Vous êtes sur la page 1sur 22

Karach Port Trust---Gate Way to Pakistan

Introduction
The Karachi Port is administered by a Board of Trustees, comprising Chairman and 10 Trustees. The Chairman is appointed by the Federal Government and is also the Chief Executive of Karachi Port Trust. The remaining 10 Trustees are equally distributed between the public and the private sector. The five public sector Trustees are nominated by the Federal Government. The seats for private sector Trustees are filled by elected representatives of various private sector organizations. This way all port users find a representation in the Board of Trustees.

Brief History
Karachi due to its geographical and strategic location is known as the gateway to Asia. Considered as a safe Harbor since time immemorial, Karachi was a small fishing village in early Nineteenth Century. Historians identify it with its proximity to a place from where a part of Alexander's Army, boarded the Greek Flotilla in 326 B.C. The first mention of Karachi as a port is found in an Arabic treatise 'Muhit' on navigation relating to the West Coast of India and the Persian Gulf. Written in 1558, this treatise warns the sailors of whirlpools and advises them to seek safety in Karachi Harbor if they found themselves drifting dangerously. It is also significant to mention that the first Muslim Conqueror of India, Mohammad Bin Qasim, landed at Daibal, in vicinity of Karachi in 711 A.D. Karachi also has the distinction of being the birth place of the founder of Pakistan, Quaid-e-Azam Mohammad Ali Jinnah and was the first capital of Pakistan till 1963. It is now the largest city with a bustling and ever increasing population of over ten million. By 1852, Karachi was an established city with a population of about 14,000 with a prosperous trade in over-seas markets. However, the existing Port started taking shape in 1854, when the projects of dredging the main navigable channel and the construction of a mole or causeway joining the main harbor with the rest of the city were undertaken. About 5 years later, construction of Manora Breakwater, Keamari Groyne, the Napier Mole Bridge, Native Jetty and the Chinna Creek were started which gave initial shape to the port. The construction of the wharves started in 1882, and by 1914 the East Wharves and the Napier Mole Boat Wharf had been completed. During the period between 1927 and 1944, the West Wharves of the Port, the lighterage berths and the ship-repairing berths were constructed. Most of these facilities were obsolete by the time Pakistan came into existence in 1947. Since then, the port administration has embarked on extensive development of the port on modern lines. At the time of independence in 1947, the Port capacity was about 1.5 million tons of dry cargo and 1.0 million tons of P.O.L. products per annum. Karachi Port is now handling over 11.74 million tons of liquid cargo and 25.45 million tons of dry cargo, including 1,213,744 TEUs which constitute about 60% of import/ export of the country.

Page 1

Karach Port Trust---Gate Way to Pakistan

Flow of Internal Communication

External Communication
In KPT for external communication following ways are in practice. www.kpt.gov.pk , KPT website is one of main source of external communication where all relevant information about Karachi Port is available, i.e. port tariffs, vessel schedules, cargo handling details, cargo locations which are updated on daily basis on this website. Letters and fax are also being used for external communication in KPT. Press releases are also issued & published in famous newspapers. Page 2

Karach Port Trust---Gate Way to Pakistan

MANAGING EXECUTIVES
DESIGNATION
Chairman General Manager (Operations) General Manager (Finance) General Manager (Planning & Development) General Manager (Engineering) General Manager (Administration) General Manager (Civil Works/Engg.) Deputy General Manager (Operations) Secretary, Karachi Port Trust

EMAIL chairman@kpt.gov.pk gmo@kpt.gov.pk gmf@kpt.gov.pk gmpd@kpt.gov.pk gme@kpt.gov.pk gma@kpt.gov.pk gmcw@kpt.gov.pk gmo@kpt.gov.pk secy@kpt.gov.pk

OFFICE TEL. NO.


99214315 99214310 99214375 99214530-40 99214316 99214530-40 99214312 99214530-40 99214320 99214530-40 99214324 99214530-40 99214346 99214530-40 99214317 99214530-40 99214311 99214530-40

Ext.2240 Ext.2244 Ext.2230 Ext.2250 Ext.2266 Ext.2223 Ext.2294 Ext.2206

HEADS OF DEPARTMENTS
DESIGNATION
Manager (Management Information Systems) Traffic Manager Deputy Conservator Chief Accounts Officer Chief Mech. & Elect. Engineer Manager Finance Chief Engineer Chief Auditor Manager Coordination Project Manager (Planning) Project Manager (East) Project Manager (West) Project Manager (Mechanical)

EMAIL mis@kpt.gov.pk trfmgr@kpt.gov.pk, tm@kpt.gov.pk dc@kpt.gov.pk cao@kpt.gov.pk cmee@kpt.gov.pk mf@kpt.gov.pk ----------------------------Page 3

OFFICE TEL. NO.


