Vous êtes sur la page 1sur 27

CASH

FLOW
MANAGEMENT
CONSTRUCTION PROJECTS

IN

Contents
Abstract........................................................................................................................................................ 5
Introduction ................................................................................................................................................. 6
Type of Contracts........................................................................................................................................ 6
Analyzing of the cash flow .......................................................................................................................... 7
Determination of the required funding. .................................................................................................... 9
Reducing of the required funding............................................................................................................ 10
Risk Factor ................................................................................................................................................ 15
Effect of risk on the cash flow .................................................................................................................. 16
Expected Monetary Value (EMV) ........................................................................................................... 17

List of references
Bibliography
Acknowledgment
Appendix I

Page 2

List of Figures
Figure 1a: Cash flow in & Out For Reimbursable & (T&M) Contract .......................................... 8
Figure 1b: Cash flow in & Out For Lump sum Contract ................................................................ 8
Figure 2: Workshop Factory ..........................................................Error! Bookmark not defined.
Figure 3: Cash Flow In&Out for Scenario "A" .............................Error! Bookmark not defined.
Figure 4: Cash Flow In&Out for Scenario "C" ............................................................................. 12
Figure 5: Cash Flow In&Out for Scenario "B" ............................................................................. 12

Page 3

List of Tables
Table 1: Payment Schedule for Workshop Factory....................................................................................... 9
Table 2: Cash In & Out for Scenario "A" ................................................................................................... 11
Table 3: Cash In & Out for Scenario "B" ................................................................................................... 11
Table 4:Cash In & Out for Scenario "C" .................................................................................................... 11

Page 4

Abstract
The cash flow is a major factor should be considered during the process of developing the project
execution management plan. The importance of cash flow management is in determining the
required amount of money to be funded by the contractor and also the time when this money will
be required. The payment method by which the contractor will receive his money from the client
is a key item in the analysis of cash flow and it should be determined in the contract. Actually it
depends on the type of contract if it is lump sum or reimbursed contract. Another key item
should be considered in the cash flow analysis is the risk, whether it is an opportunity or a threat,
especially the one which is related to the procurement procedures, in order to determine the time
for purchasing the required material, mainly for the long lead items. The purpose of this study is
describing a simple way to develop more than one scenario for the execution plan and how to
compare between these scenarios to decide the best scenario which will obtain the maximum
benefit for the contractor with a minimum required funding.

Page 5

Introduction
The ability of developing alternate scenarios for the project execution plan requires a very
experienced team to study the type of contracts, payment method, procurement procedures and
risk with any other factors to analyze the cash liquidity and the required funding for each
scenario then decide the best scenario to execute the project.
Types of Contracts
Type of contracts is an important item in the management procedures of the construction
projects. This importance comes from determination of the payment method which the contractor
will be reimbursed for his completed works and how the final contract amount will be calculated.
There are three main types of contracts can be used:
1. Fixed Price Contract (Lump Sum )
In this type of contract the total value of work is known before signing the contract and the
contractor will be entitled for invoices according to agreed payment schedule created against the
completion of a certain work stage.
The contractor abides to complete the whole required works within the contract against the
agreed amount so he will take the full responsibility of risk except for the force majeure.
There are three different ways can be used to formulate this type of contract.3
1.1. Firm Fixed Price contract.
1.2. Fixed price with incentive fee.
1.3. Fixed price with economic adjusted price.
2. Reimbursable Contract.
In this type of contract the total amount of contract will be known after completing the works
and measuring the actual quantities and determining the actual cost. The contractor will be
reimbursed periodically or after a certain percentage of completion.
In this type of the owner take the responsibility of the risk.

Page 6

There are three different ways can be used to formulate this type of contract.3
2.1. Cost plus Fixed Fee contract.
2.2. Cost plus Incentive Fee.
2.3. Cost plus Award Fee.
3. Time and Material Contract (T&M) or Remeasured Contract.
This contract is a mix between the lump sum contract and reimbursable contract where the actual
rate for the works is known but the actual quantity is unknown. So the contractor will be entitled
for payments by measuring the actual completed quantity and calculate the cost according the
agreed rate for each item.
In this type of contract the risk responsibility will be shered between the owner and contractor
Analyzing of the cash flow
The cash flow in reimbursable and (T&M) contract the cash-in will be almost parallel to the
cash-out with a difference equal to the profit. But in the lump sum contract there is a difference
in the nature between the cash in and cash out curves. This difference need to be analyzed by the
contractor in order to manage the liquidity of the money and to determine the required funding
for the project at the start and during the project life time. See fig 1a & 1b.
The difference between the cash in and cash out curves in the hatched areas at fig1b shows the
amount of the funding required to be covered by the contractor and when it will be required.
It is the contractors challenge to reduce the amount of hatched area without causing any delay
for the project.

