Vous êtes sur la page 1sur 8

BILLS OF QUANTITIES FOR THE COMPLETION OF SONGAMBELE AZIMIO DIPPING TANK S/NO DESCRIPTION UNIT QUANTITY RATE AMOUNT

Excavation and earthworks Excavate foundation trench not exeeding 1.5m deep commencing at stripped level at the collecting yard side Concrete blinding class 10 in foundation 50mm thick Approved qulity stone masonry wall 300mm thick in foundation bedded and jointed with sand/cement mortor 1:3 mix Backfilling the foundation trench and earth fill materials and compact to make levels under the floors Hardcore bed 150mm thick compacted to collection yard side Sub Total

m3

9.5

3,500.00

33,250.00

m2

11

9,500.00

104,500.00

m3

110,000.00

990,000.00

50

3,000.00

150,000.00

m2

48

9,000.00

432,000.00 1,709,750.00

Walling Well burnt bricks of approved quality 300mm thick wall (English Bond) 1.5m high bedded and jointed in sand/ cement mortor 1:4 mix at the collection and drying yards Insitu finishings internally 20mm sand cement thick plaster internally in two coats steel trowelled to smooth finish to surfaces of the wall 15mm sand cement thick plaster externally in two coats steel trowelled to smooth finish to surfaces of the wall

m2

50

20,000.00 1,000,000.00

m2

86

6,000.00

516,000.00

m2

100

5,000.00

500,000.00

Sub Total

2,016,000.00

Metal works Supply, erect and fix 100mm diameter GS pipes 2m high, 0.5m to be inserted into ground. The pipes should be spaced at 1.2m c/c at cattle gurd rail Supply 16mm diameter black bolts and nuts for fixing timber Supply and fix 50 x 150mm hardwood

No

16

30,000.00

480,000.00

No

48

3,000.00

144,000.00

timber Steel gates Supply and fix steel gates size 1200mm x1500mm high at the collectio and drying yards Sub Total Sub Total collected to Summury Add 5% contigencies Add 10% Supervision and Monitoring Total Cost for the Project

48

5,000.00

245,000.00

No

100,000.00

200,000.00 1,069,000.00 4,794,750.00 239,737.50 479,475.00 5,513,962.50

BILLS OF QUANTITIES FOR THE CONSTRUCTION OF VIP PIT AT LAELA

Excavations and earthworks Site clearance Excavation of the pit Concrete blinding class 10 in the foundation 50mm thick 300mm thick stone masonry foundation wall of aproved quality laid and jointed in sand cement mortor 1:3mix 230mm thick burnt brick wall of aproved quality (English Bond) bedded and jointed in sand cement mortor 1:3 mix Reinforced concrete cover to the pit class 25 reiforced with 12mm dia high yield tensile bars average thickenss of 150mm Supply and fix 12mm diameter high yiled bars Binding wires Formwork to support concrete 100mm thick hardcore

m2 m3

36 20

400.00 4,000.00

14,400.00 80,000.00

m2

20

9,500.00

190,000.00

m3

100,000.00

400,000.00

m2

32

19,000.00

608,000

m3

200,000.00

200,000.00

Kg Kg m2 m2

116 2 20 2

2,700.00 5,000.00 12,000.00 9,000.00

313,200.00 10,000.00 120,000.00 18,000.00

Sub Total Superstructure Walling: 200mm thick burnt brick wall of approved quality bedded and jointed in sand cement mortor mix 1:5 Ringbeam: Cast insitu reinforced concrete grade 25 to the ringbeam/lintel Supply and fix 12mm diameter high yiled bars Binding wires Sub Total Finishings: Cement, sand and lime plaster 20mm thick steel trowelled to smooth finish to walls internally

