Assignment Set-1
: Amit Sadhu : :
Learning Center Code : Course Subject Semester Module No. Date of submission Marks awarded : MCA : MC0079 Computer based Optimization Methods : IV Semester : : :
Directorate of Distance Education Sikkim Manipal University 1st Floor, Syndicate House Manipal 576104
Amit Sadhu
511234788
Comments by the Subject Evaluator: ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________
Suggestions for improvement: ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________ ________________________________________________________________
Amit Sadhu
511234788
Amit Sadhu
511234788
( )
The mean of this distribution is If For ,
) (
()
,
which is the negative exponential distribution; same as the models considered earlier. and so on. .
()
If k = the variance is zero and this corresponds to a case where the service time is constant and has value . The figure below shows the way the density functions vary as k increases.
Figure Density functions vary as k increases The measures of efficiency should take into account the number of customers getting service, number having entered during any one or more of the phases, and the number yet to join. For arrivals following Poisson distribution, with mean l and service time following the k Erlang distribution with mean,
th
Amit Sadhu
511234788
( )
( )
( )
( )
( )
( )
( )
( )
Amit Sadhu
511234788
3. Explain the algorithm for solving a linear programming problem by graphical method.
Answer: 3 Linear programming (LP) is a mathematical method for determining a way to achieve the best outcome (such as maximum profit or lowest cost) in a given mathematical model for some list of requirements represented as linear equations. More formally, linear programming is a technique for the optimization of a linear objective function, subject to linear equality and linear inequality constraints. Given a polytope and a real-valued affine function defined on this polytope, a linear programming method will find a point on the polytope where this function has the smallest (or largest) value if such point exists, by searching through the polytope vertices. An Algorithm for solving a linear programming problem by Graphical Method: (This algorithm can be applied only for problems with two variables). Step I: Formulate the linear programming problem with two variables (if the given problem has more than two variables, then we cannot solve it by graphical method). Step II: Consider a given inequality. Suppose it is in the form a1x1 + a2x2 <= b (or a1x1 + a2x2 >= b). Then consider the relation a1x1+ a2x2= b. Find two distinct points (k, l), (c, d) that lie on the straight line a1x1+ a2x2= b. This can be found easily: If x1= 0, then x2 = b / a2. If x2=0, then x1 = b / a1. Therefore (k, l) = (0, b / a2) and (c, d) = (b / a1, 0) are two points on the straight line a1x1+a2x2= b. Step III: Represent these two points (k, l), (c, d) on the graph which denotes XY-axis plane. Join these two points and extend this line to get the straight line which represents a1x1+ a2x2= b. Step IV: a1x1 + a2x2= b divides the whole plane into two half planes, which are a1x1+ a2x2 <= b (one side) and a1x1+ a2x2 >= b (another side). Find the half plane that is related to the given inequality. Step V: Do step-II to step-IV for all the inequalities given in the problem. The intersection of the half-planes related to all the inequalities and x1 >= 0, x2 >= 0 , is called the feasible region (or feasible solution space). Now find this feasible region. Step VI: The feasible region is a multisided figure with corner points A, B, C, (say). Find the co-ordinates for all these corner points. These corner points are called as extreme points.
Amit Sadhu
511234788
Find the values of the objective function at all these corner/extreme points. Step VIII: If the problem is a maximization (minimization) problem, then the maximum (minimum) value of z among the values of z at the corner/extreme points of the feasible region is the optimal value of z. If the optimal value exists at the corner/extreme point, say A (u, v), then we say that the solution x1= u and x2= v is an optimal feasible solution. Step IX: Write the conclusion (that include the optimum value of z, and the co-ordinates of the corner point at which the optimum value of z exists).
Amit Sadhu
511234788
4. Determine optimal solution to the problem given below. Obtain the initial solution by VAM. Write down the differences between PERT and CPM.
Ware houses A B C D Requirement Answer 4: The initial solution obtained by VAM Ware houses A B C D Requirement Stores III 3 (17) 5 4 4 17 /0 Availability 34 /28/11/0 15 /0 12 /0 19 /0 80 I 5 3 6 4 21 II 1 3 4 1 25 Stores III 3 5 4 4 17 IV 3 4 3 2 17 Availability 34 15 12 19 80
The solution to above problem is Z = (5x6) + (1x6) + (3x17) + (3x5) + (3x15) + (3x12) + (-1x19) Z = 30 + 6 + 51 + 15 + 45 + 36 19 Z = 164 Optimal solution test: The initial solution obtained by VAM is optimal, as it pass the optimality test (m+n-1) < = no of cells occupied. Therefore, 4 + 4 - 1 <= 7 so, 7=7
Differences between PERT and CPM CPM was developed by Du Pont and the emphasis was on the trade-off between the cost of the project and its overall completion time (e.g. for certain activities it may be possible to decrease their completion times by spending more money how does this affect the overall completion time of the project?) Definition: In CPM activities are shown as a network of precedence relationships using activity-on-node network construction Single estimate of activity time Deterministic activity times USED IN: Production management - for the jobs of repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience. PERT was developed by the US Navy for the planning and control of the Polaris missile program and the emphasis was on completing the program in the shortest possible time. In addition PERT had the ability to cope with uncertain activity completion times (e.g. for a particular activity the most likely completion time is 4 weeks but it could be anywhere between 3 weeks and 8 weeks). Basic difference between PERT and CPM:
Amit Sadhu
511234788
Though there are no essential differences between PERT and CPM as both of them share in common the determination of a critical path and are based on the network representation of activities and their scheduling that determines the most critical activities to be controlled so as to meet the completion date of the project. PERT: 1. Since PERT was developed in connection with an R and D work, therefore it had to cope with the uncertainties which are associated with R and D activities. In PERT, total project duration is regarded as a random variable and therefore associated probabilities are calculated so as to characterize it. It is an event-oriented network because in the analysis of network emphasis is given an important stages of completion of task rather than the activities required to be performed to reach to a particular event or task. PERT is normally used for projects involving activities of non-repetitive nature in which time estimates are uncertain. It helps in pinpointing critical areas in a project so that necessary adjustment can be made to meet the scheduled completion date of the project.