Page 7

100.00%
90.00%

At the end of each month the contractor will


be reimbursed according to this curve after
checking the actual % of the Completion.

80.00%
70.00%
60.00%
50.00%

Acumilative Cash out

40.00%

Acumilative Cash In

30.00%
20.00%
10.00%
0.00%
0

10

11

12

Months

Figure 1 a: Cash Flow for Reimbursable Contract & (T&M)

120.00%
100.00%

The Contractor will finish the project


according to this S-Curve

80.00%

The Contractor will


receive his payment
according to this
schedule

60.00%
40.00%
20.00%

Acumilative Cash In
Acumilative Cash out

0.00%
0

Months

Figure 1b: Cash flow in & Out For Lump sum Contract

Page 8

10

11

12

Determination of the required funding.


Table 1 shows a payment schedule for a lump sum contract to construct a new factory Consists
of three buildings B1-the main workshop, B2- Guard Room and B3- Generator room with
landscaping (Hard & Soft) for the surrounding area including services with a chain link boundary
as shown in fig 2.
B1
B3

B2

Figure 2: Workshop Factory

No.

Description

Advance Payment upon contract signing against bank guarantee.

10%

After concrete works completion

10%

After Steel Work Completion

10%

After Block works, Thermal & Moisture protection completion.

10%

After Doors & Windows installation

10%

After plaster & Finishing Works.

10%

After MEP Works

10%

After Landscaping Works

10%

After getting government authorities approval

10%

10

Final Handing Over

10%

Total

100%

Table 1: Payment Schedule for Workshop Factory

The total duration for the contract is 12 months from the start date. The total contract amount is
7,500,736.5$.

Page 9

In order to determine the required funding for this project the contractor has to go through the
following procedures:
1. Define precisely the required scope of works according to drawings, specifications, contract
and all related documents.
2. The result from the previous procedure is the WBS Work Break Down Structure
3. By analyzing the WBS the contractor will have the list of activities and can start the
estimation of cost and time required to finish each activity.
4. Assume the relationship between activities. Then develop the project time schedule and
budget (S-Curve) accordingly.
5. Draw the s-Curve and the payment schedule on the same curve in order to determine the
required funding for the project.
6. The result should be something like the chart in fig1b.
Reducing of the required funding.
To reduce the required funding the contractor will need to develop more than one scenario then
compare between the cash flow in & out for each of them. There are many methods to develop
these alternative scenarios some of them are
-

Resource leveling by moving the non critical activity within the float in order to reduce
the overtime expenses.

Adjust the schedule for the subcontractor and supplier payments.

Study the schedule of procurement taking into consideration all risk which will be
associated with it (some item may not be available later or the risk related to the long
lead item).

Negotiate the payment schedule with the owner.

The following tables No2, 3&4 shows the cash in and out for three different scenarios which
have been developed for the above mentioned project.

Page 10

Duration

10

11

12

Cash out

0%

10%

3%

1%

18%

3%

4%

9%

14%

11%

12%

10%

5%

Cash in

10%

0%

0%

10%

0%

0%

10%

10%

10%

0%

0%

20%

30%

Difference

10%

-10%

-3%

9%

-18%

-3%

6%

1%

-4%

-11%

-12%

10%

25%

(Months)

Table 2: Cash In & Out for Scenario "A"

Duration

10

11

12

Cash out

0%

12%

2%

4%

18%

2%

4%

11%

12%

10%

12%

9%

4%

Cash in

10%

0%

0%

10%

0%

0%

10%

10%

10%

0%

0%

30%

20%

Difference

10%

-12%

-2%

6%

-18%

-2%

6%

-1%

-2%

-10%

-12%

21%

16%

(Months)

Table 3: Cash In & Out for Scenario "B"

Duration

10

11

12

Cash out

0%

5%

2%

2%

16%

3%

5%

10%

17%

11%

13%

9%

5%

Cash in

10%

0%

0%

10%

0%

0%

10%

10%

10%

0%

0%

30%

20%

Difference

10%

-5%

-2%

8%

-16%

-3%

5%

0%

-7%

-11%

-13%

21%

15%

(Months)

Table 4:Cash In & Out for Scenario "C"

The following Curves show the difference between cash in & out for each scenario.

