 
Note:  Total float = ESij  = LFij  ­ ESij 
Free float = Total float ­ ­ Head slack 

* Critical activity * 

Example 3: A project consists of a series of tasks A, B, C, – D, – E, F, G, H, I with the following 
relationships.  (W  < X,Y  means  X and  Y  cannot starts until W is  completed,  X,Y  < W  means W 
cannot start until both X and Y are completed). With this notation construct the network diagram 
having the following constraints A < D, E; B, D < F; C < G, B < H; F,G < I. 

Find also the minimum time  of completion of the project, the critical path, and the total floats of 
each task, when the time (in days) of completion of each task is as follows: 
Task:  A  B  C  D  E  F  G  H  I 
Time:  23  8  20  16  24  18  19  4  10 

Fig. 9.5

Sikkim Manipal University  191 
Operations Research  Unit 11 

ES1  = 0, ES 2  = 20, ES3 = 23, ES4  = 59, ES5  = 39, ES6  = 57, ES7  = 67 

Durati  Earliest  Latest  Table  Free 


Activity  on  Float 
Start  Finish  Start  Finish  Float 
(iJ) 
DiJ  ESe  Eeij  LJ­DiJ  LJ  TFiJ  FFiJ 
(1,  2)  20  0  20  18  38  18 0 
(1,  3)  23  0  23  0  23  0* 0 
(1,  4)  8  0  8  31  39  31  31 
(2,  5)  19  20  39  38  57  18 0 
(3,  4)  16  23  39  23  39  0* 0 
(3,  7)  24  23  47  43  67  20  20 
(4,  5)  0  39  39  57  57  10 0 
(4,  6)  18  39  57  39  57  0* 0 
(5,  6)  0  39  39  57  57  18  18 
(5,  7)  4  39  43  63  67  24 24 
(6,  7)  10  37  67  57  67  0*  0 
Critical path is 1 – 3 – 4 – 6 – 7. 

Self Assessment Questions 2 
Fill in the blanks 
1.  Events do not consume ________ and _________. 
2.  Arrow’s head number is _________ than its tail number. 
3.  Dummy activity in network is introduced t keep proper _________ relationship. 
4.  Critical path calculation include both _________ and _________. 

11.4  Project Management – PERT 

Probability and Cost Consideration in Project Scheduling 
The analysis in CPM does not take into the case where time estimates for the different activities 
are probabilistic. Also it does not consider explicitly the cost of schedules. Here we will consider 
both probability and cost aspects in project scheduling. 

Probability  considerations  are  incorporated  in  project  scheduling  by  assuming  that  the  time 
estimate for each activity is based on 3 different values.  They are – 
a =  The  optimistsic time,  which  will  be  required if  the  execution  of  the  project  goes  extremely 
well. 
b =  The pessimistic time, which will be required if everything goes bad.

Sikkim Manipal University  192 
Operations Research  Unit 11 

m =  The most likely time, which will be required if execution is normal. 
a + b 
The most likely estimate m need not coincide with mid­point  of              a and b.  Then the 

a + b 
expected  duration  of  each  activity  D  can  be  obtained  as  the  mean  of  and  2  m.  i.e. 

a + b 
+ 2 m 
2  a + b + 4 m 
D= = . 
3  6 

This estimate can be used to study the single estimate D in the critical path calculation. 

The variance of each activity denoted by V is defined by 

b - a ö
variance V =  æç ÷ . 
è 6  ø
The earliest expected times for the node i denoted by E(mi)  for each node       i is obtained by 
taking  the  sum  of  expected  times  of  all  activities  leading  to  the  node  i,  when  more  than  one 
activity leads to a node i, then greatest of all E(mi)  is chosen .  Let mi  be the earliest occurrence 
time  of the  event i,  we  can  consider mi  as a  random variable. Assuming  that  all  activities of the 
network  are  statistical  independent,  we  can  calculate  the  mean  and  the  variance  of  the mi  as 
follows  E{mi  }  =  ESI  and Var{mi  }  = å V k  . Where  K defines the  activities along  the  largest path 

leading to i. 

For  the  latest  expected  time,  we  consider  the  last  node.    Now  for  each  path  move  backwords, 

substituting the  D eJ  for each activity (ij). Thus we  have E(LJ) = E(ma) and E(mi) = L(LJ) –  D  iJ  if only 

one path events from J to i or it is the minimum of {E[LJ) –  D  iJ  ] for all J for which the activities (i, j) 

is defined. 

Note:  The  probability distribution  of  times for  completing  an  event  can  be  approximated  by  the 
normal distribution due to central limit theorem. 

Since mi  represents  the  earliest  occurrence  time,  event  will  meet  a  certain  schedule  time  STi 
(specified by an analyst) with probability 
æ m - E ( m )  ST  - E ( m ) ö
Pr  (mi £ STi) = Pr ç i  i  £ i  i  ÷
ç ÷
è V ( mi )  V ( mi )  ø

= Pr  (Z £ Ki)

Sikkim Manipal University  193 
Operations Research  Unit 11 

ST i - E ( mi ) 
where Z ~N(01) and Ki  =  . It is common practice to compute the probability that event i 
V ( mi ) 

will occur no later than its LCe  such probability will then represent the chance that the succeeding 
events will occur within the (ESe, LCe) duration. 

Example 4: A project is represented by the network shown below and has the following data. 

Task  A  B  C  D  E  F  G  H  I 
Optimistic Time  5  18  26  16  15  6  7  7  3 
Pessimistic Time  10  22  40  20  25  12  12  9  5 
Most Likely Time  8  20  33  18  20  9  10  8  4 

Determine the following: 
a)  Expected task time and their variance. 
b)  The earliest and latest expected times to reach each event. 
c)  The critical path. 

