SPECIAL EDITORIAL FEATURE: THE OLEARY CHRONICLES

Arthur F. OLeary is a regular contributor and editorial advisor to Design Cost Data Magazine. Each issue of DCD presents articles by Arthur on pertinent industry topics and is a reader favorite. As a benefit to our newer readers, following are two of Arts past articles that have appeared in DCD: Coping With Changes During Construction andBuried Defects Could Mean Future Trouble. Subscribers interested in past articles of Arthur can visit www.dcd.com or call DCD at 800-533-5680. Arthur F. OLeary FAIA, MRIAI is the author of A Guide to Successful Construction Administration and coauthor with James Acret, Esq of Jobs From Hell and How To Avoid Them. Please email art@dcd.com with any suggestions of topics you would like to see covered on the practice of architecture or construction law in future issues of DCD.

Click Here to Subscribe Today for Your FREE DCD Magazine Subscription

COPING WITH CHANGES DURING CONSTRUCTION Keeping the Confusion Under Control and Limiting Disputes
Arthur O'Leary, FAIA, MRIAI It is seldom that any construction contract can be pursued from start to finish without some changes having to be made. This is in spite of the best of intentions of all parties. Despite stories about fat contractor profits in changes during construction, in reality they are an onerous economic burden on all concerned. Contractors often have difficulty in breaking even on changes. Some of the changes originate with the owner who finds that the scope of the project must be modified to reflect changes in the buildings ultimate use or for important economic reasons. Also, owners are entitled to change their minds. Other changes are caused by the necessity of correcting errors in the contract documents or to comply with evolving building code requirements. Sometimes specified materials or equipment are unavailable at the time of purchase. Projects plagued by numerous changes can become mired in confusion if they are not administered in an orderly manner. Serious problems arise when multitudes of changes are in various stages of progress. Some in the stages of deciding what to do, redesign or engineering, pricing, reconsidering, negotiation of price, contention about responsibility, approval in part, final approval, or cancelation. Some changes will have a profound effect on scheduling while others will have unexpected effects on interfacing trades. Some parts of the work may have to be

deferred while awaiting final decisions and ultimate approvals of proposed changes. In some cases the proposed changes, after careful consideration, are canceled, and the deferred work then becomes critical to the time schedule. Often, controversy develops among owner, architect, contractor, subcontractors, material suppliers, and separate contractors in respect to financial responsibility for changes that had to be made as well as their detrimental time and cost consequences. Anything that can be done to lessen the volume of changes or to simplify procedures for their administration will be a valuable advancement in efficient and economic construction. Owners Right to Make Changes Neither party has an inherent right to change any of the terms and conditions of a validly executed contract unless the contract itself contains provisions that specifically allows for changes. A construction contract would be impractical if it did not allow the owner to make changes in certain circumstances during the course of construction. Thus, construction contracts generally contain a change order procedure. This article is based on the procedures set out in the AIA standard form contracts for architectural services and construction, including the AIA general conditions. (Note 1) How Changes Become Necessary Owners need to change their original program when there are unanticipated changes in their thinking, changes in their economics, or changes in their circumstances. It would be inadvisable, improvident, and inflexible to continue with all aspects of the proposed construction if it is physically possible and economically feasible to adjust the program to the changed conditions. Contractors discover physical or economic situations, usually unanticipated, that would make it imprudent or impossible to follow the contract documents. So, they make suggestions for changing the contract requirements. They also offer recommendations in the interest of value engineering applications. Architects find it necessary to recommend changes in the contract documents in response to unforeseen situations and to improve the project. If the architect becomes aware of errors in the contract documents, it would be unconscionable not to expose them for correction. Some other sources of necessary changes are unexpected soil conditions, weather damage such as wind and rain, natural disasters such as earthquake, labor and material shortages, and fire and explosion. The construction contract allocates most of these risks between the owner and contractor and some are covered by

