Vous êtes sur la page 1sur 81

PROSSIMO DEVELOPMENT LTD

Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.
Material Rate for Budget
Name of the Project : All Project

SI
No

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35

Name of the Material

Grey Cement Comp


Sylhet Sand
Local Sand
Viti Sand
Shingless
Stone Chips
1st Class Brick
1st Class Picket
Brick Chips
Brick Surki
MS Rod (60 G)
MS Rod (60 G)
White Cement (I)
White Cement (S)
Wall Tiles 8"X12"
Wall Tiles 10"X13"
Floor Tiles 16"X16" NGH
Floor Tiles 16"X16" NGH
Floor Tiles 24"X24" NGH
Floor Tiles 12"X12" Cera
Main Door Frame (6"X2") Burma Teak
Door Frame (6"X2") Teak Chamble
Main Door Shutter Burma Teak
Partex Board
Chalk Power
Tarpin oil
Plastic Paint
Destemper Paint
Enamel Paint
Weather Coat
Snowcem
Aluminium Sliding Window
Aluminium Fixed Window
Aluminium Sliding Door
Mosquito Profing Net

Unit

Bag
Cft
Cft
Cft
Cft
Cft
Pcs
Pcs
Cft
Cft
Kg
Kg
Bag
Bag
Sft
Sft
Sft
Sft
Sft
Sft
Rft
Rft
Sft
Sft
Bag
Gallon
Gallon
Gallon
Gallon
Gallon
Kg
Sft
Sft
Sft
Sft

Present
Rate

385.00
29.00
10.00
8.00
75.00
112.00
6.20
6.20
55.00
35.00
60.00
60.00
800.00
800.00
38.00
38.00
58.00
105.00
105.00
58.00
560.00
280.00
675.00
155.00
500.00
352.00
700.00
450.00
730.00
920.00
2800.00
265.00
265.00
265.00
105.00

Projected

Projected

Rate

Rate

Present Rate Present Rate


Add 5%

Add 10%

404.25
30.45
10.50
8.40
78.75
117.60
6.51
6.51
57.75
36.75
63.00
63.00
840.00
840.00
39.90
39.90
60.90
110.25
110.25
60.90
588.00
294.00
708.75
162.75
525.00
369.60
735.00
472.50
766.50
966.00
2940.00
278.25
278.25
278.25
110.25

Approved
385.00
29.00
10.00
8.00
75.00
112.00
6.20
6.20
55.00
35.00
60.00
60.00
800.00
800.00
38.00
38.00
58.00
105.00
105.00
58.00
560.00
280.00
675.00
155.00
500.00
352.00
700.00
450.00
730.00
920.00
2800.00
265.00
265.00
265.00
105.00

36
37
38
39
40

Window Grill
Ver Grill
Stair Railing
Stone Lime
Ver Railing

Sft
Sft
Sft
Bag
Sft

95.00
120.00
165.00
500.00
165.00

99.75
126.00
173.25
525.00
173.25

95.00
120.00
165.00
500.00
165.00

TD

oy Nagar, Dhaka-1000.

Remarks

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

Analysis for Civil work


Item

Name of Item

No

Unit

Quantity

Rate

Amount

(Tk.)

(Tk.)

Analysis for 100 Cft.


Sand filling in foundation and plinth for 100 cft. of work inc. compactoin etc complete.
A.

B.

Cost of Materials :
a Cost of Viti Sand . (F.M 0.8)
TotalA)
Cost of Labour :
a Labour cost for filling, levelling, compaction etc.
Total(B)

Cft

130.00

8.00

1040.00
1040.00

Cft

130.00

1.00

130.00
130.00

Total(A+B)
Cost Per Cft Tk=

A.

B.

1170.00
11.70

Analysis for 100 Sft.


One layer brick flat soling in foundation and floor.
Cost of Materials :
a. Bricks
Nos
b. Viti Sand (F.M.-0.8)
Cft
Total(A)
Cost of Labour :
a Labour Cost Per Sft (Soling)
Sft
Total(B)
Total(A+B)
Cost Per Sft Tk=
19.65
Analysis for 100 Cft.
3'' C.C work (1:3:6), Brick Chips, MS
Cost of Materials :
a. Picket
Nos
b Local Sand (F.M. 1.5)
Cft.
e Cement
Bag
Total of (A)
Cost of Labour :
a Breaking cost of Picket
Nos
b Labour charge for Screening (Chips)
Cft.
c Labour charge for Screening (Sand)
Cft.
d Labour charge for local carrying (Picket)
Nos
e Labour charge for local carrying (Sand)
Cft.
f Curing
Nos
g Labour Cost of Casting
Cft.
h Cost for Mixing & Vibratoring Machine
Cft.
Total (B)
Total (A+B)

300.00
5.00

6.20
8.00

1860.00
40.00
1900.00

100.00

0.65

65.00
65.00
1965.00

900.00
45.00
12.00

6.20
10.00
385.00

5580.00
450.00
4620.00
10650.00

900.00
90.00
45.00
900.00
45.00
0.25
100.00
100.00

0.30
1.00
0.75
0.15
1.00
160.00
11.00
1.00

270.00
90.00
33.75
135.00
45.00
40.00
1100.00
100.00
1813.75
12463.75

Cost Per Cft


Item

124.64
Name of Item

No

A
a.
b.
c.
e
B
a
b
c
d
e
f
g
h

Analysis for 100 Cft.


4'' C.C work (1:2:4), Brick Chips, 50% CS
Cost of Materials :
Picket
Sylhet Sand (F.M. 2.5)
Local Sand (F.M. 1.5)
Cement
Total of (A)
Cost of Labour :
Breaking cost of Picket
Labour charge for Screening (Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Picket)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)

Rate

Amount

(Tk.)

(Tk.)

860.00
22.50
22.50
18.00

6.20
29.00
10.00
385.00

5332.00
652.50
225.00
6930.00
13139.50

860.00
86.00
45.00
860.00
45.00
0.25
100.00
100.00

0.30
1.00
0.75
0.15
1.00
160.00
8.25
1.00

258.00
86.00
33.75
129.00
45.00
40.00
825.00
100.00
1516.75

Unit

Quantity

Nos
Cft.
Cft.
Bag

Nos
Cft.
Cft.
Nos
Cft.
Nos
Cft.
Cft.

Total (A+B)
Cost Per Cft

14656.25
146.56

Analysis for 100 Cft. (Ground Floor)


R.C.C work (1:1:3) completed excluding cost of rod and fabrication in Column . casting
with Stone Chips, 100% CS
A.

Cost of Materials :
a. Stone Chips
b. Sylhet Sand (F.M. 2.5)
c Cement

Cft.
Cft.
Bag

82.00
41.00
22.00

112.00
29.00
385.00

9184.00
1189.00
8470.00
18843.00

Cft.
Cft.
Cft.
Cft.
Nos
Cft.
Cft.

82.00
41.00
82.00
41.00
0.25
100.00
100.00

1.00
0.75
1.25
1.00
160.00
5.85
1.00

82.00
30.75
102.50
41.00
40.00
585.00
100.00
981.25

Total of (A)
B.
a
b
c
d
e
f
g

Cost of Labour :
Labour charge for Screening (Stone Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Stone Chips)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)
Total (A+B)
Cost Per Cft

19824.25
198.24

Item

Name of Item

No

Unit

Quantity

Rate

Amount

(Tk.)

(Tk.)

Analysis for 100 Cft. (1st Floor to 6th Floor)


R.C.C work (1:1:3) completed excluding cost of rod and fabrication in Column . casting
with Stone Chips, 100% CS
A.

Cost of Materials :
a. Stone Chips
b. Sylhet Sand (F.M. 2.5)
c Cement

Cft.
Cft.
Bag

82.00
41.00
22.00

112.00
29.00
385.00

9184.00
1189.00
8470.00
18843.00

Cft.
Cft.
Cft.
Cft.
Nos
Cft.
Cft.

82.00
41.00
82.00
41.00
0.25
100.00
100.00

1.00
0.75
1.25
1.00
160.00
7.10
1.00

82.00
30.75
102.50
41.00
40.00
710.00
100.00
1106.25

Total of (A)
B.
a
b
c
d
e
f
g

Cost of Labour :
Labour charge for Screening (Stone Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Stone Chips)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)
Total (A+B)
Cost Per Cft

19949.25
199.49

Analysis for 100 Cft. (Ground Floor)


R.C.C work (1:2:4) completed excluding cost of rod and fabrication in Column . casting
with Stone Chips, 50% CS
A.
a.
b.
c.
d.

Cost of Materials :
Stone Chips
Sylhet Sand (F.M. 2.5)
Local Sand (F.M. 1.5)
Cement

Cft.
Cft.
Cft.
Bag

86.00
22.50
22.50
18.00

112.00
29.00
10.00
385.00

9632.00
652.50
225.00
6930.00
17439.50

Cft.
Cft.
Cft.
Cft.
Nos
Cft.
Cft.

86.00
45.00
86.00
45.00
0.25
100.00
100.00

1.00
0.75
1.25
1.00
160.00
5.85
1.00

86.00
33.75
107.50
45.00
40.00
585.00
100.00
997.25

Total of (A)
B.
a
b
c
d
e
f
g

Cost of Labour :
Labour charge for Screening (Stone Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Stone Chips)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)
Total(A+B)
Cost Per Cft

18436.75
184.37

Item

Name of Item

No

Unit

Quantity

Rate

Amount

(Tk.)

(Tk.)

Analysis for 100 Cft. (1st Floor to 6th Floor)


R.C.C work (1:2:4) completed excluding cost of rod and fabrication in Column . casting
with Stone Chips, 50% CS
A.
a.
b.
c.
d.

Cost of Materials :
Stone Chips
Sylhet Sand (F.M. 2.5)
Local Sand (F.M. 1.5)
Cement

Cft.
Cft.
Cft.
Bag

86.00
22.50
22.50
18.00

112.00
29.00
10.00
385.00

9632.00
652.50
225.00
6930.00
17439.50

Cft.
Cft.
Cft.
Cft.
Nos
Cft.
Cft.

