Vous êtes sur la page 1sur 38

VINAYAKA MISSIONS UNIVERSITY, SALEM

FACULTY OF MANAGEMENT STUDIES VMKV ENGINEERING COLLEGE MBA II SEMESTER (MBA 2009 REGULATIONS)

47109203 - Optimization Models for Business


QUESTION BANK Decisions
UNIT-I: Linear Programming Problem (LPP) Part A (1 Mark) 1. Define Operations Research. Operations Research is the application of scientific methods to complex problems arising from operations involving large systems of men, materials, and money in industry, business, government and defence. 2. What are the different phases in OR? (i). Judgment phase (ii). Research phase (iii). Action phase 3. What is a Linear Programming Problem? Linear Programming is the mathematical technique which involves the allocation of scarce or limited resources in an optimal manner on the basics of a given criterion of optimality. 4. Define feasible region. A region in which all the constraints are satisfied, it is called as feasible region. It is also called as Solution Space. 5. What is alternative optimal solution in LPP? If a LPP has more than one optimal solution, it is said to be an Alternative/Multiple optimal solution. 6. Define basic feasible solution. A feasible solution to an LPP which is also the basic solution is called the basic feasible solution. i.e., all basic variables assume non negative values. 7. Define unbounded solution. When the value of decision variables in LPP is permitted to increase infinitely without violating the feasibility condition, then the solution is said to be unbounded solution. 8. When an LPP is said to be infeasible?
MBA OMBD Question Bank 2012

UK Operations Research Society

In LPP there are no points that satisfy all the constraints of the given problem, it is said to be infeasible (or) no feasible solution. 9. What are the methods used to solve an LPP involving artificial variables? a. Big M Method (or) Method of Penalties (or) Charnes Penalty Method b. Two - Phase simplex Method. 10. State the fundamental conditions in the basis of the simplex method. The Feasibility condition: It ensures that if the starting solution is basic feasible, only basic feasible solutions will be obtained during computations. The Optimality condition: It guarantees that only better solutions (as compared to the current solution) will be encountered. 11. What is key column and how is it selected? Key column is the column which gives the entering variable column and is selected by most negative value in the net evaluation (Zj Cj). It is also called as Pivot column. 12. When does the simplex method indicate that the LPP has unbounded solution? The indication of unbounded solution of LPP can be obtained if all the variables in the key column are negative. 13. What is a slack variable? Slack variable is a non negative variable which is added to the left hand side of the constraint equation to convert the inequality less than or equal () in to equality equation. Slack variables refer to the amount of unused resources like raw materials, labour and money. 14. What is a surplus variable? Surplus variable is a non negative variable which is subtracted from the left hand side of the constraint to convert the inequality greater than or equal () into an equation. Surplus variable is the amount of resources by which the left hand side of the equation exceeds the minimum limit. 15. What is an artificial variable? Artificial variable is a non negative variable introduced in the constraint greater than or equal () in order to get the initial basic feasible solution. Artificial variables are temporary slack variables which are used for purposes of calculation, and are removed later. 16. Define Iso Profit Line. The objective function of maximization is represented by assuming suitable outcome (revenue) and is known as Iso Profit line. 17. Define Iso Cost Line.

MBA OMBD Question Bank 2012

The objective function of minimization problem is represented by assuming suitable cost, a line, known as Iso Cost line. 18. List out the Model of OR. Models by Function Descriptive model Predictive model Normative model Models by Structure Iconic or Physical model Analogue or Schematic models Symbolic or Mathematical models Models by nature of the Environment Deterministic models Probabilistic models Models by degree of abstraction Language Models Case studies Models by the extent of Generality General models Specific models 19. State the advantages of OR Models. OR Models provides a logical and systematic approach to the problem. OR Models indicates the scope as well as limitations of a problem. OR Models helps in finding avenues for new research and improvements in a system. OR Models makes the overall structure of the problem more comprehensible and helps in dealing with the problem in its entirety. 20. Write the standard form of LPP. Standard Form of LPP Objective function is Maximize or Minimize, Z = c1 x1 + c 2 x 2 + ................ + c n x n Subject to constraints, ai 1 x1 + ai 2 x 2 + ................ + ai n x n = bi , i = 1, 2, 3, .., n x1, x2, x3,xn 0

MBA OMBD Question Bank 2012

21. Define Redundant Constraint. The constraint does not affect the solution space, it is said to be redundant constraint. 22. Define degeneracy of LPP. If the minimum positive ratio for two or more rows are same, tie exist. If there is a tie, selection of key row is very difficult. In such case the problem is said to be degenerate. It can be solved by choosing the key row arbitrarily. 23. When does an LPP possess a Pseudo-optimal Solution? An LPP possesses a pseudo-optimal solution if at least one artificial variable is in the basis at positive level even though the optimality conditions are satisfied. 24. What is the indication of alternative optimal solution in simplex table? In optimal simplex table, in the net evaluation (Zj Cj) row if zero occurs for non-basic variables it indicates that LPP has alternate solution. 25. List out the limitations of LPP? Linear programming is applicable only to problems where the constraints and objective function are linear i.e., where they can be expressed as equations which represent straight lines. In real life situations, when constraints or objective functions are not linear, this technique cannot be used. Factors such as uncertainty, weather conditions etc. are not taken into consideration. This method doesnt take into account the effect of time. When the constraint equations are more, the computational difficulties are enormous even when computers are used. Part B (8 marks) 1. A firm manufactures two products A & B on which the profits earned per unit are Rs.3/- & Rs. 4/- respectively. Each product is processed on two machines M1 and M2. Product - A requires one minute of processing time on M1 and two minutes on M2, while B requires one minute on M1 and one minute on M2. Machine M1 is available for not more than 7 hrs. 30minutes while machineM2 is available for 10 hours during any working day. Find the number of units of products A & B to be manufactured to get maximum profit. 2. Naga & Co has two bottling plants, one located at Gandhi Nagar and another at Nehru Nagar. Each plant produces three drinks, whisky, beer and fruit juices named A, B and C respectively. The numbers of bottles produced per day are as follows.