insurance. Originating a Change Order A handy AIA form for starting the change order process is the Work Changes Proposal Request. (Note 2) It is a one page form that identifies the change and all the parties involved in the contract. The form is prepared by the architect and is directed to the contractor. It is essentially a request for a price and time proposal for carrying out the proposed change. A copy of it should be sent to all parties who are involved and a record kept of all recipients. There is no real necessity to use the AIA form as long as all the necessary information is included in the letter or office form used. The Proposal Request is not an authorization to do the work. It is not a change order. It is only a request for information which will be needed by the owner and architect in making the decision to go ahead with the change, modify it, or to cancel it. The form includes a time limit for the contractors submission of the proposal or for a commitment of the date on which the completed Proposal Request will be submitted. The Proposal Request needs to be signed only by the architect. Each Proposal Request should be serially numbered and recorded in a Change Order Log. The Change Order If the Proposal Request is acceptable to the owner, or becomes acceptable after adjustment of the scope, negotiation of the price and/or the contract time, then the Change Order can be prepared. AIAs Change Order form (Note 3) covers all the necessary details. After execution by the owner and contractor, and countersigned by the architect, it becomes a modification of the construction contract. It authorizes the contractor to do the work and obligates the owner to pay for it. Any additional drawings and/or specifications needed to explain the change should be attached to the change order. Change in Contract Price. Any change, up or down, in the contract price or unit prices should be agreed and entered into the change order form. Change in Contract Time. Any change, up or down, in the contract time should be agreed and entered into the change order form. If there is no change in time then the change order should state, No change in Contract Time or Zero (0) Days. It is a serious mistake to leave the time blank, as it will often result in a dispute. The owner will assume that the blank means no change in time, while the contractor reasons that the blank means it will be discussed later. When there is to be a change in contract time only but with no change in contract price, it is good practice to handle it as a change order complete with a change

order form and signatures of the owner and contractor. The form should clearly state the change in contract time and contract price unchanged. Pricing and Billing of Change Orders Much of the dissatisfaction with change orders is centered around the cost. Owners often assume that contractors charge inordinately large amounts for change order work. The sad fact is that work will cost more when it is not done in sequence with the original work. Also, change order work is cost-analyzed more carefully than work done under the original overall bid. Each change order will be charged with discrete amounts accounted for under each heading of labor, material, delivery, subcontracts, taxes, coordination, supervision, permits, testing, insurance, bond, overhead, and profit. Change order work will often cost 10 to 15 percent more than if it had been included in the original bid. This is for several reasons: 1. Lack of a competitive environment. 2. Inability to easily fit the change into the existing schedule. 3. The inordinate amount of paperwork and distraction experienced by the contractor. Deductive Change Orders Unit prices for adding many materials and operations will be different from those for deducting on account of the effect of associated fixed costs. It is quite common that unit prices for adding will be more than for deducting and higher for small quantities than for large quantities. For similar reasons, it is customary for contractors to attribute profit and overhead to additive but not deductive change orders. Construction Change Directives Some change orders, after preparation by the architect, are acceptable to the owner but not to the contractor. The contractor could be dissatisfied with the change in work, contract price, or time, or both. Such a change order will be signed by the owner and architect but not by the contractor. According to the AIA General Conditions, A201-1997, the contractor is obligated to go ahead with the work, with the price and time adjustments to be determined later by the architect utilizing guidelines set out in Article 7.3. This type of change should be administered by means of a Construction Change Directive. (Note 4) At any time that the contractor later agrees to its terms or mutual agreement is obtained by adjustment of its terms, it is then deemed to be a change order. In the event that the contractor finds it impossible to accept the architects determination of changed cost and time, the contractors recourse is to mediation and arbitration. (A201, Art 4.3 and 4.4) Consent of Surety On projects where the contractor is bonded, the architect should be alert to any conditions or situations that would give the surety a legal excuse to evade bond

