Académique Documents
Professionnel Documents
Culture Documents
Before you start ensure you are runnin There should only be a line with File, Edit, View etc at the top of the screen. If you can than this then click on "View" from the top line above and select "Full Screen" from the
This quiz contains 25 questions on Warning Signs and Shut in Procedures which will h prepare for your next Well Control School. Select a question from the Question Bank and choose from the answers given.
To select a question simply click on the appropriate button. Take your time answering you only get one go at each question.
To answer simply click on the "SELECT" button to the left of your choice for the questi
If you have answered correctly you will be told so and your score will be adjusted acco
If you have answered incorrectly you will get a brief explanation of how to tackle the qu but will not get a second crack at it.
Each time you return to the Question Bank you will be able to see your running score. Good Luck.
efore you start ensure you are running on full screen. c at the top of the screen. If you can see more ove and select "Full Screen" from the drop down menu.
Percentage
Percentage Score
#DIV/0!
SCORE
L DONE
QUESTION ONE
Which of the following is the first reliable indication that the well is kicking?
A: Increase in torque B: Gas cut mud C: Increase in flow rate D: Decrease in pump pressure E: Decrease in string weight
NOT CORRECT
QUESTION TWO
If the mud volume displaced is not equal to pipe displacement, what should you do pri to flow checking the well?
A: Stop tripping, call mud logger B: Stop tripping, spot a hi vis pill then continue to POOH C: Keep pulling slowly & keep watching the trip tank D: Stop tripping & install a full opening safety valve E: Stop tripping, shear pipe & call for help
T CORRECT
nd here that is to
QUESTION THREE
During drilling operations your derrickman informs you of an unusual pit level increase What is the safest response.
A: Stop drilling & circulate bottoms up B: Ignore it if your instruments show everything is normal C: Pull up, shut off pumps & check for flow D: Tell him to check it out & call you back if no change E: Reset pit level & flow show indicators
T CORRECT
nd here that is to
QUESTION FOUR
Swabbing is likely to occur:
A: When the mud viscosity is high B: When the bit is "balled" C: When the pipe is pulled too fast D: When the BHA has small clearance in the hole E: All of the above
T CORRECT
QUESTION FIVE
Which of the following best describes the Hard Shut In? R/C refers to the Remote Choke on the Choke Manifold Side Outlet refers to the HCR or Failsafe valves located on the BOP stack
A: With the R/C closed; close a BOP; open a side outlet B: With the R/C closed; open a side outlet; close a BOP C: With the R/C open; open a side outlet; close the R/C; close a BOP D: With the R/C open; open a side outlet; close the BOP; close the R/C E:
T CORRECT
de Outlet
QUESTION SIX
Which of the following best describes the Soft Shut In? R/C refers to the Remote Choke on the Choke Manifold Side Outlet refers to the HCR or Failsafe valves located on the BOP stack
A: With the R/C closed; close a BOP; open a side outlet B: With the R/C closed; open a side outlet; close a BOP C: With the R/C open; open a side outlet; close the R/C; close a BOP D: With the R/C open; open a side outlet; close the BOP; close the R/C E:
T CORRECT
QUESTION SEVEN
What should the driller do when he experiences a drilling break?
A: Circulate bottoms up B: Flow check C: Reduce weight on bit D: Increase pump speed E: Both C and D
T CORRECT
nd here that is to
QUESTION EIGHT
The purpose of shutting in a well is to:
A: Stop further influx coming into the wellbore B: Allow pressures to be determined C: To function test the BOP's D: A and B E: To make sure the drill crew stay alert
The obvious answer here is to stop further influx and this is correct.
In order to successfully kill the well you need to know formation pres and this can only accurately be calculated when the well is shut in an so this is also correct.
T CORRECT
QUESTION NINE
If total losses occurred while drilling with water based mud what would you do?
A: Continue drilling blind B: Stop drilling & fill the hole with water C: Stop drilling & shut the well in D: Spot a hi-vis pill across the shoe E: Set a barite plug
T CORRECT
QUESTION TEN
Which of the following causes swabbing?
A: Improper circulating density; pumping too fast B: Going into the hole too fast; not using trip tank C: Failure to slug hole prior to POOH D: Pulling pipe too fast; insufficient trip margin E: Running in too fast; surge pressure causing losses
T CORRECT
contribute o swabbing.
