CONTRACT NAME: : 12Z00017 : Rehabilitation of Dike with Protection Works, Banila, Viray - Depalo, Ambayaoan, Sabangan and Cabalisian River Control Projects in Umingan, San Quintin and San Nicolas all in Pangasinan under Additional Sub-Project for Post Ondoy and Pepeng Short Term Infrastructure Rehabilitation Project (POPSTIRP), Flood Control Component,Region I : Umingan, San Quintin and San Nicolas all in Pangasinan, Region I

LOCATION OF CONTRACT

BILL OF QUANTITIES
PART A - General Item and other Requirements CP-51
Item No. DESCRITION UNIT QUANTITY UNIT PRICE (PESOS) TOTAL AMOUNT Weight (PESOS) %

Proposed Billing No. 1


TOTAL AMOUNT Weight % TOTAL AMOUNT (PESOS) 70% (PESOS) 85%

SPL-I

PROJECT BILLBOARD

l.s.

1.00 77,112.00 77,112.00 0.18 77,112.00 0.18 77,112.00

SPL-II

PROVISION FOR SAFETY AND HEALTH

l.s.

1.00 825,216.00 825,216.00 1.92 577,651.20 1.34 701,433.60

SPL-III

MOBILIZATION/ DEMOBILIZATION

l.s.

1.00 487,947.16 487,947.16 1.14 243,973.58 0.57 243,973.58

SUB-TOTAL / TOTAL FOR THIS PAGE

1,390,275.16

3.24

898,736.78

2.09

1,022,519.18

Proposed Billing No. 1


Weight %

0.18

1.63

0.57

2.38

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CONTRACT ID NO. CONTRACT NAME: : 12Z00017 : Rehabilitation of Dike with Protection Works, Banila, Viray - Depalo, Ambayaoan, Sabangan and Cabalisian River Control Projects in Umingan, San Quintin and San Nicolas all in Pangasinan under Additional Sub-Project for Post Ondoy and Pepeng Short Term Infrastructure Rehabilitation Project (POPSTIRP), Flood Control Component,Region I : Umingan, San Quintin and San Nicolas all in Pangasinan, Region I

LOCATION OF CONTRACT

BILL OF QUANTITIES
PART B - Civil Works CP-51, Sub-Project - 1
Item No. DESCRITION UNIT QUANTITY UNIT PRICE (PESOS) TOTAL AMOUNT (PESOS) Weight % (PESOS) 70%

Proposed Billing No. 1


TOTAL AMOUNT Weight % TOTAL AMOUNT (PESOS) 85%

102

RIVER EXCAVATION

cu.m.

1039.70 172.00 178,828.40 0.42 125,179.88 0.29 152,004.14

104(a)

EMBANKMENT (RIVERBED MATERIALS)

cu.m.

1039.70 150.00 155,955.00 0.36 109,168.50 0.25 132,561.75

103

STRUCTURE EXCAVATION

cu.m.

1281.75 130.00 166,627.50 0.39 116,639.25 0.27 141,633.38

511(3)

FILTER CLOTH

sq.m

3484.80 204.00 710,899.20 1.65 -

511(1)

GABION,ZINC COATED, 3x1x0.50; 132pcs

cu.m.

198.00 1,335.00 264,330.00 0.62 -

511(2)

MATTRESS,ZINC COATED, 6x2x0.30; 198pcs

cu.m.

712.80 1,339.00 954,439.20 2,431,079.30 2.22 5.66 350,987.63 0.82 426,199.27

SUB-TOTAL / TOTAL FOR THIS PAGE

Proposed Billing No. 1


Weight %

0.35

0.31

0.33

0.99

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CONTRACT ID NO. CONTRACT NAME: : 12Z00017 : Rehabilitation of Dike with Protection Works, Banila, Viray - Depalo, Ambayaoan, Sabangan and Cabalisian River Control Projects in Umingan, San Quintin and San Nicolas all in Pangasinan under Additional Sub-Project for Post Ondoy and Pepeng Short Term Infrastructure Rehabilitation Project (POPSTIRP), Flood Control Component,Region I : Umingan, San Quintin and San Nicolas all in Pangasinan, Region I

LOCATION OF CONTRACT

BILL OF QUANTITIES
PART B - Civil Works CP-51, Sub-Project - 2
Item No. DESCRITION UNIT QUANTITY (PESOS) (PESOS) (PESOS) 70%

Proposed Billing No. 1


UNIT PRICE TOTAL AMOUNT Weight % TOTAL AMOUNT Weight % TOTAL AMOUNT Weight % (PESOS) 85%

102

RIVER EXCAVATION

cu.m.

6259.50 120.00 751,140.00 1.75 525,798.00 1.22 638,469.00 1.49

104(a)

EMBANKMENT (RIVERBED MATERIALS)

cu.m.

6259.50 115.00 719,842.50 1.68 503,889.75 1.17 611,866.13 1.42

103

STRUCTURE EXCAVATION

cu.m.