99214352, 92914679 99214530-40 Ext. 2276 99214361 99214530-40 Ext. 2466 99214321 99214530-40 Ext. 2242 99214547 99214530-40 Ext. 2257 99214955 99214530-4- Ext. 2510 99214393, 99214397 99214530-40 Ext. 2343 99214318 99214530-40 Ext. 2211 99214545 99214530-40 Ext. 2234 99214530-40 Ext. 2294 99214345 99214530-40 Ext. 2491 99214365 99214530-40 Ext. 2221 99214530-40 Ext. 2221 99214376 99214530-40 Ext. 2332

Karach Port Trust---Gate Way to Pakistan


Chief Medical Officer Manager (O&M) Manager (IR&W) Manager Stores Manager (Human Resources) Manager (Training and Education) Estate Manager Commandant Port Security Force Manager, Pollution Control Department Manager Port Safety

. ------------ms@kpt.gov.pk hr@kpt.gov.pk mgr.te@kpt.gov.pk ----99263030 99214343 99214530-40 99214348 99214530-40 99214351 99214530-40 99214355 99214530-40 99203950 99214347 99214530-40 99214350 99214530-40 99210425 99214530-40 99214598 99214530-40 Ext. 2353 Ext. 2500 Ext. 2561 Ext. 2487 Ext. 2300 Ext. 2285 Ext. 2320 Ext. 2365

managerportsafety@kpt.gov.pk -----

Port Intelligence Officer

99214335 99214714 99214530-40 Ext. 2627

Geographic Location

Page 4

Karach Port Trust---Gate Way to Pakistan

Container Terminals Karachi International Container Terminal


Page 5

Karach Port Trust---Gate Way to Pakistan

. The first dedicated container terminal of Karachi Port with an investment of $65 millions is operation since 1997. the terminal has capacity of 350000 TEUs. Initially an APLICTSI Venture KICT has been taken by HBH whmpao of Hong Kong and after completion of phase 2 Wirt the fourth gantry crane with 55 meters outreach commissioned in March 2004, further expansion of the terminal is underway. In the third phase KICT is extending and deepening its births with a further investment of $55 million. KICT is a modern Terminal with an efficiency of 65 TEUs per hour providing fast through put of 75000 TUEs.

Pakistan International Container Terminal


The second port terminal of Karachi Port is located on east wharves. With 600 meter long quay wall having 13.5 meter depths, the terminal has a capacity of 450000 TEUs. The terminals provide 54 meter reach gantry cranes and the state of the art equipment with 7 million investment. IFC and OPEC are core financier of the project . PICT has also made a public offering of 20% of its shares. On completion of phase 3 the terminal would have a through put of 550000 TEUs.

Karachi Port Operational Centre (KPOC)


Fully automated Karachi port operational centre is located in the port control tower at east wharf. It is the nerve centre of the port all operations taking place inside the Karachi Port and the harbour. It is managed round the clock and communicates with all concerned and emergency responses are intitated by this centre. It is equipped with 15 cameras on separate places.

Income

The income of the Karachi Port Trust is derived from the following main activities as per scale of tariff fixed for the each items as is framed under 43-43 A of the Karachi Port Trust act 1986 and notified by the federal government through SRO. 1. 2. 3. 4. 5. Cargo Handling Vessel Handling Cargo Storage Ships Movement & Services Estate Management

Expenditure
1. 2. 3. 4. 5. 6.

