Activity Planning Sanctioning Layout Excavation Soling Anti-termite treatment Plain Cement Concrete Raft/Brickwork in foundation upto plinth level Damp proof course Earth filling in foundation Brickwork/Columns upto lintel Casting of lintel Fixing of door/window frames Brickwork/Columns upto roof level Roof Slab Shuttering Roof Slab Centering/rod binding Roof Slab casting Grill and gates fixing Doors and Windows Curing Chipping of Ceiling and Inside plastering Sanitation and plumbing Electrical Wiring Outside Plastering Flooring Tile Fixing Plaster of Paris Painting and colouring Roof treatment
Who's Involved
1
Architect/Engineer Architect/Engineer Contractor/Mason Labourer Mason/Labourer Agency Mason/Labourer Mason/Labourer Mason/Labourer Labourer Mason/Labourer Mason/Labourer Carpenter/Mason Mason/Labourer Mason/Centering gang Mason/Centering gang Mason/Labourer Mason/Labourer Carpenter Labourer Mason/Labourer Plumber Electrician Mason/Labourer Mason/Labourer Mason/Labourer Painter Painter Mason/Labourer
Time Line 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
This chart is for demonstration purposes only. Please ask your architect/contractor to make a similar chart for building your home according to your needs and fund availability.