MBA OMBD Question Bank 2012

Plant at Gandhi Nagar Nehru Nagar Whisky (A) 1500 1500 Beer (B) 3000 1000 Fruit Juices (C) 2000 5000 A market survey indicates that during the month of April, there will be a demand of Products 20,000 bottles of whisky, 40,000 bottles of beer and 44,000 bottles of fruit juices. The operating costs per day for plants at Gandhi Nagar and Nehru Nagar are 600 and 400 monetary units. For how many days each plant be run in April so as to minimize the production cost, while still meeting the market demand? 3. (i) A farmer has 1000 acres of land on which he can grow corn, wheat or soyabeans. Each acre of corn costs Rs.100 for preparation, requires 7 man-days of work and yields a profit of Rs.30. an acre of wheat costs Rs.120 to prepare 10 man days of work and yields a profit of Rs.40. an acre of soybeans costs Rs.70 to prepare 8 man days of work and yields a profit of Rs.20. if the former has Rs1, 00,000 for preparation and can count on 8,000 man days of work. Formulate this as an LPP. (ii) Solve the following LPP graphically Min. Z = 4X1 + 5X2 Subject to the constraints X1 + X2 10 2X1 + 5X2 35 & X1, X2 0 (4 Marks) 4. (i) A person wants to decide the constituents of a diet which will fulfill his daily requirements of proteins, fats, carbohydrates at the minimum cost. The choice is to be made from four different types of foods. The yields per unit of these foods are given below. Food type A B C D Proteins 3 4 8 6 Yield per unit Fats Carbohydrates 2 2 7 5 6 4 7 4 Cost per unit (Rs) 45 40 85 65 (4 Marks) (4 Marks)

Minimum requirement 800 200 700 Formulate the linear programming model for the problem. (ii) Solve the following LPP graphically
MBA OMBD Question Bank 2012

Maz. Z = 3X1 + 2X2 Subject to the constraints X1 - X2 1 X1 + X2 3 & X1, X2 0 5. Use Simplex method to solve the following LPP Max. Z = 100X1 + 200 X2 + 50X3 Subject to the constraints 5X1 + 5X2 + 10X3 1000 10X1 + 8X2 + 5X3 2000 10X1 + 5X2 500 and X1, X2, X3 0 6. Use the simplex method to solve the LPP Min Z = -X1 + X2 -3X3 X1 + X2 + X3 10 -2X1 + X3 -2 2X1 -2X2 + 3X3 0 and X1, X2, X3 0 7. A firm manufactures two types of products P1 and P2 and sells them at a profit of Rs.2/- on type P1 and Rs. 3/- on type P2. Each product is processed on two machines G and H. Type P1 requires one minute of processing time on G and two minutes on H; type P2 requires one minute on G and one minute on H. The Machine G is available for not more than 6 hours 40 minutes while Machine H is available for 10 hours during any working day. Formulate the problem as a LPP and solve graphically. 8. Use two phase simplex method to solve the following LPP Max.Z = 5X1 + 3X2 Subject to the constraints 2X1 + X2 1 X1 + 4X2 6 and X1, X2 0
MBA OMBD Question Bank 2012

(4 Marks)

Subject to the constraints

9. Show that there does not exists any feasible solution to the following LPP Max. Z = 2X1 + 3X2 + 5X3 Subject to the constraints 3X1 +10 X2 + 5X3 15 33X1 -10 X2 + 9X3 33 X1 + 2X2 + X3 4 and X1, X2, X3 0 10. Show that the following LPP has an unbounded solution. Max. Z = 4X1 + X2 + 3X3 + 5X4 Subject to the constraints 4X1 - 6X2 - 5X3 - 4X4 - 20 3X1 -2X2 + 4X3 + X4 10 8X1 - 3X2 + 3X3 + 2X4 20 and X1, X2, X3,X4 0

Unit II: Transportation and Assignment problems


Part - A (1 Mark) 1. Define a transportation problem. TP is a special kind of LPP in which goods are transported from a set of sources to a set of destinations subject to the supply and demand of the source and destination, respectively, such that the total cost of transportation is minimized. 2. Write the mathematical form of a transportation problem. Minimize Z Subject to
m n


i =1 j =1

C ij X ij

X
j =1 m

ij

= ai ; i = 1,2...m = b j ; j = 1,2....n

x
i =1

ij

xij 0, i = 1,2...m, j = 1,2......n

3. Define basic feasible solution.

MBA OMBD Question Bank 2012

A feasible solution is called a basic feasible solution if the number of non negative allocations is equal to m + n 1 where m is the number of rows, n is the number of columns in a TP table. 4. Define optimal solution. Optimal solution is a feasible solution (not necessarily basic) which minimizes the total cost. 5. Define non degeneracy in a transportation problem. A basic feasible solution to a (m X n) TP that contains exactly m + n 1 non negative allocations in independent position. 6. What do you understand by degeneracy in a transportation problem? A basic feasible solution to a (m X n) TP that contains less than m + n 1 non negative allocations is called degeneracy in a TP. 7. How to resolve the degeneracy in a transportation problem? This degeneracy in a TP can be resolved by adding one (more) empty cell having the least cost and is of independent position with a non negative allocation ( >0). 8. Define balanced transportation problem. A TP is said to be balanced, if the total supply from all the sources is equal to the total demand in all the destinations. i.e., ai = bj
i =1 j =1 m n

9. How do you convert an unbalanced transportation problem in to a balanced one? The unbalanced TP is converted into a balanced one by adding a dummy row (source) or dummy column (destination) whichever is necessary. The unit TP cost for the dummy row/column elements are assigned zero. Then the problem is solved by the usual procedure. 10. List out the methods used to obtain an IBFS in a transportation problem. a. North West Corner Rule (NWC) b. Row Minima Method (RMM) c. Column Minima Method (CMM) d. Least Cost Method (LCM) e. Vogels Approximation Method (VAM) 11. List out the methods used to obtain an optimal solution in a transportation problem. Stepping Stone Method MODI method

MBA OMBD Question Bank 2012

12. State the necessary and sufficient condition for the existence of a feasible solution to a TP. The necessary and sufficient condition for the existence of a feasible solution is a solution that satisfies all conditions of supply and demand. 13. When does a TP have a unique solution? While doing optimality test, if the entire empty (non-basic) cell evaluation, = Cij (ui + vj) are positive, then the problem is said to have an unique solution. 14. What is the indication for an alternate optimal solution in TP? While performing optimality test, if some of empty (non-basic) cell evaluation, j = Cij (ui + vj) = 0, then the problem is said to have an alternate optimal solution. 15. Vogels Approximation Method results is the most economical initial basic solution? Why? Yes, it is true. In this method we are allocating the items only at the least cost and hence this method reduces the number of iterations towards optimality. Also it gives near optimal solution. Some time it may be optimal solution. 16. List the merits and demerits of using North-West Corner Rule. Merits: Since the cost factor is not considered in each time, this method is easy to compute the total transportation cost. Demerits: Since the allocations have been made without considering the unit cost, the solution obtained may not be the best solution. Therefore, to get an optimal solution it requires more number of iterations. 17. What is an assignment problem? The assignment problem is a special type of allocation problem in which a number of operations are to be assigned to an equal number of operators, where each operator performs only one operation at a minimum cost or maximum profit. 18. What is a traveling salesman problem? In this model a salesman has to visit n cities. He has to start from a particular city (home city), visit each city once and then return to his starting point (home city), 19. State the objectives of traveling salesman problem. The main objective of a salesman is to select the best sequence in which he visited all cities in order to minimize the total distance traveled or minimize the total time. 20. When is there an indication of an alternate solution in an assignment problem? If the final cost matrix contains more than the required number of zeros for assignment at independent position, then it indicates that the problem has an alternate optimal solution.
MBA OMBD Question Bank 2012

