Vous êtes sur la page 1sur 14

contents

APPLICATION CHALLENGES OF A FIELDBUS SYSTEM


Regina Alves Ischaber Bratby Instrument & Controls Engineer Washington Group International Denver, CO

KEYWORDS
Fieldbus, Fieldbus Control System, Fieldbus instruments, Segment Drawing, Fieldbus configuration, Fieldbus specification, Fieldbus engineering, Fieldbus troubleshooting, Fieldbus Commissioning.

ABSTRACT
The growing industry acceptance and lifecycle benefits of Fieldbus technology have made its consideration mandatory when planning a new or upgraded control system installation. However, there are important issues, such as troubleshooting, design optimization, and end user acceptance, which need to be addressed and resolved during the project cycle, for the benefits of the technology to be fully realized. This paper makes key engineering recommendations, and offers guidance for an efficient and safe implementation, of an H1 Foundation Fieldbus System, based on experience from a recent application on a natural gas processing plant.

INTRODUCTION
Foundation Fieldbus technology is designed to provide a digital, twoway, multi-drop communication link between field devices such as sensors, transmitters, actuators, and controllers, and various operator, engineering, and maintenance interfaces. The existing literature contains many technical papers on Foundation Fieldbus technology, with most of them emphasizing particular benefits and successful case studies. However, the application reality is that the technology is still in a state of evolution. Many experienced engineers now find themselves taking incremental steps, trying to understand and master this new digital technology. The intent of this paper is to contribute in this process by sharing our Copyright 2004 by ISAThe Instrumentation, Systems and Automation Society. Presented at the 14th Annual Joint ISA POWID/EPRI Controls and Instrumentation Conference, 47th Annual Power Industries (POWID) Conference; www.isa.org

experiences with other engineers who may be facing the practical application challenges of a Fieldbus system implementation.

EVALUATING THE NEED FOR A FIELDBUS CONTROL SYSTEM


Foundation Fieldbus technology should not be thought of as a simply digital I/O, because it is more than an I/O replacement. The advent of this new technology has opened up a wide range of new capabilities throughout all sectors of a plant. To successfully implement the technology, changes are needed in the way we execute these projects. Cultural changes are not easily achieved; everyone on the project team, including Operators and Instrument Technicians, must understand the technology and be aware of its features. Everyone involved on the project needs training in the technology, including construction personnel. Important considerations that need evaluation during preliminary project stages include the challenges that will be encountered when using Fieldbus for the first time, as well as the benefits and subsequent savings that the technology can bring. A suggested first step is to Benchmark (5) the project cost implementation difference between the technologies . All data shall be in spreadsheet and graphic format. To provide resolution in where cost difference occur, the benchmarking shall show cost and manpower data in the following activities: 1. Design phase Segment diagram versus loop drawing generation Control configuration man-hours and cost Total documentation man-hours and costs Total design schedule Marshalling and Control System footprint 2. Hardware Costs Conventional Instruments x Fieldbus Instruments costs. Use of multi-variable instruments shall be also evaluated. Complete Control System costs 3. Installation Costs: Wiring and termination manpower costs and schedule Homerun only costs Shop instrument calibration check and positioner setup costs OPC to auxiliary system versus conventional Control Systems Interfaces such Modbus. 4. Checkout & Commissioning Copyright 2004 by ISAThe Instrumentation, Systems and Automation Society. Presented at the 14th Annual Joint ISA POWID/EPRI Controls and Instrumentation Conference, 47th Annual Power Industries (POWID) Conference; www.isa.org

Loop check Device configuration download 5. Maintenance Shop Fieldbus System and Tools Cost of hardware , software, and auxiliary equipment devices. Fieldbus tools such as handheld devices and Fluke 1,2,3.

