DTP6-S1 KUIZ 1 Using the data given bellow, find the complete time for this project. Also determine the critical path. Activity 1-2 1-3 1-4 2-5 3-6 4-6 5-6 (10 mark) time 4 3 3 5 2 10 7 symbol A B C D E F G

KAWALAN PEMBUATAN (J5127)


DTP6-S1 KUIZ 1 Using the data given bellow, find the complete time for this project. Also determine the critical path. Activity 1-2 1-3 1-4 2-5 3-6 4-6 5-6 (10 mark) time 4 3 3 5 2 10 7 symbol A B C D E F G