21. State the difference between the TP and the AP. The cost matrix in TP is not necessarily a square matrix, whereas in AP, it is Supply and demand at any source and at any destination may be positive The allocations Xij in the case of TP can take any positive values satisfying TP will not provide degeneracy always, whereas in AP will always provide a square matrix. quantity ai, bj in TP, whereas in AP it will be 1 i.e., ai = bj = 1. the rim requirements, whereas in AP, Xij will take only two possible values 1 or 0. degeneracy. 22. Write the mathematical form of AP. Minimize Z Subject to X
j= 1 n n ij n n

C
i= 1 j= 1

ij

X ij

= ; i = ,2..., n 1 1 = ; j = ,2...., n 1 1

x
i= 1

ij

ad n xij =0o 1, j r i 23. How do you solve the maximization case of AP? To solve the maximization problem, first we convert the given maximization matrix into an equivalent minimization matrix form by subtracting all the elements in the given profit matrix from the highest element in that matrix. Then the problem is a minimization and can be solved by the usual assignment method (Hungarian Method). 24. Give any two applications of assignment problem in Business. AP is used in production environment in which the number of jobs are assigned to number of workers or machines in such a way that the total time (or cost) to complete all the jobs will be minimum. AP is used in traveling salesman problem. 25. Why can the TP technique or the simplex method not be used to solve an assignment problem? The TP technique or the simplex method not be used to solve an assignment problem because of degeneracy.
MBA OMBD Question Bank 2012

10

Part B (8 Marks) 1. A company has 3 plants A, B, C and three warehouses X, Y, Z. The number of units available at the plants are 60, 70, & 80 and the demand at X, Y, & Z are 50, 80, & 80 respectively. The unit cost of transportation has been displayed in the table. X Y Z A 8 7 3 B 3 8 9 C 11 3 5 Formulate the above data as transportation modal and obtain an optimum solution. 2. A product is manufactured by 4 factories A, B, C, & D. Their unit production costs are 2/-, Rs. 3/- Re.1/- and Rs. 5/- respectively. Production capacity of the factories are 50, Rs. 70,

40, and 50 units respectively. The product is supplied to four stores S1, S2, S3, & S4, requirements of which are 25, 35, 105, and 20 units respectively. Unit transportation costs are given below. S1 A B C D 2 10 13 4 S2 4 8 3 6 S3 6 7 9 8 S4 11 5 12 3

Find the transportation plan such that the total production and transportation cost is minimum. 3. There are four jobs to be assigned to the machines. Only one job could be assigned to one machine. The amount of time in hours required for the jobs in machines are given below. Job 1 2 3 4 Machine A 4 10 4 8 B 3 12 3 7 C 6 11 2 6 D 2 14 1 9 E 7 16 5 6

MBA OMBD Question Bank 2012

11

Find an optimum assignment of jobs to the machines to minimize the total processing Find for which machine no job is assigned. What is the total processing time to all the jobs? 4. Solve the following TP, Warehouse Factory F1 F2 F3 Requirement W1 19 70 40 5 W2 30 50 8 8 W3 50 40 70 7 W4 10 60 20 14 Capacity 7 9 18

time.

complete

5. Solve the transportation problem with unit TP cost in rupees and units of demand and supply as given below. Destination D1 Source S1 S2 S3 Requirement 10 9 13 60 13 12 9 40 11 12 11 55 8 10 9 45 65 44 41 D2 D3 D4 Capacity

6. A company produced two products B and C. These products are marketed in four cities. The following table gives you the sales figures of the firm. Find the transportation plan to maximize the sales. Cities Product B C Demand Trichy 90 50 75 Salem 90 70 100 Madurai 100 130 100 Chennai 110 85 30 Supply 200 100

7. A Marketing student has to select one and only one elective in each semester and the same elective should not be selected in different semesters. Due to various reasons, the expected grades in each subject if selected in different semesters, vary and they are given below.
MBA OMBD Question Bank 2012

12

Subject Marketing Services Retail Event Research Marketing Management Marketing I F E D C II E E C C III C D C A IV B A H H The grade points are H = 10, A = 9, B = 8, C = 7, D = 6, E = 5, and F = 4. How will the student select the electives in order to maximize the total expected points and what will be his maximum expected total points? 8. The processing time in hours for the jobs when allocated to the different machines is given below. Assign the machines for the jobs so that the total processing time is minimum. Mechines Jobs 1 2 3 4 M1 5 8 4 10 M2 7 5 7 4 M3 11 9 10 8 M4 6 6 7 3

Semester

9. A department head has four tasks to be performed and three subordinates, the subordinates differ in efficiency. The estimates of the time, each subordinate would take to perform, is given below in the table. How should he allocate the tasks one to each man, so as to minimize the total man hours? Men Task I II III IV A 9 13 35 18 B 26 27 20 30 C 15 6 15 20

MBA OMBD Question Bank 2012

13

10. A head of department in a college has the problem of assigning courses to teachers with a view to maximizing educational quality in his department. He has available to him one professor, two associate professors and one teaching assistant (TA). Four courses must be offered and, after appropriate evaluation, he has arrived at the following relative ratings (100 = best rating) regarding the ability of each instructor to teach each of the four courses. Teachers Course - I Course - II Course - III Course - IV 70 70 60 40

Professor -1 60 40 60 Asso. Prof - 1 20 60 50 Asso. Prof 2 20 30 40 T.A 30 10 20 How should he assign his staff to the courses to realize his objective? 11. A salesman has to visit five cities A1, A2, A3,., A5. between the five cities are as follows. To From A1 A2 A3 A4 A1 12 16 24 A2 4 14 8 A3 10 6 12 A4 14 16 8 A5 2 4 14 10

The distances given in kilometers

A5 2 6 4 16 If the salesman starts from city A1 and has comeback to city A1, which route should he select so that the total distance traveled by him is minimized.

Unit III: Sequencing problem and Game theory


Part - A (1 Mark) 1. What is a sequencing problem? The selection of an appropriate order for number different tasks to be performed on a finite number of service facilities in order to make effective use of available facilities and achieve greater output is called sequencing. 2. Define total elapsed time. Total elapsed time is the time between the starting time of the first job and completion time of the last job. 3. List out the types of sequencing problems.

