Precast reinforced concrete piles shall only be supplied upon the Architect's instruction. Rates for driving of piles shall include for driving through whatever material encountered. Piles cast shall not be driven until they are at least 4 weeks old.
Precast reinforced concrete piles shall only be supplied upon the Architect's instruction. Rates for driving of piles shall include for driving through whatever material encountered. Piles cast shall not be driven until they are at least 4 weeks old.
Droits d'auteur :
Attribution Non-Commercial (BY-NC)
Formats disponibles
Téléchargez comme PDF, TXT ou lisez en ligne sur Scribd
Precast reinforced concrete piles shall only be supplied upon the Architect's instruction. Rates for driving of piles shall include for driving through whatever material encountered. Piles cast shall not be driven until they are at least 4 weeks old.
Droits d'auteur :
Attribution Non-Commercial (BY-NC)
Formats disponibles
Téléchargez comme PDF, TXT ou lisez en ligne sur Scribd
Project Title: Cyberjaya 5-Storey Bus Terminal Project Subject: Road Works Person in Charge: Shanggara A/L Balu Date: 7/3/2021 No - Description Unit Quantity Rate (RM) Amount (RM)