Académique Documents
Professionnel Documents
Culture Documents
Initial operations: When the mine began operations in 1985, Sharp's predecessor noted that trucks often arrived from the mine with a full load of ore only to find both crushers closed. Trucks then turned around and returned to the mine and dumped the ore beside the shovel which had originally loaded it. The entire shovel truck crew then moved from their ore zone to a waste zone until the crusher was re-opened. About 15minutes of production was lost each time a shovel changed location to move from an ore zone to a waste zone. Recognizing the inefficiency of this type of operation, the superintendent started a stockpile about 120metres from the crushers. Loaded ore trucks dumped at the stockpile, instead of returning loaded to the mine when both crushers were down. It was thought to be cheaper to station a shovel, which would otherwise be spare at the stockpile, and move the ore from the stockpile to the crushers later, than to send loaded ore trucks back to the mine. The time taken for a loaded truck to come from a shovel in the mine, turn, and dump on the stockpile was effectively the same as the time needed to carry ore to one of the crushers, turn, and dump. Therefore, the cost of ore reaching the stock file was the same as the cost of ore entering the crushers. Time was spent reducing the stockpile during periods of blasting when Sunil Pandey Section B 2012116 Page 2
Problems and Solutions: Sharp felt that once shovel-truck team began to produce, it was important that the team remain on the go. Workers in the mine might feel frustrated and lose enthusiasm for their work, if their cycle was periodically disrupted and also reduce the efficiency and productivity in the mine. Accountants had suggested, however, that the fuel consumption of waiting trucks or bulldozers would only be about 10per cent of the normal amount. Also, their maintenance and supplies expenses were about 20 percent of the normal amount. A temporary idle shovel consumed electricity at its normal rate, and incurred maintenance and supplies expenses at about 20 percent of normal rates. On the other hand, Sharp wanted to use the stockpile as little as possible because of the additional cost of re-handling ore. It had also been suggested that the stockpile be used for storing various grades of ore. The varying grades of ore could then be used for blending to maintain constant grade control of the finished concentrate. Such a practice was considered impractical because of the lag between the input of crude oil and the production of finished concentrate. However, the stockpile was useful for ensuring a continuous flow of ore to the crushers during the 30minutes each day that the mine was cleared for blasting, as well as during poor road conditions and shovel breakdown. Sharp had to evaluate the courses of action open to him. He and Smith had agreed that there was an optimum point at which total waiting and stockpile rehandling costs would be minimised and further agreed that the current rule failed to minimise these costs. He knew he would be called on to recommend a new plan to Smith.