SCENARIO "A"

8,000,000.00

Acumilative Cash In

7,000,000.00

Acumilative Cash out

6,000,000.00
5,000,000.00
4,000,000.00
3,000,000.00
2,000,000.00
1,000,000.00
0

Figure 3: Cash Flow In-Out for Scenario "A"


Page 11

10

11

12

8,000,000.00

SCENARIO "B"

7,000,000.00
6,000,000.00
5,000,000.00
4,000,000.00
3,000,000.00
2,000,000.00
1,000,000.00
0

10

11

12

Figure 4: Cash Flow In-Out for Scenario "B"

8,000,000.00

SCENARIO "C"

7,000,000.00
6,000,000.00
5,000,000.00
4,000,000.00
3,000,000.00
2,000,000.00
1,000,000.00
0

10

11

12

Figure 5: Cash Flow In-Out for Scenario "C"

Appendix (I) shows the detailed calculation for each scenario.


Another point should be considered in the analysis process for these scenarios which is the time
money relationships.

Page 12

In order to do this the evaluation should be done after equalizing the three scenarios using one of
the following methods.
-

Net Present Value (NPV):

The first step is to calculate the difference between each scenario and the payment schedule as
shown in the previous tables then calculate the net present value for each scenario in this project
assume the interest rate is 10% annually according to the following equation:
NPV = =0 F(P/F, i, n)

NPV :

Net Present Value

Future Value

Interest rate

No of months

(P/F,i,n) : To convert the future value to the present value, notice that it should be divided by 12
to be monthly.
NPV ScenarionA = -70,597.92 $
NPV ScenarionB = -85,490.21 $
NPV ScenarionC = -48,391.45 $
Very important here that the negative value of the NPV for the three scenarios does not mean
that the contractor will not gain any profit but because we are using the same bill of quantity
prices as it is in the cash in and cash out and these prices including the overhead and profit so the
negative value means that due to the time money relationship the profit of the project will be
decreased by these negative amounts in case of transfer it to the net present value.
From the above we can see that scenario C has the minimum deduction so it will give the
contractor the maximum benefit. Refer to Appendix (I) for the detailed calculation.
-

Net Future Value (NFV):

Page 13

The same calculation can be made by transferring the present value to the future value using the
following equation with the same interest rate which is 10% annually:
NFV = =0 P(F/P, i, n)

NFV

Net Future Value

Present Value

Interest rate

No of months

(F/P,i,n)

: To convert the present value to the future value , notice that it should be

divided by 12 to be monthly.
NFV ScenarionA = -77,990.44 $
NFV ScenarionB = -94,442.15 $
NFV ScenarionC = -53,458.67 $
Same point that the negative value does not mean that the project has no profit.
From the above we can see that scenario C has the minimum deduction also so it will give the
contractor the maximum benefit. Refer to Appendix (I) for the detailed calculation.
-

Time To Money Factor (M):

Once these scenarios are for the same project and correspondingly the same interest rate the
calculation can be simplified by just calculate the M factor for each scenario where

M = Diff n
M

=0

Scenario factor

Diff

= (Cash in Cash out) for each month

Number of months

But the value of M factor should be used for comparing purpose only because it does not have
physical meaning like NPV or NFV.

Page 14

Notice that the time and money relationship is a reverse order relationship that is mean the value
of amount of money today is more than the Value of the same amount of money after a month or
year or any period so the bigger M factor will be for the last cash that is mean we should select
the minimum value of M factor.
M scenario

.1*0

.1*1-.03*2+.09*3-.18*4-.03*5+.06*6+.01*7-.04*8-.11*9-

.12*10+.1*11+.25*12 = 123%
M scenario A =123*7,500,736.5/100 = 9,224,918.20
M scenario

.1*0-.12*1-.02*2+.06*3-.18*4-.02*5+.06*6-.01*7-.02*8-.1*9-

.12*10+.21*11+.16*12 = 148%
M scenario B =148 *7,500,736.5/100 = 11,079,827.15
M scenario

.1*0-.05*1-.02*2+.08*3-.16*4-.03*5+.05*6+0*7-.07*8-.11*9-

.13*10+.21*11+.15*12 = 85%
M scenario C =85*7,500,736.5/100 = 6,411,656.95
From the above calculation we can see that scenario C has the Minimum value for M factor so it
will give the contractor the maximum profit.
Risk Factor
Risk is another big challenge should be considered during development of the execution plans.
The risk is not always a threat (Negative) but some time it may be opportunity (Positive) and the
role of contractor is to study all possible risk and develop a plan to increase the probability and
impact of the positive risk and mitigates the probability and impact of the negative risk.
The risk can be divided into two main categories:
-

External Risk which is coming from factors out of the contractors control like
(Hurricanes, price changes due to market condition...Etc).