Fig. 9.6 
d)  The probability of an event occurring at the proposed completion data if the original contract 
time of completing the project is 41.5 weeks. 
e)  The duration of the project that will have 96% channel of being completed. 

Solution: 
a)  Using the formula we can calculate expected activity times and variance in the following table 

D = 1  ( a + b + 4 m )  V  = æç b - a ö÷
6  è 6  ø

Sikkim Manipal University  194 
Operations Research  Unit 11 

b) 
Activity  a  B  m  v 
1­2  5  10  8  7­8  0.696 
1­3  18  22  20  20­00  0.444 
1­4  26  40  33  33­0  5.429 
2­5  16  20  18  18­0  0.443 
2­6  15  25  20  20­0  2.780 
3­6  6  12  9  9­0  1.000 
4­7  7  12  10  9­8  0.694 
5­7  7  9  8  8­0  0.111 
6­7  3  5  4  4­0  0.111 

Forward Pass: 
E1  = 0     E2  = 7.8    E 3  = 20      E4  = 33    E5  = 25­8     E6  = 29    E7  = 42.8 

Backward Pass: 
L7  = 42.8    L6  = 38.8   L5  = 34.8    L4  = 33.0   L3  = 29.8  L2  = 16.8   L1  = 0. 
The E­values and L­values are shown in Fig. 

Fig. 9.7 
c)  The  critical  path  is  shown  by  thick  line  in  fig.  The  critical  path  is  1­4­7  and  the  earliest 
completion time for the project is 42.8 weeks. 
d)  The  last  event  7  will  occur  only  after  42.8  weeks.  For  this  we  require  only  the  duration  of 
critical activities. This will help us in calculating the standard duration of the last event. 

Expected length of critical path = 33+9.8 = 42.8 
Variance of article path length = 5.429+0.694 = 6.123

Sikkim Manipal University  195 
Operations Research  Unit 11 

Probability of meeting the schedule time is given by  Pi  (Z £ Ki) = 
Pi  (Z – 0.52) = 0.30 (From normal distribution table) 

Thus the probability  that the project can be completed in less than or equal to 41.5 weeks is 
0.30.  In other words probably that the project will get delayed beyond 41.5 weeks is 0.70. 
e)  Given that P (Z £ Ki) = 0.95. But Z0.9S = 1.6 u, from normal distribution table. Then 1.6 u = 
ST i - E ( m i )  ST i  - 42 . 8 
is 1 . 6 u  = or 
V ( m i )  2 . 47 

Sji = 1.64´2.47+42.8 = 46.85 weeks. 

Self Assessment Questions 3 
I)  True or False 
1)  In a project network, a sequence of activities may form a loop. 
2)  A critical activity must have its total and free floats equal to zero. 
3)  A non­critical activity cannot have zero total float. 
4)  The critical path of project network represents the minimum duration needed to complete 
the network. 
5)  A network may include more than one critical path. 

11.5.  Summary 
Critical  Path  computations  are  quite  simple,  yet  they  provide  valuable  information  that 
simplifies  the  scheduling of  complex projects.    The  result  is  that  PERT­CPM  techniques 
enjoy  tremendous  popularity  among  practitioners  in  the  field.  The  usefulness  of  the 
techniques  is  further  enhanced  by  the  availability  of  specialized  computer  systems  for 
executing, analyzing and controlling network projects. 

Terminal Questions 
1.  Write down the basic difference between PERT and CPM. 
2.  Explain Project Management (PERT) 
3.  A project has 10 activities.  The following table shows the information about the activities. 

Activity  Preceding activity  Duration in weeks 


A  ­  6 
B  ­  3 
C  A  5 
D  A  4

Sikkim Manipal University  196 
Operations Research  Unit 11 

E  A  3 
F  C  3 
G  D  5 
H  B, D, E  5 
I  H  2 
J  I, G, F  3 

a.  Draw the network 
b.  Find the project duration 
c.  Identify the CPM 
d.  Prepare the schedule 
4.  A small project consisting of eight activities has the following characteristics: 
TIME ESTIMATES (IN WEEKS) 
Activity  Preceding activity  Most optimistic  Most likely time  Most pessimistic 
time (a)  (m)  time (b) 
A  None  2  4  12 
B  None  10  12  26 
C  A  8  9  10 
D  A  10  15  20 
E  A  7  7.5  11 
F  B, C  9  9  9 
G  D  3  3.5  7 
H  E, F, G  5  5  5 

a.  Draw the PERT network for the project. 
b.  Determine the critical path. 
c.  If a 30­week deadline is imposed, what is the probability that the project will be finished within 
the time limit? 
d.  If  the project  manager  wants  to be  99%  sure  that  the project is  completed on  this  schedule 
date, how many weeks before that date should he start the project work? 

Answers To Self Assessment Questions 
Self Assessment Questions 1 
1. True  2. True  3. True  4. False  5. True 

Self Assessment Questions 2 
1. Time, resource 
2. Greater than

Sikkim Manipal University  197 
Operations Research  Unit 11 

3. Precedence 
4.  Forward pass & backward pass 

Self Assessment Questions  3 
1) False  2) True  3) True  4) True  5) False 

Answer for Terminal Questions 
1.  Refer to Section 11.2 
2.  Refer to Section 11.4 
3.    b)  20  weeks  c)  A – D – H – I ­ J 
4.    b) A – D – G – H   c) 0.6591    d) 34.7 weeks

Sikkim Manipal University  198 

Vous aimerez peut-être aussi