Académique Documents
Professionnel Documents
Culture Documents
Submitted to the Mechatronics Engineering Department The Hashemite University In partial fulfillment Of the requirements for the degree of Bachelor in Mechatronics Engineering
EXECUTIVE SUMMARY
Through my training schedule on CABLECO company I've to visit all the departments and practice some of their jobs, in first day I was taken to a tour to company machines and departments and have learned some of safety procedures and dangerous situation and places, first I trained on Quality control department for one week where I look at their work and tried the testing machines which some used for raw materials and some for in process testing and I understood the testing procedure through various manufacturing processes, then I moved to maintenance department and work with them for four weeks where I learned the types of maintenance, and went to field with maintenance technician to perform the preventive maintenance daily and worked with technician when a break down occurs, in spite of that the mechanical and electrical maintenance sections are grouped together I've scheduled myself to work two weeks with electrical technicians and two weeks with mechanical technicians, finally I moved to work in production department for three weeks where I learned how production order is made and how production program is made depending on production order and how production engineers are responsible of observing the production procedure and solve problems occurs like machine break down and tell maintenance engineers about it and to deal with the operators mistakes in production and I have a look at all production machines such as rod break down, stranding , insulation and coiling & rewinding machines also I have learned many things about cables types and its applications.
TABLE OF CONTENTS
EXECUTIVE SUMMARY .............................................................................................................. i TABLE OF CONTENTS................................................................................................................. ii LIST OF FIGURES ........................................................................................................................ iii Chapter 1 Introduction ..................................................................................................................... 1 1.1 General nature of the training ............................................................................................... 1 1.2 Training schedule.................................................................................................................. 1 1.3 Background information ....................................................................................................... 1 1.3.1 Company profile : ......................................................................................................... 1 1.4 A brief outline of the report .................................................................................................. 2 Chapter 2 Company Profile ............................................................................................................. 3 2.1 Production Department ......................................................................................................... 3 2.1.1 Drawing Section ........................................................................................................... 4 2.1.2 Stranding Section.......................................................................................................... 5 2.1.3 Insulation Section ......................................................................................................... 9 2.1.4 Coiling and rewinding section: ................................................................................... 10 2.2 Quality Control Department ............................................................................................... 11 2.3 Maintenance Department .................................................................................................... 18 2.3.1 Types of Maintenance: ............................................................................................... 18 2.3.2 Main maintenance department: .................................................................................. 18 Chapter 3 Technical Discussion..................................................................................................... 20 3.1 Problems Encountered and Solutions ................................................................................. 20 3.1.1 Q.C Problems: ............................................................................................................ 20 3.1.2 Electrical Maintenance problems: .............................................................................. 20 3.1.3 Mechanical Maintenance problems: ........................................................................... 24 3.1.4 New installations: ....................................................................................................... 25 3.2 Other Information ............................................................................................................... 26 Chapter 4 Conclusions ................................................................................................................... 29 4.1 Benefits of Training ............................................................................................................ 29 REFERENCES .............................................................................................................................. 30
ii
LIST OF FIGURES