Internal risk which is coming from factors under the contractors control (personal errors,
cost overrun due to changesetc).

Page 15

In order to develop a risk management plan the contractor has to go through the following steps:

Identification of risk

The objective from this procedure is to gather the information about all the expected risks
and this could be done by project team experience, the recorded lessons learned from the
previous projects, brainstorming sessions, the market conditions and many other methods.
The result will be a risk list contains the description of each risk and the affected activities by
each one.
-

Risk Assessment

Here the contractor should analyze each risk separately. Analyzing should be quantitative and
qualitative.
Quantitative analysis is to study the impact of the risk on the project and qualitative is to study
the probability of the risk to be occurred.
-

Risk Management plan.

Establish the procedure to mitigate the effect of negative risks and increase the effect of positive
risk and determine the authorized person to perform these procedures and follow up the risk
situation.
Effect of risk on the cash flow
The previous analysis for the three different scenarios in the workshop factory project did not
consider the effect of expected risks in order to do this we have to determine the effect of each
risk on the project budget then apply the time money relationship to see the effect of this risk on
the net cash flow.

Page 16

In scenario A the cost of steel works was distributed as 25% at the first months then 50% at the
fourth month finally 25% at the eighth month.
In scenario C the cost of steel works was distributed as 10% at the first months then 50% at the
fourth month finally 40% at the eighth month.
But during negotiation with the steel subcontractor the deal was for scenario A the cost will not
be increased but if we will go for scenario C the cost should be increased by 5% that is beacuse
scenario A will allow the subcontractor to buy the most of material in advance but in scenario C
the subcontractor has to divide the purchasing into two orders one in advance and one after three
months and the cost of the material may be increased according to the market condition.
The final deal with the subcontractor is the main contractor can go for the scenario C but the
increasing of cost will not be considered unless the cost of raw material is already occurred.
After studying the probability of increasing the raw material cost according to the market
condition the result is 35%.
So the contractor now has to study the effect of this risk by the following procedure.
Expected Monetary Value (EMV)
EMV is a technique calculates the average outcome for a certain future event that may or may
not occurs.
EMV = Probability percentage % * cost effect of the risk.
In the mentioned scenario the probability of risk to be occurred is 35%.
The effect of risk will be adding 5% on the total cost of the steel works which is =
.05*1,650,460=82,523$.....Refer to (Appendix I)
Expected Monetary Value (EMV) = Probability % * cost effect.
EMV = 0.35* 82,523 = 28,883.05$
This additional cost should be distributed on two payments at 4th months and 8th months equally.

Page 17

So in case of considering this risk there are another two values should be considered during
calculation of NPV & NFV , because it additional cost on the contractor these value will be a
negative values (Cash out).
For the payment at 4th month = (-28,883.05*.5) * .9673 =- 13,969.3$
For the payment at 8th month = (-28,883.05*.5) * .9357 =- 13,152.9$
The total value = - 27,122.2$
The Modified NPV ScenarionC = -48,391.45 27,122.2 = - 75,513.65 QR
From the previous calculation the NPV ScenarionA = -70,597.92 QR
So in this case it is better to execute according to scenario A.
The same if we calculating it for the NFV
For the payment at 4th month = (-28,883.05*.5) * 1.0686 =- 15,432.2QR
For the payment at 8th month = (-28,883.05*.5) *1.0337 =- 14928.2QR
The total value = - 30,360.4QR
The Modified NFV ScenarionC = -53,458.67 - 30,360.4 = -83,819.07 QR
From the previous calculation the NFV ScenarionA = -77,990.44 QR
So in this case it is better to execute according to scenario A.
As we check it using the M factor also the effect of this risk will be
M for payment after 4 months = -28,883.05*.5*4 = -57,766.1
M for payment after 8 months = -28,883.05*.5*8 = -115,532.2
The Modified M factor for Scenario C = 11,079,827.15 57,766.1-115,532.2 = 10,958,518.85
So the modified M factor for Scenario C is bigger than M factor for Scenario A which is =
9,224,918.20
The result is the same as NPV and NFV that scenario A will give the contractor the best benefit.
From the above calculation, it is clear that the risk is a very important factor and has significant
effect on the project cash flow. This effect makes the study and analysis of expected risk is a

Page 18

vital and essential process and it should be done by an expert team in order to assure the success
of completing project on time with the required quality and maximum profit.