1565.32 139.00 217,579.48 0.51 152,305.64 0.35 184,942.56 0.43

511(3)

FILTER CLOTH

sq.m

3590.40 204.00 732,441.60 1.70 -

511(1)

GABION,ZINC COATED, 3x1x0.50; 132pcs

cu.m.

1632.00 1,228.00 2,004,096.00 4,425,099.58 4.66 10.30 1,181,993.39 2.75 1,435,277.68 3.34

SUB-TOTAL / TOTAL FOR THIS PAGE

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CONTRACT ID NO. CONTRACT NAME: : 12Z00017 : Rehabilitation of Dike with Protection Works, Banila, Viray - Depalo, Ambayaoan, Sabangan and Cabalisian River Control Projects in Umingan, San Quintin and San Nicolas all in Pangasinan under Additional Sub-Project for Post Ondoy and Pepeng Short Term Infrastructure Rehabilitation Project (POPSTIRP), Flood Control Component,Region I : Umingan, San Quintin and San Nicolas all in Pangasinan, Region I

LOCATION OF CONTRACT

BILL OF QUANTITIES
PART B - Civil Works CP-51, Sub-Project - 3
Item No. DESCRITION UNIT UNIT PRICE QUANTITY (PESOS) (PESOS) %

Proposed Billing No. 1


TOTAL AMOUNT Weight TOTAL AMOUNT Weight TOTAL AMOUNT Weight (PESOS) 70% % (PESOS) 85% %

102

RIVER EXCAVATION

cu.m.

8334.75 101.00 841,809.75 1.96 589,266.83 1.37 715,538.29 1.67

104(a)

EMBANKMENT (RIVERBED MATERIALS)

cu.m.

8334.75 121.00 1,008,504.75 2.35 705,953.33 1.64 857,229.04 1.99

103

STRUCTURE EXCAVATION

cu.m.

3680.25 101.00 371,705.25 0.86 260,193.68 0.61 315,949.46 0.74

511(3)

FILTER CLOTH

sq.m

5332.80 204.00 1,087,891.20 2.53 -

511(1)

GABION,ZINC COATED, 3x1x0.50; 132pcs

cu.m.

2424.00 1,213.00 2,940,312.00 6,250,222.95 6.84 14.54 1,555,413.83 3.62 1,888,716.79 4.39

SUB-TOTAL / TOTAL FOR THIS PAGE

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CONTRACT ID NO. CONTRACT NAME: : 12Z00017 : Rehabilitation of Dike with Protection Works, Banila, Viray - Depalo, Ambayaoan, Sabangan and Cabalisian River Control Projects in Umingan, San Quintin and San Nicolas all in Pangasinan under Additional Sub-Project for Post Ondoy and Pepeng Short Term Infrastructure Rehabilitation Project (POPSTIRP), Flood Control Component,Region I : Umingan, San Quintin and San Nicolas all in Pangasinan, Region I

LOCATION OF CONTRACT

BILL OF QUANTITIES
PART B - Civil Works CP-51, Sub-Project - 4
Item No. DESCRITION UNIT QUANTITY UNIT PRICE (PESOS) (PESOS) %

Proposed Billing No. 1


TOTAL AMOUNT Weight TOTAL AMOUNT (PESOS) 70% Weight % TOTAL AMOUNT (PESOS) 85% Weight %

102

RIVER EXCAVATION

cu.m.

28763.74 102.00 2,933,901.48 6.83 2,053,731.04 4.78 2,493,816.26 5.80

104(a)

EMBANKMENT (RIVERBED MATERIALS)

cu.m.

28763.74 102.00 2,933,901.48 6.83 2,053,731.04 4.78 2,493,816.26 5.80

103

STRUCTURE EXCAVATION

cu.m.

4867.50 109.00 530,557.50 1.23 371,390.25 0.86 450,973.88 1.05

511(3)

FILTER CLOTH

sq.m

7814.40 204.00 1,594,137.60 3.71 -

511(1)

GABION,ZINC COATED, 3x1x0.50; 132pcs

cu.m.

3552.00 1,186.00 4,212,672.00 12,205,170.06 9.80 28.40 4,478,852.32 10.42 5,438,606.39 12.66

SUB-TOTAL / TOTAL FOR THIS PAGE

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CONTRACT ID NO. CONTRACT NAME: : 12Z00017 : Rehabilitation of Dike with Protection Works, Banila, Viray - Depalo, Ambayaoan, Sabangan and Cabalisian River Control Projects in Umingan, San Quintin and San Nicolas all in Pangasinan under Additional Sub-Project for Post Ondoy and Pepeng Short Term Infrastructure Rehabilitation Project (POPSTIRP), Flood Control Component,Region I : Umingan, San Quintin and San Nicolas all in Pangasinan, Region I

LOCATION OF CONTRACT

BILL OF QUANTITIES
PART B - Civil Works CP-51, Sub-Project - 5
Item No. DESCRITION UNIT QUANTITY (PESOS) (PESOS) %

Proposed Billing No. 1


UNIT PRICE TOTAL AMOUNT Weight TOTAL AMOUNT Weight TOTAL AMOUNT Weight (PESOS) 70% % (PESOS) 85% %

102

RIVER EXCAVATION

cu.m.