2. 3. 4.
CPM: 1. 2. 3. Since CPM was developed in connection with a construction project which consisted of routine tasks whose resources requirement and duration was known with certainty, therefore it is basically deterministic. CPM is suitable for establishing a trade-off for optimum balancing between schedule time and cost of the project. CPM is used for projects involving activities of repetitive nature.
Project scheduling by PERT-CPM: It consists of three basic phases: planning, scheduling and controlling. 1. 2. 3. Project Planning. Scheduling. Project Control.
Amit Sadhu
511234788
The analysis of Finite Queuing Models is more complex than those with infinite population although the approach is similar. L.G. Peck and R. N. Hazelwood have provided solutions to such problems in their book Finite Queuing Tables (John Wiley & Sons Inc 1958) Notations: Notations used are different and are given below: N = Population (machines, customers etc.) M = Service channels (repairmen, telephone lines etc.) T = Average service time (repair time, length of conversation on a telephone etc.) W = Average waiting time U = Average running time (of machines) or mean time between calls for service per unit H = Average number of units being serviced L = Average number of units waiting for service J = Average number of units in operation F = Efficiency Factor X = Service Factor D = Probability that if a unit calls for service, it will have to wait. Let us consider a machine shop with N machines. The inter breakdown time of these machines follows a negative exponential distribution with mean U. The number of breakdowns follows Poisson distribution with mean
It is assumed that machines are kept running (or in operation) except when they are under repairs or waiting for repair crew to attend. If M repair crews are available, the time taken by any crew follows a negative exponential distribution with mean T. Naturally, a machine which has broken down will have to wait for repairs if all the repair crews are busy.
Amit Sadhu
511234788
Measures of System Efficiency: Efficiency of the Repair System for a given set of machines, the efficiency of the repair system may be judged by the extent to which machines have to wait for repairs. If W is the average time for which a machine has to wait, the efficiency factor F is defined as
At any point of time, a machine will either be running or under repair or waiting for repairs. Therefore, the total number of machines . , and correspond to the probability that a machine is being repaired, running or waiting for repairs respectively.
In the finite queuing tables, service factor X is defined as The formulae for other properties of the system are given below:
Use of Finite Queuing Tables: The tables give the values of F and D for different values of N, M and X. They are arranged in the ascending order of the values of the population. For each N, the value of X increases from .001 to .950. For a given service factor X, several values of M can be found. For each value of X and M, values of D and F are tabulated. The steps in the use of Finite Queuing Tables may be summarized as follows: (i) Find mean service time T and mean running time U. (ii) Compute the service factor (iii) Select the table corresponding to the population N. (iv) For the given population, locate the service factor value. (v) Read off from tables, values of D and F for the number of service crews M. If necessary, these values may be interpolated between relevant values of X. (vi) Calculate the other measures L, W, H, and J from the formulae given. The overall efficiency F of the system will increase with the number of service channels (M) provided. As mentioned earlier, addition of service crews involves cost, which should be justified by the increase in the efficiency of the system i.e. additional running time of machines possible. However, it will be seen from the tables that as M increase the rate of increase in efficiency decreases. The practical significance is that beyond a certain value of M, it is not worthwhile increasing M as there would be no appreciable increase in the efficiency of the system. Example: In a chemical plant there are five hoppers of the same size which give food to material to grinding mills. Due to changes in the requisite of material, there are variations in the time taken for emptying the hoppers. On the basis of past experience this time was found to follow negative exponential distribution with an average of 10 hours between getting emptied. Whenever a hopper gets empty it has to be filled by a pay loader. Although the capacity of the hoppers is the same, the time taken to fill the hoppers varies due to different locations from which the material is to be loaded. The time for filling the hopper also was found to follow negative exponential distribution with an average of 2.5 hours. The company hires the
Amit Sadhu
511234788
pay loaders at a cost of Rs. 100 per hour irrespective of whether it is operated or not. If the mill has to be stopped due to its hopper getting empty it costs Rs.1000 per hour in terms of loss of profits. Determine the number of pay loaders which the company should engage to minimize overall cost. Solution: Since T = 2.5 and U = 10
For N = 5, X = 0.200 we have the following values from the tables: M D F 3 0.028 0.998 2 0.194 0.976 1 0.689 0.801 We now prepare a table as below: 1. Number of Pay Loaders 2. Overall efficiency of the system (f) 3. N(1-X) 4. Average number of mills running per hour J = NF(1-X) 5. Expected profit @ 1000 per hour 6. Load cost @ Rs. 100 per hour per day loader 7. Expected net profit per hour (5-6)
As increasing the number of pay loaders beyond two reduces profits, the company should engage only two pay loaders.
Amit Sadhu
511234788
6. Customers arrive at a small post office at the rate of 30 per hour. Service by the clerk on duty takes an average of 1 minute per customer a. Calculate the mean customer time. i. Spent waiting in line. ii. Spent receiving or waiting for service. b. Find the mean number of persons. i. In line. ii. Receiving or waiting for service.
Answer 6: Mean arrival rate = 30 customers per hour = 1/2 customer per minute Mean service rate = 1 per minute Traffic intensity a) Mean customer time i. Mean customer time spent waiting in line per minute
( )
ii.
minute
( )
b)
minutes
( )
ii.
customer
( )
cusomter
Amit Sadhu
511234788