Page 19

List of References
1. AACE International. Economic Analysis. Skills and Knowledge of Cost Engineering
5th edition. 2004.
2. Sullivan, William. Bontadelli, James. Wicks, Elin. Chapter 5 Comparing Alternatives.
Engineering Economy 11th edition.2000.
3. Project Management Institute (PMI) USA. PMBOK-Guide 4th edition. 2008.

Page 20

Bibliography
EMV: Expected monetary value
I: Interest Rate
N: Number of time periods
NFV: Net Future Value
NPV: Net Present Value.

Page 21

Acknowledgment
This paper would not have been possible without the great support from my superiors. In this
regard I am grateful to the following for their review and helpful suggestion:
- Eng M. Hendy, Head of Technical Department at James cubit & Partner Consultancy (Qatar).
- Eng M. Al-Gendy, Projects Manager at James cubit & Partner Consultancy (Qatar).
- Eng Elham Amer, Project Manager at Al-Goman Contracting (Qatar).

Last but not least, I am thankful to my wife for her understanding and continuing support which
saw me through the extended hours

Page 22

APPENDIX I

Page 23

WORKSHOPFACTORY
Cost Estimate for The Wrokshop Factory

BILL NO. - DESCRIPTION

Amount (Qatari
Riyal)

% Of Total

BILL NO.01 - PRELIMINARY

618,051

Amount
8%

BILL NO.02 - EARTH WORK

52,480

1%

BILL NO.03 - CONCRETE WORK

405,735

5%

BILL NO.04 - STEEL STRUCTURE

1,650,460

22%

307,575

4%

62,400

1%

BILL NO.05 - BLOCK WORK


BILL NO.06 - W.PROOFING & THERMAL
PROTECTION
BILL NO.07 - DOORS & WINDOWS

378,798

5%

BILL NO.08 - PLASTER & FINSHING

724,349.5

10%

BILL NO.09 - PAINTING

119,015

2%

10 BILL NO.10 - LANDSCAPING

1,170,100

16%

11 BILL NO.11 - EQUPMENT

48,565

1%

12 BILL NO.12 - MECHANICAL (HVAC)

126,450

2%

13 BILL NO.13 - PLUMPING & DRAINAGE

687,162

9%

1,149,596

15%

7,500,736.5

100%

14 BILL NO.14 - ELECTRICAL


TOTAL

1/1

WorkshopFactory

Senarion "A"
Month

10

11

12

BILL NO.01 - PRELIMINARY

51504

51504

51504

51504

51504

51504

51504

51504

51504

51504

51504

51504

BILL NO.02 - EARTH WORK

52480

BILL NO.03 - CONCRETE WORK

202868

BILL NO.04 - STEEL STRUCTURE

412615

Total
618,051
52,480

202868

405,735
825230

412615

BILL NO.05 - BLOCK WORK


BILL NO.06 - W.PROOFING &

102525

102525

1,650,460

102525

307,575
62400

BILL NO.07 - DOORS & WINDOWS

189399

BILL NO.08 - PLASTER & FINSHING

144870

144870

144870

BILL NO.09 - PAINTING

62,400
113639

75760

378,798

144870

144870

724,350

119015

BILL NO.10 - LANDSCAPING


BILL NO.11 - EQUPMENT

292525

292525
31613

119,015
292525

292525

48565

48,565

BILL NO.12 - MECHANICAL (HVAC)


BILL NO.13 - PLUMPING &

137432

BILL NO.14 - ELECTRICAL

459838

Total Cash out / month


Acumilative Cash out

0
0

719467
719467

254372
973839

51504
1025343

1336573
2361915

Month

Entiteled Payemtn / Month

10%

1,170,100

202594
2564510

291462
2855971

31613

31613

31613

126,450

137432

137432

137432

68716

68716

687,162

229919

114960

114960

114960

114960

1,149,596

697863
3553835

1082393
4636227

835304
5471531

936842
6408373

748335
7156707

10

344029
7500737

7,500,737

Payment Schedule for Senario "A"