MBA OMBD Question Bank 2012

14

Processing n jobs through 2 machines Processing n jobs through 3 machines Processing n jobs through m machines Processing 2 jobs through m machines 4. Define the term idle time. Idle time is the time for which a machine remains idle during the total elapsed time. 5. Define processing time. Processing time is the time required by each job on each machine. 6. Write any two assumptions in sequencing problem. No machine can process more than one operation at a time. Each operation, once started, must be performed till completion. 7. Write the conditions for applying Johnsons Algorithm for finding the optimal sequencing order of N jobs through 3 machines. The following conditions (either one or both) must be satisfied. Minimum processing time on Machine A Maximum Processing time on Machine B Minimum processing time on Machine C Maximum Processing time on Machine B If any one of the conditions satisfied, the given three machines problem can be converted into two machines problems namely G & H. where G = A + B and H = B + C 8. Write the conditions for applying Johnsons Algorithm for finding the optimal sequencing order of N jobs through M machines. The following conditions (either one or both) must be satisfied. Min. processing time on M/C. M1 Max. Processing time on M/C [M2, M3, , Mm-1] Min. processing time on M/C. Mm Max. Processing time on M/C [M2, M3, , Mm-1] If any one of the conditions satisfied, the given M machines problem can be converted into two machines problems namely G & H. Where, G = M1 + M2 +. + Mm-1 and H = M2 + M3 +..+Mm 9. Define a game. The competitive situation with a finite number of competitors with conflicting interests and where the action of one depends upon the action taken by the other. (or)

MBA OMBD Question Bank 2012

15

Game is defined as an activity between two or more persons involving activities by each person according to a set of rules, at the end of which each person receives some befit or satisfaction or suffers loss (negative benefit). 10. Distinguish between pure and mixed strategies. If a player plays only one particular course of action all the time, he is said to be adopting pure strategy, whereas player plays each of his course of action a certain part of the time (i.e., in fixed proportion), he is said to use mixed strategies. 11. Define a saddle point. A saddle point is that position in the payoff matrix where the maximin value of the row coincides with minimax value of the column. 12. What is a two persons zero sum game? A game with two players, where the sum of the points won equals the sum of the points lost (i.e., gain of one player equals the loss of the other) is known as Two-person zero sum game. 13. Define zero sum game. Give an Example. A game wherein the gain of one player equals the loss of other is called zero sum game. For example, A and B are the players, As gain is equal the loss of the player B. two person zero sum game is always zero sum game. 14. What is meant by minimax principle? Minimax principle is the principle minimizes the maximum losses. Minimax is the maximum of each column and take the minimum among the maximum values (i.e., maximum of row minima). 15. State the rules of dominance. (i) If all the elements in a column (say Kth column) are greater than or equal to he corresponding elements in another column (Rth column), Kth column is dominated by Rth column. (ii) If all the elements in a row (say Ith row) are less than or equal to the corresponding elements in another row (say Jth row), Ith row is dominated by Jth row. 16. What are the types of games that can be solved graphically? The games in which the payoff matrix is of the form (m X 2) and (2 X n) are solved graphically. 17. Define the term players. Finite number of participants (competitors) in a game is called players. The players may be any two companies competing for tenders, two persons bidding in a game etc
MBA OMBD Question Bank 2012

16

18. When do you say a game is stable? A game is sad to be stable, if there is a saddle point.

19. Define value of the game. The value of the game is defined as the expected outcome of the game when players follow their optimal strategies. 20. What kind of games are solved graphically? The games in which the payoff matrix in the form of (m x 2) or (2 x n), they can b solved by using graphical method. 21. Find the Dominating row and Dominating column in the 5 payoff Matrix -2 -4 4 1 8 2 -1 5

Row II is dominated by row I and Column II is dominated by Column III. 22. What is meant by fair game? A game is fair, if the value of minimax and the value of maximin is equal to zero Minimax = Maximin = 0. 23. When do you say a game is strictly determinable? A game is strictly determinable, if the value of maximin and minimax is equal to the game value. i.e., Maximin = V = Minimax. 24. Define Strategy. Strategy is a set of rules (Programmes) that specifies which of the available courses of action the player should make at each play. (Or) Strategy is defined as a complete set of plans of action specifying precisely what the player will do under every possible future contingency that might occur during the play of the game. 25. When do players apply mixed strategies? Players apply mixed strategies when there is no saddle point in the given payoff matrix. i.e.,

MBA OMBD Question Bank 2012

17

Part B (8 Marks) 1. There are five jobs each of which has to go through four machines M1, M2, M3, & M4. in the order M1 - M2 - M3 - M4. Processing times are given below. Machine M1 M2 M3 Job A 11 4 6 B 13 3 7 C 9 5 5 D 16 2 8 E 17 6 4

M4 15 8 13 9 11 Find the optimal sequence and the total minimum elapsed time. And also calculate idle time of the machines. 2. Use graphic method to find the minimum elapsed total time sequence of 2 jobs and Machines, when we are given the following information. Machines Job-1 Sequence Time (in hrs) Job-2 Sequence Time (in hrs) A 2 C 4 B 3 A 5 C 4 D 3 D 6 E 2 E 2 B 6 five

3. (i) Find the sequence that minimizes the total elapsed time (in hrs) required to complete the following jobs on 2 machines in the order M1 - M2. Job : A 8 5 B 6 3 C 10 7 D 11 12 E 10 8 F 14 6 G 4 7 (5 Marks) (3 Marks) Player B I I
MBA OMBD Question Bank 2012

Machine M1 : Machine M2 :

Also find out the idle time for the machines. (ii) Solve the following game II 2

18

Player A

II III

-2 -4

-3 -5

4 (i) Consider the game G with the following pay - off Player B I I Player A II 2 -2 II 6

(4 Marks)

a) Show that G is strictly determinable, whatever may be b) Determine the value of G. (ii) Two players A & B match coins. If the coins show two heads, A wins Rs.2/-, if there are two tails A wins nothing, and loses Re.1/-. When there are one head and one tail. Determine the optimum strategies for the players and the value of the game. following jobs on 3 machines in the order M1 - M2 - M3. Job : A 3 4 6 B 8 3 7 C 7 2 5 D 4 5 11 E 9 1 5 F 8 4 6 G 7 3 12 Machine M1 : Machine M2 : Machine M3 : (4 Marks) 5. Find the sequence that minimizes the total elapsed time (in hrs) required to complete the

Also calculate the idle time for the machines. 6. Find an optimal sequence for the following problem. There are four jobs, each of which must go through five machines in the prescribed order. (Passing is not allowed). Processing times (in hours) are given below. Machines Jobs 1 2 3 4 A 7 6 5 8 B 5 6 4 3 C 2 4 5 3 D 3 5 6 2 E 9 10 8 6

Also find the total minimum elapsed time and idle time. 7. Using dominance property to solve the game Player B
MBA OMBD Question Bank 2012