86.00
45.00
86.00
45.00
0.25
100.00
100.00

1.00
0.75
1.25
1.00
160.00
7.10
1.00

86.00
33.75
107.50
45.00
40.00
710.00
100.00
1122.25

Total of (A)
B.
a
b
c
d
e
f
g

Cost of Labour :
Labour charge for Screening (Stone Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Stone Chips)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)
Total(A+B)
Cost Per Cft

18561.75
185.62

Analysis for 100 Cft. (Ground Floor)


R.C.C work (1:1:3) completed excluding cost of rod and fabrication in Column, Beam,
Slab Stair. casting with Brick Chips, 50% CS
A
a.
b.
c.
e
B
a
b
c
d
e
f
g
h

Cost of Materials :
Picket
Sylhet Sand (F.M. 2.5)
Local Sand (F.M. 1.5)
Cement
Total of (A)
Cost of Labour :
Breaking cost of Picket
Labour charge for Screening (Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Picket)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)

Nos
Cft.
Cft.
Bag

820.00
20.50
20.50
22.00

6.20
29.00
10.00
385.00

5084.00
594.50
205.00
8470.00
14353.50

Nos
Cft.
Cft.
Nos
Cft.
Nos
Cft.
Cft.

820.00
86.00
41.00
820.00
41.00
0.25
100.00
100.00

0.30
1.00
0.75
0.15
1.00
160.00
5.85
1.00

246.00
86.00
30.75
123.00
41.00
40.00
585.00
100.00
1251.75

Total(A+B)
Cost Per Cft

15605.25
156.05

Item

Name of Item

No

Unit

Quantity

Rate

Amount

(Tk.)

(Tk.)

Analysis for 100 Cft. (1st Floor to 6th Floor)


R.C.C work (1:1:3) completed excluding cost of rod and fabrication in Column, Beam,
Slab Stair. casting with Brick Chips, 50% CS
A
a.
b.
c.
e
B
a
b
c
d
e
f
g
h

Cost of Materials :
Picket
Sylhet Sand (F.M. 2.5)
Local Sand (F.M. 1.5)
Cement
Total of (A)
Cost of Labour :
Breaking cost of Picket
Labour charge for Screening (Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Picket)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)

Nos
Cft.
Cft.
Bag

820.00
20.50
20.50
22.00

6.20
29.00
10.00
385.00

5084.00
594.50
205.00
8470.00
14353.50

Nos
Cft.
Cft.
Nos
Cft.
Nos
Cft.
Cft.

820.00
86.00
41.00
820.00
41.00
0.25
100.00
100.00

0.30
1.00
0.75
0.15
1.00
160.00
7.10
1.00

246.00
86.00
30.75
123.00
41.00
40.00
710.00
100.00
1376.75

Total(A+B)
Cost Per Cft

15730.25
157.30

Analysis for 100 Cft. (Ground Floor)


R.C.C work (1:2:4) completed excluding cost of rod and fabrication in Column, Beam,
Slab Stair. casting with Brick Chips, 50% CS
A
a.
b.
c.
e
B
a
b
c
d
e
f
g
h

Cost of Materials :
Picket
Sylhet Sand (F.M. 2.5)
Local Sand (F.M. 1.5)
Cement
Total of (A)
Cost of Labour :
Breaking cost of Picket
Labour charge for Screening (Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Picket)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)
Total(A+B)

Nos
Cft.
Cft.
Bag

860.00
22.50
22.50
18.00

6.20
29.00
10.00
385.00

5332.00
652.50
225.00
6930.00
13139.50

Nos
Cft.
Cft.
Nos
Cft.
Nos
Cft.
Cft.

860.00
86.00
45.00
860.00
45.00
0.25
100.00
100.00

0.30
1.00
0.75
0.15
1.00
160.00
5.85
1.00

258.00
86.00
33.75
129.00
45.00
40.00
585.00
100.00
1276.75
14416.25

Cost Per Cft

Item

144.16

Name of Item

No

Unit

Quantity

Rate

Amount

(Tk.)

(Tk.)

Analysis for 100 Cft. (1st Floor to 6th Floor)


R.C.C work (1:2:4) completed excluding cost of rod and fabrication in Column, Beam,
Slab Stair. casting with Brick Chips, 50% CS
A
a.
b.
c.
e

Cost of Materials :
Picket
Sylhet Sand (F.M. 2.5)
Local Sand (F.M. 1.5)
Cement

Nos
Cft.
Cft.
Bag

860.00
22.50
22.50
18.00

6.20
29.00
10.00
385.00

5332.00
652.50
225.00
6930.00
13139.50

Nos
Cft.
Cft.
Nos
Cft.
Nos
Cft.
Cft.

860.00
86.00
45.00
860.00
45.00
0.25
100.00
100.00

0.30
1.00
0.75
0.15
1.00
160.00
7.10
1.00

Total (B)

258.00
86.00
33.75
129.00
45.00
40.00
710.00
100.00
1401.75

Total(A+B)

14541.25

Total of (A)
B
a
b
c
d
e
f
g
h

Cost of Labour :
Breaking cost of Picket
Labour charge for Screening (Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Picket)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine

Cost Per Cft

145.41

Analysis for 100 Cft. (All Floor)


R.C.C work (1:2:4) completed excluding cost of rod and fabrication in Lintel casting
with Brick Chips, 50% CS
A
a.
b.
c.
e
B
a
b
c
d
e
f
g
h

Cost of Materials :
Picket
Sylhet Sand (F.M. 2.5)
Local Sand (F.M. 1.5)
Cement
Total of (A)
Cost of Labour :
Breaking cost of Picket
Labour charge for Screening (Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Picket)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)

Nos
Cft.
Cft.
Bag

860.00
22.50
22.50
18.00

6.20
29.00
10.00
385.00

5332.00
652.50
225.00
6930.00
13139.50

Nos
Cft.
Cft.
Nos
Cft.
Nos
Cft.
Cft.

860.00
86.00
45.00
860.00
45.00
0.25
100.00
100.00

0.30
1.00
0.75
0.15
1.00
160.00
12.00
1.00

258.00
86.00
33.75
129.00
45.00
40.00
1200.00
100.00
1891.75

Total(A+B)
Cost Per Cft

Item

Name of Item

No

A
a.
b.
c.
e
B
a
b
c
d
e
f
g
h

15031.25
150.31

Unit

Quantity

Rate

Amount

(Tk.)

(Tk.)

Analysis for 100 Cft. (All Floor)


R.C.C work (1:2:4) completed excluding cost of rod and fabrication in False Slab,
Cost of Materials :
Picket
Nos
860.00
6.20
5332.00
Sylhet Sand (F.M. 2.5)
Cft.
22.50
29.00
652.50
Local Sand (F.M. 1.5)
Cft.
22.50
10.00
225.00
Cement
Bag
18.00 385.00
6930.00
Total of (A)
13139.50
Cost of Labour :
Breaking cost of Picket
Nos
860.00
0.30
258.00
Labour charge for Screening (Chips)
Cft.
86.00
1.00
86.00
Labour charge for Screening (Sand)
Cft.
45.00
0.75
33.75
Labour charge for local carrying (Picket)
Nos
860.00
0.15
129.00
Labour charge for local carrying (Sand)
Cft.
45.00
1.00
45.00
Curing
Nos
0.25 160.00
40.00
Labour Cost of Casting
Cft.
100.00
12.00
1200.00
Cost for Mixing & Vibratoring Machine
Cft.
100.00
1.00
100.00
Total (B)
1891.75
Total(A+B)
Cost Per Cft

A.
a.
b.
c.
B.
a
b
c
d
e

15031.25
150.31

Analysis for 100 Cft. (Ground Floor)


10" brick work (1:6) in super structure.
Cost of Materials :
Brick
Local Sand (1.5F.M.)
Cement
Total (A)
Cost of Labour :
Labour charge for Screening
Labour charge for local carrying (Picket)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Brick work
Total (B)

Nos.
Cft
Bag

1150.00
36.00
4.00

6.20
10.00
385.00

7130.00
360.00
1540.00
9030.00

Cft.
Nos
Cft.
Nos
Cft.

36.00
1150.00
36.00
0.25
100.00

0.75
0.15
1.00
160.00
4.00

27.00
172.50
36.00
40.00
400.00
675.50

Total(A+B)

Cost Per Sft

9705.50
97.06

Item

Name of Item

No

A.
a.
b.
c.
B.
a
b
c
d
e

Analysis for 100 Cft. (1st Floor to 6th Floor)


10" brick work (1:6) in super structure.
Cost of Materials :
Brick
Local Sand (1.5F.M.)
Cement
Total (A)
Cost of Labour :
Labour charge for Screening
Labour charge for local carrying (Picket)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Brick work
Total (B)

Cost Per Sft

A.

Rate

Amount

(Tk.)

(Tk.)

1150.00
36.00
4.00

6.20
10.00
385.00

7130.00
360.00
1540.00
9030.00

36.00
1150.00
36.00
0.25
100.00

0.75
0.15
1.00
160.00
4.70

27.00
172.50
36.00
40.00
470.00
745.50

Unit

Quantity

Nos.
Cft
Bag

Cft.
Nos
Cft.
Nos
Cft.

Total (A+B)

9775.50
97.76

Analysis for 100 Cft. (Ground Floor)


5" Brick work (1:4) in super structure
Cost of Materials :
a. Brick
b. Local Sand (1.5F.M.)
c. Cement

Nos.
Cft
Bag

500.00
17.00
2.60

6.20
10.00
385.00

3100.00
170.00
1001.00
4271.00

Cft.
Nos
Cft.
Nos
Cft.

17.00
500.00
17.00
0.25
100.00

0.75
0.15
1.00
160.00
3.00

12.75
75.00
17.00
40.00
300.00
444.75
4715.75

Nos.
Cft
Bag

500.00
17.00
2.60

6.20
10.00
385.00

3100.00
170.00
1001.00
4271.00

Cft.

17.00

0.75

12.75

Total (A)
B.
a
b
c
d
e

Cost of Labour :
Labour charge for Screening (Sand)
Labour charge for local carrying (Picket)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Brick work

Cost Per Sft

A.

B.

Total (B)
Total(A+B)

Analysis for 100 Cft. (1st Floor to 6th Floor)


5" Brick work (1:4) in super structure
Cost of Materials :
a. Brick
b. Local Sand (1.5F.M.)
c. Cement
Total (A)
Cost of Labour :
a Labour charge for Screening (Sand)

47.16

b
c
d
e

Labour charge for local carrying (Picket)


Labour charge for local carrying (Sand)
Curing
Labour Cost of Brick work

Nos
Cft.
Nos
Cft.

500.00
17.00
0.25
100.00

0.15
1.00
160.00
3.50

Total (B)
Total(A+B)

Cost Per Sft


Item

A
a.
c.
B
a
b
c
d
e

Analysis for 100 Cft. (Ground Floor)


25 mm thick cement plaster inside Brick wall (1:5)
Cost of Materials :
Local Sand (1.5 F.M.)
Cement .in bag
Total (A)
Cost of Labour :
Labour charge for washing (Sand)
Labour charge for Screening (Sand)
Labour charge for local carrying (Sand)
Labour cost for plaster work
Curing
Total (B)

Cost Per Sft

4765.75
47.66

Name of Item

No

75.00
17.00
40.00
350.00
494.75

Rate

Amount

(Tk.)

