Project Hydro Gemini (PHG)

Charlie McCullough/Project Manager Tamika Roland/Project Coordinator Alex Torres/Research Analyst Chris Gonzalez/Research Analyst

Cost Management Plan


Project Name: Hydro Gemini Prepared by: Charlie McCullough Date: 1/11/11 Person(s) authorized to request cost changes (see Cost Change Request): Name: Charlie McCullough Title: Project Manager Name: SS Hydro Inc. Title: Client Person(s) to whom Cost Change Request forms must be submitted for approval: Name: Charlie McCullough Title: Project Manager Name: David Belton Title: PMO Acceptable reasons for changes in Project Cost (e.g., approved scope changes, increased raw materials costs, etc.): Increased procurement cost: concrete foundation (quick dry), asphalt, binding agent, lime base. Contractor and subcontractor human asset acquisitions. Describe how you will calculate and report on the projected impact of any cost changes (time, quality, etc.): After careful consideration of any cost change request, any request that is approved or denied will be placed in final documentation. Calculation of costs have been planned and mitigated prior to project concept which formally introduced the project. Calculations are done with ROM (Range of Magnitude) estimates providing ballpark figure as well. Cost variance and earned value (EV) are expressed and represented in chart/graph form. Describe any other aspects of how changes to the Project Cost will be managed: Changes in project cost will be mitigated with bottom up estimations providing adequate monetary fluctuation in anticipation of increased and decreased costs associated with this project.

Cost Breakdown (Concrete Road)


Salesperson
Jimmy Weir

Job Concrete Item # 20589300 35082940 90756 20589310

Job Type Full Service Description Quick Dry Concrete Asphalt Binding Agent Lime Base

Job Size 2,187 yards Unit Price $80 per sq yard $25 per sq yard $12 per sq yard Discount $50 per sq yard $15 per sq yard $5 per sq yard Line Total $174,960 $32,805 $10,935

Qty 1

Total Discount Subtotal Sales Tax Total

$190,469

$218,700

$26,509.09 $245,209.09

Cost Breakdown (Gantry Crane)


North American Industries 80 Holton Street Woburn, MA 01801 781-897-4100 Fax 781-729-3343 info@naicranes.com Comments: Project Hydro Gemini Bill To: Charlie McCullough SS Hydro Inc. 1234 ABC Lane Houston, Texas 7002 713-865-0668

Date 2/1/11

Description
One (1) Gantry Crane- Ten (10) Ton, 60 Span Single Girder crane with a 200 Runway 25 High

Amount $66,220.00

Human Resource Plan


McCullogh is PMO of Chydro and has appointed the job of Project Manager of separate departments to the following team members: } Alex Torres is PM over the bungalows and crane operations } Tamika Roland is PM of Human Resources } Chris Gonzalez is PM of the concrete an admin building
} Charlie

Human Resources Plan


the project managers will report to the PMO at the end of the day via email } Bi weekly meetings on Wednesday and Friday have been schedule for all the project managers to share their progress
} All

WBS FOR CONSTRUCTION