11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

OPERATORS MANUAL

P/N 640020495-01 Rev. A

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

OPERATORS MANUAL

HEAD WEAR PLATE PACKING UNIT PISTON INNER SLEEVE

BODY

11 - 5K MODEL 7022 ANNULAR BOP SCREWED HEAD

Page 1 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

Table of Content
1.0 Installation & Operation ................................................................................................................... 3 1.1 Principle of Operation ...................................................................................................................... 3 1.2 Operation ......................................................................................................................................... 6 1.2.1 Surface Installation ................................................................................................................... 6 1.2.2 Surface Stripping Operations .................................................................................................... 9 2.0 Physical Data ................................................................................................................................. 11 2.1 Engineering Data ............................................................................................................................ 11 2.2 Bolt Data ........................................................................................................................................ 12 2.3 Inside Dimensions .......................................................................................................................... 13 2.4 Outside Dimensions ....................................................................................................................... 14 3.0 Maintenance and Testing ................................................................................................................ 15 3.1 Maintenance Procedure .................................................................................................................. 15 3.2 Seal Testing.................................................................................................................................... 17 4.0 Disassembly and Assembly ............................................................................................................ 19 4.1 Disassembly ................................................................................................................................... 19 4.2 Assembly ....................................................................................................................................... 22 5.0 Parts & Storage .............................................................................................................................. 24 5.1 Parts List ........................................................................................................................................ 26 5.2 Diverter storage .............................................................................................................................. 26 5.3 Rubber Goods Storage.................................................................................................................... 26

Page 2 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD


1.0 Installation & Operation 1.1 Principle of Operation

Figure 1.1

Cross section of Diverter / BOP with Packing Unit fully Open

The 11 - 5K Model 7022 Blowout Preventer is an annular type BOP which seals off reliably on almost any shape or size drill pipe, drill collars, casing, tool joints in the well bore or completely seal off (CSO) of the open bore. The 11 5K annular BOP has been designed for use on surface installations Closing action begins when hydraulic fluid is pumped into the closing chamber of the annular BOP below the piston and raises the piston pushing the element up; the elements spherical shape causes it to close in at the top as it moves upward. Because the well bore pressure below the sealed off packing unit tends to push the piston down and decreases the closing force; therefore, closing pressure must be maintained during well control operations. During well control operations, drill pipe can be rotated and tool joints stripped through a closed packing unit while maintaining a full seal on the pipe. The annular BOP can be operated with any normal close and open units having a separate pressure regulator valve for the annular blowout preventer and sufficient accumulator volume. (See Section 2.1 of this manual for close and open chamber volume). The hydraulic operating fluid should be clean, light petroleum hydraulic oil, or water with a water-soluble oil added. In cold climates, anti-freeze should be added to prevent freezing. Page 3 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

The closing time of the diverter is determined by the rate at which the hydraulic fluid can be delivered to the closing chamber. Using short, large diameter control lines, large bore control valves, and a large accumulator volume can reduce closing time. An excessively high setting on the pressure regulator valve will have little effect on the diverter closing time.

Figure 1.2

The piston squeezes packing unit rubber inward to close the opening by upward force

Page 4 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

Figure 1.3 The annular BOP opens to full bore to allow passage of large diameter tools through open bore

Figure 1.4 The annular BOP with packing unit seals off on drill pipe

Figure 1.5 The annular BOP diverter with packing unit seals off on square or hexagonal kellys

Figure 1.6 The annular BOP diverter with packing unit closed on open hole

Page 5 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

1.2

Operation 1.2.1 Surface Installation Operation for 11 5K annular BOP requires opening and closing pressure. Figure 1.7 shows the surface installation of the annular BOP with hydraulic operating pressure line connecting to the closing chamber and opening chamber of the diverter. Pressure applied to the closing chamber raises the piston and pushes the packing unit up; the elements spherical shape causes it to close in at the top as it moves upward. Well pressure or test pressure acts on the piston below the sealed off packing unit and tends to increase the closing force acting on the packing unit. Figure 1.8, Control Pressure graph shows the relationship of closing pressure and well pressure required to effect optimum seal off for the 11 5K annular BOP. During normal drilling operations, it is recommended that the pressure regulator valve for the annular BOP be set at the initial closing pressure shown for the size pipe being used. This pressure will ensure that initial seal off is achieved should a kick be encountered. During diverter testing operations, once initial seal off is achieved, closing pressure should be maintained as well pressure is increased.