The main areas in which incurred expenses are: Salaries and Wages Operating material and supplies Outside repair and maintenance Administration and Overheads Loan Interest

Port Operations/Functions
Primary functions of Karachi Port Trust are CARGO HANDLING and VESSEL HANDLING. Page 6

Karach Port Trust---Gate Way to Pakistan

CARGO HANDLING
CARGO TYPES
Containers (TEUs) Containers (TONs) TP Cont. (TEUs) General Cargo Sub. Total Gen. Cargo Bulk Cargo Total Dry Cargo Liquid Cargo

Import
1,569 20,673 2,880 23,553 1,701 25,254 56,764 82,018

Export
3,183 46,086 100 46,186 9,412 55,598 55,598

Total
4,752 66,759 2,980 69,739 11,113 80,852 56,764 137,616

GRAND TOTAL

Container Handling
Type of Handling
Import Export Total

Loaded Containers
20' 795 1,118 1,913 40' 198 770 968 Over 40' 0 0 0

Empty Containers
20' 68 127 195 40' 155 199 354 Over 40' 0 0 0

Total Teus
1,569 3,183 4,752

Shipwise Cargo Handling


Berth No. Name of Ship Working Berthing Date Agent Steve- dor e Discharging Dis. Bal. 24 Hrs Sh. Loading Bal. 24 Hrs

BULK OIL PIERS


OP-II OP-III Akaki Quetta D.Crude Oil D.Crude Oil 12-02-12 PNSC 11-02-12 PNSC 73,764 Comp. 41,764 69,544 Comp. 15,000 -

EAST WHARVES
4 5 11/12 NMB Chungo Tres King Hero CF Crystal Country Crafts L.Rice D.GC D.Canola D.L.GC 13-02-12 EAST WIND 11-02-12 TRANSBRIDGE 14-02-12 OC-SERVICES MMS MARHABA NT 152 Shifted from B.No.11/12 8,679 2,326 56,060 2,728 152 32,643 13,967 100 100 863

P.I.C.T
6/7 6/7 8/9

6 9 (EAST WHARVES)
D.L.Cnt. D.L.Cnt. D.L.Cnt. 12-02-12 NOT PROVIDED 13-02-12 NOT PROVIDED 12-02-12 NOT PROVIDED PMS PMS PMS 10,382 Comp. 14,406 602 10,321 Comp. 6,384 6,748 970 3,896 6,384 9,618 358 14,406

Valerie Schulte HanjinMonaco Glen CanyonBridge

13,010 Comp.

70 14,868

WEST WHARVES
20 21 25 Sea Merchant Pacific Traffic Tabernacle Prince D.Wheat L.Rice L.Cement 07-02-12 5 STAR-SH. 06-02-12 GENERAL-SH 13-02-12 ARGONAFTIS CMDR FC 10,173 5,527 1,701 3,109 5,440 20,359 8,641 5,440 12,350

K.I.C.T
26/27 28/29 29/30

26-30 (WEST WHARVES)


D.L.Cnt. D.L.Cnt. D.L.Cnt. 13-02-12 U.M.A 12-02-12 NTO PROVIDED 14-02-12 NTO PROVIDED MTO MTO MTO 10,237 Comp. 18,796 Comp. 285 961 4,486 16,728 Comp. 16,070 824 13,385 Comp. 10,118 285 10,809 -

Hyundai Freedom Lindavia Violetta

Vessel Handling
Page 7

Karach Port Trust---Gate Way to Pakistan

.
Purpose Berth Alloted Special Request

1. Arrival Schedule - OFF PORT


Vessel's Name L.O.A Status Time/Date Draft (In Mtrs.)

a) Oil Tanker Ships


Maribel DL Ace 228.0 125.0 Off Port 0200/15 9.1 D.Mogas 6.2 L.Ethanol OP-III OP-II -

b) Container Ships
Wan Hai-602 Marcampania Bravo 276.0 163.0 208.0 Off Port 1400/14 0230/15 11.5 D.L.Cnt. 8.5 D.L.Cnt. 10.5 D.L.Cnt. 8/9 1/2 6/7 PICT East Wharf PICT

c) General Cargo Ships


Wo Long Song 179.0 1200/15 9.9 D.Gen.Cargo 24 West Wharf

d) BM Pride 165.0 Off Port 6.2 Bunkering SRB-1 East Wharf

2. Sailing Schedule
Vessel's Name Glen Canyon Bridge Hanjin Monaco King Hero L.O.A 285.0 261.0 160.0 Time/Date 1400/14 1445/14 0200/15 From Berth 8/9 6/7 5 Ship Type Container Ships Container Ships General Cargo Remarks

3. Shifting Schedule
Vessel's Name Peace Traffic L.O.A From Berth 5 To Berth Time/Date 1500/14 Reason 177.0 21

Shipping Services Ships Repair


Repairs can be carried out at the anchorage, except in the monsoon season. Two ship repair jetties are available in the port. In addition, Karachi Shipyard and Engineering Works Ltd. provide all kinds of repair and ship-building facilities. Immobilization of main Engine: Request for immobilization must be included by the master of the vessel in their arrival messages so that the permission of the Deputy Conservator, Karachi Port Trust may be obtained for the period required to carry out maintenance and necessary repairs. Oil tankers are not permitted to immobilize engines, particularly at oil pier berths.

