TENDER: 7
PRICE BID
Name of work Name of Contractor Tender Fee Class of Registration Issue of tender Receipt of tender
: : : : : :
Construction of New Compound Wall with Concertina Coil Fencing around SVP Bhavan in SVNIT, Surat.
`.500=00
The Director, S. V. National Institute of Technology, Ichchhanath, Surat 395 007. 91-0261-2259571, 2259582-84
Name of Work :-
Construction of New Compound Wall with Concertina Coil Fencing around SVP Bhavan in SVNIT, Surat.
SCHEDULE B (PWD SOR 2011-12)
Sr. No 1
Quantity 20.00
Item Descriptions Demolition including stacking of serviceable materials and disposal of unserviceble materials with all lead and lift. (!) R.C.C work SOR - 20.3 , P-72 Demolition of brick work and stone masonary including stacking of serviceable materials and disposal of unserviceable mateirals with all lead and lift (ii) in cement mortar SOR -20.11(iiI), P-72 Excavation for foundation up to 1.5 M. Depth including sorting out and stacking of useful materials and disposing of the excavated stuff up to 50 meter lead (A) Loose or soft soil SOR -1. 4.0.0,(A) P -19 Excavation for foundation for depth from 1.5m to 3.0m including sorting out and stacking of useful materials and disposing of the excavated stuff up to 50 meter lead (B) Dense or Hard soil SOR - 2. 4.0.0,(B) P -19 Boring holes 3.5m deep in lordinary soil (for cast in situ piles) and getting out the soil and disposal of the surplus excaated soil as directed within a lead of 50 metre follwoing diameter of pilses. (iii) 300 mm SOR-4.27(iii),P-20 Providing and laying cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20mm nominal size) and curing complete excluding cost of form work and reinforcement for reinforced cement concrete work including adding plasticizer @ 100 ml per cement bag, Fosroc or equivelent (as per IS 9103) in cement concrete etc. completed as per the direction by Engineer-In-Charge. (B) Independent piers, columns and pillars up to floor two level (As per R.A on SOR Base ) Providing and laying cement cocnrete 1:3:6 (1 Cement : 3 coarse sand : 8 hand broken stone aggregates 40 mm nominal size) and
Rate `. Ps 331.00
Per Cmt
Amount Ps `. 6620.00
40.00
173.00
Cmt
6920.00
125.00
61.10
Cmt
7637.50
45.00
83.90
Cmt
3775.50
22.00
443.00
Each
9746.00
6.00
4108.00
Cmt
24648.00
5.00
2804.00
Cmt
14020.00
Sr. No
Quantity
Item Descriptions curing complete excluding cost of form work in (A) Foundation and plinth SOR-5.3.2,P-21
Rate `. Ps
Per
Amount Ps `.
13.00
Providing and laying cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20mm nominal size) and curing complete including the cost of necessary formwork, compacting with vibrator, curing,centering & shuttering in true line and level etc. but excluding cost of reinforcement for reinforced cement concrete work including adding plasticizer @ 100 ml per cement bag, Fosroc or equivelent (as per IS 9103) in cement concrete etc. completed as per the direction by Engineer-In-Charge.(A) Foundations, footings, base of columns and mass concrete (As per R.A on SOR Base ) Providing & laying ordinary CEMENT CONCRETE 1 : 1.5 : 3 (1 Cement : 1.5 Coarse sand : 3 stone aggregate 20mm nominal size kapchi) including the cost of necessary formwork, compacting with vibrator, curing & shuttering in true line and level etc. but excluding cost of reinforcement in RCC work for GROUND BEAMS and PLINTH BEAMS including adding plasticizer @ 100 ml per cement bag Fosroc or equivelent (as per IS 9103) in cement concrete etc. completed as per the direction by Engineer-In-Charge. (As per R.A on SOR Base ) Providing and laying ordinary cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregates 20mm nominal size) and finishing smooth with curing etc. complete including the cost of formwork but excluding the cost of reinforcement for R.C.C. work for COLUMN including adding plasticizer @ 100 ml per cement bag Fosroc or equivelent (as per IS 9103) in cement concrete etc. completed as per the direction by Engineer-In-Charge. above Plinth level upto floor two level (i.e. Ground floor) for cross sectional area 0.05 to 0.085 sqm (As per R.A on SOR Base ) Providing and laying ordinary cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregates 20mm nominal size) for R.C.C. COPING including
4324.00
Cmt
56212.00
22.00
5379.00
Cmt
118338.00
10
22.00
7607.00
Cmt
167354.00
11
15.00
5776.00
Cmt
86640.00
Sr. No
Quantity
Item Descriptions finishing smooth with curing etc. complete including the cost of formwork but excluding the cost of reinforcement and including adding plasticizer @ 100ml per cement bag Fosroc or Equi. (as per IS 9103) in cement concrete etc., completed directed by Engineer In Charge. (As per R.A on SOR Base )
Rate `. Ps
Per
Amount Ps `.