(Tk.)

Unit

Quantity

Cft.
Bag

10.42
1.67

10.00
385.00

104.20
642.95
747.15

Cft.
Cft.
Cft.
Sft
Nos

10.42
10.42
10.42
100.00
0.25

0.75
0.75
1.00
3.15
160.00

7.82
7.82
10.42
315.00
40.00
381.05

Total(A+B)

1128.20
11.28

Analysis for 100 Cft. (1st Floor to 6th Floor)


25 mm thick cement plaster in side Brick wall (1:5)
Cost of Materials :
a. Local Sand (1.5 F.M.)
Cft.
c. Cement .in bag
Bag
Total (A)
Cost of Labour :
a Labour charge for washing (Sand)
Cft.
b Labour charge for Screening (Sand)
Cft.
c Labour charge for local carrying (Sand)
Cft.
d Labour cost for plaster work
Sft
e Curing
Nos
Total (B)
Total(A+B)
11.78
Cost Per Sft
Analysis for 100 Cft. (Ground Floor)
20 mm thick cement plaster outside Brick wall (1:5)
Cost of Materials :
a. Local Sand (1.5 F.M.)
Cft.
c. Cement .in bag
Bag
Total (A)
Cost of Labour :
a Labour charge for washing (Sand)
Cft.
b Labour charge for Screening (Sand)
Cft.

10.42
1.67

10.00
385.00

104.20
642.95
747.15

10.42
10.42
10.42
100.00
0.25

0.75
0.75
1.00
3.65
160.00

7.82
7.82
10.42
365.00
40.00
431.05
1178.20

7.81
1.25

10.00
385.00

78.10
481.25
559.35

7.81
7.81

0.75
0.75

5.86
5.86

c Labour charge for local carrying (Sand)


d Labour cost for plaster work
e Curing

Cost Per Sft

Item

A
a.
c.
B
a
b
c
d
e

A
a.
c.
B
a
b
c
d
e

A
a.
c.
B
a
b
c

7.81
100.00
0.25

1.00
3.60
160.00

Total (B)

7.81
360.00
40.00
419.53

Total(A+B)

978.88
9.79

Name of Item

No

Cft.
Sft
Nos

Unit

Quantity

Analysis for 100 Cft. (1st Floor to 6th Floor)


20 mm thick cement plaster out side Brick wall (1:5)
Cost of Materials :
Local Sand (1.5 F.M.)
Cft.
7.81
Cement .in bag
Bag
1.25
Total (A)
Cost of Labour :
Labour charge for washing (Sand)
Cft.
7.81
Labour charge for Screening (Sand)
Cft.
7.81
Labour charge for local carrying (Sand)
Cft.
7.81
Labour cost for plaster work
Sft
100.00
Curing
Nos
0.25
Total (B)
Total(A+B)
10.39
Cost Per Sft
Analysis for 100 Cft. (Ground Floor)
20 mm thick plaster On Concrete Surfaces including Chipping (1:4)
Cost of Materials :
Local Sand (1.5 F.M.)
Cft.
7.50
Cement .in bag
Bag
1.50
Total (A)
Cost of Labour :
Labour charge for washing (Sand)
Cft.
7.50
Labour charge for Screening (Sand)
Cft.
7.50
Labour charge for local carrying (Sand)
Cft.
7.50
Labour cost for plaster work
Sft
100.00
Curing
Nos
0.25
Total (B)
Total(A+B)
10.71
Cost Per Sft
Analysis for 100 Cft. (1st Floor to 6th Floor)
20 mm thick plaster On Concrete Surfaces including Chipping (1:4)
Cost of Materials :
Local Sand (1.5 F.M.)
Cft.
7.50
Cement .in bag
Bag
1.50
Total (A)
Cost of Labour :
Labour charge for washing (Sand)
Cft.
7.50
Labour charge for Screening (Sand)
Cft.
7.50
Labour charge for local carrying (Sand)
Cft.
7.50

Rate

Amount

(Tk.)

(Tk.)

10.00
385.00

78.10
481.25
559.35

0.75
0.75
1.00
4.20
160.00

5.86
5.86
7.81
420.00
40.00
479.53
1038.88

10.00
385.00

75.00
577.50
652.50

0.75
0.75
1.00
3.60
160.00

5.63
5.63
7.50
360.00
40.00
418.75
1071.25

10.00
385.00

75.00
577.50
652.50

0.75
0.75
1.00

5.63
5.63
7.50

d Labour cost for plaster work


e Curing

Sft
Nos

100.00
0.25

4.10
160.00

Total (B)
Total(A+B)

Cost Per Sft

Item

A.

B.

11.21

Name of Item

No

Unit

Analysis for 100 Sft. (Ground Floor)


12 mm Thick Plaster with Net Cement Finishing (NCF)
Cost of Materials :
a. Sand (1.5 F.M.)
Cft.
b. Cement
Bag
c. Neat cement finishing
Bag
Total (A)
Cost of Labour :
a Labour cost for Plaster
Sft
b Labour cost for NCF
Sft
c Labour charge for washing (Sand)
Cft.
d Labour charge for Screening (Sand)
Cft.
e Labour charge for local carrying (Sand)
Cft.
f Curing
Nos
Total (A)

Cost Per Sft

A.
a.
b.
c.
B.
a
b
c
d
e
f

Quantity

Rate

Amount

(Tk.)

(Tk.)

5.00
1.00
0.50

10.00
385.00
385.00

50.00
385.00
192.50
627.50

100.00
100.00
5.00
5.00
5.00
0.25

3.60
1.00
0.75
0.75
1.00
160.00

360.00
100.00
3.75
3.75
5.00
40.00
512.50

Total (A+B)

1140.00
11.40

Analysis for 100 Cft. (1st Floor to 6th Floor)


12 mm Thick Plaster with Net Cement Finishing (NCF)
Cost of Materials :
Sand (1.5 F.M.)
Cft.
Cement
Bag
Neat cement finishing
Bag
Total (A)
Cost of Labour :
Labour cost for Plaster
Sft
Labour cost for NCF
Sft
Labour charge for washing (Sand)
Cft.
Labour charge for Screening (Sand)
Cft.
Labour charge for local carrying (Sand)
Cft.
Curing
Nos
Total (A)

Cost Per Sft

410.00
40.00
468.75
1121.25

Total (A+B)

5.00
1.00
0.50

10.00
385.00
385.00

50.00
385.00
192.50
627.50

100.00
100.00
5.00
5.00
5.00
0.25

4.10
1.00
0.75
0.75
1.00
160.00

410.00
100.00
3.75
3.75
5.00
40.00
562.50
1190.00

11.90

Item

Name of Item

No

A
a
b
B
a.
c.
C
a
b
c
d

A
a
b
B
a.
c.
C
a
b
c
d

Unit

Analysis for 100 Sft. (All Floor)


Floor Tiles (Homogeneous 12"x12")
Cost of Materials :
R A K ( N.G.Homogenious 12"x12" ) i/c 5% wastage Sft
Pointing Materials
Sft
Total (A)
1"Thick Bsase materials (cenent morter) (1:3)
Local Sand (1.5 F.M.)
Cft.
Cement .in bag
Bag
Total (B)
Cost of Labour :
Labour cost per Sft. (Tiles)
Sft
Labour charge for Screening (Sand)
Cft.
Labour charge for local carrying (Sand)
Cft.
Curing
Nos
Total (C)
Total (A+B+C)
So, Cost per Sft.
83.03
Analysis for 100 Sft. (All Floor)
Floor Tiles (Ceramic Tile : 12"x12")
Cost of Materials :
Ceramic Tile (12"x12") i/c 5% wastage
Sft
Pointing Materials
Sft
Total (A)
1"Thick Bsase materials (cenent morter) (1:3)
Local Sand (1.5 F.M.)
Cft.
Cement .in bag
Bag
Total (B)
Cost of Labour :
Labour cost per Sft. (Tiles)
Sft
Labour charge for Screening (Sand)
Cft.
Labour charge for local carrying (Sand)
Cft.
Curing
Nos
Total (C)
Total (A+B+C)
So, Cost per Sft.

Quantity

Rate

Amount

(Tk.)

(Tk.)

105.00
100.00

58.00
1.00

6090.00
100.00
6190.00

9.37
2.50

10.00
385.00

93.70
962.50
1056.20

100.00
9.37
9.37
0.25

10.00
0.75
1.00
160.00

1000.00
7.03
9.37
40.00
1056.40
8302.60

105.00
100.00

58.00
1.00

6090.00
100.00
6190.00

9.37
2.50

10.00
385.00

93.70
962.50
1056.20

100.00
9.37
9.37
0.25

10.00
0.75
1.00
160.00

1000.00
7.03
9.37
40.00
1056.40
8302.60

83.03

Item

Name of Item

No

Analysis for 100 Sft. (All Floor)


Wall Tiles (Glazed 8"x12")
Cost of Materials :
a Glazed 8"x12"
b Pointing Materials

B
a.
c.
C
a
b
c
d

Total (A)
"Thick Bsase materials (cenent morter) (1:2)
Local Sand (1.5 F.M.)
Cement .in bag
Total (B)
Cost of Labour :
Labour cost per Sft. (Tiles)
Labour charge for Screening (Sand)
Labour charge for local carrying (Sand)
Curing
Total (C)

Rate

Amount

(Tk.)

(Tk.)

Unit

Quantity

Sft
Sft

105.00
100.00

38.00
1.00

3990.00
100.00
4090.00

Cft.
Bag

6.25
2.50

10.00
385.00

62.50
962.50
1025.00

Sft
Cft.
Cft.
Nos

100.00
6.25
6.25
0.25

10.00
0.75
1.00
160.00

1000.00
4.69
6.25
40.00
1050.94

Total (A+B+C)

So, Cost per Sft.


Analysis for 100 Sft. (All Floor)
Wall Tiles (Glazed 10"x13")
Cost of Materials :
a Glazed (10"x13") i/c 5% wastage
b Pointing Materials and curring

B
a.
c.
C
a
b
c
d

6165.94
61.66

Total (A)
"Thick Bsase materials (cenent morter) (1:2)
Local Sand (1.5 F.M.)
Cement .in bag
Total (B)
Cost of Labour :
Labour cost per Sft. (Tiles)
Labour charge for Screening (Sand)
Labour charge for local carrying (Sand)
Curing
Total (C)
Total (A+B+C)

Sft
Sft

105.00
100.00

38.00
1.00

3990.00
100.00
4090.00

Cft.
Bag

6.25
2.50

10.00
385.00

62.50
962.50
1025.00

Sft
Cft.
Cft.
Nos

100.00
6.25
6.25
0.25

10.00
0.75
1.00
160.00

1000.00
4.69
6.25
40.00
1050.94
6165.94

So, Cost per Sft.

