Vous êtes sur la page 1sur 3

(ATS) AUTOMATIC TRANSFER SWITCH

JOB-NO. CUSTOMER PROJECT DRAWING

Ref. Revision: Date:

EEICQC-F-34 1 March 28, 2011

PANEL TAG NO. NO OF SECTIONS INSPECTION REF: SHOP ORDER NO.

A.
S/N 1. 2. 3. 4.

VISUAL TEST
ITEM(S) Check the equipment tag number is correct against the tag number shown on the One Line Diagram and the equipment data sheet. Check the nameplates against, the One Line Diagram and the equipment data sheet. Verify that all internal control and instrumentation terminations are securely and properly connected. Verify that all control wires terminal markings are properly and clearly printed. No visible signs of hand markings. Verify that the number of sections is correct. Verify that all components (e.g. MCB, CT, CPT/VT, relays, fuses, etc.) are installed properly. Verify that the incoming power connections / lugs are properly secured Verify that control wirings are correctly and properly identified. Verify that the cubicle is clean and free from debris. STATUS Not Done

Done

Date

5. 6. 7. 8. 9.

B.
10. 11. 12. 13.

MECHANICAL TEST
Check switch to insure positive interlock between normal and alternate sources. Check tightness of all cable connections and bus joints. Perform manual transfer operation. Verify that all internal control and instrumentation terminations are securely and properly terminated.

C.
14. 15. 16. 17. 18. 19. 20. 21. 22.

ELECTRICAL TEST
Verify continuity of all power and control leads. Verify that the Overload Reset button operates freely and correctly. Carry out Current Transformer (CT) and Voltage Transformer (VT) Tests. ( Attached computer generated test reports affixed with QC stamped) Perform automatic transfer by simulating loss of normal power. Perform automatic transfer by return to normal power. Monitor and verify correct operation and timing Normal Voltage sensing relays. Monitor and verify correct operation and time delay upon transfer. Monitor and verify correct operation and timing of Alternate voltage sensing relays. Monitor and verify correct operation and timing of Automatic transfer operation.

Page 1 of 3

(ATS) AUTOMATIC TRANSFER SWITCH


23. 24. 25.

Ref. Revision: Date:

EEICQC-F-34 1 March 28, 2011

26. 27. 28. 29. 30.

Monitor and verify correct operation and timing of mechanical and electrical interlocks and limit switches Monitor and verify correct operation and timing, of time-delay and Re-transfer upon normal power restoration. Verify that space heaters have been correctly installed operate properly.(if applicable as per customers request or approved data schedule) Carry out Insulation Resistance Test. Carry out Hi-Pot Test. Verify that the Ammeter is accurately calibrated by current injection. Verify that the Voltmeter is accurately calibrated by voltage application. Carry out a complete functional check of the Control Scheme.

* N/A Not Applicable

D.

One Minute Insulation Resistance Test


Serial No.: 677 Cal Due Date:

Test Equipment: SEFELEC

Resistance Test Results (Test Voltage = 1000Vdc) Test Description


AB+C+ Ground BA+C+ Ground CA+B+ Ground

PHASE TO PHASE
A - B B - C C - A

Pass / Fail

E.

Over-potential Withstand (Hi-Pot) Test Method and Results


Serial No.: 071325002 Test Voltage ( 2.5 KVac) Time Cal Due Date: Measured Leakage Current PASS / FAIL (Pass if no disruptive charge or flashover)

Test Equipment: BAUR Rated AC Voltage (V)

Description
AB+C+ Ground BA+C+ Ground CA+B+ Ground

Page 2 of 3

(ATS) AUTOMATIC TRANSFER SWITCH

Ref. Revision: Date:

EEICQC-F-34 1 March 28, 2011

Test Voltages and Minimum Acceptable Resistance


(NETA 1990 TABLE 10.1 P.190)

Max Equip Rating (V) 250 600 5000 8000 15000 35000

Minimum Test Voltage (dc) 500 1000 2500 2500 2500 15000

Minimum Acceptable Resistance (M)

25 100 1000 2000 5000 100000

Dielectric tests ANSI/IEEE C37.20.2 ANSI/IEEE C37.20.1 & C37.20.3 Metal-Clad, Station-Type Cubical and Metal Enclosed MV Switchgear, C37.23 Bus, Outdoor Circuit Breakers, and ANSI C37.32 Air Switches Power Frequency Field Reference DC Field Test Voltage for 60 seconds Rated Maximum Test Voltage for 60 sec. duration Voltage AC duration 4.76 kVac 14.25 kVac 20.25 kVdc 8.25 kVac 19.5 kVac 27.75 kVdc 15 kVac 27 kVac 37.5 kVdc 15.5 kVac 37.5 kVac 52.5 kVdc 25.8/27 kVac 45 kVac 38.0 kVac 60 kVac 72.5 kVac 120 kVac *Notes: 1.
The presence of the column headed 'dc withstand' does not imply any requirement for a dc withstand test on ac equipment. The column is given as a reference only for those using dc tests and represents values believed to be approximately equivalent to the corresponding power frequency withstand test values specified for each class of bus. Direct current withstand tests are recommended for flexible bus to avoid loss of insulation life that may result from the dielectric heating that occurs with rated frequency withstand testing. Because of the variable voltage distribution encountered when making 'dc withstand tests' and variances in leakage currents associated with various insulation systems, the manufacturer should be consulted for recommendations before applying 'dc withstand tests' to this equipment.

2.

3.

COMMENTS

QUALITY CONTROL ENGINEER

CUSTOMER

DATE

Page 3 of 3

Vous aimerez peut-être aussi