FIGURE1.1:CABLECOLOGO ................................................................................................................................. . 1 FIGURE2.1:CABLEPRODUCTIONSTAGES................................................................................................................ 3 FIGURE2.2:RODBREAKDOWNMACHINE.............................................................................................................. 4 FIGURE2.3:DOUBLETWISTSRANDINGMACHINE..................................................................................................... 6 FIGURE2.4:BOWSTRANDINGMACHINE................................................................................................................. 7 FIGURE2.5:CAGESTRANDINGMACHINEPARTS....................................................................................................... 8 FIGURE2.6:ARMORINGMACHINE......................................................................................................................... 9 FIGURE2.7:INSULATIONMACHINE...................................................................................................................... 0 1 FIGURE2.8:MICROMETER.................................................................................................................................. 1 1 FIGURE2.9:BENDINGTESTINSTRUMENT.............................................................................................................. 1 1 FIGURE2.10:TORSIONTESTINSTRUMENT............................................................................................................. 2 1 FIGURE2.11:TENSILETESTINSTRUMENTFORMETALS............................................................................................ 2 1 FIGURE2.12:OVENANDWATERPATH,FIGURE2.13:DIGITALTHERMOCOUPLE.............................................. 3 1 FIGURE2.14:TENSILETESTINSTRUMENTFORINSULATIONMATERIALS....................................................................... 3 1 FIGURE2.15:NANOOHMMETER ......................................................................................................................... 5 . 1 FIGURE2.16:MICROSCOPE................................................................................................................................ 5 1 FIGURE2.17:HIGHPOTTESTCONTROLUNIT........................................................................................................ 6 1 FIGURE2.18:INSULATIONRESISTANCEMEASURINGINSTRUMENT.............................................................................. 6 1 FIGURE2.19:INSULATIONRESISTANCETESTPROCEDURE ......................................................................................... 7 . 1 FIGURE2.20:DIAMETERTESTER.......................................................................................................................... 9 1 FIGURE2.21:SPARKTESTERCHAINS,FIGURE2.22:SPARKTESTER................................................... 9 1 FIGURE3.1:EMERSONOPTIONALMODULES,FIGURE3.2:EMERSONUNIDRIVESP........................................ 1 2 FIGURE3.3:SEIMENSMICROMASTER4VARIABLESPEEDDRIVE................................................................................ 1 2 FIGURE3.4:TROUBLESHOOTINGWITHSDPFORMICROMASTER4............................................................................. 2 2 FIGURE3.5:MICROMASTER4FROMINSIDE........................................................................................................... 2 2 FIGURE3.6:EXTRODUREHEADFIGURE3.7:THERMOCOUPLESENSOR................................................... 3 2 FIGURE3.8:ADAMTHERMOCOUPLEINPUTMODULE4018..................................................................................... 3 2 FIGURE3.9:SEIMENSU315FIELDPOWERSUPPLY............................................................................................... 4 2 FIGURE3.10:THREEPHASECIRCUITBREAKER........................................................................................................ 5 2
iii
Chapter 1 Introduction
1.1 General nature of the training
During my training, I worked in the three major departments in the factory, which are Q.C department, Production department and maintenance department. In Q.C department, I worked on testing instruments and check the product in every production stage. In maintenance department, I worked with technicians in the preventive maintenance and work with them to solve the problems when a break down occurs either it is mechanical or electrical problem. In the production department, I worked with operators on production machines to know how it work, also I worked with production engineers through the observation of production stages.
Manufacturing company (CABLECO) is a shareholding company was established in 1983 in Jordan, for production of electrical wires (Armoured & not armoured).the factory is
located at Zarqa city, and equipped with series of production lines designed to produce wires and cables of copper and aluminum conductors insulated/sheathed by (ordinary PVC or special kind of PVC) or (XLPE) or (P.E) or (Synthesis
Figure 1.1 : Cableco Logo
German standards (IEC, BS, VDE) to comply with Jordanian and International markets. The factory is also equipped with series of (Testing and Measuring) equipments calibrated according international standard/Traceability to monitor and control the quality of company production, starting from raw material, going through various production/manufacturing stages and up to delivery stages/finished products. The objective of the company is to produce high quality cables to satisfy the customer requirements therefore, it has achieved registration to ISO 9002/1994 in year 1996 and ISO 9001/2000 in year 2003. Figure 1.1 shows the company logo.
2. Bow Stranding machines : This machine perform stranding operation where it consists of several bows in series and the last bow contain the central wire. This machines used for larger diameter conductor than DT machines. Stranding operation occur on pay off on bow machine. General parts of bow stranding machines: Pay off, bows: several bows to make stranding operation, cradles, eyelets, die, rollers : to make shaped conductor, capstans, gears, traverse, take up. Figure 2.4 Shows one of Bow stranding machines
3. Cage Stranding machines : This machine makes stranding operation for large diameter conductor. It consists of many cages and every cage has many payoff's and all the cages spin to make the strand. General parts of cage stranding machines: Cages , die, capstans, gearbox, traverse, take up. Figure 2.5 shows one of cage machines parts.