Pilotage
Page 8

Karach Port Trust---Gate Way to Pakistan


Pilotage is compulsory for vessels of 200 GRT and upwards. Pilot boards at the Outer Anchorage.

Vessels are pilotage day and night, subject to tides, length and draft to berths lying on the East and West of the fairway, which is 4.27 miles long. Pilotage distance is about 5 to 6 miles.

Fuel Companies
Different fuel companies have provided 3 grades of petroleum for the ships i.e. furnace oil, light diesel oil and high speed diesel oil. All types can be supplied at berth and at anchorage by barge

Fresh Water
Fresh Water is available at all BOP and berths No. 18 to 25 at West Wharf through shore supply lines for ships and tankers.

Tugs And Barges


Five Tugs are available at the Port, two are of 40 Tons and 3 are of 25 Tons bollard pull. Tug operations inside the harbor are rendered by Karachi Port Trust on signal from the Pilot. Tug operation is not provided outside the breakwater except in very special circumstances, at the discretion of the Deputy Conservator. This is subject to weather conditions and availability of tugs. Tug operations outside the breakwater are governed under special terms and conditions.

Projects
As the new generation of container ships comes on the drawing boards, Karachi Port takes the initiative of bracing itself to handle and cater for fifth and sixth generation ships. This involves the development of a deep water container port at Keamari Groyne, which is the natural choice for such a port. Project consultants are M/s Royal Haskoning and M/s Scot Wilson of UK. Ten berths at 18m depth, with 5 km of quay wall have been planned. The project shall be carried out in phases and on publicprivate partnership (PPP). Total cost of the project is US$ 1.6 billion. In Phase I, four berths with 1500 m quay wall is planned to be constructed. Project is scheduled for completion in 2013.

Page 9

Karach Port Trust---Gate Way to Pakistan

PDWCP Phase-1 - The Concession Agreement

The Phase 1 of PDWCP comprises 4 berths and will have 1500m quay length. A design vessel, (similar to Emma Maersk), of 400 m LOA, 55.0m Beam and l5m Draft with 11,000 TEUs on board, has been used for planning the PDWCP. The channel and berthing face will be dredged to 16m initially, but the Quay wall is designed for 18m depth. The container terminal will have both road and rail connections to the hinterland including the proposed Cargo Village in the Western Backwaters of Karachi Port. The viability of PDWCP with respect to the geographical location of the port was proved when in response to the KPTs request for proposals for setting up of the PDWCP, four world renowned firms responded. After an exhaustive exercise of evaluation of the most competitive bid, M/s Hutchison Port Holdings Limited (HPH) of Hong Kong has been awarded the Concession. HPH is the worlds largest container operator. In 2006, HPH handled 59.1 million TEUs worldwide and of which, 13.1 million were transshipment. HPH operates 257 berths in 45 ports in 23 countries alongwith a number of transportation related service companies. The lease of the terminal will be for an initial period of 25 years extendable for another 25 years, on mutually agreed terms and conditions. M/s. Hutchison Port Holdings Limited (HPH) Hong Kong will be required to develop the site into a full-fledged state of the art Container Terminal capable of receiving and handling Super Post Panamax Container Ships. Terminal Capacity will be 3.1 Million TEUs Expected initial investment by M/s. HPH is US $457 Million. All equipment will be new and current models from internationally accredited manufacturers.
THE SCOPE OF INFRASTRUCTURE DEVELOPMENT BEING CARRIED OUT AT PDWCP BY KPT: Dredging and Reclamation: The dredging and reclamation contract has been signed with

China International Water and Electric Company (CWE). Total 33 million cum dredging including 8 million cum reclamation is planned at a cost of Rs 19 Billion. Completion is scheduled in 2011. The existing Port Approach Channel is to be widened and deepened so as to link it to the new PDWCP harbour. This shall initially increase the depth of existing channel from -12.2 meters to -16.0 meters.