19

I I Player A II III -5 5 -4

II 3 5 -2

III 1 4 0

IV 20 6 -5

8. Using graphical method solve the rectangular game. Player B I I Player A II -2 4 -3 1 0 2 II -1 III 5 IV -2 V 6

9. Using graphical method solve the rectangular game. Player B I I Player A II III 6 3 8 II 5 6 4

10. Solve the following rectangular game by using graphical method. Player B I I Player A II 5 4 3 7 3 II 3 III 4 IV 0

Unit IV: Network Project Scheduling & Replacement theory


Part - A (1 Mark) 1. What do you mean by Project? Project is a combination of interrelated activities all of which must be executed in a certain order before the entire task can be completed to achieve a set goal. 2. What is a network? Network is a graphical representation of a projects operations and is composed of all the events and activities in sequence, along with their inter relationships and inter dependence. 3. Define an activity.
MBA OMBD Question Bank 2012

20

An activity is any portion of a project which consumes time or resources and has a definable beginning and ending. It is denoted by an arrow with description and time estimates within parenthesis along the arrow. 4. What do you mean by concurrent activities? Activities which can be accomplished concurrently or together are called concurrent activities. 5. Define the term total float. Total float is the amount of time within which an activity can be delayed without affecting the project completion time. It is the difference between the LST and EST of the same activity. 6. Define earliest start time. Earliest start time (EST) for an activity represents the time at which an activity can begin at the earliest. 7. Define latest finish time. The latest finish time (LFT) of an activity represents the latest by which an activity must be completed without delaying the completion of the project. 8. What is slack time in a network? It is a free time in a network. It is equal to the difference between the latest finish time and the earliest finish time (or) the difference between latest start time and the earliest start time of the activity. 9. Define Optimistic time. It is the smallest time taken to complete the activity if every thing goes on well or under best possible conditions. 10. Define total float. Total float is the amount of time by which the completion of an activity can be delayed beyond the earliest expected completion time without delaying the overall project. It is the difference between the late start and early start times of the same activity. 11. Define critical path. The critical path in a network diagram is the longest continuous chain of activities (a path along which it takes the longest possible time duration) through the network starting from first to the last event. 12. State the relationship among the floats. Independent Float Free Float Total Float 13. State any one difference between direct cost and indirect cost.

MBA OMBD Question Bank 2012

21

Direct costs are directly dependent upon the amount of resources involved in the execution of all the activities of the project. Increase in direct cost will decrease in project duration. Indirect cost is associated with general and administrative expenses, insurance cost, taxes etc. Increase in indirect cost will increase in project duration. 14. Define the cost-time slope of an activity. The cost slope represent the rate of increase in the cost of performing the activity per unit decrease in time and is called cost-time slope (or) cost-time trade off. It varies from activity to activity. Cost slope = Crash Cost - Normal Cost Normal Time - Crash Time

15. Define Crashing. The deliberate reduction of activity time by putting an extra effort is called crashing the activity. 16. Define crash time. Crash time is the absolute minimum time required to achieve the crash cost i.e., possible and any attempts to further crash would only raise the activity cost without reducing the time. 17. Define Crash cost. Crash cost is the least cost of completing an activity by employing all possible means like overtime, additional resources etc i.e., the activity cost corresponding to the crash time is called the crash cost. 18. Define optimum duration of a project. The total project cost is the sum of direct cost and indirect cost. It is the time duration of a project at which the total project cost associated it is minimum. (Or) Optimum duration of a project is the duration, for which the total cost associated with it is minimum. 19. Define the least duration of a project. Least duration of a project is the minimum duration beyond which no more crashing the activity is possible. Here, the total cost associated with it is not necessarily minimum. 20. What is resource scheduling? Resource scheduling is the effective allocation of available resources to various activities in such a manner that the allocation is considered as acceptable under the given situation.
MBA OMBD Question Bank 2012

22

21. What is resource leveling? Resource leveling refers to the scheduling of activities within the limits of the available floats in such a way that the variations in resource requirements are minimized. (Or) There are various activities in a project demanding varying levels of resources. The overall resources of the organization are limited. The demand on certain specified resources should not go beyond the specified level. This operation of resource allocation is called resource leveling or Load leveling. 22. What is replacement Problem? The replacement problems are concerned with the situations that arise when some items such as men, machines, electric light bulbs, etc need replacement due to their decreased efficiency, failure of breakdown. Such decreased efficiency or complete breakdown may either be gradual or all of a sudden. (Or) Efficiency of certain items decreases due to wear and tear and require expensive maintenance cost. Certain items like bulb fail suddenly. In such cases the old items have to be replaced by new ones to prevent any further increase in expenditure. This is called replacement. 23. Mention any two situations where the replacement of items is necessary? The old item has become in worse condition and works badly or requires expensive maintenance. The old item has failed due to accident or otherwise and does not work at all, or the old item is expected to fail shortly. A better or more efficient design of machine or equipment has become available in the market. 24. What is salvage value? Salvage value is the actual worth or cost of machine at the given period of time. When the age of the machine increases, the salvage value decreases. It is also known as resale value. 25. What is meant by running cost? The cost which is required to maintain and run to operate the machine is called running cost. 26. Define optimum replacement policy. Replace the equipment at the end of n years, if the maintenance cost in the (n + 1) th year is more than the average total cost in the nth year and the nth years maintenance cost is less than the previous years average total cost. 27. What are the types of failures?
MBA OMBD Question Bank 2012

23

Gradual failure Sudden failure o Progressive failure o Regressive failure o Random failure 28. Define group replacement. Under this policy we take decisions as to when all the items should be replaced, irrespective of whether they have failed or not, with a provision that if any item fails before the replacement time it may be replaced individually. 29. What are the types of failures in replacement theory? (a) Replacement of items with gradual deterioration Replacement of items that deteriorate with time, ignoring time value of money. Replacement of items that deteriorate with time, considering time value of money. (b) Replacement of items that fail suddenly Individual Replacement Policy Group Replacement Policy 30. What is discount factor? Let r% be the rate at which money value decreases. The present worth factor of unit amount to be spend after one year is given by V = (1 + r)-1 where, V is called the discount factor. It is also called present worth factor. (Or) The present worth factor of unit amount to be spent after one year is given by V = (1 + r) -1, where r is the interest rate, then V is called discount factor or discount rate. Part B (8 Marks) 1. Consider a project consisting of 7 jobs A, B, .., G with the following precedence relations and time estimates(days). Job Predecessors a m b A 2 5 8 B A 6 9 12 C A 5 14 17 D B 5 8 11 E C, D 3 6 9 F 3 12 21 G E, F 1 4 7 Draw the project network and find the probability that the project will be completed,
MBA OMBD Question Bank 2012