coverage. Bonding companies base their bond premium on the contract price, which they use as a measure of their financial loss exposure. When the accumulation of change orders changes the suretys financial exposure to a significant degree, the bonding company might claim to be exonerated from further obligation. Under usual bond language, the owner is allowed to make changes but might have to pay additional bond premium to cover the value of changes. The simple way of keeping the bonding company informed is to send it a copy of all executed change orders. Architects Minor Changes The architect is entitled to make minor changes in the work not involving adjustments in the contract price or time. (Note 5) Such changes must be consistent with the contract documents and must be in writing. A change order could be issued and the owners and contractors signatures would preclude either from asserting later claims concerning the scope of the change, cost, or time. Some Improper Ways to Order Changes A change in the contract can only be made by an agreement between the owner and contractor. Thus, architects must be careful when carrying out their contract administration duties that they do not purposely or inadvertently create the erroneous impression that they are ordering or authorizing changes in the contract. Some ordinary situations are fraught with this possible hazard: 1. In the reviewing, correcting, and approving of shop drawings, any change in the contract requirements should be identified and processed as a change order. The architect is not empowered by the contract to require anything not in the contract documents. 2. In preparing field reports of site visitations, avoid ordering work that is not clearly required by the contract documents. New requirements can only be ordered by a change order agreed by owner and contractor. (Note 6) 3. In issuing supplemental instructions, avoid changing the contract requirements. (Note 7) 4. Issuance of Changed Drawings or Specifications. Any changes that elaborate on the original requirements or add new requirements should be clearly identified so change orders may be priced, prepared, and agreed by owner and contractor. 5. Casual conversations by owner or architect at the jobsite should be carefully monitored so the contractor or site superintendent is not left with the erroneous concept that contract changes have been sanctioned. The Change Order Log The architect is now required to maintain records relative to changes in the work. This is a new requirement in the latest edition of AIAs owner-architect agreement. (Note 8) The AIA has not as yet devised a form of change order log but it should not be too difficult to invent a schedule in which to record dates and status of all change order requests, proposals, reviews, and approvals as the documentation is sent to

and received from owner, contractor, consulting engineers, and others involved in the process. The main objectives will be to know the status of the contract sum and time at all times as well as the status of all change orders in process. Informal Changes Some changes will occasionally occur outside the formal process. These are highly susceptible to dissatisfaction and controversy and should be avoided if at all possible. Contractors Unauthorized Changes normally become known only after discovery by the owner or architect. These would be usually in the form of covert deviations from the contract documents. Contractors sometimes solve practical problems without consultation with the owner or architect. Sometimes the changes are for the purpose of reducing the production cost and increasing profit. Experienced contractors are well aware that there is little or no chance of getting paid for this type of change and are fortunate if the work, after discovery, is allowed to remain. Sometimes, after negotiation, the contractor will be required to offer a credit in lieu of removal and replacement, at the option of the owner. (Note 9) Unwritten Change Orders. During construction some owners visiting the jobsite might enter into informal discussions with the contractor or job superintendent. The owner might ask the contractor to move a door opening, change a window, add an electrical outlet, or raise a ceiling. The contractor assents, assuming that the paperwork will catch up in due course of time. The owner is pleased with the ease of dealing with the contractor but fails to reach an agreement on costs and time. Later, after the changed work is carried out, the contractor quotes the cost and asks for additional time, say three days. At this point the owner expresses the view that the work would not have been authorized at this price and definitely would not be approved if the project time must be extended three days. Some owners in this situation would refuse to pay for the work, since there is no written change order as required by the contract. Most judges and arbitrators would not enforce this provision, however, if the extra work was one with the owners knowledge and consent. Additional Uses for the Change Order Process The change order process can conveniently be used to formalize all adjustments in the contract work, cost, or time, such as: Owners carrying out of contractors work (A201, 2.4.1) Resolution and accounting of contract allowances (A201, 3.8.2.3) Cost differences resulting from owners rejection of subcontractors (A201, 5.2.3) Cost of property insurance ordered by contractor and charged to owner (A201, 11.4.1.2) Cost of insurance charged to contractor (A201, 11.4.4) Cost of replacing insured damaged property (A201, 11.4.9) Cost of uncovering and replacing work which was not required to be inspected and which after uncovering proved to be in accordance with the contract

documents (A201, 12.1.2) Reconciliation of contractors requests for additional time due to conditions determined by the architect to be justified for delay (A201, 8.3.1) Owners acceptance of uncorrected defective or non-conforming work, with or without a credit, should be formalized with a change order. (A201, 12.3.1) Notes 1. General Conditions of the Contract for Construction, AIA Document A201-1997. 2. Work Changes Proposal Request, AIA Document G709-2001. 3. Change Order, AIA Document G701-2000. 4. Construction Change Directive, AIADocument G714-2001. 5. A201-1997, Subparagraph 7.4.1. 6. Field Report, AIA DocumentG711-1972. 7. Architects Supplemental Instructions, AIA Document G710-1992. 8. Standard Form of Agreement Between Owner and Architect With Standard Form of Architects Services, AIA Document B141-1997, Subparagraph 2.6.5.4. 9. A201-1997, Subparagraph 12.3.1. *** For additional information on the administration of change orders, see Chapter 14, Change Orders in A Guide to Successful Construction Effective Contract Administration, by Arthur F. OLeary, FAIA, MRIAI.
BACK TO TOP