Page 10

Karach Port Trust---Gate Way to Pakistan

From approximately 33.0 million cubic meters of dredging to be carried out, about 8.0 million cubic meters of the material shall be used for reclamation works and for creating stockpiles of material for future use in the terminal construction. The Dredging and Reclamation works shall also complement other modules of the Pakistan Deep Water Container Port namely, the Marine Protection Works and the Quay Wall construction works.

Marine Protection Works: The second component is Marine Protection Works (MPW) in

which three breakwaters and a sand dyke are planned to be built. The contract has

Page 11

Karach Port Trust---Gate Way to Pakistan


Billion. Completion is scheduled in 2012.

been awarded to M/s China Harbour Engineering Company (CHEC) at a cost of Rs 12.8

The Marine protection works for the project shall include construction of 3 breakwaters and a sand dyke. The marine protection works have been envisaged to comprise of three rock or concrete (CORE-LOC units) armoured breakwaters to provide shelter to the port basin and for preventing sediment transport into the basin. The scope consists of:
Keamari Extension - Repairs as deemed necessary to strengthen existing

Groyne. To be constructed to accommodate a future -18.0mPD dredged depth at PDWCP harbour entrance.) Repairs to existing Keamari Groyne are also planned.
Oyster Rocks Breakwater - Construction of breakwater (-18.0mPD dredged depth

at PDWCP harbour entrance) and Construction of concrete pedestrian access along shore side. To be constructed to accommodate a future -18.0mPD dredged depth at PDWCP harbour entrance. Construction of concrete pedestrian access along shoreside)
Manora Breakwater

To be constructed to accommodate a -18.0mPD dredged depth at Port entrance) Keeping in view the significance of the project, the design parameters have been set keeping in view that the wave conditions at the entrance to the Port of Karachi are Page 12

Karach Port Trust---Gate Way to Pakistan


dominated by southwesterly (180 to 270) offshore and waves propagating from the Indian Ocean.

The design life and standard for the breakwaters are 50 years and the Design standard adopted for a life of 100 years. As per good engineering practice of model test the final design of large breakwater structures have been tested through physical modelling.
Quay Wall Construction: The contract for quay wall been awarded to M/s China Harbour

Engineering Company (CHEC) at a cost of 18 Billion. Completion is scheduled in 2012. A tied bored pile quay wall has been designed, in which the quay wall is to be built using 2.5m diameter circular reinforced concrete piles, restrained by steel anchor ties attached to a piled anchor beam located 50 metres (centre to centre) behind the quay wall. The anchor beam is supported by 1.6m diameter reinforced concrete piles at 2.6 metre centres. The design is selected to use proven technology and good earthquake resistance. The following facilities are provided in relation with the present design:
A straight quay length of 1,500m, providing a nominal four berths of 375m length with a depth alongside of -16.5m initially and -18.0m finally, and able to accommodate vessels in the capacity range 750 TEU to 14,500 TEU; Crane rail slots for the installation of crane rails to allow operation of STS cranes. Appropriate marine furniture including fenders and bollards for the expected vessels and ladders. Karachi International Container Terminal ( KICT)

KICT, is already operational at the West Wharf. It was developed in phases. Initially two phases were operational with terminal area of 135,122 sqm and an annual capacity of 400,000 TEUs. Previously with only two phases functional, terminal area of 135,122 sq.m. Cost of Phase I & II is USD 65 million. Phase-III has also been completed. This was inaugurated by Honarable Prime Minister Syed Yousuf Raza Gilani in November, 2008. In this phase, the terminal has an area of 260,000 sq.m with an additional investment of US$ 55 million. The total Terminal capacity shall be increased to 700,000 TEUs. The 973 m long berths of the terminal are deepened to cater for 14 meter draught

Page 13

Karach Port Trust---Gate Way to Pakistan


empty handler, 50 chasis etc. Presently they are handling 806,000 TEUs per year
Pakistan International Container Terminal (PICT)

container ship. The Terminal is equipped with 6 gantry cranes, 15 RTGs, 4 Top lift, 4

The second Container Terminal on BOT was awarded by KPT in June 2002. This Terminal at Berths 6-9 East Wharf has 600 m quay wall with - 13.5 m depth over an area of 207,000 sqm. The terminals planned capacity is 450,000 TEUs. This was a US $ 75 million project. PICT was also developed in Phases. In Phase-I Two modern gantry cranes and associated equipment were deployed. Phase-II was completed in May 2006 with additional deployment of one more ship to shore gantry crane and Phase-lll has been completed in January 2009. Presently they are handling 603,000 TEUs per year
Reconstruction of Berths

