Half brickwork in common bricks in cement and mortar (1:3) in Stretcher Bond with fabric reinforcement at every fourth course, non load bearing wall and circular on plan to 4m mean redius 150m
2

Estimating Data Brick Material cost for common clay brick = RM 450 for 1000 pieces. 1m of half brick wall requires 60 pieces of bricks. 1m / (0.225mm x0.075mm) =59.25 Allow 5% of wastage on brick. Cement Mortar Material cost for ordinary portland cement including. Unloading is RM 17.00/50kg bag. Material cost for sand including unloading is RM 38.00 / tonne. 1m3 of ordinary portland cement = 1420kg 1m3 of sand = 1600kg Allow 33.33% waste and shrinkage for cement mortar. Mortar required for 1m2 of half brickwall is 0.02m3 60[(0.225 x 0.115 x0.01)+(0.115 x 0.075 x 0.01)]=0.02m3 Others Allow RM 2.50/m2 of brick for Exmet including supply, wastage and lay. Allow RM 0.08m2 for DPC including supply, lapped and lay. Labour Data 1 gang of bricklayer consist of 1 bricklayer and 2 labourers. Bricklayer rate is RM 85/day for 8 hours day RM 68.33*125%= RM 85.41 Labourer rate is RM 60/ day for 8 hours day RM 47.50 *125%= RM 59.38 Output for 1 gang of bricklayer is at 120 bricks/hour including mix of mortar, laying brick, exmet, and DPC. Allow 10% of the total cost for profit Allow 5% for overhead No scaffolding required.

Item A 1 Materials

Descriptipn

Calculation

Amount

Bricks Common day bricks RM 400/1000 pieces 60 no of bricks required for half brickwall Add wastage 5% Total

RM 450.00/1000 RM 0.45 x 60 piece RM 27.00/m2 * 5%

RM 0.45/Piece RM 27.00/m2 RM 1.35/m2 RM 28.35/m


2

Cement Mortar (1:3)/ m2 Ordinary Portland Cement including unloading 1m at 1420kg/m at RM 12/50kg bag
3 3

(1450kg/m x RM 12.00)/50

RM348/m

Sand including unloading 3m3 at 1600kg/m3 at RM 38/tonne (1600m3/1000) xRM 38.00 x 3m3 RM 530.40/4m3 x 33.33% RM 707.18 /4m3 (RM 176.78/m3) x 0.02m3 RM 182.40/3m3 RM 176.78/4m3

Add shrinkage & wastage 33.33%

Cost/m33 0.02m3 of mortar required per m2 of half brickwall

RM 176.78/m3 RM 3.54/m2

Other cost Allow exmet at RM 2.50 or RM 25? Allow RM 0.80/m


2

RM2.5 RM 0.80 RM 28.35 + RM 3.54 + RM 2.5 +RM 0.80 RM 35.19

Total Material costs

Labour Hourly rate for a gang 1 Bricklayer of RM 85/day 2 Labourer at RM 55/day

RM 85/8hr (RM 60/8hr) x2

RM 10.60 Rm 15.00 RM 25.63

Time Analysis 60 pieces 1m2 of half brickwall consist of 60 pieces of bricks 1 gang can lay 120 bricks/ hour Time required Labour cost

60 pcs/(120pcs/hr) RM 25.63 x 0.5hr

0.5 hr RM 12.81

Item C

Descriptipn Total cost including profit and overhead Labour cost + material cost Add overhead 5% Add profit 10% Total cost

Calculation

Amount

RM 35.19+ RM 12.81 RM 48.00 x 5% RM 50.40 x 10%

RM 48.00/m

RM 2.40/m2 RM 5.04 /m2 RM 55.44/m2

CALCULATION FOR REFERRENCE ONLY! 0.016875 59.2592593 27.00 1.35 28.35

348

182.40 530.4 176.78232 707.18 176.79558 3.5359116

35.19

10.625 15 25.625

85.4125 59.375

0.5 12.8125

48.00 2.39992058 5.03983322 55.44