OPENING CHAMBER LINE CLOSING CHAMBER LINE

Figure 1.7

Page 6 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

1500 CLOSING PRESSURE (PSI)

1000

500

0 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 5,000 WELL/TEST PRESSURE (PSI) 5-1/2" through 8-5/8" pipe 4-1/2" through 5" pipe 3-1/2" pipe 2-7/8" pipe 2-3/8" pipe CSO

Figure 1.8

Closing pressure Vs well / test pressure for different drilling pipes

Page 7 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD


CONTROL SYSTEM

HYDROSTATIC HEAD

Figure 1.9

CAUTION:

The 11 5K annular BOP is sensitive to its position relative to the control system. If the control system is located at a level higher than the closing chamber of the diverter, the hydrostatic head of the operating fluid may be sufficient to prevent the piston from coming completely down. This will prevent the packing unit from opening to full bore. For these situations, the installation of a spring-activated normally closed 2-way valve rated for 3000 psi in the closing line to drain the fluid head is recommended (refer to Figure 1.9). Be sure to drain the fluid into a container.

Page 8 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

1.2.2 Surface Stripping Operations

OPENING CHAMBER LINE CLOSING CHAMBER LINE

Figure 1.10

Surface Hookup

During well control operations, drill pipe can be rotated and tool joints stripped through a closed packing unit while maintaining a full seal off on the pipe. Rotation or stripping through a closed and sealed packing unit will shorten its life. Longest life for the packing unit is obtained by adjusting the closing forces low enough to maintain a seal on the drill pipe with a slight amount of drilling fluid leakage as the tool joint passes through the packing unit. Slow tool joint stripping speeds reduce surge pressures, prolonging packing unit life. The pressure regulator valve should be set to provide and maintain the proper control pressure. If the pressure regulator valve does not respond fast enough for effective diverter control, a surge absorber (accumulator) should be installed in the closing chamber control line adjacent to the diverter (Figure 1.11). Pre-charge the accumulator to one-half of the closing pressure required to affect a seal off at the existing well pressure for the pipe size in use. CAUTION: Rotation of drill pipe in one position generates heat that is detrimental to the packing unit if continued for a long period of time.

Page 9 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

OPENING CHAMBER LINE CLOSING CHAMBER LINE

Figure 1.11

Surface Hookup with surge absorber

Page 10 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

2.0

Physical Data

2.1

Engineering Data

English
Bore Working Pressure Shell Test Pressure (Factory Test Only) Closing Chamber Test Pressure (Factory Test Only) Opening Chamber Test Pressure (Factory Test Only) Volume Closing Chamber Volume Opening Chamber Piston Stroke Port Size Weight Shackle Swivel Safe Working Load (Each) 11 in 5000 psi 10000 psi 4500 psi 4500 psi 10.40 gallons 8.62 gallons 7.125 inches 1.00 11 NPT 8,225 lb 8,000

Metric 279.4 mm 351.54 kg/cm2 703.1 kg/cm2 316.4 kg/cm2 316.4 kg/cm2 39.37 liters 32.63 liters 180.98 mm 3731 kg 4 Ton

Page 11 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

2.2

Bolt Data

Recommended Torque Ref. No. 6 7 13 14 16 17 Description Cap Screw Inner Body Sleeve Cap Screw - Wear Plate Head Lock Screw Pipe Plug Piston Indicator Connecting Stud Connecting Nut Eyebolt - Piston Eyebolt - Head Thread Ft-Lbs 3/4 10 UNC 1/2 13 UNC 1.00 8 UNC 1/2 NPT 1 7/8 8 UN 1 7/8 8UN 5/8 11 UNC 1 7 UNC 152 45 360.8 50 2533 2533 Snug Snug Meter-Kg 21 6.2 49.7 6.9 350 350 Snug Snug