to connect and maintain

6. Spare Parts Stocking costs for Foundation Fieldbus instruments and non-Foundation Fieldbus instruments Management, tracking , and software upgrade of Foundation Fieldbus instruments. The most significant savings can be achieved only if the end user is able to establish an effective maintenance and asset management program. When evaluating overall costs, manufacturers specialist fees and training costs should be included for the asset management program implementation. Other benefits, such as interoperability, greater system functionality, plug and play, common look and feel, are not typically converted into cost savings, but should also be considered when evaluating the need for the technology. Unfortunately Foundation Fieldbus benefits are not necessarily extended to the design-engineering phase since the engineers prime concern is to perform well, on schedule, and within budget. Developing a new design philosophy will add risks to the job. Implementation of Foundation Fieldbus technology will require training of the engineering team. The engineer should evaluate the resources available, such as tools, standards, availability of skilled people, project schedule and budget before recommending implementation of Foundation Fieldbus. The technology should be implemented only when the proper resources are available or when mandate by the end user. The end user should be aware that asset management implementation is usually not included in the engineering scope of work, and if required, the engineering scope of work should specifically include this effort. Any doubts about the technology should be addressed up-front. An informed end-user will guarantee a successful implementation. If the end-user has no specific plans to take advantage of the Foundation Fieldbus capabilities, such as through asset management, it may not be possible to achieve significant savings or successfully realize the benefits of the technology. In this case the project may be better served with a conventional analog system. Copyright 2004 by ISAThe Instrumentation, Systems and Automation Society. Presented at the 14th Annual Joint ISA POWID/EPRI Controls and Instrumentation Conference, 47th Annual Power Industries (POWID) Conference; www.isa.org

CONTROL ARCHITECTURE
Foundation Fieldbus architecture specifies two types of network segments HSE and H1 links. HSE is in the early stages. HSE interfaces take full advantage of the low cost and ready availability of commercial off the shelf Ethernet technology and runs at 100 Mbits/ or higher. Segment configuration execution speed should be carefully estimated during Fieldbus segment design and configuration. The number of data transmissions over the bus will be reduced to a minimum if excessive number of control function blocks is implemented on the field devices. Spare capacity should be adequate to meet unforeseen changes and future needs. The control system supplier should play a critical role in the Control Architecture design and should be involved at the very earliest moment of the design. The E&C engineer should keep in mind that the vendors priorities may not match his/her own, and that in the end the control architecture is the engineers responsibility. The vendor should agree with the engineers architecture, or propose an alternative. The engineer should not hesitate in requiring the vendor to guarantee the system performance as long as the vendor had the opportunity to participate in the design.

SELECTING A FOUNDATION FIELDBUS CONTROL SYSTEM


Traditional practices for selecting control system are no longer sufficient or applicable to Foundation Fieldbus. Additional consideration is needed since a successful Foundation Fieldbus system implementation is more heavily based on seamless integration of all of its components. The engineer should define the basic control system performance criteria, including the relative priorities of determinism, repeatability, and throughput speed (the rate at which input data from devices can be delivered to all nodes that need it, and that the resulting output data can be delivered to all destination devices). The following checklist can be used to supplement other established evaluation standards and tools, for application to Fieldbus systems host and components evaluation and selection.

Copyright 2004 by ISAThe Instrumentation, Systems and Automation Society. Presented at the 14th Annual Joint ISA POWID/EPRI Controls and Instrumentation Conference, 47th Annual Power Industries (POWID) Conference; www.isa.org