4. Armoring Machines: This machine is used to make a stranded amouring about cables from steel or aluminum to provide a protection for it. Due to the cable diameter is very large all the take ,cater pillar , pay off is spinning to make stranding operation. General parts of armouring machines: Pay off, armouring eyelet , armoring die, steel tape machine : it is used to make a steel tape layer above armouring so that the sheathing layer will not stick with cable, cater pillar : it is used to make a tension to pull cable to the take up, traverse , take up. Figure 2.6 shows general parts of armouring machines
10
Bending Test: it is used to count how much bends material can sustain before fracture.
11
Torsion Test: it is used to how many torsions material can sustain before fracture.
Tensile Test: it is used to know how much material can elongate before fracture.
12
Aging Test: in this tests the material is put in special ovens and hot water path for several days and see how much it sustain before defected. Figure 2.12 shows ovens used and figure 2.13 shows the digital thermocouple used to sense the temperature of water on water path.
Tests for raw insulation materials (PVC, XLPE, PE, EPR (ethyl propel rubber), Low Smoke Zero Halogen): Tensile Test : it is used to test a specimen called dum-bell from made from some material and shows how much it can elongate before fracture, figure 2.14 shows instrument used.
13
In process testing : Wire drawing Wire drawing (O.H) tests: 1. resistance 2. breaking load 3. diameter_ovality 4. surface 5. wire material 6. other properties Wire drawing (annealed) tests: 1.resistance 2.diameter 3.elongation 4.wire material 5.other properties Stranding conductor Conductor stranding (O.H) tests: 1.resistance_no of wires 2.breaking load of each wire 3.diameter of each wire_ovality 4.diameter of conductor 5.lay length and stranding direction 6.conductor material Conductor stranding (annealed) tests: 1.resistance_No of wire*diameter 2.diameter of conductor 3.elongation of each wire 14
4.lay length and stranding direction 5.conductor material Laying up of cores 1.Non compressed core 2.diameter of each core 3.color sequence, cores No and dummy 4.conductor resistance 5.conductor material 6.lay length an direction 7.insulation material. cure Insulation & sheathing 1.avarege (insulation, sheathing) thickness 2.minimum(insulation,sheathing) thickness 3.over all diameter_ovality 4.conductor resistance 5.conductor material 6.adhesion 7.insulation,sheathing material,curing 8.printing 9.appearence 10.other properties
Resistance Test: this test is a very important one , and it tests the resistance of the conductor because this is what costumer strictly request , because resistance is what determine how much conductor can sustain current.
Diameter: we used a special microscope to test diameter for very thin wires beside to micrometer. Figure 2.16 shows microscope used,
15
Finished Products Tests : High Voltage or High Pot Test: in this test the finished product is applied to a high voltage and high current to test its insulation and sustainability. Figure 2.17 shows control unit used in this test.
Insulation Resistance test: we used a special instrument to tests the insulation resistance for finished products.
16
Notes : We concern about resistance because it effects current. We concern about insulation resistance because it effects voltage (if insulation can handle voltage and no drop occurs). High voltage test to find small defects. Insulation resistance test to find large defects.
Another mission for Q.C dept is to test in process tools such as SPARK TESTER, COUNTER, DIAMETER TEST, and if there is any wrong with it they request electrical maintenance engineers to fix and calibrate it.