Page 12 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

2.3

Inside Dimensions

L H C G K F B J E

D A
Figure 2-1

NOMINAL DIMENSION

B Major O.D. Piston 30.726 H Top of Sleeve to Bottom of Wear Plate 12.187

C Upper I.D Body 30.754 J

D Minor O.D. Piston 23.233

E Top of Body to Top of Sleeve 13.125 K

F Lower I.D Body 23.254 L

Bore INCHES NOMINAL DIMENSION 11.015 G

Piston Height INCHES 23.282

Packing Unit Height 12.187

Stroke 7.125

Head Height 14.455

Page 13 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

2.4

Outside Dimensions

A H B

E F G
Figure 2-2

NOMINAL DIMENSIONS - INCHES A 52.41 B 33.75 C 13.46 D 48.583 E 9.69 F 25.75 G 32.00 H 37.50

Page 14 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

3.0

Maintenance and Testing 3.1 Maintenance Procedure

Prior to placing the T3 annular BOP into service, the following visual inspections (as noted in Figure 3.1) should be performed.
1 6 3 2 7

2 7 5

4 3 1
Figure 3-1 Areas and Parts Requiring Maintenance

1.

Inspect the upper and lower connections for pitting, wear, and damage especially in ring grooves and stud bolt holes. Worn or damaged ring grooves must be repaired in a T3 Energy Services Inc. authorized machine shop. The T3 annular BOP is a primary pressure vessel. As supplied, the diverter surfaces exposed to well bore fluids meet the requirements for H2S service. Proper handling and repair are required to maintain the original integrity. Field welding is not recommended as it induces undesirable stresses that must be relieved by proper heat-treating procedures or controlled by special welding procedures. Page 15 of 27

NOTE:

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

2.

Check the body for wear and damage especially in the internal cylinder walls for pits and vertical scores. Check the wear plate for damage to the surface that contacts the packing unit. Remove minor pits and scores with emery cloth. Coat the repaired surface with silicon grease or castor oil. Severe pits and scores that require machining and/or welding must be repaired in a T3 Energy Services Inc. authorized machine shop. Inspect the vertical bore for wear and damage from drill string and drill tools especially in the area of the ring grooves. If wear is excessive, the area must be repaired. Check the inner body sleeve for wear, damage, and looseness. Check slots in inner body sleeve for cuttings that may restrict piston movement. Check the piston for damage and wear especially the seal surfaces for pits and vertical scores and the tapered bowl for pits and gouges Remove minor pits and scores on the walls with emery cloth. Coat the required surface with silicon grease or castor oil. Severe pits and scores that require machining and/or welding must be repaired in a T3 Energy Services Inc. authorized machine shop. Remove sharp or rolled edges with emery cloth or a grinder. The repair is satisfactory when the surface is relatively smooth. Inspect the packing unit for wear, cracking, hardness, and correct elastomer composition. Check the seal rings for nicks, cuts, fraying of lips, and abrasion. Replace worn or damaged seal rings.

3.

4.

5.

6. 7.

Page 16 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

3.2

Seal Testing

Head Gasket (8) U-Seal (11)

U-Seal (10)

U-Seal (9)

Figure 3-2

Seals

a)

Test seals 9 and 10. Pressurize closing chamber with pressure referenced in Figure 1.8. Apply 1500 psi if no packing unit is installed. Use the recommended test mandrel if a packing unit is installed. Open opening port to atmosphere Closing fluid is visible at opening port seal 10 is leaking Closing chamber pressure gauge is dropping and no fluid is detected at bottom flange - seal 9 is leaking Page 17 of 27

IF: IF:

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

b)

Test seals 8, 10 and 11. Pressurize opening chamber (1500 psi) Open closing port to atmosphere. Fluid is detected coming from area between body and head seal 8 is leaking Fluid is seen coming into the wellbore seal 11 is leaking Fluid is visible at closing port seal 10 is leaking.

IF: IF: IF:

c)

Test seals 9 and 11. Open closing port to atmosphere. Open opening port to atmosphere. Install blind flange on top of preventer. Pressurize wellbore (5000 psi maximum) Fluid is detected coming from the opening port seal 11 is leaking. Fluid is detected coming from the closing port seal 9 is leaking.