1. Does the control system use open scaleable system architecture that can deploy commercial software standards such as OPC (OLE for Process Controls) and ODBC (Open Database Connectivity)? 2. Does the Control System use Open Network protocol? The engineer should be aware that an open network protocol must have all the layer defined by an open standard and that a Ethernet protocol is only related to the first two layers of any protocol, therefore it can be also proprietary.(1) 3. How easy and cost effective can the system migrate existing or third party control products? Does the vendor offer a migration plan for future updates?(1) 4. Does the system support Fieldbus bridges on both H1 and HSE? Foundation Fieldbus bridges define how the devices in different ports can communicate to guarantee full plant integration. Some systems will have the communication inside their proprietary CPU, no guaranteeing the FF (1) schedule, the control performance and the openness of the system. 5. Is there any license policy to run function blocks in the process control station?(1) 6. Can it support redundant Fieldbus interface modules connected to the same Fieldbus H1 port? (1) Are they treated redundantly? . 7. Is there any known issue in the system? If yes how would they affect the control system performance? 8. Does the system accept both Fixed Fieldbus function blocks and instantiable Fieldbus Foundation Function blocks? (Fixed Foundation Fieldbus is defined where the block is always present, in fixed quantities, running all the time. Devices with instantiable blocks have a library of block types that can be executed inside of the device).(1) 9. Can any power supply be used in the system or only special brands? What are the minimum requirements? 10. What kind of Fieldbus barriers for IS applications does the system use? How many devices can be connected to each safety barrier? Do we need to use a repeater connected to the safety barrier or is it already embedded in the barrier? 11. How many devices can be connected per Fieldbus segment? How many devices can be connected in one Fieldbus interface module? 12. How many back-up masters can be configured in one segment? Is there any restriction? 13. Does the system accept any Fieldbus approved device with no restriction? Does the system have a list with approved devices to guarantee a smooth integration? 14. If a listed device presents problems would the manufacturer offer support? 15. Does the system take full advantage of the Fieldbus technology? Or it is more like an old DCS with Fieldbus communication?(1) 16. Can the manufacturer supply any reference from existing users? 17. How the vendor handles future upgrade revisions? The Control System must be kept current to assure it will work with new Foundation Fieldbus instruments revisions and the current revision level has to be backwards compatible with older Foundation Fieldbus Instruments. Copyright 2004 by ISAThe Instrumentation, Systems and Automation Society. Presented at the 14th Annual Joint ISA POWID/EPRI Controls and Instrumentation Conference, 47th Annual Power Industries (POWID) Conference; www.isa.org

EVALUATING A FIELDBUS INSTRUMENT


The field device has now become an integral part of control system architecture and has capabilities that before were only available on control system CPU. Making the right selection of Fieldbus instruments for your application involves looking beyond the process application. To select the right device the instrument engineer will be required to interact with all the components of the project. The Fieldbus instrument specification should be done early on in the project because it impacts the segment design and configuration. The vendor documentation also should be required very early in the project. Instrument manuals should have a section for Fieldbus parameters and troubleshooting. A checklist developed for Fieldbus instruments evaluation, is presented below. 1. What is the subscriber or publisher (VCRs) limit for the device? A subscriber VCR is an output from a field device to an input in another device on the segment. A publisher VCR is an output from a controller to the input of a parameter in a Fieldbus device. 2. Does the device have Link Active Scheduler (LAS) capabilities? 3. Does the device have Foundation Fieldbus approval? 4. Is the device certified for hazardous area location? If yes, what are the certifications? 5. Has the field device at least rudimentary diagnostic capability, such as maintaining and divulging a count of erroneous messages received during a given period? Is the instrument provided with statistical process monitoring capability?(1) 6. Is the device a true Fieldbus instrument or it is an analog device with an analog to digital converter? 7. Are the device description files and capability files available for every device revision? 8. What are the Fieldbus blocks available on the device? Is there any license policy to use instantiable blocks the instrument block? 9. Is the device tested for interoperability with the host system? If a device has interoperability problems, how will the manufacturer support the user to solve the problem? 10. Can the manufacturer make available a device to be used during the control systems FAT? 11. What is the device maximum current draw? What is the power consumption? 12. Can the instrument be calibrated through third party calibration tools? 13. Can calibration parameters and alarm settings be written through a third party configuration tool? Copyright 2004 by ISAThe Instrumentation, Systems and Automation Society. Presented at the 14th Annual Joint ISA POWID/EPRI Controls and Instrumentation Conference, 47th Annual Power Industries (POWID) Conference; www.isa.org

