Week n°: 03 from 17/01/11 to 23/01/11

Rovinari Site Week Total Quantity done W02 TW 02 done W03 TW 03 % W49 % W50 % W02 % W03

Piping Activities (U3+C)


GRP GRP Spools 919 97 543 45 588 45% 49% 59% 64%
Lamination 687 91 470 41 511 51% 55% 68% 74%
Support 1600 0 111 0 111 6% 7% 7% 7%
CS CS Spools 428 26 149 61 210 27% 29% 35% 49%
Welding 980 34 173 76 249 14% 14% 18% 25%
Support 750 10 138 13 151 16% 17% 18% 20%
5364 258 1584 236 1820 23.1% 24.7% 29.5% 33.9%

RC pipes (U3)
Spools 33 5 17 3 20 30% 36% 52% 61%
Lamination 23 2 5 2 7 9% 13% 22% 30%
Support 25 1 2 0 2 0% 4% 8% 8%
Valves 5 3 3 0 3 0% 0% 60% 60%
Expansion joints 15 0 0 0 0 0% 0% 0% 0%
101 11 27 5 32 11.9% 15.8% 26.7% 31.7%

Electricity (U3+C)
Cable Tray 7000 0 6500 100 6600 93% 93% 93% 94%
Instrumentation 592 0 150 150 25% 25% 25% 25%
I&C Pulling 44905 3000 11000 2000 13000 11% 18% 24% 29%
MV/LV connection 159 0 9 2 11 6% 6% 6% 7%
MV / LV pulling 56819 0 23380 23380 41% 41% 41% 41%
109475 3000 41039 2102 43141 32.0% 34.7% 37.5% 39.4%

Quality
NCR opened NA 6 80 4 84
Average time to close (days) NA 127 127
Absorber welds controlled/rework U3 536 46 46 9% 9% 9% 9%
Absorber welds controlled/rework U6 169 0 0 0% 0% 0% 0%

Absorber progress
Absorber N°3
Shell 2350 2020 2020 86% 86% 86% 86%
Reinforcements 4500 4250 4250 92% 94% 94% 94%
Spray Headers 97% 97% 97% 97%
Mist Eliminator 6% 26% 67% 69%
Nozzles, Doors 71% 77% 83% 83%
Decontamination 15% 18% 21% 30%
84.3% 86.2% 88.5% 88.7%
Absorber N°6
Shell 2350 400 1600 100 1700 51% 51% 68% 72%
Reinforcements 4500 100 1600 1600 29% 33% 36% 36%
Spray Headers 49% 59% 59% 59%
Mist Eliminator 1% 5% 8% 8%
Nozzles, Doors 0% 0% 0% 0%
Decontamination 0% 0% 0% 0%
39.0% 42.4% 50.1% 51.8%

Limestone area
Limestone silo steel structure (t) 490 2 490 490 99.6% 99.6% 100.0% 100.0%
Limestone silo (t) 140 4 140 140 97.1% 97.1% 100.0% 100.0%
Limestone slurry tank (t) 52 0.5 52.0 52.0 99.0% 99.0% 100.0% 100.0%
Limestone slurry tank lining (%) 100 1.6 1.6 30.0 0.0% 0.0% 1.6% 30.0%
Limestone area equipments
installation (number) 13 2 5 5 15.4% 23.1% 38.5% 38.5%

82.3% 83.5% 87.1% 88.1%

Absorber building cladding (U3)


secondary steel structure (kg) 58500 283 12283 1775 14058 13.7% 20.5% 21.0% 24.0%
Cladding surface ( m2) 7400 1193 1193 685 1878 0.0% 0.0% 16.1% 25.4%

9.6% 14.4% 19.5% 24.4%