17
installed it is the maintenance engineers and technician responsibilities to provide the machine with what necessary to make it work from configuration to electrical and mechanical connections and services. Service maintenance : it almost occurs every morning where mechanical and electrical technicians check factory services such as lights, emergency buzzers, water and air supplies , heaters and main water pumps
18
19
20
2-Emergency light was on at rewinding machine (RL6) The emergency light was on because one of four emergency circuits that are series has a problem on it, those circuits are pay off ready, take up ready, caterpillar ready, traverse ready. We solved this problem by checking every circuit, following it element by element on drawing and we found that one of the contactor on payoff unit was defected so we replaced it an problem solved 3-Traverse motor not working on rewinding machine (RL6) A-First we check the power supply and found no problem and none of the fuse is shorted. B-we then check control circuit and AC Drive unit (Seimens MicroMaster 4, see figure 3.3 ), and found that there is a problem on it because nothing is displayed on screen module (it is off),we start checking the inverter itself and its connection and we found nothing with connections, so we check the Status Display Panel on inverter to found what is problem and referring trouble shooting with SDP and on inverter manual (see figure 3.4 ) we found that the problem is on inverter itself, so we disconnected it from panel and opened it and found that two of three phase wires was cut as in figure 3.5 so we reconnected then return inverter to panel and connect it to motor and power and problem solved. 21
Figure 3.3: Seimens MicroMaster 4 Variable Speed Drive
22
4-Tempreture reading on insulation machine (Pan 90) was not stable The temperature reading for extruder head (see figure 3.6 ) that is displayed on HMI was not stable ,so first we check the thermocouple sensor (K type) (see figure 3.7 ) that is connected to ADAM Thermocouple Input Module 4018 (see figure 3.8 ) and found that it's wires was defected so we replace the thermocouple and problem was solved. Thermocouple sensor
5-Annealer motor on the Multi-wire drawing machine (MMH101) was not working. A-First we check Operator Panel and found errors F04 & F07. B-We check ladder Manuel that came with the machine and found that F04 means: Not Ready For Operation and found that F07 means : Field Monitoring error on 12G2
23
C-we follow the field circuit of the motor on control panel (using drawing) and found that the unit that control the field on motor (SEIMENS U315, see figure 3.9 ) was defected, so we replaced it and problem solved.
6-Take up DC motors on Insulation machine (TR100) was not working. A-First we check main power supply (because the problem was on all take up) and we found no problem. B-Then we check control circuits from drawing by following each line and checking components one by one like enable ready, relays, contactors, timers, etc. c- We found a problem that one of ready enables relays was not activated and that means the enable signal on DC DRIVE (SEIMENS SIMOREG 6RA70) is not enabled. d-we check control signal line on drive (24 V DC) from main PLC and we found that the cable is loose so we fasten it and problem solved.
C-we then checked motor internal bearing and found that it was defected so we replaced it and problem was solved.
Finally the machine needed some services to work such as air lines (for pneumatic cylinders) and that is the mechanical technicians responsibility to provide the machine with that. Now the machine is ready to operate (note that the internal electrical and mechanical connections and the driver and controller programming was ready from the manufacturing company). 25
Accuracy
26
B- Second we start checking using testing tools as DMM. First we check relays because it is easiest to discover defects, we check it by applying a control signal on its coil pin and checking if its contactors change position or not. Then we check IC ships (apply signal on input and check output, or apply open and short circuit test on a specific pins), note that most defects happens on those ships. Apply continuity, short , open circuit by following each signal line on card drawing and checking current, voltage levels if it is as desired or not.
To check bearing (rotary or linear) if it is defected and must be replaced, we rotate or move it and if there is a noise on it that means it is defected.
27
To check if the rotating body if it is balanced or not, we can check that by looking or by using a specific instrument on turning machine.
28
Chapter 4 Conclusions
In this chapter, I have talked about the benefits of my training and how it was valuable.
29
REFERENCES
[1] Eng.Nabeel Al-Betawi "Head of Production Department" [2] Eng.Majed Mahmoud "Head of Maintenance Department" [3] Eng.Hamza Ali " Head of Q.C Department" [4] Web sites:
30