14. Does the device have an automated software wizard to allow easy setup and calibration from the host system? 15. Can the device be field calibrated? If yes, how? 16. How does the vendor handle firmware updates? Is the vendors presence required to update the software? 17. Does its guarantee include interoperability with other Foundation Fieldbus approved devices? 18. Does the instrument operation and installation manual include Fieldbus configuration and start up sections? 19. Does the device have any reset capabilities? If yes, how it is done? 20. Can the instrument be bought pre-configured? Fieldbus instruments should be sized and specified in basically the same way as conventional instruments, but some additional features are required. As a minimum , Foundation Fieldbus instruments shall have the following features: 1. 2. 3. 4. Foundation Fieldbus Certification Function blocks shall be downloadable into the devices by the end user. User shall be able to download upgraded revision into the devices Instrument shall be capable of performing continuous diagnostics , including self-tests function and to provide specific diagnostic information to the host system. 5. Fieldbus instruments shall have automated software wizards to allow easy set-up and calibration.

SEGMENT DESIGN AND TOPOLOGY CONSIDERATIONS


Fieldbus wiring can influence the effective implementation of the technology as well as impacting the ease of maintaining the system in the future. Because there are many useful wiring installation guides available on the web, this paper will only touch on selected points. Figure 1 shows a tree, or chicken foot topology. It is a practical topology if devices on the same segment are well separated, but in the general area of the same junction box. This type of topology also allows the user to disconnect a device with less of a chance of, by mistake, disconnecting the entire segment. In the gas plant project junction bricks with individual short-circuit protection were not provided, thus any individual device had the potential to disturb the communication across the entire segment. The use of short circuit protection on branch trunks would have eliminated some headaches during start-up. With the plant up and running, the segment became stable and communication problems disappeared.

Copyright 2004 by ISAThe Instrumentation, Systems and Automation Society. Presented at the 14th Annual Joint ISA POWID/EPRI Controls and Instrumentation Conference, 47th Annual Power Industries (POWID) Conference; www.isa.org

FIG.2 (2)- TREE TOPOLOGY Following are some recommendations for segment design: 1. The segment design should be defined at a later stage in the project after the control strategy is defined, the P&IDs consolidated, and the instruments selected and located. 2. When designing the topology the engineer should also consider the construction schedule. Wiring of new devices can disturb the segment and cause countless frustrations during commissioning. 3. We recommend that at least one instrument on the segment has to have Backup Link Active Scheduler (LAS) capability. The instrument used as LAS backup should have a monitoring function only. The LAS backup should be identified on the segment drawing. 4. Redundant process measurements shall be on separate H1 segments. 5. Limit the number of devices per segment as follows: (5) For segments with only monitoring instruments, limit segment to 12 devices. Segments should not contain more than (4) control valves or damper actuators. For loops requiring 1 or 0.5 second execution time, limit segment to 8 devices For loops requiring 0.25 second execution time limit segment to 3 devices with a maximum of one final control element 6. The segment designer should follow closely the vendor wiring recommendations. Special attention should be given to installation limitations, such as spur length, number of instruments per barrier and segment, power draw, number of VCRs, grounding, shielding, and polarity. 7. All function blocks shall reside on the same segment if the PID function is implemented on the field device 8. Access the need for individual short circuit protector for each segment. Access risk area and I/O group segregation. Copyright 2004 by ISAThe Instrumentation, Systems and Automation Society. Presented at the 14th Annual Joint ISA POWID/EPRI Controls and Instrumentation Conference, 47th Annual Power Industries (POWID) Conference; www.isa.org