12
8000.00
TMT Bar Fe-415 steel reinforcement for R.C.C work including ,bending, binding, and placing in position complete upto floor two level. SOR - 14(A) 5.4.11, P - 23 Filling available excavated earth (excluding rock) in trenches plinth, sides of foundations etc, in layers not exceeding 20 cm in depth consolidating each depo sited layer by ramming and watering. ( SOR-I 4.12 P-20 ) Brick work using common burnt clay buliding brick having crushing strength not less than 35 Kg/sq.cm. in cement mortar 1:6 ( 1 Cement : 6 fine sand )in super structure above plinth level up to floor two level (B) conventional SOR - 6.13(B)P-30 +6.19(B) P-30 20mm thick sand face cement plaster on wall up to height 10 metres above ground level consisting of 12mm thick backing coat of c.m.1:3 (1 cement : 3 sand) and 8mm thick finishing coat of c.m.1:1 (1 cement : 1 sand) etc. complete SOR-17.95, P-63 Steel work weided,in built up section,framed work including cutting hositing,fixing in position and applying a priming coat of red lead paint. (A) In beams and joists,channels,angles tees flats with connection plates or angles cleats as in main and cross beams,hip and trussed purlins coneected to common rafters and the like. SOR-11.4,P-47(A) painting two coat (excluding priming coat ) on new steel and other metal surface with synthetic enemal paint brushing to give an even shade including cleaning the surface of all dirt,dust and other foreign matters SOR - 19.19, P - 68 Providing and fixing six rows of G.I barbed
48.20
Kg.
385600.00
13
148.00
39.00
Cmt
5772.00
14
135.00
2729.00
Cmt
368415.00
15
1000.00
199.00
Smt
199000.00
16
1000.00
60.39
Kg.
60390.00
17
30.00
49.60
Smt
1488.00
18
280.00
54.00
Rmt
15120.00
Sr. No
Quantity
Item Descriptions wire weighing not less than 9.38 kg per 100running meter over "y" shaped angle iron posts over compound wall fixed with fixing staplews/clips/binding wire as per requirement etc complet as per direction of engineer-in-charge. (As per R.A )
Rate `. Ps
Per
Amount Ps `.
19
280.00
Providing and fixing hot dip concertina coil of 610mm dia made out of 2.59 mm (12SWG) hot dip galvanised (G.I coating not less than 200 grams per sqm ) thick wire having 80 nos of spikes and 200 nosof clips made out of stainless steel (AISI 304) 1.5mm thick dia,G.Istrips 0.5 mm thickness (G.I coating not less than 120 gms per sqm) weight of one coil should not be less than 15kg. etc complete at the top of the compound wall fixed with S.S clips and binding wires wherever necessary etc complete. (NOTE: streching lenth of one coil should not be more than 9 meter) (As per R.A.) Cleaning the surfaces from loose dirt, algae, mortar droppings, dust particles, oil, grease etc. by wire brushing, then washing and rinsing the surface with clean water, providing and applying and filling major visible cracks, joints etc. with pure acrylic crack sealing compound, having tensile strength and volume shrinkage as per IS 1962 : 1979, ahesion to concrete or walls as per ASTM D 4541 and elongation as per ASTM D 412, hardness as per ASSTM D 22420, apperance, color and skin forming as per IS 101:1987, using "Chemistik Crackseal Caulking Compound" or its equivalent quality as approved by the Engineer in Charge, allowing it to dry for 24 hours, providing & applying one coat of primer over the prepared surface of "Chemistik Prime N Seal"(Ready to Use) or its equivalent quality as approved by the Engineer in Charge, providing and applying on the prepared surface first coat of Elastomeric Coating of "Chemistik Pro Decor Super ( heavy duty elastomeric coating) or its equivalent quality as approved by the Engineer in Charge having elongation as per ADTM D 412, antifungal quality as per BS 3900 / G 6, dry film thickness of65 microns per coat and finish, consistancy &
231.00
Rmt
64680.00
20
1000.00
115.57
Smt
115570.00
Sr. No
Quantity
Item Descriptions color as per IS 101:1987, durability as per IS 5411 (Part II) Appendix -F, impermeability to water as per ASTM C 642, 1977, allowing it to dry for 8 to 10 hours as per IS 5411 (Part II) Appendix - A, then applying the second coat as above of approved shade and color, allowing it to dry as per company's instruction, the work being carried out by Company's certified and experienced applicator only, giving a written guarantee for 05 years against any defect in workmanship and performance etc. complete. The rate shall be applicable on all floors at any height.and all type of surface. The payment may be made on flat sq.mt. basis irrespective of sand faced or smooth plaster. (As per R A)
Rate `. Ps
Per
Amount Ps `.
21
25.00
Providing and Fixing 25mm thick Thermocoal Sheet between all expansion joints column and beams including all labour charges etc. complete. As per Market Rate Supplying and Applying SBR on cold joints of concrete withpacking size in 20ltr drum of brand FOSROCK, ROFF,PERMA or equivelant As per Market Rate
50.00
Smt
1250.00
22
20.00
220.00
Ltr
4400.00
Total Say
` `
17,23,596.00 17,23,596.00
I/ We am/ are willing to carry out the work at _____________ % above/below percent (should be written in figures and words) of the estimated rates mentioned above. Amount of my/ our tender works out as under. Estimated amount Put to tender
`. ___________
Note 1. All work shall be carried out as per Public Works Department Handbook and other specifications of PWD/CPWD/SVNIT or as directed. 2. All the columns is Scheduled be filled in ink and the total of the entries in the last column should be struck by the contractor under his signature. 3. Rates quoted include clearance of site (prior commencement of work and at its close) in all respects and hold good for work under all conditions, site, moisture, weather etc. 4. To be continued on additional sheets, if found necessary.