KPT has 30 dry cargo berths and 560 meter quay wall at Napier Boat Whraf for country craft. Out of which 17 # berths situated at East Wharves & 11 # berths @ west Wharves. Two container terminals (PICT & KICT) occupied 9 # berths (6 to 9 berths for PICT) & (30 to 26 berth for KICT). The rest of berths are operational under KPT management. Due to collapse of berth # 10 & 14 in August 2007, KPT declared these 9 # berth (ie.10 to 17A) non operational since August 2007. Due to shortage of berths, KPT had initiated step in year 2005 to appoint M/s Scott Wilson +ZCL for planning & detailed designing of old & outlived berths # 10-17A including SRBs, before this berth collapse incident occurred in year 2007. Thereafter KPT decided to commence the berth reconstruction in phases. In 1st phase, KPT awarded the work to Contractor M/s Ssangyong +Usmani (JV) and they commenced the work from 20th March 2007 and was to be completed in March 2010, but said work could not reasons. completed within time i.e. 24 months due to various technical

Page 14

Karach Port Trust---Gate Way to Pakistan

The supervision of project work is being done by the supervision consultants M/s Lyon Associate (USA) + Techno (JV) of execution. The cost of the project is Rs. 5.5 Billon and funded by KPT own resources. Physical completion progress of work is about 60 %. The total quay wall length is 777.823 meter between berth 10 to 14, included 2 meter dia cast in-situ concrete piles connected /associated with tie rods & other allied fixture for supporting of the berths structures. Project completion of phases is October, 2010 and July 2011.
RECONSTRUCTION OF BERTH 15- 17 A INCLUDING SRBS `1 & 2 AT EAST WHARVES.

The project Reconstruction of 15 -17A will be executed in 2nd phase of reconstruction sequence of reconstruction of berths t at east wharves. The design & planning of the project has already been completed. KPT is intending to finance this project through World Bank soft loan. The negotiation with World Bank is almost finalized, and it will be materialized very soon. The Concept of project has been approved by CDWP of Planning & Commission. The cost of the project is Rs 9.224 Billion including some important assignments (KPTs Institutional Strengthening of project & EIA report & its improvement) to be carried out under the loan facility. On the basis of World Bank guidelines, KPT initiated Prequalification stage and invited contracting local /international firms to participating in PQ stage. In response 9 firms participated with local JVs partners in this stage of prequalification. KPTs design Page 15

Karach Port Trust---Gate Way to Pakistan

consultant prepared a prequalification Report and the same has been forwarded to World Bank for its approval. Recently KPT received some queries from word bank on PQ report, hence y KPT shall reply on these queries accordingly; however World Bank is principally agreed to the PQ report for the selection of the contracting firms. The tender documents have been reviewed by World Bank and send back to KPT for its minor changes. The tender document shall be floated to the prequalified contractor very soon.
Port Grand (Food Court)

Another project is the establishment of a Food Street, at our Natives Jetty Bridge and its adjoining area within rotary of Jinnah Bridge.

The project is offered on Build Operate and Transfer basis for 21 years. This scenic stretch, has ample area for landscaping, walkways and joy rides, dinner cruises etc. Infrastructure has been completed and outlets are being awarded.

Page 16

Karach Port Trust---Gate Way to Pakistan

SECURITY MEASURES AT KARACHI PORT


1. Karachi Port with regard to Security has taken a giant leap forward in the area of technology and sophistication. The Security Sector has been totally revamped with the induction of Port Security Force. Karachi Port Trust is fully alive to the global security environments and is proactively poised to meet future formidable security challenges. The goal of Karachi Port Trust is to provide secure environment in which trade be conducted with high assurance and equilibrium of security & safety versus efficiency. KPT after having evaluated the global security environments has embarked upon revolutionizing security on the port introducing state of art security infrastructure as per requirements of IMO and implementation of ISPS Code in real spirit. Following cutting edge equipments / measures has been installed/ implemented on the port.

a)

VIDEO MANAGEMENT SYSTEM (VMS)