BURIED DEFECTS COULD MEAN FUTURE TROUBLE Who Pays for Uncovering and Correction of the Work?
By Arthur F. OLeary, FAIA, MRIAI Years after a building is built, occupied, and operated successfully, a hidden defect comes to light. Something that was not in conformance with the contract documents, the building code, or accepted workmanship standards. It could be something very easy to fix, such as a copper piping joint inadvertently left unsoldered. But the cost to find the defect, uncover the joint, and restore all the damaged finishes might be quite extensive. Inconvenience to the building users could be enormous, depending on the location of the repair and the use of the building. Consequential damage to other building elements or contents could add heavily to the cost. Other more significant defects, such as inadequate structural members, inferior materials, or other major deviations from the buildings specified standards, could be extremely difficult and costly to rectify while the building remains in use. Repairs that require complete vacation of the building are even more disruptive

and expensive. Construction Inspection Most of these types of defects are avoided entirely by the normal systems of inspection during construction. Government building inspection furnishes a basic protection, but it has its limitations. It is only a spot-check at best, not a comprehensive examination. Furthermore, it is for the sole purpose of testing compliance with the building code. The building inspector will not be judging the work against a higher standard that might be specified in the contract documents. The contractor is the most significant figure in quality control on any building site. The contractor and its superintendent set the standards for their own personnel as well as for their subcontractors and suppliers. The contractor warrants that the work will be in accordance with the requirements of the contract documents. (A201-1997, 3.5.1) The architect and engineering consultants are also present in a position of oversight through their periodic jobsite visits. Projects on which the AIA general conditions are a part of the contract, have provisions to facilitate the architects access and examination of the work in progress. (A201-1997, 3.16) Sometimes the construction progress gets ahead of the architects program of site visitations or important work is completed and covered between the architects scheduled visits. The result may be that critical work gets covered up before the architect has seen it. Architects are frequently suspicious of the motives of contractors who cover their work with undue haste. Specifying Work to Be Left Open for Inspection The architect must decide at the time of specifying which portions of the work are important enough to specify leaving open for the architects or engineering consultants examination before they are finally covered. This might include plumbing piping or electrical conduits that will be buried in trenches, roof sheathing that will be covered with roofing, or structural connections that will be hidden behind plaster or other finishes. Subterranean waterproofing is often kept open for examination before backfilling. When work is left open for the architects inspection, the burden is on the architect to examine the work promptly and not unduly disrupt the contractors progress schedule. If a contractor covers work that was previously specified to be left open for examination, then the architect may request in writing that the work be uncovered for inspection. The contractor must pay for the uncovering and reinstatement of the finishes even if the work, upon inspection, proves to be not defective. This is also the case if the architect had merely requested, even though not specified in the contract documents, that the work be left open for

inspection. (A201-1997, 12.1.1) No extension of the contract time should be granted. When the architect has neither specified nor requested the work to be left open for inspection, the situation is different. If the uncovered work proves to be defective, then the contractor must pay all the costs of uncovering, correcting the work, and reinstating the finishes with no extension of the contract time. On the other hand, however, if the uncovered work is not defective, then the owner must pay all the related costs as well as grant an appropriate extension of the contract time. (A201-1997, 12.1.2) This places the architect in a vulnerable position with the client who might feel that the architect used poor judgment in ordering the inspection. The client might also criticize the architect for not previously specifying or requesting the work to be left open for examination. A persistent client might also raise the question of the frequency and adequacy of the architects site visitations. The cost of uncovering the work and reinstating the finishes could be very expensive, depending on the situation involved. In addition, the contract time extension might be costly as well a inconvenient. Discussion with the Owner An architect would be foolish indeed to order the uncovering of work without a complete prior discussion with the owner of the possible consequences. The architect would have had to convince the owner that it was necessary to examine the work. Normally the reason that an architect would ask to expose covered work is if there was some reasonable suspicion or concern that it was improperly done. When the integrity of the building or one of its systems might be materially compromised if improperly executed, then the architect should explain this and all its ramifications to the client. The client should realize that the cost of uncovering important work might be less in the long run than living with the uncertainty of the condition of uninspected work. Accepting Defective Work Work not conforming to the contract documents is considered to be defective. (A201-1997, 3.5.1) When the work is found to be defective, the owner or architect might decide to accept it anyway, if it will satisfy realistic requirements for service, longevity, capacity, and appearance. However, only the owner has the power to accept defective work. (A201, 12.3.1) Although the architect lacks the power to make this decision, the architects assistance in making the decision would be considered valuable by most owners. The architect should completely explain the advantages and disadvantages of retaining the defective work. In most cases it would be appropriate for the architect to make a recommendation and be prepared to explain it. However, the final decision belongs to the owner.