Item
No

A.

61.66

Name of Item
Analysis for 100 Sft. (All Floor)
Stair & Lobby Tiles (N.G.Hom 16"x16")
Cost of Materials :
a N.G.Hom Tiles (16"x16") i/c 5% wastage
b Pointing Materials and curring

Amount

(Tk.)

(Tk.)

105.00
100.00

105.00
1.00

11025.00
100.00
11125.00

9.37
2.50

10.00
385.00

93.70
962.50
1056.20

100.00
9.37
9.37
0.25

10.00
0.75
1.00
160.00

1000.00
7.03
9.37
40.00
1056.40
13237.60

Quantity

Sft
Sft

Total (A)
1"Thick Bsase materials (cenent morter) (1:3)
a. Local Sand (1.5 F.M.)
Cft.
c. Cement .in bag
Bag
Total (B)
Cost of Labour :
a Labour cost per Sft. (Tiles)
Sft
b Labour charge for Screening (Sand)
Cft.
c Labour charge for local carrying (Sand)
Cft.
d Curing
Nos
Total (C)
Total (A+B+C)
So, Cost per Sft.
132.38
Analysis for 1 Cwt. (Ground Floor)
Fabrication of M.S. rod in (40 Grade)
Cost of Materials :
a. Cost of Material M.S. rod
b. Material wastage 1.5%

Rate

Unit

Cwt

1.00

3000.00

3000.00
45.00
3045.00

Cwt
Cwt

1.00
1.00

90.00
10.00

90.00
10.00
100.00
3145.00

1.00

3000.00

3000.00
45.00

Total (A)
B.

Cost of Labour :
a. Labour charge for fabrication binding
b. Labour charge for local carrying (Rod)
Total(B)
Total(A+B)

A.

Cost Per Kg
Analysis for 1 Cwt. (1st Floor to 6th Floor)
Fabrication of M.S. rod in (40 Grade)
Cost of Materials :
a. Cost of Material M.S. rod
b. Material wastage 1.5%

62.90

Cwt

Total (A)
B.

Cost of Labour :
a. Labour charge for fabrication binding
b. Labour charge for local carrying (Rod)

3045.00
Cwt
Cwt

1.00
1.00

105.00
10.00

Total(B)
Total(A+B)
Cost Per Kg

Item

A.

3160.00
63.20

Name of Item

No

Analysis for 1 Cwt. (Ground Floor)


Fabrication of M.S. rod in (60 Grade)
Cost of Materials :
a. Cost of Material M.S. rod
b. Material wastage 1.5%

Rate

Amount

(Tk.)

(Tk.)

Unit

Quantity

Cwt

1.00

3000.00

3000.00
45.00
3045.00

Cwt
Cwt

1.00
1.00

90.00
10.00

90.00
10.00
100.00

Total (A)
B.

Cost of Labour :
a. Labour charge for fabrication binding
b. Labour charge for local carrying (Rod)
Total(B)
Total(A+B)
Cost Per Kg

A.
a.
b.
B.
a.
b.

3145.00
62.90

Analysis for 1 Cwt. (1st Floor to 6th Floor)


Fabrication of M.S. rod in (60 Grade)
Cost of Materials :
Cost of Material M.S. rod
Material wastage 1.5%
Total (A)
Cost of Labour :
Labour charge for fabrication binding
Labour charge for local carrying (Rod)
Total(B)

Cwt

1.00

3000.00

3000.00
45.00
3045.00

Cwt
Cwt

1.00
1.00

105.00
10.00

105.00
10.00
115.00

Total(A+B)
Cost Per Kg

A.

3160.00
63.20

Analysis for 100 Sft. (All Floor)


Window Grills
Cost of Materials :
a Steel Grill as per Design
b Fitting Materials

Sft
Sft

100.00
100.00

95.00
2.00

9500.00
200.00
9700.00

Sft

100.00

3.50

350.00

Total (A)
B

105.00
10.00
115.00

Cost of Labour :
a Labour cost for fitting

Total (A)

350.00

Total (A+B)

10050.00

So, Cost per Sft. Tk.

Item
No

A.

100.50

Name of Item
Analysis for 100 Sft. (All Floor)
Varandah safety grill
Cost of Materials :
a Steel Grill as per Design
b Fitting Materials

Rate

Amount

(Tk.)

(Tk.)

Unit

Quantity

Sft
Sft

100.00
100.00

95.00
2.00

9500.00
200.00
9700.00

Sft

100.00

3.50

350.00
350.00

Total (A)
B

Cost of Labour :
a Labour cost for fitting
Total (A)
Total (A+B)
So, Cost per Sft. Tk.

A.

10050.00
100.50

Analysis for 100 Sft. (All Floor)


Varandah railing
Cost of Materials :
a Steel Grill as per Design
b Fitting Materials

Sft
Sft

100.00
100.00

165.00
2.00

16500.00
200.00
16700.00

Sft

100.00

3.50

Total (B)

350.00
350.00

Total (A+B)

17050.00

Total (A)
B

Cost of Labour :
a Labour cost for fitting

So, Cost per Sft. Tk.

A.

Analysis for 100 Sft. (All Floor)


Stair box rail -Typical design
Cost of Materials :
a Steel Grill as per Design & Painting per Sft.
b Fitting Materials
Total (A)
Cost of Labour :
c Labour cost for fitting
Total (B)

170.50

Sft
Sft

100.00
100.00

165.00
2.00

16500.00
200.00
16700.00

Sft

100.00

4.40

440.00
440.00

Total (A+B)
So, Cost per Sft. Tk.

Item
No

A.

17140.00
171.40

Name of Item

Rate

Amount

(Tk.)

(Tk.)

Unit

Quantity

Mond
Sft

1.00
1000.00

500.00
0.02

500.00
20.00
520.00

Sft

1000.00

0.20

Total (B)

200.00
200.00

Total (A+B)

720.00

Analysis for 1000 Sft. (All Floor)


White washing 3 coats
Cost of Materials :
a. Slaked Stone lime
b. Blue
Total (A)

A.

Cost of Labour :
a. Labour cost for 1000 Sft. .

So, Cost per Sft. Tk.


0.72
Analysis for 200 Sft. (All Floor)
Distempering 2 coats
Cost of Materials :
a. Distemper (1 Gall. Covering 190Sft.)
Gallon
b. Chalk Powder ,pastic paint -putting mat etc
Sft
c. Maintenance coat-for hand over
Sft
Total (A)
Cost of Labour :
a. Labour Cost for 200 Sft.

Sft.

1.05
200.00
200.00

450.00
0.60
0.30

472.50
120.00
60.00
652.50

200.00

1.50

300.00
300.00

Total (B)
Total (A+B)
So, Cost per Sft. Tk.

A.

952.50
4.76

Analysis for 200 Sft. (All Floor)


Plastic Paint 3 coats
Cost of Materials :
a. Plastic (1 Gall. Covering 190Sft.)
Gallon
b. Chalk Powder ,pastic paint -putting mat etc
Sft
c. Maintenance coat-for hand over
Sft
Total (A)

1.50
200.00
200.00

700.00
0.60
0.30

1050.00
120.00
60.00
1230.00

Cost of Labour :
a. Labour Cost for Pastic Paint

Sft.
Total (B)

350.00
350.00

Total (A+B)

1580.00

So, Cost per Sft. Tk.

Item

A.

Unit

Analysis for 200 Sft. (All Floor)


Weather coat paint 2 coats
Cost of Materials :
a. Weather coat (1 Gall. Covering 190Sft.)
Gallon
b. Chalk Powder ,Weather coat -putting mat etc
Sft
e Maintenance coat-for hand over
Sft
Total (A)

B
a
b

Quantity

Rate

Amount

(Tk.)

(Tk.)

1.05
200.00
200.00

920.00
0.60
0.30

966.00
120.00
60.00
1146.00

200.00

2.00

Total (B)

400.00
400.00

Total (A+B)

1546.00

Cost of Labour :
a. Labour Cost for Weather coat

a
b

1.75

7.9

Name of Item

No

200.00

Sft.

So, Cost per Sft. Tk.


7.73
Analysis for 100 Rft. (All Floor)
Supply with Main Door Frame with necessary Fittings
Cost of Materials :
Door Frame (6"x2") of wood finish
Rft.
Cost of hold fast and necessary hardware
Rft.
Total (A)
Cost of Labour :
Labour charge for fitting
Rft.
Civil works
Rft.
Total (B)

100.00
100.00

560.00
5.50

56000.00
550.00
56550.00

100.00
100.00

5.00
4.00

500.00
400.00
900.00

Total (A+B)

So, Cost per Rft. Tk.


Analysis for 100 Sft. (All Floor)
Main Door shutter (Solid)
a. Material Cost: ( 2'-2"x6'-10" )
Door shutte -wood
Necessary hardware Hings

57450.00
574.50

Sft
Nos

100.00
100.00

475.00
15.00

47500.00
1500.00
49000.00

Sft

100.00

10.00

1000.00

total
B

b. Cost of Labour :
Labour charge for fitting

50000
So, cost per Sft.

Item

Name of Item

No

500.00

Analysis for 100 Sft. (All Floor)


Flush Door Shutter with necessary fittings
Cost of Materials :
a Door Shutter
b Necessary hardware
Total (A)
Cost of Labour :
a Labour charge for fitting

Rate

Amount

(Tk.)

(Tk.)

Unit

Quantity

Sft.
Sft.

100.00
100.00

155.00
3.00

15500.00
300.00
15800.00

Sft.

100.00

6.00

600.00
600.00
16400.00

Sft
Nos

100.00
100.00

145.00
15.00

14500.00
1500.00
16000.00

Sft

100.00

10.00

1000.00
17000.00

100.00
100.00
125.00
100.00

165.00
70.00
15.00
5.00

16500.00
7000.00
1875.00
500.00
25875.00

Total (B)
Total (A+B)

So, cost per Sft.


Analysis for 100 Sft. (All Floor)
Solid door shutter-Gamari wood
a. Material Cost: ( 2'-2"x6'-10" )
Door shutte -wood
Necessary hardware Hings

164.00

Total (A)
B

Cost of Labour :
Labour charge for fitting
Total (B)
Total (A+B)

A.
a.
b
c
d

So, cost per Sft.