As part of mitigation strategies, KPT has installed state of the art harbour and area scanning cameras on the port with following specification: i) ii) iii) iv) Espirit TM Image Pak System, PTZ outdoor colour Digital Camera System. Spectra III TM Series high Resolution speed Dome, 16 x for surveillance of gates, plinths and quay wall. Digital, distributed, Networked integrated for Video Management and surveillance over Inter Protocol (IP) networks. Digital recording and surveillance serve as high capacity Data base.

b)

VMS GREATLY ENHANCES SECURITY, SAFETY AND EMERGENCY RESPONSE ON THE PORT AND RENDERS ADVANTAGES AS UNDER:
i)
It tracks ships right from anchorage to the berth. Page 17

Karach Port Trust---Gate Way to Pakistan


ii) iii) iv) v) vi) vii) viii) ix) Assists in identification and monitoring of ships without transponders.

Provides Surveillance and monitoring of all the ships/ crafts inside the harbour. Assists in identification of suspicious ships/ crafts in the harbour. Allows Surveillance and monitoring of the ships at the berths. Surveillance and monitoring of cargo operations. Surveillance and monitoring of vehicular traffic on the port. Enable to activate prompt response to meet emergencies. Helps in maintaining historical record of movement of ships/ cargo.

c)

VESSEL TRACKING SYSTEM (VTS):

KPT has installed cutting edge Vessel Tracking System in the port to surveil/ monitor vessels in the Port Area / Territorial Waters/ harbour. The system receives vessel information transmitted by them and displays their position on a shore based computer work station on an electronic chart. User can select both the desired areas and amount of details required; system continuously automatically to logs the reports, records latitude and longitude, speed and course of all tracked vehicles. Historical track information can be recalled and printed out either as chart or data base report in real time along with history of the track. VTS has greatly helped in managing vessel traffic diversity on the port. The system provides: i) ii) iii) iv) v) vi) vii) Better Command and Control. Effective utilization of assets. Quick emergency response. Safe and secure passage of ships. Identification and monitoring of aligned/ non aligned ships. Dynamic data base for recording of information/ activities. UAIS as per ISPS Code required.

2. a)

IMPLEMENTATION OF ISPS CODE:


The Karachi Port has complied with ISPS Code as per requirements of IMO on 01 July 2004. The Karachi Port has been divided into three Port Facilities as under:

i)

Port Facility - I: Oil Pier I, II, III, Mooring Area and Anchorage Area The Port Facility Security Officer I can be contacted on PFSO-I, Contact No.0333-2378561. Port Facility II: Berth No.5 and 10 -17
Page 18

ii)

Karach Port Trust---Gate Way to Pakistan

The Port Facility Security Officer II can be contacted on PFSO II Contact No.-0334-3159881 iii) Port Facility III: Berth No.18-25 The Port Facility Security Officer III can be contacted on PFSO III Contact No.0333-2378562

b)

The Two Private Terminals in Karachi Port have been declared as two separate identity and Facility namely: i) PICT (Pakistan International Container Terminal) Facility: Berth No.6-9 PFSO Col (R) Saleemullah Contact No.0321-2430530 KICT (Karachi International Container Terminal) Berth No.26-30 PFSO Lt Col. (R) M. Ramzan Contact No.0333-2160970

ii)

c)

All the Port Facilities are being monitored by: i) ii) iii) iv) Harbour Patrol by boats with armed port security personnel. Mobile Patrols through Mobile Vans and Motor Cyclist on wharves, Roads and Jetties. Excess Control System at Entry/ Exits Gates is equipped with Biometrics, Smart Card Recorders and CCTV. Computerized Gate Pass System for Entry with in bonded area.

3.

KARACHI PORT OPERATION CENTRE (KPOC)

The State of the art KPOC has been established at a strategic location having panoramic view of the port to supervise, monitor and control activities. The centre is fully computerized and all the reports and returns are being electronically generated. Intranet, Internet and direct communication facilities help in making prompt and real time decision making. KPOC serves as a nerve centre and houses representatives of departments of the Port. Functions of KPOC are:

i) ii) iii) iv) v) vi) vii)

To collect, collate process and disseminate information. Monitor and control port operations. Act as communication centre. Act as focal point to render technical assistance. Monitor and control marine pollution in the harbour. Co-ordinate and maintain security activities on the port. To activate emergency response to handle crises situation.
Page 19