If defective work is allowed to remain, the contract sum will be equitably adjusted. Naturally, the owner could not decide to accept defective work that is a building code violation or if it affects safety or the integrity of mechanical, electrical, or structural systems.
Title: Impact of Construction Material on Environment - (Steel & Concrete) Authors: Kare, Sridhar
Lomite, Heera

Department: Hgskolan i Bors/Ingenjrshgskolan (IH) Issue Date: 16-Mar-2009 Series/Report no.: Magisteruppsats Media type: text Keywords: impacts on environment recycling reuse steel concrete material select co2 emissions life cycle assessment Abstract: All around the globe the consumption of raw materials by the construction industries is accumulating day by day resulting with an depletion of natural resources, increasing the environmental impacts and CO2 emissions all over the surroundings. Today steel and concrete are widely used and are dominating construction materials in construction industry. These two construction materials are different products and have distinct production flow with significant impact on the environment. The amount of embodied energy and operational energy which is consumed in the process of production, recycling and reuse are becoming increasingly more important in the construction industries due to the potential shortage of natural resources in the near by future and due to the inflation in the energy prices. This masters thesis determines some of the problems of antagonistic environmental impacts due to the use of steel and concrete in the construction industries. To mitigate these environmental impacts there are two technology and policy strategies summarized in this thesis. i. Reduce consumption; and ii. Material selection to reduce impacts. i. Reduce consumption: All around the globe the consumption of materials is growing day by day with an increase in the population resulting with a depletion of virgin materials. This depletion of virgin materials can be reduced with the help of recycling and reuse of the structural members. Recycling of structural members is already practiced widely than reuse; reuse of the structural members additionally reduces the consumption of virgin materials. High level of reuse of the structural materials can be achieved by establishing design standards and regulations for structural sections, and developing a market for reusable structural sections. ii. Material selection to reduce impacts: For the selection of construction materials with minimum impact on the environment the designers needs to have apropos education or tools. The main areas for augmentation are identified as education of designers, and standardization and simplification of selection tools like Life Cycle Assessment (LCA). Some of the main recommendations are: LCA tools standardization; reduce the impact sections and make these impact sections comprehendible and integrate uncertainty data and educating designers about material selection tools with organized programs.

1.8 The Changing Environment of the Construction Industry


The construction industry is a conglomeration of diverse fields and participants that have been loosely lumped together as a sector of the economy. The construction industry plays a central role in national welfare, including the development of residential housing, office buildings and industrial plants, and the restoration of the nation's infrastructure and other public facilities. The importance of the construction industry lies in the function of its products which provide the foundation for industrial production, and its impacts on the national economy cannot be measured by the value of its output or the number of persons employed in its activities alone. To be more specific, construction refers to all types of activities usually associated with the erection and repair of immobile facilities. Contract construction consists of a large number of firms that perform construction work for others, and is estimated to be approximately 85% of all construction activities. The remaining 15% of construction is performed by owners of the facilities, and is referred to as forceaccount construction. Although the number of contractors in the United States exceeds a million, over 60% of all contractor construction is performed by the top 400 contractors. The value of new construction in the United States (expressed in constant dollars) and the value of construction as a percentage of the gross national products from 1950 to 1985 are shown in Figures 1-6 and 1-7. It can be seen that construction is a significant factor in the Gross National Product although its importance has been declining in recent years. Not to be ignored is the fact that as the nation's constructed facilities become older, the total expenditure on rehabilitation and maintenance may increase relative to the value of new construction.

Figure 1-6: Value of New Construction in the United States, 1975-1995

Figure 1-7: Construction as Percentage of Gross Domestic Product in the United States, 1975-1995

Owners who pay close attention to the peculiar characteristics of the construction industry and its changing operating environment will be able to take advantage of the favorable conditions and to avoid the pitfalls. Several factors are particularly noteworthy because of their significant impacts on the quality, cost and time of construction.