1,953,600.00

m2

18

17,000.00

306,000.00

m3

200,000.00

Kg Kg

50 1

2,700.00 5,000.00

135,000.00 5,000.00 446,000.00

m2

21

6,000.00

126,000.00

Ditto but 15mm thick externally 25mm thick cement sand floor screed mix ratio 1:3 stell trowelled to smooth finish Sub Total Roofing: Supply and fix 28 guge corrugated iron sheets by GALGO or as per approved manufacturer 50 x 100mm wall plate and rafters including adjoining members 50 x 75mm Purlin 25 x 200mm fascia and burge boards Sub Total Frames, Top and Painting: Fabricate, erect and fix in position hardwood door frame (Mninga) size 2100 x 700 with one labour Supply and fix Flush door to frames 2050 x 650mm Supply and fix brass hinges 100mm Barrel bolts 150mm long Fabricate erect and fix window frames size 500 x 500mm to openings Supply and fix PVC vent pipe Sub Total Painting and Decorations: Oil paint to internal walls Ditto to fascia and barge boards Apply clear varnish to frames and door surfaces Sub Total Sub Total collected to Summury Add 5% contigencies Add 10% Supervision and Monitoring Total Cost for the Project

m2

13

5,000.00

65,000.00

m2

8,000.00

32,000.00 223,000.00

m2

11

19,000.00

209,000.00

m m m

40 20 13

3,500.00 3,000.00 6,000.00

140,000.00 60,000.00 78,000.00 487,000.00

No

60,000.00

120,000.00

No Pair No.

2 3 2

110,000.00 4,000.00 1,500.00

220,000.00 12,000.00 3,000.00

No. m

2 6

35,000.00 6,000.00

70,000.00 36,000.00 461,000.00

m2 m

21 13

4,000.00 1,500.00

48,000.00 19,500.00

m2

6,000.00

24,000.00 91,500.00 3,662,100.00 183,105.00 366,210.00 4,211,415.00

BILLS OF QUANTITIES FOR THE COMPLETION OF KALEMBE DIPPING TANK S/NO DESCRIPTION UNIT QUANTITY RATE Walling: 300mm thick burnt brick wall of aproved quality (English Bond) bedded and jointed in sand cement mortor 1:3 mix 2 m to collection and drying yards walls 24 20,000.00 Insert, erect and construct by aproved quality burnt brick columns 300 x 300 x 1500mm spaced as directed by the engineer on existing walls and jointed with sand cement mortor 1:4 mix Sub Total Insitu finishings internally 20mm sand cement thick plaster internally in two coats steel trowelled to smooth finish to surfaces of the wall 15mm sand cement thick plaster externally in two coats steel trowelled to smooth finish to surfaces of the wall Plastering to dipp tank lintels, columns and the like trowelled steel to smooth finish Ditto but to plinth area

AMOUNT

480,000.00

Na

25,000.00

200,000.00 680,000.00

90

6,000.00

540,000.00

m2

93

5,000.00

465,000.00

m2 m
2

43 25

5,000.00 5,000.00

215,000.00 125,000.00

Sub Total Steel gates Supply and fix steel gates size 1200mm x1500mm high at the collectio and drying yards Slabs to collection and drying yards: Excavate foundation trench not exceeding 1.5 m deep 300mm thick stone masonry foundation wall of aproved quality laid and jointed in sand cement mortor 1:3mix 150mm thick hardcore and compact Plain concrete slab grade 20 at the entrance to collection and drying yards 100mm thick to hardcore bed Sub Total Sub Total collected to Summury Add 5% contigencies Add 10% Supervision and Monitoring Total Cost for the Project

1,345,000.00

No

100,000.00

200,000.00

3,000.00

15,000.00

m3 m2

3 6

100,000.00 9,000.00

300,000.00 54,000.00

m3

160,000.00

320,000.00 889,000.00 2,914,000.00 145,700.00 291,400.00 3,351,100.00

S/NO

BILLS OF QUANTITIES FOR THE COMPLETION OF LAELA SLAUGHTING YARD DESCRIPTION UNIT QUANTITY RATE AMOUNT Site preparation Clear collection yard area by removing all the debris and throw away from site Excavate to remove vegetable soil average depth of 150mm deep Excavate foundation trench commencing at stripped level not exceeding 1.5m deep and 400mm wode Concrete blinding class 10 in foundation 50mm thick Approved quality stone masonry 300mm thick wall, bedded and jointed in sand cement mortor mix 1:4 Backfilling the foundation trench and earth fill materials and compact to make levels under the floors Sub Total Walling 150mm thick hardcore and compact 100mm thick oversite plain concrete class 20 on top of the hardcore bed 230mm thick burnt brick wall of approved quality (English bond) bedded and jointed in sand cement mortor 1:4 with 1.5m height Fabricate, erect and construct by aproved quality burnt brick columns 300 x 300 x 1500mm spaced as per archtectural drawing provided and jointed with sand cement mortor 1:4 mix