Analysis for 100 Rft. (All Floor)
Stair Hand Rail -Teak Chamble
Cost of Materials :
Stair hand rest
Labor charge for manufacture & fixing
polishing cost
Cost of hared ware etc

170.00

Rft.
Rft.
Rft.
Rft.

Total (A)
So, Cost per Rft. Tk.
258.75
Analysis for 100 Cft.
4" Thick finished lime terracing (2:2:7)

A.
a
b
c
d
e

Cost of Materials :
I. 1st class Brick
Breaking cost
ii. Stone Lime
iii. 1st class Surki
iv. Chitagur, Garlic, Meti, Khoar

Pcs
Nos
Mond
Cft
LS

900.00
900.00
12.50
27.00

6.20
0.30
500.00
35.00

5580.00
270.00
6250.00
945.00
50.00
13095.00

Sft

100.00

7.50

750.00
13845.00

Total (A)
B.

Cost of Labour :
a Lime terracing With chipping
Total (B)

So, Rate Per Cft.

Tk.

138.45

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

Analysis of Civil work-2010


Sl No

Description

4
5

Unit

Rate

L.S
Sft

6000.00
0.50

Cft
Cft

2.00
2.25

Cft
Cft
Sft

1.00
11.70
19.65

Cft
Cft

124.64
146.56

Cft
Cft
Cft
Cft
Cft
Cft
Cft
Cft
Cft
Cft

198.24
199.49
184.37
185.62
156.05
157.30
144.16
145.41
150.31
150.31

Cft
Cft
Sft
Sft

97.06
97.76
47.16
47.66

a
b
c
d

Site Mobilization
Site cleaning
Lay-out work
Earth Excavition
Earth work up to 7-6"
Earth work above 7-6"
Filling Work
Earth fill/sand fill
Sand fill with Royalty
One layer BFS
C.C Work
3'' CC (1:3:6)-BC,MS
4'' CC (1:2:4)-BC 50% CS
RCC Works:
RCC (1:1:3),SC 50% CS (Ground Floor)
RCC (1:1:3),SC 50% CS (1st Floor to 6th Floor)
RCC (1:2:4),SC 50% CS (Ground Floor)
RCC (1:2:4),SC 50% CS (1st Floor to 6th Floor)
RCC (1:1:3),BC 50% CS (Ground Floor)
RCC (1:1:3),BC 50% CS (1st Floor to 6th Floor)
RCC (1:2:4),BC 50% CS (Ground Floor)
RCC (1:2:4),BC 50% CS (1st Floor to 6th Floor)
RCC (1:2:4),BC 50% CS (Ground Floor),Lintel
RCC (1:2:4),BC 50% CS (1st Floor to 6th Floor) False Slab
Brick Work
10"Thick Brick work(1:6) (Ground Floor)
10"Thick Brick work(1:6) (1st Floor to 6th Floor)
5" Thick Brick work (1:4) (Ground Floor)
5" Thick Brick work (1:4) (1st Floor to 6th Floor)

a
b
c
d
e
f
g
h

Plaster Work
25 mm Plaster-(1:5)-Brick walls in side (Ground Floor)
25 mm Plaster-(1:5)-Brick walls in side (1st Floor to 6th Floor)
20 mm Plaster-(1:5)-Brick walls out side (Ground Floor)
20 mm Plaster-(1:5)-Brick walls out side (1st Floor to 6th Floor)
20 mm Plaster-(1:4)-on R.C.C Surfaces (Ground Floor)
20 mm Plaster-(1:4)-on R.C.C Surfaces (1st Floor to 6th Floor)
Plaster with NCF (Ground Floor)
Plaster with NCF (1st Floor to 6th Floor)

Sft
Sft
Sft
Sft
Sft
Sft
Sft
Sft

11.28
11.78
9.79
10.39
10.71
11.21
11.40
11.90

a
b
c
d

Tiles Work
Floor Tiles (Homogeneous 12" x 12")
Floor Tiles (Ceramic 12" x 12")
Wall Tiles (Ceramic 8'' x 12")
Wall Tiles (Ceramic 10 x 13")

Sft
Sft
Sft
Sft

83.03
83.03
61.66
61.66

a
b
a
b

a
b
a
b
c
d
e
f
g
h
i
j

Stair & Lobby (Homogeneous 16" x 16")

Sft

132.38

Description

Unit

Rate

Sl No
10

11

12

13

14

15

16
17
18

a
b
c
d

Re-Bar Work
Re-Bar 40 Grade
Re-Bar 40 Grade
Re-Bar 60 Grade
Re-Bar 60 Grade

a
b

From work
Materials & Labour (Ground Floor)
Materials & Labour (1st Floor to 6th Floor)

(Ground Floor)
(1st Floor to 6th Floor)
(Ground Floor)
(1st Floor to 6th Floor)

Grill Work
Window grill
Ver Safety grill
Ver railing
Stair Box railing
Paint Work
White wash
Distempering
Plastic paint
Weather coat
Main Door Frame
Door Farme (6" x 2" )

Internal Door frame


Internal Door frame (6" x 2" )

a
b
c
d
a
b
c
d

Door Shutter
Door Shutter
Partex Door Shutter
Partex Door Shutter
Stair Hand Rest
Stair Hand rest Teak Chamble (3"x 2" )
Aluminium works
3" Section Sliding Aluminium Door Window Fixed works

Lime Terracing
4" Thick finished lime terracing (2:2:7)

a
a
a

Kg
Kg
Kg
Kg

62.90
63.20
62.90
63.20

Sft
Sft

20.00
22.00

Sft
Sft
Sft
Sft

100.50
100.50
170.50
171.40

Sft
Sft
Sft
Sft

0.72
4.76
7.90
7.73

Rft

574.50

Rft

574.50

Sft

500.00

Sft

164.00

Sft

258.75

Sft

253.00

Sft

138.45

joy Nagar, Dhaka-1000.

Remarks

Remarks

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.
Name of the Project:

Construction Area

0.00

Per Floor Area

Average BOQ Qty Per Total Cons.area and Per Floor Cons.area
SI

Description of work

No

Unit

Per Total

Per Floor

Cons Area

Area

Cons Area

Area

Average

Average

Average

Average

Lay-out

LS

0.2013

1.2487

Earth Excavation

Cft

0.9639

Earth filling

Cft

0.3213

Sand filling

Cft

3" thick C.C work (1:3:6) BC,MS

Cft

4" thick C.C work (1:2:4) BC,50% CS

Dressing & Leveling

One Layer Brick flat soling

Polythene sheel laying (Double layer)

10

Pile boring

11

R.C.C work :

Per Total Per Floor


0.00

2000.92

1773.15

1887.04

5.9761

9581.17

8486.06

9033.61

1.9922

3193.72

2828.92

3011.32

0.4026

2.4973

4001.84

3546.17

3774.01

0.0208

0.1290

206.75

183.18

194.97

Cft

0.0974

0.6028

968.16

855.98

912.07

Sft

0.2652

1.6438

2636.09

2334.20

2485.14

Sft

0.2844

1.7642

2826.94

2505.16

2666.05

Sft

0.2831

1.7557

2814.01

2493.09

2653.55

Rft

0.0000

0.0000

0.00

0.00

0.00

0.00

0.00

0.00

a) Footing (1:1:3) SC,50% CS

Cft

0.1231

0.7632

1223.61

1083.74

1153.68

b) Column upto PL (1:1:3) SC,50% CS

Cft

0.0167

0.1032

166.00

146.54

156.27

c) Lift wall (1:1:3) SC,50% CS

Cft

0.0054

0.0333

53.68

47.29

50.48

d) U.G.W.R (1:1:3) BC,50% CS

Cft

0.0173

0.1075

171.96

152.65

162.31

e) Grade Beam (1:2:4) BC,50% CS

Cft

0.0195

0.1210

193.83

171.82

182.83

f) U.G.W.R Top Slab (1:2:4) BC,50% CS

Cft

0.0045

0.0279

44.73

39.62

42.17

g) Pile (1:1:3) Shingless ,50% CS

Cft

0.0000

0.0000

0.00

0.00

0.00

0.00

0.00

0.00

a) Footing

Kg

0.2242

1.3893

2228.55

1972.81

2100.68

b) Column upto PL

Kg

0.1384

0.8584

1375.70

1218.93

1297.31

c) Lift wall

Kg

0.0196

0.1223

194.82

173.67

184.25

d) U.G.W.R

Kg

0.0662

0.4102

658.03

582.48

620.26

e) Grade Beam

Kg

0.0986

0.6112

980.08

867.90

923.99

g) Pile

Kg

0.0000

0.0000

0.00

0.00

0.00

0.00

0.00

0.00

12

13

Re-Bar work (60 Grade)

Form work (M+L)

a) Footing & C.C

Sft

0.0595

0.3693

591.43

524.41

557.92

b) Column upto PL

Sft

0.0515

0.3190

511.91

452.98

482.45

c) Lift wall

Sft

0.0104

0.0644

103.38

91.45

97.41

d) U.G.W.R

Sft

0.0553

0.3431

549.68

487.20

518.44

Sft

0.0620

0.3842

616.28

545.56

580.92

0.00

0.00

0.00

e) Grade Beam
Total (a+e)

Sft

14

12 mm Plaster with NCF (1:6)

Sft

0.0352

0.2186

349.89

310.41

330.15

15

Patent Stone with NCF

Sft

0.0081

0.0501

80.51

71.14

75.83

16

PVC water stopper 10"

Rft

0.0027

0.0166

26.84

23.57

25.21

SI
No

Description of work

Unit

Per Total

Per Floor

Cons Area

Area

Cons Area

Per Total Per Floor


Area

Average

Average

Average

Average

0.00

X) R.C.C work :