New Technologies
In recent years, technological innovation in design, materials and construction methods have resulted in significant changes in construction costs. Computer-aids have improved capabilities for generating quality designs as well as reducing the time required to produce alternative designs. New materials not only have enhanced the quality of construction but also have shortened the time for shop fabrication and field erection. Construction methods have gone through various stages of mechanization and automation, including the latest development of construction robotics.

The most dramatic new technology applied to construction has been the Internet and its private, corporate Intranet versions. The Internet is widely used as a means to foster collaboration among professionals on a project, to communicate for bids and results, and to procure necessary goods and services. Real time video from specific construction sites is widely used to illustrate construction progress to interested parties. The result has been more effective collaboration, communication and procurement. The effects of many new technologies on construction costs have been mixed because of the high development costs for new technologies. However, it is unmistakable that design professionals and construction contractors who have not adapted to changing technologies have been forced out of the mainstream of design and construction activities. Ultimately, construction quality and cost can be improved with the adoption of new technologies which are proved to be efficient from both the viewpoints of performance and economy.

Labor Productivity
The term productivity is generally defined as a ratio of the production output volume to the input volume of resources. Since both output and input can be quantified in a number of ways, there is no single measure of productivity that is universally applicable, particularly in the construction industry where the products are often unique and there is no standard for specifying the levels for aggregation of data. However, since labor constitutes a large part of the cost of construction, labor productivity in terms of output volume (constant dollar value or functional units) per person-hour is a useful measure. Labor productivity measured in this way does not necessarily indicate the efficiency of labor alone but rather measures the combined effects of labor, equipment and other factors contributing to the output. While aggregate construction industry productivity is important as a measure of national economy, owners are more concerned about the labor productivity of basic units of work produced by various crafts on site. Thus, an owner can compare the labor performance at different geographic locations, under different working conditions, and for different types and sizes of projects. Construction costs usually run parallel to material prices and labor wages. Actually, over the years, labor productivity has increased in some traditional types of construction and thus provides a leveling or compensating effect when hourly rates for labor increase faster than other costs in construction. However, labor productivity has been stagnant or even declined in unconventional or large scale projects.

Public Scrutiny
Under the present litigious climate in the United States, the public is increasingly vocal in the scrutiny of construction project activities. Sometimes it may result in considerable difficulty in siting new facilities as well as additional expenses during the construction process itself. Owners must be prepared to manage such crises before they get out of control. Figure 1-8 can serve to indicate public attitudes towards the siting of new facilities. It represents the cumulative percentage of individuals who would be willing to accept a new industrial facility at various distances from their homes. For example, over fifty percent of the people surveyed would accept a tenstory office building within five miles of their home, but only twenty-five percent would accept a large factory or coal fired power plant at a similar distance. An even lower percentage would accept a hazardous waste disposal site or a nuclear power plant. Even at a distance of one hundred miles, a significant fraction of the public would be unwilling to accept hazardous waste facilities or nuclear power plants.

Figure 1-8: Public Acceptance Towards New Facilities (Reprinted from Environmental Quality - 1980, the Eleventh Annual Report of the Council on Environmental Quality, U.S. Government Printing Office, Washington, DC, December 1980.)

This objection to new facilities is a widespread public attitude, representing considerable skepticism about the external benefits and costs which new facilities will impose. It is this public attitude which is likely to make public scrutiny and regulation a continuing concern for the construction industry.

International Competition
A final trend which deserves note is the increasing level of international competition in the construction industry. Owners are likely to find non-traditional firms bidding for construction work, particularly on large projects. Separate bids from numerous European, North American, and Asian construction firms are not unusual. In the United States, overseas firms are becoming increasingly visible and important. In this environment of heightened competition, good project management and improved productivity are more and more important. A bidding competition for a major new offshore drilling platform illustrates the competitive environment in construction. As described in the Wall Street Journal: Through most of the postwar years, the nation's biggest builders of offshore oil platforms enjoyed an unusually cozy relationship with the Big Oil Companies they served. Their top officials developed personal friendships with oil executives, entertained them at opulent hunting camps- and won contracts to build nearly every major offshore oil platform in the world....But this summer, the good-old boy network fell apart. Shell [Oil Co.] awarded the main contract for [a new] platform - taller than Chicago's Sears Tower, four times heavier than the Brooklyn Bridge - to a tiny upstart. The winning bidder arranged overseas fabrication of the rig, kept overhead costs low, and proposed a novel assembly procedure by which construction equipment was mounted on completed sections of the platform in order to speed the completion of the entire structure. The result was lower costs than those estimated and bid by traditional firms. Of course, U.S. firms including A/E firms, contractors and construction managers are also competing in foreign countries. Their success or failure in the international arena may also affect their capacities and vitality to provide services in the domestic U.S. market.