QUESTION ELEVEN
Which of the following causes of well kicks is totally avoidable and due to lack of alertness by the driller?
A: Lost circulation B: Gas cut mud C: Not filling the hole with the right amount of mud D: Abnormal pressure E: Drilling breaks
The driller should be constantly monitoring the well on trips to ensur is taking the correct amount of mud for the steel removed.
T CORRECT
QUESTION TWELVE
What do you do if the hole stays full but does not take the correct amount of mud on a trip?
A: Observe; watch for flow; if none continue to POOH B: Stop; spot a hi-vis pill; continue to POOH C: Go back to bottom; circulate bottoms up D: Check for gas cut mud at surface E: Pull to the shoe; circulate gas out
If you do not get the correct hole fill on a trip out then you must run o back to bottom and circulate bottoms up as you have most likely ind a kick.
T CORRECT
p out then you must run or strip you have most likely induced
QUESTION THIRTEEN
If the well does not flow while circulating but flows when the pumps are shut down then the mud weight should be increased by approximately:
A: An amount equal to pressure loss in the annulus B: .83 ppg C: 5.83 ppg D: None of the above E:
T CORRECT
QUESTION FOURTEEN
If connection gas is noticed while drilling a reservoir what would be considered to be a good drilling practice if an increase in mud weight is not an option at this time?
A: Flow check well for longer during connections B: Increase drilling rate to get through zone quicker
C: Control drilling rate to ensure only one slug of gas in annulus at any one tim D: Try & minimise connection time E: Both C and D are correct
T CORRECT
QUESTION FIFTEEN
When the pipe is off bottom and the well kicks the recommended practice is to:
A: Install safety valve; secure well & strip to bottom B: Circulate & kill the well C: Bullhead the influx back D: Finish the trip then strip to bottom E: Run back to bottom as fast as you can
The best way to kill a well is with the bit on bottom so having shut th in you will need to strip back to bottom.
T CORRECT
QUESTION SIXTEEN
If the well does not flow while circulating but flows with the pumps shut down then mud weight should probably be increased by: Current Mud Weight = 12 ppg APL = 220 psi Well Depth = 14300 feet TVD
T CORRECT
QUESTION SEVENTEEN
Which of the following can cause a well to kick?
A: Lost circulation B: Swabbing C: Not keeping the hole full D: Insufficient mud weight E: All of the above
T CORRECT
QUESTION EIGHTEEN
Rapid movement of the drill pipe into the hole may cause high pressure increases whi could cause losses. This increase in pressure is called:
T CORRECT
QUESTION NINETEEN
Is it a good practice to conduct unscheduled pit or flow sensor drills?
A: Yes B: No C: D: E:
T CORRECT
go wrong it will and it
QUESTION TWENTY
Why should the well be closed in quickly after a kick has been detected?
A: Minimise the influx into the wellbore B: Pressures will be lower on the annulus side C: SIDPP is always higher with bigger kicks D: Both A and B are correct E: None of the above are correct
T CORRECT
the influx.
A: Yes B: No C: D: E:
T CORRECT
e installed.
A: True B: False C: D: E:
You may have to increase the mud weight but first of all you should determine whether or not this will be possible without causing losse
T CORRECT
A: Pick off bottom; stop pumping; flow check - if positive shut in B: Be alert to shut well in C: Continue drilling until at least twenty barrels have been gained in the pits D: Alert the toolpusher and let him decide what to do next E: Increase the pump speed
WENTY THREE
A driller should be aware that if he suspects the well has kicked then he must flow check and if positive shut the well in.
T CORRECT
the well has kicked then
A: The drillpipe pressure decrease B: The casing pressure decrease C: The reduction in hydrostatic pressure of the mud column D: Formation pressure being lower than hydrostatic pressure E: None of the above are correct
WENTY FOUR
ydrostatic pressure
T CORRECT
d taking a kick.
A: Increase speed of pulling each stand B: Water back the mud to a lighter weight C: Add mud weight or trip margin D: Leave mud weight as it is & continue to POOH E: Run or strip back to bottom & circulate the hole clean
T CORRECT
To exit click on "File" in the top left hand corner of this scre and choose "Exit" from the drop down menu that appears.
You will be asked if you wish to save changes - please sele Thanks for your time.