0.00

0.00

0.00

A) Ground Floor

0.00

0.00

0.00

a) Column (1:1:3) SC,50% CS

Cft

0.0168

0.1040

166.99

147.68

157.34

b) Lift wall (1:1:3) SC,50% CS

Cft

0.0000

0.0000

0.00

0.00

0.00

c) Beam (1:2:4) BC,50% CS

Cft

0.0206

0.1277

204.76

181.33

193.05

d) Slab (1:2:4) BC,50% CS

Cft

0.0703

0.4359

698.78

618.98

658.88

e) Stair (1:2:4) BC,50% CS

Cft

0.0052

0.0320

51.69

45.44

48.56

f) Lintel (1:2:4) BC, MS

Cft

0.0006

0.0037

5.96

5.25

5.61

g) False Slab (1:2:4) BC, MS

Cft

0.0004

0.0025

3.98

3.55

3.76

h) Sunshed & Drop wall (1:2:4) BC, MS

Cft

0.0004

0.0025

3.98

3.55

3.76

0.00

0.00

0.00

a) Column (1:1:3) SC,50% CS

Cft

0.0160

0.0992

159.04

140.86

149.95

b) Lift wall (1:1:3) SC,50% CS

Cft

0.0000

0.0000

0.00

0.00

0.00

c) Beam (1:2:4) BC,50% CS

Cft

0.0211

0.1308

209.73

185.74

197.74

d) Slab (1:2:4) BC,50% CS

Cft

0.0703

0.4359

698.78

618.98

658.88

e) Stair (1:2:4) BC,50% CS

Cft

0.0052

0.0320

51.69

45.44

48.56

f) Lintel (1:2:4) BC, MS

Cft

0.0022

0.0133

21.87

18.89

20.38

g) False Slab (1:2:4) BC, MS

Cft

0.0039

0.0241

38.77

34.22

36.49

h) Sunshed & Drop wall (1:2:4) BC, MS

Cft

0.0033

0.0204

32.80

28.97

30.89

0.00

0.00

0.00

B) First Floor

C) 2nd Floor
a) Column (1:1:3) SC,50% CS

Cft

0.0160

0.0992

159.04

140.86

149.95

b) Lift wall (1:1:3) SC,50% CS

Cft

0.0000

0.0000

0.00

0.00

0.00

c) Beam (1:2:4) BC,50% CS

Cft

0.0211

0.1308

209.73

185.74

197.74

d) Slab (1:2:4) BC,50% CS

Cft

0.0703

0.4359

698.78

618.98

658.88

e) Stair (1:2:4) BC,50% CS

Cft

0.0052

0.0320

51.69

45.44

48.56

f) Lintel (1:2:4) BC, MS

Cft

0.0022

0.0133

21.87

18.89

20.38

g) False Slab (1:2:4) BC, MS

Cft

0.0039

0.0241

38.77

34.22

36.49

h) Sunshed & Drop wall (1:2:4) BC, MS

Cft

0.0033

0.0204

32.80

28.97

30.89

0.00

0.00

0.00

D) 3rd Floor
a) Column (1:1:3) SC,50% CS

Cft

0.0160

0.0992

159.04

140.86

149.95

b) Lift wall (1:1:3) SC,50% CS

Cft

0.0000

0.0000

0.00

0.00

0.00

c) Beam (1:2:4) BC,50% CS

Cft

0.0211

0.1308

209.73

185.74

197.74

d) Slab (1:2:4) BC,50% CS

Cft

0.0703

0.4359

698.78

618.98

658.88

e) Stair (1:2:4) BC,50% CS

Cft

0.0052

0.0320

51.69

45.44

48.56

f) Lintel (1:2:4) BC, MS

Cft

0.0022

0.0133

21.87

18.89

20.38

g) False Slab (1:2:4) BC, MS

Cft

0.0039

0.0241

38.77

34.22

36.49

h) Sunshed & Drop wall (1:2:4) BC, MS

Cft

0.0033

0.0204

32.80

28.97

30.89

SI
No

Description of work

Unit

Per Total

Per Floor

Cons Area

Area

Cons Area

Area

Average

Average

Average

Average

E) 4th Floor

Per Total Per Floor


0.00

0.00

0.00

0.00

159.04

140.86

149.95

a) Column (1:1:3) SC,50% CS

Cft

0.0160

0.0992

b) Lift wall (1:1:3) SC,50% CS

Cft

0.0000

0.0000

0.00

0.00

0.00

c) Beam (1:2:4) BC,50% CS

Cft

0.0211

0.1308

209.73

185.74

197.74

d) Slab (1:2:4) BC,50% CS

Cft

0.0703

0.4359

698.78

618.98

658.88

e) Stair (1:2:4) BC,50% CS

Cft

0.0052

0.0320

51.69

45.44

48.56

f) Lintel (1:2:4) BC, MS

Cft

0.0022

0.0133

21.87

18.89

20.38

g) False Slab (1:2:4) BC, MS

Cft

0.0039

0.0241

38.77

34.22

36.49

h) Sunshed & Drop wall (1:2:4) BC, MS

Cft

0.0033

0.0204

32.80

28.97

30.89

0.00

0.00

0.00

F) 5th Floor
a) Column (1:1:3) SC,50% CS

Cft

0.0160

0.0992

159.04

140.86

149.95

b) Lift wall (1:1:3) SC,50% CS

Cft

0.0000

0.0000

0.00

0.00

0.00

c) Beam (1:2:4) BC,50% CS

Cft

0.0211

0.1308

209.73

185.74

197.74

d) Slab (1:2:4) BC,50% CS

Cft

0.0703

0.4359

698.78

618.98

658.88

e) Stair (1:2:4) BC,50% CS

Cft

0.0052

0.0320

51.69

45.44

48.56

f) Lintel (1:2:4) BC, MS

Cft

0.0022

0.0133

21.87

18.89

20.38

g) False Slab (1:2:4) BC, MS

Cft

0.0039

0.0241

38.77

34.22

36.49

h) Sunshed & Drop wall (1:2:4) BC, MS

Cft

0.0033

0.0204

32.80

28.97

30.89

0.00

0.00

0.00

G) 6th Floor (Top Floor)


a) Column (1:1:3) SC,50% CS

Cft

0.0033

0.0205

32.80

29.11

30.96

b) Lift M Room (1:1:3) SC,50% CS

Cft

0.0058

0.0360

57.65

51.12

54.39

c) Beam (1:2:4) BC,50% CS

Cft

0.0000

0.0000

0.00

0.00

0.00

d) Slab (1:1:3) SC,50% CS

Cft

0.0000

0.0000

0.00

0.00

0.00

e) Stair (1:2:4) BC,50% CS

Cft

0.0000

0.0000

0.00

0.00

0.00

f) Lintel (1:2:4) BC, MS

Cft

0.0000

0.0000

0.00

0.00

0.00

g) False Slab (1:2:4) BC, MS

Cft

0.0000

0.0000

0.00

0.00

0.00

h) Sunshed & Drop wall (1:2:4) BC, MS

Cft

0.0000

0.0000

0.00

0.00

0.00

j) OHWT (1:1:3) BC,50% CS

Cft

0.0146

0.0907

145.12

128.79

136.96

SI
No

Description of work

Unit

Per Total

Per Floor

Cons Area

Area

Cons Area

Per Total Per Floor


Area

Average

Average

Average

Average

0.00

Y) Re- bar work :