24

(i) 4 days earlier than expected. (ii) Not more than 4 days later than expected (iii) If the project due date is 30 days, find the probability of meeting the due date. (iv) If the project due date is 35 days, find the probability of meeting the due date. 2. (i) Distinguish between PERT and CPM. relationships are given below. Activity A B C D E F G H Predecessor A B B C D 3. (i) Identify the critical path for the following network diagram. I E J H,I (4 Marks) (4 Marks) K F,G (4 Marks)

(ii) Construct a network for each of the projects whose activities and their precedence

2
2

6
1

2 1

3 4

5 8 3

7 5

4 5

(ii) A firm is considering replacement of a machine whose cost price is Rs.17500 and the scrap value is Rs.500. The maintenance costs (in Rs.) are found from experience to be as follows. Year Maintenance Cost (Rs.) : 200 300 3500 1200 1800 2,400 3,300 4,500 (4 Marks) When the machine should be replaced? resale values are given below. Year O & M cost (Rs.) 1 1000 2 3 4 5 6 7 8 : 1 2 3 4 5 6 7 8

4. (i) The cost of equipment is Rs.10, 000. The annual operation and maintenance cost; and

1200 1400 1700 2000 2500 3000 3500

Resale value (Rs.) 6000 4000 3200 2600 2500 2400 2000 1600 Determine at what time it could be replaced? (4 Marks) (ii) A machine cost is Rs.500/- . Operation and maintenance costs are zero for the first year and increase by Rs.100/- every year. If money is worth 5% every year determine the best age at which the machine should be replaced. The resale value of the machine is negligibly
MBA OMBD Question Bank 2012

25

small. What is the weighted average cost of owning and operating the machine? (4 Marks) 5. A project consists of a series of labeled A, B, C, .., H, I with the following relationships [W< X, Y means X & Y can not start until W is completed; X, Y <W means W can not start until both X & Y are completed] with this notation construct the network diagram having the following constraints. A<D, E; B, D < F, H; C < G; F, G < I Find also the minimum time of completion of the project, when the time (in days) of completion of each task is as follows. Task : Time : A 23 B 8 C 20 D 16 E 24 F 18 G 19 H 4 I 10

6. Calculate earliest start, earliest finish, latest start and latest finish of each activity of the project given below and determine the critical path of the project, Total float, Independent float and free float. Activity 1-2 1-3 1-5 2-3 2-4 3-4 3 3-5 5 3-6 10 4-6 7 5-6 4

Duration 8 7 12 4 10 (in weeks) 7. A project schedule has the following characteristics. Activity to tm tp
1- 2 1 2 3 2- 3 1 2 3 2- 4 1 3 5 3- 5 3 4 5 4- 5 2 3 4 4- 6 3 5 7 5- 7 4 5 6

6- 7 6 7 8

7- 8 2 4 6

7- 9 4 6 8

8- 10 1 2 3

9- 10 3 5 7

a) Construct a PERT network diagram. b) Identify the critical path and compute the expected project completion time. c) What is the probability factor for completing the project in 30 weeks? 8. The following mortality rates have been observed for a certain electric bulb. Week 1 2 3 4 5 6 7 8

Percentage of failure 5 13 25 43 68 88 96 100 There are 1000 bulbs in a factory and its costs Rs. 4/- to replace individual bulb. If all bulbs are replaced simultaneously then the cost would be only Re.1/- per bulb. Determine the best replacement policy.

MBA OMBD Question Bank 2012

26

9. The following failure rate have been observed for certain items Month End 1 2 3 4 5

Probability of failure to date 0.10 0.30 0.55 0.85 1.00 The cost of replacing an individual item is Rs.1.25. The decision is made to replace all items simultaneously at fixed intervals and also to replace an individual item as they fail. If the cost of group replacement is 30 paise, what is the best interval of group replacement? 10. The yearly cost of two machines A & B when the money neglected is as follow. Year 1 2 3 MA 2900 2600 2700 MB 3400 2100 2700 Find their cost patterns if money value is 10% worth and hence find which machine is most economical.

Unit V: Decision Theory Part - A (1Mark)


1. What is decision making? Decision making is an integral part of any business organization. It involves by choosing the best among several alternative decisions through a proper evaluation to achieve desired outcome. 2. List out the different environments in which decisions are made. Decision - making under certainty Decision - making under uncertainty Decision - making under risk Decision - making under conflict. 3. Define payoff. It is the effectiveness associated with specified combination of course of action and state of nature. It is also known as profits or conditional values. 4. Define opportunity loss table. Opportunity loss table is a payoff table which represents the cost or loss incurred because of failure to take the best possible action. It is the numerical difference between the optimal outcome and the actual outcome for a given decision. 5. Define uncertainty. Uncertainty refers to a completion when one cannot specify the relative probability distribution of the outcomes of his decision. (Or)
MBA OMBD Question Bank 2012

27

State of knowledge in which one or more alternatives result in a set of possible specific outcomes, but where the probabilities of the outcomes are neither known nor meaningful. 6. Define certainty. An environment in which the decision maker is in a position to know exactly what will happen by his decision during the period in which such a decision is made. 7. Define risk. Risk refers to a situation in which one can specify the relative probability distribution of the outcomes of his decision. 8. Define the term Act. The acts are the alternative courses of action of strategies that are available for decision maker. The objective is to choose the best alternative from the available alternatives. Decision alternatives are also called Action or Strategies or Courses of action. 9. Define the term Event. Events are the occurrences which affect the achievement of the objectives. Events are also called States of nature or outcomes for the decision problem. The events constitute a mutually exclusive and exhaustive set of outcomes, which describe the possible behaviour of the environment in which the decision is made. 10. Define decision maker. Decision maker is a person who is responsible for making decision. He has to select one from a set of possible courses of action. 11. What are the approaches that are used in decision environment with risk? Expected Monetary Value Criterion (EMV) Expected Opportunity Loss Criterion (EOL) Expected Value of Perfect Information Criterion (EVPI)

12. What is Expected Monetary Value? The expected monetary value for a given course of action is the expected value of the conditional payoff for that action. The conditional payoffs are obtained for each action by considering various act-event combinations. 13. What are the methods used for decision making under uncertainty? Maximax (or) Minimin criterion - Criterion of Optimism Maximin (or) Minimax criterion Criterion of Pessimism Laplace criterion Equally likely decision Criterion of regret (savage Criterion)
MBA OMBD Question Bank 2012