IF: IF:

Page 18 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

4.0

Disassembly and Assembly 4.1 Disassembly

Refer to figures 4-1 and 4-2 while following this procedure

Plug (14)

Head (4) Wear Plate Cap Screw (7) Wear Plate (5)

DETAIL G

DETAIL H

Packing Unit (12) Body (1) Piston (3)

Inner Body Sleeve (2)


DETAIL J

Inner Body Sleeve Cap Screw (6)

Figure 4-1

Page 19 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

Head Cap Screw (13)

U-Seal (11)

U-Seal (10)

U-Seal (9)

Figure 4-2

4.1.1 Vent all Pressure Vent the closing chamber to atmosphere ensuring that no trapped pressure exists, which will cause injury to personnel, and/or damage to equipment. Open the valves in the control system to exhaust the pressure and/or loosen the hydraulic connections to allow the pressure to leak out. WARNING: STAND CLEAR OF ESCAPING PRESSURE TO AVOID INJURY

Page 20 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD


4.1.2 Head Removal (item 4)

Figure 4-3

Remove head lock screw (item 13) Unscrew blowout preventer head (item 4) in counter-clockwise direction as shown on figure 4-3 Lift off blowout preventer head with two 1 7UNC eyebolts installed in top of head.

NOTE:

Do not attempt to loosen the blowout preventer head by applying heat.

Page 21 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

4.1.3 Packing Unit Removal (Item 12) Install two eyebolts into packing unit. Lift packing unit of piston. Use a sling of adequate length to prevent side loading of eyebolts. 4.1.4 Piston Removal (Item 3) Install two 5/8 11UNC eyebolts in top of piston. Slowly lift piston vertically to free from preventer body. If a vertical lift is unfeasible of if the piston does not freely lift out, slowly apply low (50 psi) hydraulic pressure to the closing chamber. DO NOT USE AIR OR GAS! 4.1.5 Inner Body Sleeve Removal (Item 2) Remove 6 inner body sleeve cap screws (item 9) from around the body sleeve. Lift out the inner body sleeve with a sling and hooks under the slots.

4.2

Assembly Refer to Figure 4-1 and Figure 4-2 while following this procedure. 4.2.1 Clean and Inspect All Parts Before Assembly Ensure that working surfaces are free of burrs, rough edges, or other defects. Inspect all seals and replace any damaged seals or seals in use over one year. Coat all seals and non-extrusion rings with silicon grease or castor oil before installation. CAUTION: Use of petroleum base oil or grease will reduce seal life 4.2.2 Inner Body Sleeve Installation (item 2) Install inner body sleeve (item 2) into inside bottom of blowout preventer body. Install 6 inner body sleeve cap screws ( item 6) and torque torque to 152 ftlbs. 4.2.3 Piston Installation (item 3) Lubricate and install the lower U-seals (Item 9) on the lower segment of the piston Lubricate and install the upper U-seals (Item 10) on the upper segment of the piston Install two (5/8 - 11UNC) eyebolts on top of piston. Lubricate all mating surfaces before lowering the piston into the body. Ensure that the piston is Page 22 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD


aligned vertically with the body prior to lowering. With proper vertical alignment, the piston will slide its normal stroke to the bottom of the preventer body. CAUTION: Be careful not to damage the seals during assembly Remove eyebolts

4.2.4 Install the Packing Unit (Item 12) Lubricate the piston bowl with silicon grease or castor oil. Lift the packing unit with two eyebolts and set it into the piston bowl which is already installed inside of the preventer.. 4.2.5 Install the Head (Item 4) Lubricate and install the head gasket (Item 8) in the seal groove on outside of the preventer head. Lubricate and install U-seals (item 11) in seal grooves on inside of the head. Clean threads of foreign matter and check threads for burrs or rough edges. Lubricate locking threads of the head with anti-seize compound. Install two 1 7UNC eyebolts installed in top of head. Lift head and install wear plate (item 5) with cap screws (item 7). Torque the screws to 45 ft-lbs. Lower and align the lead thread of the head with the lead thread of the body Screw head clockwise (right hand) into body until it shoulders against top of body Line up lock screw hole in head with hole in body and install head cap screw (item 13). Torque the screw to 360 ft-lbs Remove eyebolts from head. Preventer is ready for use/testing.