Contractor Financed Projects


Increasingly, some owners look to contractors or joint ventures as a resource to design, to build and to finance a constructed facility. For example, a utility company may seek a consortium consisting of a design/construct firm and a financial investment firm to assume total liability during construction and thereby eliminate the risks of cost escalation to ratepayers, stockholders and the management. On the other hand, a local sanitation district may seek such a consortium to provide private ownership for a proposed new sewage treatment plant. In the former case, the owner may take over the completed facility and service the debt on construction through long-term financing arrangements; in the latter case, the private owner may operate the completed facility and recover its investment through user fees. The activities of joint ventures among design, construction and investment firms are sometimes referred to as financial engineering. This type of joint venture has become more important in the international construction market where aggressive contractors often win contracts by offering a more attractive financing package rather than

superior technology. With a deepening shadow of international debts in recent years, many developing countries are not in a position to undertake any new project without contractor-backed financing. Thus, the contractors or joint ventures in overseas projects are forced into very risky positions if they intend to stay in the competition.

ScienceDaily (Feb. 18, 2009) A team of researchers from the Polytechnic University of Catalonia (UPC) has developed a method that makes it possible to evaluate the environmental impacts caused during the construction of buildings in advance. Before beginning the works, with just the project data, the new method makes it possible to predict up to 37 environmental impacts. This information, according to the creators, could help improve environmental management in the construction processes.
Share This:

107

Related Ads:

Construction Green Building Environment Engineering


See Also: Matter & Energy

Civil Engineering Construction Engineering


Earth & Climate

Environmental Issues Environmental Policy Sustainability


Reference

Environmental impact assessment Environmental engineering Engineering geology Remediation


"This model identifies in advance the environmental impacts associated with carrying out a particular construction project, making it possible to program the inclusion of environmental improvement procedures or apply preventive measures right from the project study, planning and preparation phases", Marta Gangolells, a member of the Group of Construction Research and Innovation

(GRIC) at UPC and one of the authors of the study, explained to SINC. The technique can be applied to the construction of both single-family homes and apartment buildings. Researchers began by classifying the environmental aspects into nine categories: emissions into the air, water spills, waste generation, soil pollution, resource consumption, local impacts, impacts associated with transportation, effects on biodiversity and emergency situations and incidents. This division is based on the EMAS (Eco-Management and Audit Scheme) Community Regulations, a piece of legislation that aims to improve organizations' environmental performance. To increase the level of precision, the researchers subdivided these categories into specific impacts. For example, the "emissions into the air" category includes two environmental impacts: greenhouse gas generation (emissions from the machinery and vehicles used on the work site) and emissions composed of volatile organic compounds (VOC) and chlorofluorocarbons (CFC). New environmental indicators The team has identified 37 environmental impacts, according to the online version of the magazine Building and Environment, and for each one they have developed an "environmental forecast indicator". This parameter, which is based on the information in the project documents, makes it possible to evaluate the impacts objectively. Continuing with the example, the greenhouse gas emissions can be estimated by analyzing the volume of material dug per square meter of construction surface area and the existence of special machinery or electricity generators on the work site. On the other hand, the VOC and CFC emissions are forecast with the percentage of synthetic paints and varnishes used. The project measurement status also includes other practical information, such as the amount of thixotropic mud (semi-solid) used on the site, which is used as an indicator of the environmental impact from "dumping water from the construction of foundations and retaining walls". To draw up the study, financed with funds from the Ministry of Public Works, the researchers analyzed statistics from 55 new construction residential sites. By doing so, they established ranges related to the magnitude of each environmental impact (nonexistent, hardly significant, slightly significant and extremely significant). They have also confirmed the validity of the method by testing it on four new construction projects. GRIC coordinator Miquel Casals concludes that these results will offer "a major incentive to construction companies that want to follow an environmental management system, either under the umbrella of ISO 14000 standards (environmental management for companies) or the EMAS Community Regulations".