28

Hurwicz criterion Criterion of realism 14. Define Laplace criterion. The Laplace criterion uses of all information by assigning equal probabilities to the possible payoff for each action and then selecting that alternatives which corresponds to the maximum expected payoff. It is an equally likely decision criterion. 15. Define decision tree. A decision tree is a graphical representation of various decision alternatives, states of nature, probabilities attached to the states of nature and the conditional benefits and losses. (Or) Type of tree-diagram used in determining the optimum course of action, in situations having several possible alternatives with uncertain outcomes. The resulting chart or diagram (which looks like a cluster of tree branches) displays the structure of a particular decision, and the interrelationships and interplay between different alternatives, decisions, and possible outcomes. 16. Define states of nature. States of nature are the occurrences which affect the achievement of the objectives. It is also known as events. The events constitute a mutually exclusive and exhaustive set of outcomes. A future event not under the control of decision maker. 17. What is maximin principle? The maximin criterion is based upon the conservative approach to assume that the worst possible is going to happen. The decision maker considers each strategy and locates the minimum payoff for each; and then selects that alternative which maximizes the minimum payoff. 18. State the relationship between decision and decision making. Decision making is the systematic process of selecting the suitable course of action among the several alternatives where as decision is the final outcome of decision making process. 19. What are the steps involved in decision making process? Determine the various alternative course of action from which the final decision is to be made. Identify the possible outcomes called the states of nature which are available to the decision maker. Tabulate the payoff function for all the decision alternatives with respect to the states of nature from different combinations. Construct the regret or opportunity loss table. Select the optimum decision criterion which results in largest payoff.

MBA OMBD Question Bank 2012

29

20. What is Expected Opportunity Loss Criterion? The Expected Opportunity Loss (EOL) is the cost of not picking the best solution. In other words, it's the amount lost by not picking the best alternative. The minimum expected opportunity loss is found by constructing an opportunity loss table and computing EOL for each alternative. 21. What is EVPI Criterion? The expected profit with perfect information is the expected return, in the long run, if we have perfect information before a decision is made. It may be defined as the maximum amount one would be willing to pay, to acquire effect information as to which event would occur. 22. Define Hurwicz criterion. Hurwicz criterion stipulates that a decision makers view may fall somewhere between the extreme pessimism and the extreme optimism of the maximum criterion. It is made by assigning weights with certain degrees of optimism and pessimism. 23. Distinguish between decision under certainty and decision under uncertainty. If the decision maker knows with certainty the consequences of every alternative or decision choice, the problem is a decision problem under certainty. If the decision maker faces multiple states of nature but he has no means to arrive at probability values to the likelihood of occurrence of these states of nature, the problem is a decision problem under uncertainty. 24. What are the steps involved in Maximin criterion? Following steps are involved in Maximin criterion Determine the minimum assured payoff for each alternative. Choose that alternative which corresponds to the maximum of the above minimum payoffs. 25. What are the steps involved in EMV criterion? Following steps are involved in EMV Criterion List conditional profit for each act-event combinations, along with the corresponding event probabilities. For each act, determine the expected conditional profits. Determine EMV for each act. Choose the act at which corresponds to the optimal EMV.

MBA OMBD Question Bank 2012

30

Part B (8 Marks) 1. Under an unemployment promotion program, it is proposed to allow sale of news papers on the buses during the off peak hours. The vendor can purchase the news paper at a special concessional rate of 25 paise per copy against the selling price of 40 paise. Any unsold copies are, however a dead loss. A vendor has estimated the following probability distribution for the number of copies demanded. Number of copies 15 16 17 18 19 20

Probability 0.04 0.19 0.33 0.26 0.11 0.07 (a) How many copies should he order so that his expected profit will be maximum? (b) Compute EPPI. (c) The vendor is thinking of spending on a small market survey to obtain additional information regarding the demand levels. How much should he be willing to spend on such a survey? 2. (i) A decision problem has been expressed in the following payoff table. Customer Category E1 E2 E3 E4 Supplies level A1 7 10 23 32 A2 12 9 20 24 A3 20 10 14 21 A4 27 25 23 17 (4 Marks)

Using Hurwicz principle to find optimal solution [ =0.5] (ii) The details for two competing alternatives are shown in table below. Alternative - I Annual Revenue 2000 3000 5000 Probability 0 .15 0.2 0.4 Alternative - II Annual Revenue 4000 2500 3500 Probability 0. 3 0.4 0.2 0.1

4000 0.25 1200 Find the best alternative, when the interest rate is 0%.

(4 Marks)

3. The research department of Hindustan lever has recommended to the marketing department to launch a shampoo of three different types. The marketing manager has to decide one of

MBA OMBD Question Bank 2012

31

the types of shampoo to be launched under the following estimated payoffs for various levels of sales. Estimated Levels of Sale(units) Types of shampoo Egg Shampoo Clinic Shampoo 15,000 30 40 10,000 10 15 5,000 10 5

Deluxe Shampoo 55 20 3 What will be the marketing managers decision if (i) Maximin (ii) Minimax (iii) Maximax (iv) Minimin (v) laplace and (vi) Hurwicz criterion [ =0.5] is applied? 4. A motor parts dealer finds that the cost of a particular item in stock for a week is Rs.20/- and the cost of a unit shortage is Rs. 50/-. The probability distribution of weekly sales in terms of hundreds is as follows. Weekly sales (00 Units) Probability 0 0.1 1 0.1 2 0.2 3 0.2 4 0.2 5 0.15 6 0.05

How many units per week should the dealer order? Also find the expected value of perfect information. 5. The parker flower shop promises its customers delivery within four hours on all flower orders. All flowers are purchased on the previous day and delivered to parker by 8.00AM. the next morning. Parkers daily demand for roses is as follows Demand Probability 7 0.1 8 0.2 9 0.4 10 0.3

Parker purchases roses for Rs.10.00 per dozen and sells them for Rs.30.00. All unsold roses are donated to a local hospital. How many dozens of roses should parker order each evening to maximize its profits? What is the optimum expected profit? 6. An ice-cream retailer buys ice-cream at a cost of Rs.5 per cup and sells it for Rs.8 per cup; any remaining unsold at the end of the day can be disposed of at a salvage price of Rs. 2 per cup. Past sales have ranged between 15 and 18 cups per day; there is no reason to believe that sales volume will take on any other magnitude in future. Find the EMV if the sale history has the following probabilities.