9. Access installation of TBs/boxes vs purchased prefabricated connectors and bricks.

HOW TO EFFECTIVELY CONFIGURE A FIELDBUS LOOP


In a Fieldbus system the engineer must configure the network, the control strategy, and the field devices. For the network configuration we recommend that at least one instrument on the segment should be configured as backup link master. This will allow the instrument to take the LAS role if the master-linking device is not present on the network. The following guidelines should be used for control strategy and device configuration. 1. A configuration guideline shall be set for the project. The guideline shall define all typical control parameters defined. The guideline shall set function block and control module philosophy for the project. 2. Use standard blocks as much as possible. The engineer should be aware that although some instruments have the same function, they are not configured in the same way. 3. Before starting to configure the device, the engineer should read the instrument manuals to ensure the right parameters were selected for configuration. If necessary a standard block should be created for each manufacturer type. 4. Test the library standard configuration modules during FAT. Although interoperability was not a problem in our project we had some software inconsistencies that caused headaches during start up. The problem was aggravated because the instrument manufacturers did not have any knowledge of the host system and vice versa. 5. Macrocycle and module execution times should be within the limits established by the control system manufacturer. Use conservative execution times to minimize the loading on the segment. Module execution time determines how often a module executes. The port macrocyle is the execution time for a single interaction of the Fieldbus function blocks running in all the devices on the port.) (3) 6. Make sure that the subscriber and publisher (VCRs) limits have been not reached. 7. Be aware of the Stake Link count limits. The Stale Link limit specifies the number of communications that can be lost before that device status is set to BAD. (3) 8. Transfer the control function, such as PID, to the field instruments as much as possible. 9. Make sure that the configuration block is using the number of the logical hardware channel that is connected to the I/O block. The failure to set a valid channel number will place the device in Out of Service (OOS) mode. (3) 10. Use write requests only when necessary. Limit the number of write requests to the limits recommend by the vendor. (3) Copyright 2004 by ISAThe Instrumentation, Systems and Automation Society. Presented at the 14th Annual Joint ISA POWID/EPRI Controls and Instrumentation Conference, 47th Annual Power Industries (POWID) Conference; www.isa.org

11. Limit periodic writes to Static or Non-Volatile Parameters Fieldbus devices have a non-volatile memory write limit which can stop its operation after the limit is reached. (3) 12. Before starting the configuration, make sure that all the known issues for the devices were considered. 13. Use valid units and XD_Scale. Engineers shall be aware that each Fieldbus instrument only supports certain engineering units. 14. Make sure that the device description files and capability file are available for each instrument revision. 15. Test graphic faceplates during FAT. Some Fieldbus instruments may require a different faceplate. 16. The control strategy should be implemented such that a PID output of 100 % always means that the valve is open, independently of the actuator being air to open or air to close. 17. Execution speed, advanced diagnostics, failure mode, and operator access should be considered when locating where the PID block resides. 18. When all function blocks of a PID loop cannot reside on the same segment, the PID control shall reside in the host system. 19. When the PID function resides on the field device, it should be located in the final control element

ENGINEERING DOCUMENTATION AND DRAWINGS


As stated above, the E&C engineers job is better done through established standards. Therefore, changes in the documentation should be few and simple. 1. P&I Drawings -From our experience some small changes, as shown on Figure 2, should be made on the P&Ids to convey the Fieldbus information.
FIT 001 FF FIC 001 FF

FE 001

IA

FY 001

FF FCV 001

FIG. 2 FIELDBUS LOOP ON P&ID DRAWING Copyright 2004 by ISAThe Instrumentation, Systems and Automation Society. Presented at the 14th Annual Joint ISA POWID/EPRI Controls and Instrumentation Conference, 47th Annual Power Industries (POWID) Conference; www.isa.org