m2

171

400.00

68,400.00

m2

171

1,000.00

171,000.00

m3

15

3,000.00

45,000.00

m2

14

9,500.00

142,500.00

m3

14

95,000.00

1,330,000.00

m3

27

3,000.00

81,000.00 1,837,900.00

m2

65

9,000.00

585,000.00

m2

65

10,000.00

650,000.00

m2

72

19,000.00

1,368,000.00

Na

14

25,000.00

350,000.00

Sub Total Finishings Internal and external plastering 20mm thick steel trowelled to a smooth finish to walls Ditto the columns Fabricate, erect and fix in position steel/grill gate doors size 1400 x 1250 mm at the collecting and entrance to slaughtering yard

2,953,000.00

m2 m2

144 25

6,000.00 6,000.00

864,000.00 150,000.00

No.

150,000.00

300,000.00

Sub Total Soak Pit Excavate pit for keeping animals' remains and the like average depth 3m and 1.5m diameter Concrete blinding class 10 in foundation 50mm thick Aproved stone masonry foundation wall 300mm thick bedded and jointed in sand cement mortoe 1:3 mix 230mm thick wall of approved quality burnt bricks, bedded and jointed in sand cement mortor 1:3 mix Reinforced concrete cover class 25 to the pit with 12mm diameter high yield tensile bars Supply and fix PVC vent pipe to the pit 150mm diameter Fabricate inspection cover to the pit 400 x 400mm

1,314,000.00

m3

14

6,000.00

84,000.00

m2

9,500.00

38,000.00

m3

100,000.00

400,000.00

m2

21

19,000.00

399,000.00

m3

1.5

260,000.00

390,000.00

12

6,000.00

72,000.00

No.

50,000.00

50,000.00

Sub Total Sub Total collected to Summury Add 5% contigencies Add 10% Supervision and Monitoring Total Cost for the Project

1,433,000.00 7,537,900.00 376,895.00 753,790.00 8,668,585.00

BILLS OF QUANTITIES FOR THE COMPLETION OF MILEPA DIPPING TANK S/NO DESCRIPTION UNIT QUANTITY RATE AMOUNT Insitu finishings internally 20mm sand cement thick plaster internally in two coats steel trowelled to smooth finish to surfaces of the wall 15mm sand cement thick plaster externally in two coats steel trowelled to smooth finish to surfaces of the wall Plastering to dipp tank lintels, columns and the like steel trowelled to smooth finish Ditto but to plinth area

103

6,000.00

818,000.00

96

5,000.00

480,000.00

m2 m2

50 30

5,000.00 5,000.00

250,000.00 150,000.00

Sub Total Steel gates Supply and fix steel gates size 1200mm x1500mm high at the collectio and drying yards Slabs to collection and drying yards: Excavate foundation trench not exceeding 1.5 m deep 300mm thick stone masonry foundation wall of aproved quality laid and jointed in sand cement mortor 1:3mix 150mm thick hardcore and compact Plain concrete slab grade 20 at the entrance to collection and drying yards 100mm thick to hardcore bed Sub Total

1,698,000.00

No

100,000.00

200,000.00

m3

3,000.00

15,000.00

m3 m2

3 6

100,000.00 9,000.00

300,000.00 54,000.00

160,000.00

320,000.00 889,000.00

Sub Total collected to Summury Add 5% contigencies Add 10% Supervision and Monitoring Total Cost for the Project

2,587,000.00 129,350.00 258,700.00 2,975,050.00

Vous aimerez peut-être aussi