29197.25 100.00 2,919,725.00 6.79 2,043,807.50 4.76 2,481,766.25 5.77

104(a)

EMBANKMENT (RIVERBED MATERIALS)

cu.m.

29197.25 103.00 3,007,316.75 7.00 2,105,121.73 4.90 2,556,219.24 5.95

103

STRUCTURE EXCAVATION

cu.m.

3397.50 110.00 373,725.00 0.87 261,607.50 0.61 317,666.25 0.74

511(3)

FILTER CLOTH

sq.m

7972.80 204.00 1,626,451.20 3.78 -

511(1)

GABION,ZINC COATED, 3x1x0.50; 132pcs

cu.m.

3624.00 1,202.00 4,356,048.00 12,283,265.95 10.14 28.58 4,410,536.73 10.26 5,355,651.74 12.46

SUB-TOTAL / TOTAL FOR THIS PAGE

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CONTRACT ID NO. CONTRACT NAME: : 12Z00017 : Rehabilitation of Dike with Protection Works, Banila, Viray - Depalo, Ambayaoan, Sabangan and Cabalisian River Control Projects in Umingan, San Quintin and San Nicolas all in Pangasinan under Additional Sub-Project for Post Ondoy and Pepeng Short Term Infrastructure Rehabilitation Project (POPSTIRP), Flood Control Component,Region I : Umingan, San Quintin and San Nicolas all in Pangasinan, Region I

LOCATION OF CONTRACT

BILL OF QUANTITIES
PART B - Civil Works CP-51, Sub-Project - 6
Item No. DESCRITION UNIT QUANTITY

Proposed Billing No. 1


UNIT PRICE TOTAL AMOUNT Weight TOTAL AMOUNT Weight % TOTAL AMOUNT Weight % (PESOS) (PESOS) % (PESOS) 70% (PESOS) 85%

102

RIVER EXCAVATION

cu.m.

4310.45 101.00 435,355.45 1.01 304,748.82 0.71 370,052.13 0.86

104(a)

EMBANKMENT (RIVERBED MATERIALS)

cu.m.

4310.45 113.00 487,080.85 1.13 340,956.60 0.79 414,018.72 0.96

103

STRUCTURE EXCAVATION

cu.m.

798.50 104.00 83,044.00 0.19 58,130.80 0.14 70,587.40 0.16

511(3)

FILTER CLOTH

sq.m

1531.20 204.00 312,364.80 0.73 -

511(1)

GABION,ZINC COATED, 3x1x0.50; 132pcs

cu.m.

696.00 1,201.00 835,896.00 2,153,741.10 1.95 5.01 703,836.21 1.64 854,658.26 1.99

SUB-TOTAL / TOTAL FOR THIS PAGE

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS CONTRACT ID NO. CONTRACT NAME: : 12Z00017 : Rehabilitation of Dike with Protection Works, Banila, Viray - Depalo, Ambayaoan, Sabangan and Cabalisian River Control Projects in Umingan, San Quintin and San Nicolas all in Pangasinan under Additional Sub-Project for Post Ondoy and Pepeng Short Term Infrastructure Rehabilitation Project (POPSTIRP), Flood Control Component,Region I : Umingan, San Quintin and San Nicolas all in Pangasinan, Region I

LOCATION OF CONTRACT

BILL OF QUANTITIES
PART B - Civil Works CP-51, Sub-Project - 7
Item No. DESCRITION UNIT QUANTITY (PESOS) (PESOS) % (PESOS) 70% (PESOS) 85%

Proposed Billing No. 1


UNIT PRICE TOTAL AMOUNT Weight TOTAL AMOUNT Weight % TOTAL AMOUNT Weight %

102

RIVER EXCAVATION

cu.m.

1776.25 101.00 179,401.25 0.42 125,580.88 0.29 152,491.06 0.35

104(a)

EMBANKMENT (RIVERBED MATERIALS)

cu.m.

1776.25 107.00 190,058.75 0.44 133,041.13 0.31 161,549.94 0.38

103

STRUCTURE EXCAVATION

cu.m.

881.00 164.00 144,484.00 0.34 101,138.80 0.24 122,811.40 0.29

511(3)

FILTER CLOTH

sq.m

1742.40 204.00 355,449.60 0.83 -

511(1)

GABION,ZINC COATED, 3x1x0.50; 132pcs

cu.m.

792.00 1,220.00 966,240.00 1,835,633.60 2.25 4.27 359,760.80 0.84 436,852.40 1.02

SUB-TOTAL / TOTAL FOR THIS PAGE

TOTAL AMOUNT 70%

13,940,117.68

32.44 Percent Accomplished

TOTAL AMOUNT 85%

16,858,481.70

39.23 Percent Accomplished

Note: 70% and 85% on Items River Excavation, Embankment and Structure Excavation
Submitted by: WERR CORPORATION INTERNATIONAL (Name of Firm) ROGER C. CAS (Name of Signatory) PRESIDENT (Position/Title) Date: