Académique Documents
Professionnel Documents
Culture Documents
The boiler involved in the accident was a water tube unit with attached
economizer and super heater. Total heating surface is 2203 sq.m and its
design pressure is about 12 000 KPa and it can produce 160,000 kg/hr of
steam.
The burner system can burn 8 different types of fuel using various
nozzles.
The boiler is protected from overpressure by 2 PSVs at the steam drum
and 1 PSV at the superheater.
INTRODUCTION
On 9 Dec 2000, at about 2:30am, three personnel were trying to re-start
the boiler when an explosion occurred inside the furnace of the boiler.
The three personnel were badly injured with more than 50% 2nd degree
burns on their bodies.
Two of them subsequently passed away later in the hospital:
Deceased 1 - Technician/ Male / 23 yrs old
Deceased 2 - Technician/ Female / 21 yrs old
2:30 2000 9
% 50
23 / /
21 / /
PHOTOGRAPHS OF BOILER
AFTER EXPLOSION
PHOTOGRAPHS OF BOILER
AFTER EXPLOSION
PHOTOGRAPHS OF BOILER
AFTER EXPLOSION
PHOTOGRAPHS OF BOILER
AFTER EXPLOSION
PHOTOGRAPHS OF BOILER
AFTER EXPLOSION
DESCRIPTION OF ACCIDENT
LPG
The boilers were in the commissioning stage at the time of the
accident. Written operational procedures were available for cold and
hot start-up of the boilers
Investigations revealed that the startup team encountered some
difficulties in lighting the boiler with LPG some time back. To
overcome the problem, they devised a temporary manual bypass
method.
This bypass method was not the same as the operational procedures.
) (
) (
.
The bypass method was used by the startup team as a temporary
measure and they had stopped using it when a permanent solution
was found to overcome the problem.
This method was only to be used by the startup team and no process
technicians were instructed to use it.
Investigations revealed that process technicians were present working
on this method with the startup team when it was used. This method
had been used on several occasions by most of the process
technicians
Company Internal Safety Management System
Pre-Startup Safety Review (PSSR) was claimed to be carried out
on the Boiler. But the PSSR document was not available for our
review during the investigation.
It was found that the bypass valves did not have any sealed wire
when the startup team first implemented the bypass method.
However, the team did not find out further why there was no
sealed wire on these valves.
8
9
Training & Experience
All technicians were given 8 months of orientation and training program.
This included technical and S.M.S. training.
The 2 deceased were Process Technicians but were not certified boiler
attendants. The injured was a Supervisor and a certified 1st Class Steam
Boiler Attendant.
The injured claimed that he was unaware of the bypass method and that it
was being used on 9 Dec. He also felt that the training provided was
insufficient for him to operate the boiler.
SITE FINDINGS
%50
( LPG )
% 66
( LPG )
Site investigations after the accident confirmed that the 2 bypass
valves were 50% open. This confirmed that the bypass method
was utilized to restart the boiler.
Data records confirmed that the LPG control valve was about
66% open just before the explosion.
The block valves before and after the control valve were fully
open.
A direct path was therefore established to allow LPG to enter the
firebox, resulting in the explosion of the boiler.
50% open
1st Trip valve
100% close
100% closed
Control valve
66% open
Block valve
100% open
Block valve
100% open
Block valve
100% open
CAUSE OF ACCIDENT
( LPG )
Use of temporary bypass method to restart the boiler after it had
tripped.
Two bypass valves of the trip valves were opened without first closing
the two block valves, downstream of the LPG control valve
Non-compliance of the company internal S.M.S.s safety requirements:
- The use of unauthorized temporary bypass method
- The removal of sealed wire on the bypass valves.
CONCLUSION
Air (Oxygen)
LPG
FIRE
TRIANGLE
LESSONS LEARNT
All personnel who are operating boiler must follow Safe
Operating Procedures.
Authorization must be obtained before introducing change to
the boiler system or procedures.
Ensure all personnel who are operating boiler received adequate
training and supervision.
Ensure proper documentation.
ACTIONS TAKEN
( BMS ) ( )
The company had been instructed to carry out a thorough
inspection and examination on the remaining Boiler and carry out
necessary rectification works to restore the boiler to safe
operating condition.
The company had also thoroughly reviewed the BMS and carried
out rectification to improve the system.
They had also reviewed and audited their internal S.M.S. to
identify weaknesses and to close such gaps.
THANK YOU