Karach Port Trust---Gate Way to Pakistan

Contact No. OI/C KPOC Operation Room Officer

9263050, Ext. 2302 9263046, 9214555 9214530 Ext. 2557, 2539, 2693

4. Karachi Port is manned and performs 24 hours a day 7 days a week. In case of any clarification / assistance one can contact on following numbers: S.No. 1. 2. 3. 4. 5. 6. Designation General Manager (Ops) Traffic Manager Dt. Conservator Commandant Port Security Force Operation Room Officer Manager Port Safety Telephone Numbers 9214375, 9214379 9214361, 9214530 Ext.2466 9214354, 9214530 Ext.2242 9214350, 9214530 Ext.2291 9263046, 9214555, 9214530 Ext.2557, 2539, 2693 9214598, Ext. 2487

Page 20

Karach Port Trust---Gate Way to Pakistan

Summary
Karachi Port is one of those public enterprises in Pakistan which has basic and vital role for the nation as well as for the economy of the country, without which the economic development may become stand-still. Significance of this port for Pakistan becomes more prominent when one takes into account the difficulties of the land locked countries like Afghanistan, Central Asian States and Nepal etc. inconnection with their international trade. In case of our country, which has import oriented economy, struggling to boost up its exports in order to reduce the yawning trade gap, and which has very little prospect of regional trade through land routes, the significance of the Karachi Port becomes more important its major sea port. After 1947, this port jumped to the status of jugular vein for newly created stat and since then it has been functioning as a gateway for its international commerce. If one has a view of the economic of its capacity for dry cargo far before however, containerization came to help and extra burden is being offset, to large extent, in the form of CY container Cargo which constitutes about 50% of the total import container traffic. The burden of the port has also been shed in the way that a considerable volume of dry cargo in build form like, wheat, ores, cement and fertilizers etc. has been shifted to Port Qasim. Two international container terminals i.e. Karachi International Container Terminal & Pakistan International Container Terminals being administrated by private public sector are very useful addition toward upgrading the Karachi Port. These International container terminals are saving lot of time of vessel agents/operators with the use of stat of the art equipment. Another Pakistan Deep Sea Water Container Terminal is also under process project of Karachi Port Trust, which is considered as the Asias biggest container terminal which will make Karachi Port Trust more effective for Pakistans Economy. In spite of this a lot of development which could have made by the authorities but still need to be planned. Even now, it is not too late to make amends for the pas mistake. The Karachi Port still can be developed upto the modern level requirements and it can be introduced into the regional competition if sincere efforts are made. For this purpose the thing of foremost importance is that maximum share in this developmental and operational activities is to be given to the private sector because from decades old traditional bureacratic set up of this administration which has become used to take each step under directions of the Federal Government, cannot be expected any revolution in this direction.

Page 21

Karach Port Trust---Gate Way to Pakistan

LIST OF ABBREVIATIONS
AN BAN BCAN BB CCAN CHAN CBM CY CFS DG ECAN EGM FRAN FCL FCAN GC GDAN GoP HAN HLAN HTAN HFAN IGM IMDG LCL LFAN MAN MCAN MoC MoD OAAN OV PAN PDPT PD PDAN PDPft PT PTO SAN SLAN SWAN TAN TEU WAN Amplifying Note Barges Amplifying Note Berth Charges Amplifying Note Break Bulk Country Craft Amplifying Note Chain Amplifying Note Cubic Meter Consignee Yard Container Freight Station Dangerous Goods Electric Quay Crane Amplifying Note Export General Manifest Fire Relief Amplifying Note Full Container Load Floating Crane Amplifying Note General Clauses Graving Dock Amplifying Note Government of Pakistan Haulage Amplifying Note Heavy Lift Crane Amplifying Note Hire of Tug Amplifying Note Hard and Foreshore Amplifying Note Import General Manifest International Maritime Dangerous Goods Less than Container Load License Fee Amplifying Note Mooring Amplifying Note Miscellaneous Craft Amplifying Note Ministry of Communications Ministry of Defence Outer Anchorage Amplifying Note Original Vessel Pilotage Amplifying Note Per Day Per Ton Per Day Port Dues Amplifying Note Per Day Per Foot Per Ton Part thereof Storage Amplifying Note Salvage Amplifying Note Supply of Water Amplifying Note Towage Amplifying Note Twenty Equivalent Unit Wharfage Amplifying Note.

Page 22

Vous aimerez peut-être aussi