5

10%

10%

10%

10%

11

12

Total

20%

30%

100%
7,500,737

Amount
Acumilative Cash In

750,074
750,074

750,074

750,074

750,074
1,500,147

1,500,147

1,500,147

750,074
2,250,221

750,074
3,000,295

750,074
3,750,368

3,750,368

3,750,368

1,500,147
5,250,516

2,250,221
7,500,737

Diff = Monthlu Cash in - Monthly cash

750,074

719,467-

254,372-

698,569

1,336,573-

202,594-

458,612

52,210

332,319-

835,304-

936,842-

751,813

1,906,192

0.951426524

0.943563494

436,335.62

49,263.83

1.051053313

1.042366922

482,025.66

54,422.39

Summision

(P/F , I ,n)

NPV = (P/F , I , n) * Diff

750,073.65

(F/P,I,n)

0.991735537 0.983539376 0.975410951


(713,520.74) (250,184.63)

1.104713067 1.095583207 1.086528801 1.077549224

NFV = (F/P , I ,n)* Diff

828,616.16

(788,235.69) (276,382.23)

(P/F , I ,n) =1 / (1+i)^n

I = .1/12

(F/P , I ,n) = (1+i)^n

I = .1/12

0.967349704

681,392.24 (1,292,933.16)

1.068643858

752,742.91 (1,428,320.15)

0.959355078
(194,359.82)

1.059812091
(214,711.84)

1/1

0.935765449
(310,972.64)

1.03375232
(343,535.54)

0.92803185
(775,188.39)

1.025208912
(856,360.75)

0.920362166
(862,233.79)

1.016736111
(952,520.94)

0.912755867
686,221.50

1.008333333
758,077.86

0.90521243
1,725,508.42

1
1,906,191.70

0.00
Summision
(70,597.92)

Summision
(77,990.44)

NAFFCO(QATARFACTORY)
WorkshopFactory

Senarion "B"
Month

10

11

12

BILL NO.01 - PRELIMINARY

51504

51504

51504

51504

51504

51504

51504

51504

51504

51504

51504

51504

BILL NO.02 - EARTH WORK

52480

BILL NO.03 - CONCRETE WORK

135245

135245

135245

BILL NO.04 - STEEL STRUCTURE

660184

Total
618,051
52,480
405,735

660184

BILL NO.05 - BLOCK WORK


BILL NO.06 - W.PROOFING & THERMAL
BILL NO.07PROTECTION
- DOORS & WINDOWS

76894

165046

76894

76894

165046

1,650,460

76894

307,575
62400

62,400

189399

BILL NO.08 - PLASTER & FINSHING

144870

144870

144870

BILL NO.09 - PAINTING

151519

37880

378,798

144870

144870

724,350

119015

BILL NO.10 - LANDSCAPING


BILL NO.11 - EQUPMENT

234020

234020

234020

31613

31613

31613

119,015
234020

234020

48565

BILL NO.12 - MECHANICAL (HVAC)

48,565
31613

BILL NO.13 - PLUMPING & DRAINAGE

137432

BILL NO.14 - ELECTRICAL

574798

1,170,100
126,450

137432

137432

137432

68716

68716

687,162

114960

114960

114960

114960

114960

1,149,596

TOTAL

899413

186749

263643

1363380

128398

314395

834824

879445

776799

916217

651950

285524

Acumilative

899413

1086163

1349806

2713186

2841584

3155979

3990803

4870247

5647046

6563263

7215212

7500737

Month

10

10%

7,500,737

Payment Schedule for Senario "B"


5

10%

10%

10%

10%

11

12

Total

30%

20%

100%
7,500,737

Amount

750,074

750,074

750,074

750,074

750,074

2,250,221

1,500,147

Acumilative

750,074

750,074

750,074

1,500,147

1,500,147

1,500,147

2,250,221

3,000,295

3,750,368

3,750,368

3,750,368

6,000,589

7,500,737

Diff = Monthlu Cash in - Monthly cash out

750,074

899,413-

186,749-

486,431

1,363,380-

128,398-

435,678

84,750-

129,371-

776,799-

916,217-

1,598,271

1,214,623

Summision

(P/F , I ,n)