2. Datasheets Instrument datasheets should include the classical information but also the information required by the Fieldbus device specification. Our recommendation is to maintain the traditional ISA type datasheet and to add a second page with the following Fieldbus requirements: LAS capable ( Yes/ No) Minimum Operating Voltage Quiescent Current Draw (mA) Polarity Sensitivity ( Yes /No) DD Revision Level Channel Numbers and description Function blocks available Number of VCR parameters 3. Logic Drawings the self-documenting features of the control system should replace this document. Try to use the self-documentation feature as much as possible. 4. I/O List - If possible the engineer should import the project I/O List or the Instrument Index to the control system database. Working on a common database will reduce the chances of mistake during design. 5. Location Drawings are required (three dimensional location is preferred). This document shall be as accurate as possible and must be available as early in the project as possible, since it is necessary to the design of Instrument Segment Diagrams. 6. Instrument Segment Diagram (ISD) Loop Drawings - When a loop is contained on a H1 segment loop drawings should be replaced by segment drawings. When loops are on multiple segments or contained conventional I/Os a traditional loop drawing is required in addition to ISD drawings. If loop drawings are mandated, segment drawings should be also issued. If only individual loop diagrams are used technicians could be misled into believing that disconnecting would only affect the single loop. Figure 3 shows a segment drawing using a chicken foot topology. Additional information such as trunk and branch length, current draws and device configuration could be added. Soft data and configuration data are not shown on the ISD diagram.

Copyright 2004 by ISAThe Instrumentation, Systems and Automation Society. Presented at the 14th Annual Joint ISA POWID/EPRI Controls and Instrumentation Conference, 47th Annual Power Industries (POWID) Conference; www.isa.org

CONTROLLER: FRONT01
DWG. 700XXX

JB-FF-86107 DWG. 703503

SG-01-03-02A
TS-1 POWER ERROR PORT 1 PORT 2 12 + 11 10 SH + + SH 9 8 7 OR BL

FRONT01-03-02 FIT-810 FIT-811A FIT-812A

(OR)

+ SH TRUNK +

4 SH + -

(BL)

FY813A-FB2

FY-813A FY-814A LY-811A LY-812A

24VDC

(BL)

(OR)

POWER CONDITIONER CARD NO. 3, CHANNEL NO. 2

FIT810-FB1 (OR) FIT810-FB2 (BL) FIT811A-FB1 (OR) FIT811A-FB2 (BL) FIT812A-FB1 (OR) FT812A-FB2 (BL)
(OR)

SG-03-02A

FY813A-FB1 (BL) FY814A-FB2 FY814A-FB1 (BL)LY811A-FB2


(OR)

SH 1 + SH 2 + SH 3 + SH TRUNK -

5 SH + 6 SH + 7 SH +

FOUNDATION FIELDBUS H1 CARD CARD NO 3


CH 1 CH 2 (+)

24VDC TS-5 F5 F6

(OR) (BL)

LY811A-FB1 LY812A-FB2

(OR)

LY812A-FB1

(+)

(+)

(-)

(-)

(-)

C5 C7

(BL) (OR)

8 SH +

+ SH TERMINATOR

GND GND

CH 1 DWG 703065

SPARE

1 2 3 4 5 6 7 8

(OR) (BL)

(BL)

FB + -

NODE NUMBER: XXXX


SG-01-04-02A DWG. 703069 120 VAC TO JB-C-86109 DWG 700455
(BK) (RD*) (BL**) AC L1 N G FB + (OR) (BL) (OR) (BL) FB + -

NODE NUMBER: XXXX

NODE NUMBER: XXXX

120 VAC TO JB-C-86109 DWG 700455

(BK) (RD*) (BL**)

AC L1 N G

FB + -

(OR) (BL) (OR) (BL) FB + -

NODE NUMBER: XXXX

NODE NUMBER: XXXX

120 VAC TO JB-C-86109 DWG 700455

(BK) (RD*) (BL**)

AC L1 N G

FB + -

(OR) (BL)

NOTES 1. * INDICATES NEUTRAL CONDUCTOR TAPED WHITE. 2. ** INDICATES GROUND CONDUCTOR TAPED GREEN.

