Académique Documents
Professionnel Documents
Culture Documents
Quality Control
Prepared by: R.
S E V
Potential Causes
O C C
Current Controls
D E T
R P N
Actions Recommended
Resp.
Actions Taken
S E V
O C C
D E T
R P N
Goods Inward Metal Out of Spec Metal Goods Inward Metal Out of Spec Metal Die tooling procurement Die tooling procurement In-adequate material used in manufacture
Poor Finish, Insufficient strength customer complaint Poor Finish, Insufficient strength customer complaint Die Damage , Down time production loss, customer complaint Late delivery of tooling, late start to production, customer concern Misruns, Coldshuts, NCU, Customer concern Porosity after finishing operation, Loss production, Customer complaint Loss of production, short fall at finishers, customer complaint
Full spec with delivery, Every ingot colour coded QA cert with every delivery
147
Metal booked out of stores 10% audit on incoming ingot carried out at independant lab. Approved suppliers list drawn up
28
147
14
Poor design In-adequate preparation Poor tool maker, equipment out of calibration Operator Error
Only used Person 196 experienced purchasing approved tool makers tooling 14 105 Monitor casting temps Quality daily Engineer Monitor casting temps Quality daily Engineer
21
Dimensionally incorrect
7 7
1 5
2 3
0 Procedure drawn up 8 2 3 48
Operator Error
126
Procedure drawn up
126
Clipping
Clipping Damage
Poor operator control, poorly designed clipping tool Viewer error unaware of acceptance standard agreed with customer
42 Final View sheet 112 updated, Digital Images to be used 0 Final Viewers Sheets updated using digital images to high light potential problems
Final View
24 0
Issue No. 2
AQC 18