Rabo Dam

258 km, 400 KV Transmission Line

Dam features on Kurket River

Highlights of the 258 km, 400 KV double circuit transmission line from Raigarh to the PGCIL sub-station at Raipur

Catchment area: 783 sq km Submergence area: 681 ha Top level of dam: RL 261.50 m Max height of spillway: 18 m Length of right dyke : 1133 m Length of main earth dam: 244.25 m Length of spillway: 144.75 m Length of left dyke: 210 m Total gates in spillway: 10 Size of spillway gates: 12 m x 8.5 m Size of pump house: 13.5 m x 19.5 m Reservoir capacity: 36 m.cu.m Number of pumps: 3 Pump capacity: 4000 (Cum/hr)

Total length: 258 km Total towers: 701 Forest: 5.920 hectare at village Rabo (Raigarh) 400 KV crossing: 5 (PGCIL) 220 KV crossing: 6 (4 CSEB+1 PGCIL) 132 KV crossing: 3 (CSEB) Railway crossing: 2 (SECR) River crossing: 4 (Mand, Asdeo, Sheonath)