(OR) (BL)

FB + -

NODE NUMBER: XXXX

PROJECT XYZ

NODE NUMBER: XXXX

FIG.3 SEGMENT DRAWING SAMPLE

COMMISSIONING, TROBLESHOOTING, AND START-UP


With the proper procedures, right equipment, right personnel, and vendor support the Fieldbus commissioning will be easier, faster, and greater savings will be achieved. 1. Proper Procedures - The commissioning and start-up of a Fieldbus installation is very different from an analog system and will require the creation of new procedures. The segment checkout should be verified before starting the single loop checkout. 2. Proper Equipment - Fieldbus tools shall include but not be limited to Fluke 1,2,3 industrial scope meter and Fieldbus tester. 3. Right Personnel Proper training should be provided for everyone involved during commissioning. It is desirable that at least a project member to have some knowledge of IT technology. 4. Vendor Support Vendors technician shall be required to have Fieldbus experience. The host system specification should require the installation of PC Anywhere connections to be used by the manufacturer specialists.

Copyright 2004 by ISAThe Instrumentation, Systems and Automation Society. Presented at the 14th Annual Joint ISA POWID/EPRI Controls and Instrumentation Conference, 47th Annual Power Industries (POWID) Conference; www.isa.org

FACTORY ACCEPTANCE TEST


During the FAT, the complete host, including all linking devices, controllers, and conventional I/O subsystems should be subject to hardware and functional tests. 1. A complete functional test shall be conducted for each type of Fieldbus device. The test shall include, but not be limited to, plug-and-play, and interconnectivity with host system. Verify access to all function blocks, and device operations.(5) 2. Test configuration blocks and graphic faceplates for each Fieldbus. 3. Verify easy access to calibration wizard and setup procedures from the host system. Tests should (5) include a calibration and setup for each type of Fieldbus device. 4. Test redundancy failure for H1 cards and power supplies. All H1 cards shall be tested. 5. Each H1 segment port shall be tested by live connection of at least one Fieldbus device. 6. Redundancy fail-over test shall be done for all H1 cards and Fieldbus power supply. 7. Ping all the host-level network nodes. Test switchover from the primary to the secondary host level and vice-versa

SPARE PARTS AND CONTROL SYSTEM LEVEL UPDATE PROGRAM


A Fieldbus Device spare parts program shall be developed . Fieldbus instruments are completely different from, and not replaced by conventional instruments. A Fieldbus device spare parts program shall be developed. Management , tracking , and upgrade of Fieldbus instruments revision levels shall be include in this program. Spare parts program shall consider that a Fieldbus instrument brand may not be interchangeable with another brand. Sometimes changes in the configuration and segment design are required to replace a Fieldbus device with another instrument brand . Instrument vendor shall be required to recommend quantity of spare Foundation Fieldbus instruments and associated software.

HOW TO FACILITATE INTRODUCTION OF THE THECHNOLOGY


The easiest way to facilitate the introduction of Fieldbus technology is to start to introduce the technology gradually to the end users. Test potential Fieldbus candidate devices and determine how they will serve the ultimate goals of the end user. With a few non-critical loops, the plant technicians and Copyright 2004 by ISAThe Instrumentation, Systems and Automation Society. Presented at the 14th Annual Joint ISA POWID/EPRI Controls and Instrumentation Conference, 47th Annual Power Industries (POWID) Conference; www.isa.org

operators will gain experience and graduate upwards from there. Training is also an important component for ultimate end user acceptance.

CONCLUSION
As one can see a successful Fieldbus implementation will require planning, standards, and training. Be prepared and reap the great benefits brought by the Fieldbus technology.

REFERENCES
Evaluating a Foundation Fieldbus System 20 Questions & Answers http:// www.smar.com Fieldbus Topologies http:// www.vcsum.org (3) http://plant web.emersonprocess.com (4) Fieldbuses for Process Control Engineering, Operation, and Maintenance by Jonas Berge (5) Aramco FF Specification http://iceweb.com.au
(1) (2)

Copyright 2004 by ISAThe Instrumentation, Systems and Automation Society. Presented at the 14th Annual Joint ISA POWID/EPRI Controls and Instrumentation Conference, 47th Annual Power Industries (POWID) Conference; www.isa.org

Vous aimerez peut-être aussi