Page 23 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

5.0

Parts & Storage

Plug (14)

Head (4) Wear Plate Cap Screw (7) Wear Plate (5)

DETAIL G

DETAIL H

Packing Unit (12) Body (1) Piston (3)

Inner Body Sleeve (2)


DETAIL J

Inner Body Sleeve Cap Screw (6)

Figure 5-1

Page 24 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

Nuts (17) Studs (16) Head Cap Screw (13) Shackle (15)

U-Seal (11)

U-Seal (10)

U-Seal (9)

Figure 5-2

Page 25 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD

5.1

Parts List Refer Fig 5.1 & 5.2


Item 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Part Name Assembly Body Sleeve, Inner Body Piston Head Wear Plate Cap Screw, Socket Head Cap Screw, Socket Head Head Gasket U-Seal U-Seal U-Seal Packing Unit Cap Screw, Socket Head Plug, Pipe Shackle, Swivel Stud Nut Qty 1 1 1 1 1 6 6 1 2 2 2 1 1 1 4 16 16 Part Number SN067020386-01 SN280020375-01 SN880020385-01 SN725020379-01 SN575020380-01 SN73A020381-01 UB100029-01 UB100141 SN520CS0007 SN840CS0010 SN840CS0009 SN840CS0008 SN473CS0005 SN830CS0011 UB100050 UB100157 UN9300187080950 UN6700187

5.2

Diverter storage At the conclusion of each well or prior to placing the annular BOP in storage for even a brief period, it is recommended that the preventer be disassembled, cleaned, inspected, lubricated thoroughly with non-petroleum base oil such as cast oil or rapeseed oil, and reassembled. Replacement of worn packing units, or packers, seat rings, and other parts can be made conveniently at this time Flange or hub faces and ring grooves should be protected with covers, and ports should be plugged.

5.3

Rubber Goods Storage The term rubber goods include synthetic compounds such as Nitrile Copolymers and Neoprene, as well as natural rubber parts. The ideal storage situation for rubber goods would be in vacuum-sealed containers maintained in a cool, dry, dark storage area. The following recommendations will allow vendors and users of oil field equipment to maximize normally available storage facilities for rubber goods.

Page 26 of 27

*T3-1259262/A*

Operators Manual:

11 - 5K MODEL 7022 ANNULAR BOP, SCREWED HEAD


1. Keep the rubber storage area as dark as possible preferably indoors, not outdoors, and away from direct sunlight, skylights, windows, and direct artificial lighting. 2. Select a cool location (approximately 650 F) that is away from heaters, stoves, and direct blasts of space heaters. 3. Keep rubber goods away from electrical machinery (motors, switch gear, or any high voltage equipment producing corona). Avoid locations susceptible to drafts that will carry the atmosphere from electrical machinery to the rubber good storage area. 4. The practice of first-in, first out is essential with rubber goods. 5. Store rubber goods in a relaxed position in their normal shape. For example, do not hang o-rings on nails. Do not keep assemblies in stretched attitudes, e.g., o-rings on glands, BOP testers, and operators parts. 6. Rubber goods storage areas should be kept as dry as possible. Remove oil, grease or other foreign materials from storage area to preclude spillage on rubber goods. 7. If storage for extended periods is anticipated, sealed containers are recommended. Impervious surface coverings such as waxing will increase shelf life.

Factors that accelerate the deterioration of rubber goods are atmosphere, light and heat. The term aging means cumulative effects of all three attacking agents over a period of time. Other factors that will affect rubber goods include stretching or bending from normal shape, extreme cold, chemical reactions with solvents and petroleum products. Exposure to the atmosphere allows oxygen to react with the rubber goods. Ozone (O3), a very active form of oxygen, is especially detrimental to rubber goods. The principal sources of ozone contributing to rubber goods deterioration are: (1) atmospheric ozone, and (2) ozone created by electrical discharges such as lighting, high voltage corona, or electrical machinery. Points of strain in rubber goods attacked first by ozone and will be characterized by deep cracks. Ozone and normal oxygen (O2) will attack rubber goods much as steel rusts. Oxidation is characterized by a hard skin, which eventually crazes in small cracks and may turn chalky or assume a bark-like appearance. Strong, direct light, especially sunlight, has a harmful effect on rubber goods. The ultraviolet content of the light spectrum accelerates cracking. Light, especially sunlight, is undesirable and should be avoided at all times. Heat, whether the result of sunlight, artificial or accidental heating, will also have harmful effects upon rubber goods. Heat results in a gradual hardening of the rubber goods. The process is greatly accelerated when ozone or oxygen is present. In extremely cold climates, some rubber goods will become so brittle that they will shatter when dropped or handled roughly. Any stretching or bending of rubber goods in storage from a relaxed, normal shape will result in accelerated aging or cracking. Rubber goods, both natural and synthetic, possess some degree of susceptibility to deterioration from various solvents, especially oil field liquid hydrocarbons. These materials cause swelling/shrinkage of the rubber goods with which they are in contact.