MBA OMBD Question Bank 2012

32

Market size Probability

15 0.1

16 0.2

17 0.4

18 0.3

7. A company is going to develop a new product in the market. Three alternative decisions are available for the management. A1: Advertising in a television. Advertising cost is Rs. 3000/- per day A2: Appointing salesmen for marketing. Cost is Rs. 1200/- per day A3: Conducting exhibition cost Rs. 900/- per day. The unit price is fixed at Rs. 25/- product and the cost of units associated with the respective decision alternatives are 9, 5 and 11. The expected demands for the item are as follows. Demand Probability 200 0.3 300 0.2 400 0.4 500 0.1

The company has to decide the best alternative decisions among the three decisions. 8. Dhana & Co is currently working with a process which after paying for materials, labour, etc brings a profit of Rs. 12,000. The following alternatives are made available to the company. a) The company can conduct research (R1) which is expected to cost Rs. 10,000 having 90% chances of success, the company gets a gross income of Rs. 25,000 b) The company conduct research (R2) which is expected to cost Rs. 8,000 having a probability of 60% success, the gross income will be Rs. 25,000. c) The company can pay Rs. 6000 as royalty for a new process which will bring a gross income of Rs. 20,000. d) The company continues the current process. Because of limited resources, it is assumed that only one of the two types of research can be carried out at a time. Use decision tree analysis to locate the optimal strategy for the company. 9. A department store with a bakery section is faced with the problem of how many cakes to buy in order to meet the days demand. The departmental store prefers not to sell day old cakes in competition, left over cakes are therefore, a complete loss. On the other hand, if a customer desires a cake and all of them have been sold, the customer will buy elsewhere and the sales
MBA OMBD Question Bank 2012

33

will be lost. The store has therefore, collected information on the past sales based on selected 100 day period as shown in table below. Sales per day 15 16 17 18 No. of days 20 40 30 10 Probability 0.2 0.4 0.3 0.1 Construct the conditional profit and the opportunity loss tables. What is the optimal number of cakes that should be bought each day? A cake costs Rs. 2/- and sells for Rs. 2.50. 10. The research department of consumer products division has recommended to the marketing department to launch soap with three different perfumes. The marketing manager has to decide the type of perfume to launch under the following estimated payoff for the various levels of sales. Estimated Levels of Sale(units) Types of Perfume I II 20,000 250 40 10,000 15 20 2,000 10 5 (d)

III 60 25 3 Examine which type can be chosen under (a) Maximax; (b) Minimax; (c) Maximin; Laplace and (e) Hurwicz criterion [use =0.5] -------------------

VINAYAKA MISSIONS UNIVERSITY, SALEM


MBA OMBD Question Bank 2012

34

FACULTY OF MANAGEMENT STUDIES


(MBA 2009 REGULATION)

II SEMESTER

Optimization Models for business decisions


Model Question Paper Duration: 3 hrs Answer all questions. All questions carry equal marks Part A (10 X 1 = 10 Marks) 1. Define Operations Research. 2. What is a slack variable? 3. Define non degeneracy in a transportation problem. 4. State the objectives of travelling salesman problem. 5. Define the term idle time. 6. Define zero sum game. Give an Example. 7. Define an activity. 8. What are the types of failures in replacement theory? 9. List out the different environments in which decisions are made. 10. Define state of nature. Part B (5 X 8 = 40 Marks) 11. (a) Naga & Co has two bottling plants, one located at Gandhi Nagar and another at Nehru Nagar. Each plant produces three drinks, whisky, beer and fruit juices named A, B and C respectively. The numbers of bottles produced per day are as follows. Plant at Gandhi Nagar Nehru Nagar Whisky (A) 1500 1500 Beer (B) 3000 1000 Fruit Juices (C) 2000 5000 A market survey indicates that during the month of April, there will be a demand of Products 20,000 bottles of whisky, 40,000 bottles of beer and 44,000 bottles of fruit juices. The operating costs per day for plants at Gandhi Nagar and Nehru Nagar are 600 and 400 monetary units. For how many days each plant be run in April so as to minimize the production cost, while still meeting the market demand? (Or) (b) Show that there does not exists any feasible solution to the following LPP
MBA OMBD Question Bank 2012

Max Marks: 50

35

Max. Z = 2X1 + 3X2 + 5X3 Subject to the constraints 3X1 +10 X2 + 5X3 15 33X1 -10 X2 + 9X3 33 X1 + 2X2 + X3 4 and X1, X2, X3 0 12. (a) Solve the transportation problem with unit TP cost in rupees and units of demand and supply as given below. Destination D1 Source S1 S2 S3 Requirement . (Or) (b) A department head has four tasks to be performed and three subordinates, the subordinates differ in efficiency. The estimates of the time, each subordinate would take to perform, is given below in the table. How should he allocate the tasks one to each man, so as to minimize the total man hours? Men Task I II III A 9 13 35 B 26 27 20 C 15 6 15 10 9 13 60 13 12 9 40 11 12 11 55 8 10 9 45 65 44 41 D2 D3 D4 Capacity

IV 18 30 20 13. (a) Find the sequence that minimizes the total elapsed time (in hrs) required to complete the following jobs on 3 machines in the order M1 - M2 - M3. Job : A 3 4 B 8 3 C 7 2 D 4 5 E 9 1 F 8 4 G 7 3

Machine M1 : Machine M2 :
MBA OMBD Question Bank 2012

36

Machine M3 : (Or)

11

12

Also calculate the idle time for the machines. (b) Using dominance property to solve the game Player B I I Player A II III -5 5 -4 II 3 5 -2 III 1 4 0 IV 20 6 -5

14. (a) Consider a project consisting of 7 jobs A, B, .., G with the following precedence relations and time estimates(days). Job Predecessors a m b A 2 5 8 B A 6 9 12 C A 5 14 17 D B 5 8 11 E C, D 3 6 9 F 3 12 21 G E, F 1 4 7 Draw the project network and find the probability that the project will be completed, (i) 4 days earlier than expected. (ii) Not more than 4 days later than expected (iii) If the project due date is 30 days, find the probability of meeting the due date. (iv) If the project due date is 35 days, find the probability of meeting the due date. (Or)

(b) The yearly cost of two machines A & B when the money neglected is as follow. Year 1 2 3 MA 2900 2600 2700 MB 3400 2100 2700 Find their cost patterns if money value is 10% worth and hence find which machine is most economical.

MBA OMBD Question Bank 2012

37

15. (a) The research department of Hindustan lever has recommended to the marketing department to launch a shampoo of three different types. The marketing manager has the types of shampoo to be launched under the following estimated levels of sales. Estimated Levels of Sale(units) Types of shampoo Egg Shampoo Clinic Shampoo 15,000 30 40 10,000 10 15 5,000 10 5 to decide one of payoffs for various

Deluxe Shampoo 55 20 3 What will be the marketing managers decision if (i) Maximin (ii) Minimax (iii) Maximax (iv) Minimin (v) laplace and (vi) Hurwicz criterion [ =0.5] is applied? (Or) (b) The parker flower shop promises its customers delivery within four hours on all flower orders. All flowers are purchased on the previous day and delivered to parker by 8.00AM. the next morning. Parkers daily demand for roses is as follows Demand Probability 7 0.1 8 0.2 9 0.4 10 0.3

Parker purchases roses for Rs.10.00 per dozen and sells them for Rs.30.00. All unsold roses are donated to a local hospital. How many dozens of roses should parker order each evening to maximize its profits? What is the optimum expected profit? --------------------

MBA OMBD Question Bank 2012

38

Vous aimerez peut-être aussi