0.991735537 0.983539376 0.975410951

0.967349704

0.959355078

0.951426524

0.943563494

0.920362166

0.912755867

0.90521243

Summision

NPV = (P/F , I , n) * Diff

750073.65

-891980.0826 -183675.241

-1318865.239 -123179.2733

414515.8428

-79967.00616 -121060.9119 -720893.8885 -843251.1401

1458831.414

1099491.882

-85490.20976

1.10471307

1.095583207 1.086528801 1.077549224

(F/P,I,n)
NFV = (F/P , I ,n)* Diff

828616.163 -985382.0532 -202908.439

(P/F , I ,n) =1 / (1+i)^n

I = .1/12

(F/P , I ,n) = (1+i)^n

I = .1/12

474469.783

524152.9694

1.068643858

0.935765449

1.059812091

1.051053313

1.042366922

1.016736111

1.008333333

Summision

-1456967.664 -136077.7529

457921.0682

-88340.59667 -133737.5713 -796380.8988 -931550.5537

1611590.127

1214623.05

-94442.15186

1/1

1.03375232

0.92803185

0.00

1.025208912

WorkshopFactory

Month
BILL NO.01 - PRELIMINARY
BILL NO.02 - EARTH WORK
BILL NO.03 - CONCRETE
O - STEEL
BILL NO.04
S
BILL NO.05 - C
BLOCK WORK

1
51504
52480
135245
165046

2
51504

3
51504

135245

135245

Senarion "C"
5
6
51504
51504

4
51504

7
51504

825230

8
51504

9
51504

10
51504

11
51504

37880
144870

292525

151519
144870
119015
292525

31613
137432
114960

31613
68716
114960

12
51504

660184
153788

153788

BILL NO.06 - W.PROOFING &


C O&
BILL NO.07 - O
DOORS
S
BILL NO.08 - O
PLASTER
&
S
G
BILL NO.09 - PAINTING

62400
189399
144870

BILL NO.10 - LANDSCAPING


BILL NO.11 - EQUPMENT
BILL NO.12 - MECHANICAL
( - PLUMPING
C)
BILL NO.13
&
G
BILL NO.14 - ELECTRICAL

144870

144870

292525

292525

48565
137432
344879

31613
137432
229919

31613
137432
229919

68716
114960

TOTAL

404275

186749

186749

1221613

205292

391289

784737

1255522

835304

974722

710455

344029

Acumilative

404275

591025

777774

1999387

2204679

2595968

3380705

4636227

5471531

6446253

7156707

7500737

Month
%

0
10%

3
10%

8
10%

10

11
30%

12
20%

Payment Schedule for Senario "C"


5
6
7
10%
10%

Amount

750,074

750,074

750,074

750,074

750,074

2,250,221

1,500,147

Acumilative

750,074

750,074

750,074

1,500,147

1,500,147

1,500,147

2,250,221

3,000,295

3,750,368

3,750,368

3,750,368

6,000,589

7,500,737

Diff = Monthlu Cash in -

750,074

404,275-

186,749-

563,324

1,221,613-

205,292-

358,785

34,664-

505,449-

835,304-

974,722-

1,539,766

1,156,118

(P/F , I ,n)
NPV = (P/F , I , n) * Diff

1
750073.65

(F/P,I,n)
NFV = (F/P , I ,n)* Diff

1.10471307 1.09558321 1.0865288


828616.163 -442917.18 -202908.44

Total
618,051
52,480
405,735
1,650,460
307,575
62,400
378,798
724,350
119,015
1,170,100
48,565
126,450
687,162
1,149,596
7,500,737

Total
100%
7,500,737
Summision
0.00

0.99173554 0.98353938 0.97541095 0.967349704 0.95935508 0.95142652 0.943563494 0.935765449 0.92803185 0.92036217 0.912755867 0.90521243 Summision
-400934.13 -183675.24 549472.789 -1181727.022 -196947.683 341357.09 -32707.3075 -472981.3362 -775188.39 -897096.929 1405430.632 1046532.429 -48391.452

(P/F , I ,n) =1 / (1+i)^n

I = .1/12

(F/P , I ,n) = (1+i)^n

I = .1/12

1.07754922 1.068643858 1.05981209 1.05105331 1.042366922 1.03375232 1.02520891


607009.77 -1305469.283 -217570.679 377101.637
-36132.19 -522508.6627 -856360.75

1/1

1.01673611
-991034.7

1.008333333
1552597.585

1
1156118.05

Summision
-53458.669

Vous aimerez peut-être aussi