0.00

0.00

0.00

A) Ground Floor

0.00

0.00

0.00

a) Column (60 Grade) in/c 3% wastage

Kg

0.1421

0.8806

1412.47

1250.45

1331.46

b) Lift wall (60 Grade) in/c 3% wastage

Kg

0.0000

0.0000

0.00

0.00

0.00

c) Beam (60 Grade) in/c 3% wastage

Kg

0.1352

0.8395

1343.89

1192.09

1267.99

d) Slab (40 Grade) in/c 3% wastage

Kg

0.2031

1.2602

2018.81

1789.48

1904.15

e) Stair (40 Grade) in/c 3% wastage

Kg

0.0195

0.1207

193.83

171.39

182.61

f) Lintel (40 Grade) in/c 3% wastage

Kg

0.0038

0.0237

37.77

33.65

35.71

g) False Slab (40 Grade) in/c 3% wastage

Kg

0.0024

0.0147

23.86

20.87

22.37

h) Drop wall (40 Grade) in/c 3% wastage

Kg

0.0025

0.0155

24.85

22.01

23.43

0.00

0.00

0.00

B) First Floor
a) Column (60 Grade) in/c 3% wastage

Kg

0.1317

0.8167

1309.10

1159.71

1234.41

b) Lift wall (60 Grade) in/c 3% wastage

Kg

0.0000

0.0000

0.00

0.00

0.00

c) Beam (60 Grade) in/c 3% wastage

Kg

0.1352

0.8395

1343.89

1192.09

1267.99

d) Slab (40 Grade) in/c 3% wastage

Kg

0.2031

1.2602

2018.81

1789.48

1904.15

e) Stair (40 Grade) in/c 3% wastage

Kg

0.0195

0.1207

193.83

171.39

182.61

f) Lintel (40 Grade) in/c 3% wastage

Kg

0.0164

0.1012

163.02

143.70

153.36

g) False Slab (40 Grade) in/c 3% wastage

Kg

0.0142

0.0879

141.15

124.82

132.98

h) Drop wall (40 Grade) in/c 3% wastage

Kg

0.0122

0.0757

121.27

107.49

114.38

0.00

0.00

0.00

C) 2nd Floor
a) Column (60 Grade) in/c 3% wastage

Kg

0.1223

0.7585

1215.66

1077.07

1146.37

b) Lift wall (60 Grade) in/c 3% wastage

Kg

0.0000

0.0000

0.00

0.00

0.00

c) Beam (60 Grade) in/c 3% wastage

Kg

0.1352

0.8395

1343.89

1192.09

1267.99

d) Slab (40 Grade) in/c 3% wastage

Kg

0.2031

1.2602

2018.81

1789.48

1904.15

e) Stair (40 Grade) in/c 3% wastage

Kg

0.0195

0.1207

193.83

171.39

182.61

f) Lintel (40 Grade) in/c 3% wastage

Kg

0.0164

0.1012

163.02

143.70

153.36

g) False Slab (40 Grade) in/c 3% wastage

Kg

0.0142

0.0879

141.15

124.82

132.98

h) Drop wall (40 Grade) in/c 3% wastage

Kg

0.0122

0.0757

121.27

107.49

114.38

0.00

0.00

0.00

a) Column (60 Grade) in/c 3% wastage

Kg

0.1159

0.7185

1152.05

1020.27

1086.16

b) Lift wall (60 Grade) in/c 3% wastage

Kg

0.0000

0.0000

0.00

0.00

0.00

c) Beam (60 Grade) in/c 3% wastage

Kg

0.1352

0.8395

1343.89

1192.09

1267.99

d) Slab (40 Grade) in/c 3% wastage

Kg

0.2031

1.2602

2018.81

1789.48

1904.15

e) Stair (40 Grade) in/c 3% wastage

Kg

0.0195

0.1207

193.83

171.39

182.61

D) 3rd Floor

f) Lintel (40 Grade) in/c 3% wastage

Kg

0.0164

0.1012

163.02

143.70

153.36

g) False Slab (40 Grade) in/c 3% wastage

Kg

0.0142

0.0879

141.15

124.82

132.98

h) Drop wall (40 Grade) in/c 3% wastage

Kg

0.0122

0.0757

121.27

107.49

114.38

SI
No

Description of work

Unit

Per Total

Per Floor

Cons Area

Area

Cons Area

Area

Average

Average

Average

Average

E) 4th Floor

Per Total Per Floor


0.00

0.00

0.00

0.00

1097.38

972.42

1034.90

a) Column (60 Grade) in/c 3% wastage

Kg

0.1104

0.6848

b) Lift wall (60 Grade) in/c 3% wastage

Kg

0.0000

0.0000

0.00

0.00

0.00

c) Beam (60 Grade) in/c 3% wastage

Kg

0.1352

0.8395

1343.89

1192.09

1267.99

d) Slab (40 Grade) in/c 3% wastage

Kg

0.2031

1.2602

2018.81

1789.48

1904.15

e) Stair (40 Grade) in/c 3% wastage

Kg

0.0195

0.1207

193.83

171.39

182.61

f) Lintel (40 Grade) in/c 3% wastage

Kg

0.0164

0.1012

163.02

143.70

153.36

g) False Slab (40 Grade) in/c 3% wastage

Kg

0.0142

0.0879

141.15

124.82

132.98

h) Drop wall (40 Grade) in/c 3% wastage

Kg

0.0122

0.0757

121.27

107.49

114.38

0.00

0.00

0.00

F) 5th Floor
a) Column (60 Grade) in/c 3% wastage

Kg

0.1093

0.6780

1086.44

962.76

1024.60

b) Lift wall (60 Grade) in/c 3% wastage

Kg

0.0000

0.0000

0.00

0.00

0.00

c) Beam (60 Grade) in/c 3% wastage

Kg

0.1352

0.8395

1343.89

1192.09

1267.99

d) Slab (40 Grade) in/c 3% wastage

Kg

0.2031

1.2602

2018.81

1789.48

1904.15

e) Stair (40 Grade) in/c 3% wastage

Kg

0.0195

0.1207

193.83

171.39

182.61

f) Lintel (40 Grade) in/c 3% wastage

Kg

0.0164

0.1012

163.02

143.70

153.36

g) False Slab (40 Grade) in/c 3% wastage

Kg

0.0142

0.0879

141.15

124.82

132.98

h) Drop wall (40 Grade) in/c 3% wastage

Kg

0.0122

0.0757

121.27

107.49

114.38

0.00

0.00

0.00

G) Top Floor
a) Column (60 Grade) in/c 3% wastage

Kg

0.0190

0.1175

188.86

166.85

177.86

b) Lift M Room (60 Grade) in/c 3% wastage

Kg

0.0267

0.1653

265.40

234.73

250.06

c) Beam (60 Grade) in/c 3% wastage

Kg

0.0000

0.0000

0.00

0.00

0.00

d) Slab (40 Grade) in/c 3% wastage

Kg

0.0000

0.0000

0.00

0.00

0.00

e) Stair (40 Grade) in/c 3% wastage

Kg

0.0000

0.0000

0.00

0.00

0.00

f) Lintel (40 Grade) in/c 3% wastage

Kg

0.0000

0.0000

0.00

0.00

0.00

g) False Slab (40 Grade) in/c 3% wastage

Kg

0.0000

0.0000

0.00

0.00

0.00

h) Drop wall (40 Grade) in/c 3% wastage

Kg

0.0000

0.0000

0.00

0.00

0.00

i) OHWT (40 Grade) in/c 3% wastage

Kg

0.0670

0.4158

665.98

590.44

628.21

SI

Description of work

No

Unit

Per Total

Per Floor

Cons Area

Area

Cons Area

Per Total Per Floor


Area

Average

Average

Average

Average

0.00

Z) From work

0.00

0.00

0.00

A) Ground Floor

0.00

0.00

0.00

a) Column

Sft

0.0604

0.3743

600.38

531.51

565.94

b) Lift wall

Sft

0.0000

0.0000

0.00

0.00

0.00

c) Beam

Sft

0.0412

0.2554

409.53

362.67

386.10

d) Slab

Sft

0.1629

1.0107

1619.23

1435.19

1527.21

e) Stair

Sft

0.0161

0.0996

160.03

141.43

150.73

f) Lintel

Sft

0.0041

0.0251

40.75

35.64

38.20

g) False Slab

Sft

0.0018

0.0109

17.89

15.48

16.69

h) Sunshed & Drop wall

Sft

0.0035

0.0214

34.79

30.39

32.59

0.00

0.00

0.00

a) Column

Sft

0.0591

0.3661

587.45

519.86

553.66

b) Lift wall

Sft

0.0000

0.0000

0.00

0.00

0.00

c) Beam

Sft

0.0420

0.2608

417.48

370.34

393.91

d) Slab

Sft

0.1629

1.0107

1619.23

1435.19

1527.21

e) Stair

Sft

0.0161

0.0996

160.03

141.43

150.73

f) Lintel

Sft

0.0102

0.0636

101.39

90.31

95.85

g) False Slab

Sft

0.0149

0.0923

148.11

131.07

139.59

h) Sunshed & Drop wall

Sft

0.0186

0.1153

184.88

163.73

174.31

0.00

0.00

0.00

a) Column

Sft

0.0591

0.3661

587.45

519.86

553.66

b) Lift wall

Sft

0.0000

0.0000

0.00

0.00

0.00

c) Beam

Sft

0.1460

0.9006

1451.24

1278.85

1365.05

d) Slab

Sft

0.1629

1.0107

1619.23

1435.19

1527.21

e) Stair

Sft

0.0161

0.0996

160.03

141.43

150.73

f) Lintel

Sft

0.0130

0.0805

129.22

114.31

121.77

g) False Slab

Sft

0.0209

0.1294

207.75

183.75

195.75

h) Sunshed & Drop wall

Sft

0.0231

0.1434

229.61

203.63

216.62

0.00

0.00

0.00

B) First Floor

C) 2nd Floor

D) 3rd Floor
a) Column

Sft

0.0591

0.3661

587.45

519.86

553.66

b) Lift wall

Sft

0.0000

0.0000

0.00

0.00

0.00

c) Beam

Sft

0.1460

0.9006

1451.24

1278.85

1365.05

d) Slab

Sft

0.1629

1.0107

1619.23

1435.19

1527.21

e) Stair

Sft

0.0161

0.0996

160.03

141.43

150.73

f) Lintel

Sft

0.0130

0.0805

129.22

114.31

121.77

g) False Slab

Sft

0.0209

0.1294

207.75

183.75

195.75

h) Sunshed & Drop wall

Sft

0.0231

0.1434

229.61

203.63

216.62

SI

Description of work

No

Unit

Per Total

Per Floor

Cons Area

Area

Cons Area

Area

Average

Average

Average

Average

E) 4th Floor

Per Total Per Floor


0.00

0.00

0.00

0.00

587.45

519.86

553.66

a) Column

Sft

0.0591

0.3661

b) Lift wall

Sft

0.0000

0.0000

0.00

0.00

0.00

c) Beam

Sft

0.1460

0.9006

1451.24

1278.85

1365.05

d) Slab

Sft

0.1629

1.0107

1619.23

1435.19

1527.21

e) Stair

Sft

0.0161

0.0996

160.03

141.43

150.73

f) Lintel

Sft

0.0130

0.0805

129.22

114.31

121.77

g) False Slab

Sft

0.0209

0.1294

207.75

183.75

195.75

h) Sunshed & Drop wall

Sft

0.0231

0.1434

229.61

203.63

216.62

0.00

0.00

0.00

a) Column

Sft

0.0591

0.3661

587.45

519.86

553.66

b) Lift wall

Sft

0.0000

0.0000

0.00

0.00

0.00

c) Beam

Sft

0.1460

0.9006

1451.24

1278.85

1365.05

d) Slab

Sft

0.1629

1.0107

1619.23

1435.19

1527.21

e) Stair

Sft

0.0161

0.0996

160.03

141.43

150.73

f) Lintel

Sft

0.0130

0.0805

129.22

114.31

121.77

g) False Slab

Sft

0.0209

0.1294

207.75

183.75

195.75

h) Sunshed & Drop wall

Sft

0.0231

0.1434

229.61

203.63

216.62

0.00

0.00

0.00

F) 5th Floor

G) Top Floor
a) Column

Sft

0.0124

0.0766

123.26

108.77

116.01

b) Lift M Room

Sft

0.0151

0.0934

150.09

132.63

141.36

c) Beam

Sft

0.0000

0.0000

0.00

0.00

0.00

d) Slab

Sft

0.0000

0.0000

0.00

0.00

0.00

e) Stair

Sft

0.0000

0.0000

0.00

0.00

0.00

f) Lintel

Sft

0.0000

0.0000

0.00

0.00

0.00

g) False Slab

Sft

0.0000

0.0000

0.00

0.00

0.00

h) Sunshed & Drop wall

Sft

0.0000

0.0000

0.00

0.00

0.00

i) OHWT

Sft

0.0439

0.2720

436.37

386.24

411.30

SI

Description of work

No

Unit

Per Total

Per Floor

Cons Area

Area

Cons Area

Area

Average

Average

Average

Average

0.00

A) Ground Floor
1

0.00

0.00
0.00

Brick Work:
a 10" Thick brick work (1:6)

Cft

0.0015

0.0090

14.91

12.78

13.85

b 5" Thick brick work (1:4)

Sft

0.0952

0.5907

946.29

838.79

892.54

a 25 mm Thick Plaster (1:5) B/W (in side)

Sft

0.1904

1.1811

1892.58

1677.16

1784.87

b 20 mm Thick Plaster (1:5) B/W (out side)

Sft

0.2427

1.5053

2412.44

2137.53

2274.98

c 20 mm Thick Plaster (1:4) on Concrete

Sft

0.2754

1.7085

2737.48

2426.07

2581.77

a Tiles work in Lobby & Stair

Sft

0.0160

0.0993

159.04

141.01

150.02

b Tiles work in Floor

Sft

0.0000

0.0000

0.00

0.00

0.00

c Tiles work in Skirting

Sft

0.0000

0.0000

0.00

0.00

0.00

d Tiles work in Toilet Floor

Sft

0.0000

0.0000

0.00

0.00

0.00

e Tiles work in Toilet wall

Sft

0.0000

0.0000

0.00

0.00

0.00

0.00

0.00

0.00

Plastering Work:

Tiles Work:

Paint Work:
a Ceiling

Sft

0.2754

1.7085

2737.48

2426.07

2581.77

b Wall

Sft

0.1904

1.1811

1892.58

1677.16

1784.87

c Weather coat

Sft

0.2427

1.5053

2412.44

2137.53

2274.98

d Enamel

Sft

0.0018

0.0113

17.89

16.05

16.97

e White washing

Sft

0.0000

0.0000

0.00

0.00

0.00

f French Polish

Sft

0.0000

0.0000

0.00

0.00

0.00

Rft

0.0000

0.0000

0.00

0.00

0.00

b Internal Door Frame

Rft

0.0034

0.0212

33.80

30.10

31.95

c Main Door shutter

Sft

0.0000

0.00

0.00

0.00

d Flush Door shutter

Sft

0.0034

0.0211

33.80

29.96

31.88

e Plastic door with Shutter

Pcs

0.0002

0.0012

1.99

1.70

1.85

f Cat Door work

Pcs

0.0002

0.0012

1.99

1.70

1.85

a Window grill

Sft

0.0037

0.0227

36.78

32.23

34.51

b Varandah safety grill

Sft

0.0000

0.0000

0.00

0.00

0.00

c Varandah railing

Sft

0.0000

0.0000

0.00

0.00

0.00

d Stair railing (Grill)

Sft

0.0028

0.0174

27.83

24.71

26.27

e Stair hand rest

Rft

0.0010

0.0062

9.94

8.80

9.37

a Aluminium Sliding window

Sft

0.0000

0.0000

0.00

0.00

0.00

b Aluminium fixed window

Sft

0.0037

0.0227

36.78

32.23

34.51

c Aluminium Sliding door

Sft

0.0000

0.0000

0.00

0.00

0.00

Door Frame & Door Shutter:


a Main Door Frame

Per Total Per Floor

Grill Work:

Aluminium Work:

Common Work:
a Marble works

Sft

0.0057

0.0356

56.66

50.55

53.61

b Main Gate

Sft

0.0054

0.0332

53.68

47.14

50.41

c Mortice type Door lock

Pcs

0.0002

0.0012

1.99

1.70

1.85

SI

Description of work

No

Unit

Per Total

Per Floor

Cons Area

Area

Cons Area

Per Total Per Floor


Area

Average

Average

Average

Average

0.00

B) First Floor
1

Brick Work:
a 10" Thick brick work (1:6)

Cft

0.0160

0.0995

159.04

141.29

150.17

b 5" Thick brick work (1:4)

Sft

0.2305

1.4302

2291.17

2030.88

2161.03

a 25 mm Thick Plaster (1:5) B/W (in side)

Sft

0.4255

2.6424

4229.47

3752.21

3990.84

b 20 mm Thick Plaster (1:5) B/W (out side)

Sft

0.1092

0.6774

1085.45

961.91

1023.68

c 20 mm Thick Plaster (1:4) on Concrete

Sft

0.2054

1.2738

2041.68

1808.80

1925.24

a Tiles work in Lobby & Stair

Sft

0.0148

0.0918

147.11

130.36

138.73

b Tiles work in Floor

Sft

0.1224

0.7595

1216.66

1078.49

1147.57

c Tiles work in Skirting

Sft

0.0146

0.0904

145.12

128.37

136.75

d Tiles work in Toilet Floor

Sft

0.0136

0.0844

135.18

119.85

127.52

e Tiles work in Toilet wall

Sft

0.0751

0.4664

746.49

662.29

704.39

0.00

0.00

0.00

a Ceiling

Sft

0.2054

1.2738

2041.68

1808.80

1925.24

b Wall

Sft

0.4250

2.6390

4224.50

3747.38

3985.94

c Weather coat

Sft

0.1092

0.6774

1085.45

961.91

1023.68

d Enamel

Sft

0.0416

0.2581

413.50

366.50

390.00

e White washing

Sft

0.0180

0.1121

178.92

159.18

169.05

f French Polish

Sft

0.0303

0.1880

301.18

266.96

284.07

Rft

0.0018

0.0110

17.89

15.62

16.76

b Internal Door Frame

Rft

0.0062

0.0384

61.63

54.53

58.08

c Main Door shutter

Sft

0.0023

0.0140

22.86

19.88

21.37

d Flush Door shutter

Sft

0.0085

0.0524

84.49

74.41

79.45

e Plastic door with Shutter

Pcs

0.0006

0.0036

5.96

5.11

5.54

f Cat Door work

Pcs

0.0005

0.0028

4.97

3.98

4.47

Plastering Work:

Tiles Work:

Paint Work:

Door Frame & Door Shutter:


a Main Door Frame

Grill Work:
a Window grill

Sft

0.0151

0.0935

150.09

132.77

141.43

b Varandah safety grill

Sft

0.0165

0.1022

164.01

145.12

154.57

c Varandah railing

Sft

0.0092

0.0568

91.45

80.66

86.05

d Stair railing (Grill)

Sft

0.0028

0.0174

27.83

24.71

26.27

e Stair hand rest

Rft

0.0010

0.0062

9.94

8.80

9.37

a Aluminium Sliding window

Sft

0.0116

0.0721

115.30

102.38

108.84

b Aluminium fixed window

Sft

0.0100

0.0619

99.40

87.90

93.65

c Aluminium Sliding door

Sft

0.0107

0.0667

106.36

94.71

100.54

a Marble works

Sft

0.0024

0.0152

23.86

21.58

22.72

b Main Gate

Pcs

0.0001

0.0006

0.99

0.85

0.92

c Mortice type Door lock

Pcs

0.0007

0.0040

6.96

5.68

6.32

Aluminium Work:

Common Work:

SI

Description of work

No

Unit

Per Total

Per Floor

Cons Area

Area

Cons Area

Per Total Per Floor


Area

Average

Average

Average

Average

0.00

C) 2nd Floor
1

Brick Work:
a 10" Thick brick work (1:6)

Cft

0.0160

0.0995

159.04

141.29

150.17

b 5" Thick brick work (1:4)

Sft

0.2305

1.4302

2291.17

2030.88

2161.03

a 25 mm Thick Plaster (1:5) B/W (in side)

Sft

0.4255

2.6424

4229.47

3752.21

3990.84

b 20 mm Thick Plaster (1:5) B/W (out side)

Sft

0.1092

0.6774

1085.45

961.91

1023.68

c 20 mm Thick Plaster (1:4) on Concrete

Sft

0.2054

1.2738

2041.68

1808.80

1925.24

a Tiles work in Lobby & Stair

Sft

0.0148

0.0918

147.11

130.36

138.73

b Tiles work in Floor

Sft

0.1224

0.7595

1216.66

1078.49

1147.57

c Tiles work in Skirting

Sft

0.0146

0.0904

145.12

128.37

136.75

d Tiles work in Toilet Floor

Sft

0.0136

0.0844

135.18

119.85

127.52

e Tiles work in Toilet wall

Sft

0.0751

0.4664

746.49

662.29

704.39

0.00

0.00

0.00

a Ceiling

Sft

0.2054

1.2738

2041.68

1808.80

1925.24

b Wall

Sft

0.4250

2.6390

4224.50

3747.38

3985.94

c Weather coat

Sft

0.1092

0.6774

1085.45

961.91

1023.68

d Enamel

Sft

0.0416

0.2581

413.50

366.50

390.00

e White washing

Sft

0.0180

0.1121

178.92

159.18

169.05

f French Polish

Sft

0.0303

0.1880

301.18

266.96

284.07

Rft

0.0018

0.0110

17.89

15.62

16.76

b Internal Door Frame

Rft

0.0062

0.0384

61.63

54.53

58.08

c Main Door shutter

Sft

0.0023

0.0140

22.86

19.88

21.37

d Flush Door shutter

Sft

0.0085

0.0524

84.49

74.41

79.45

e Plastic door with Shutter

Pcs

0.0006

0.0036

5.96

5.11

5.54

f Cat Door work

Pcs

0.0005

0.0028

4.97

3.98

4.47

Plastering Work:

Tiles Work:

Paint Work:

Door Frame & Door Shutter:


a Main Door Frame

Grill Work:
a Window grill

Sft

0.0151

0.0935

150.09

132.77

141.43

b Varandah safety grill

Sft

0.0165

0.1022

164.01

145.12

154.57

c Varandah railing

Sft

0.0092

0.0568

91.45

80.66

86.05

d Stair railing (Grill)

Sft

0.0028

0.0174

27.83

24.71

26.27

e Stair hand rest

Rft

0.0010

0.0062

9.94

8.80

9.37

a Aluminium Sliding window

Sft

0.0116

0.0721

115.30

102.38

108.84

b Aluminium fixed window

Sft

0.0100

0.0619

99.40

87.90

93.65

c Aluminium Sliding door

Sft

0.0107

0.0667

106.36

94.71

100.54

a Marble works

Sft

0.0024

0.0152

23.86

21.58

22.72

b Main Gate

Pcs

0.0001

0.0006

0.99

0.85

0.92

c Mortice type Door lock

Pcs

0.0007

0.0040

6.96

5.68

6.32

Aluminium Work:

Common Work:

SI

Description of work

No

Unit

Per Total

Per Floor

Cons Area

Area

Cons Area

Per Total Per Floor


Area

Average

Average

Average

Average

0.00

D) 3rd Floor
1

Brick Work:
a 10" Thick brick work (1:6)

Cft

0.0160

0.0995

159.04

141.29

150.17

b 5" Thick brick work (1:4)

Sft

0.2305

1.4302

2291.17

2030.88

2161.03

a 25 mm Thick Plaster (1:5) B/W (in side)

Sft

0.4255

2.6424

4229.47

3752.21

3990.84

b 20 mm Thick Plaster (1:5) B/W (out side)

Sft

0.1092

0.6774

1085.45

961.91

1023.68

c 20 mm Thick Plaster (1:4) on Concrete

Sft

0.2054

1.2738

2041.68

1808.80

1925.24

a Tiles work in Lobby & Stair

Sft

0.0148

0.0918

147.11

130.36

138.73

b Tiles work in Floor

Sft

0.1224

0.7595

1216.66

1078.49

1147.57

c Tiles work in Skirting

Sft

0.0146

0.0904

145.12

128.37

136.75

d Tiles work in Toilet Floor

Sft

0.0136

0.0844

135.18

119.85

127.52

e Tiles work in Toilet wall

Sft

0.0751

0.4664

746.49

662.29

704.39

0.00

0.00

0.00

a Ceiling

Sft

0.2054

1.2738

2041.68

1808.80

1925.24

b Wall

Sft

0.4250

2.6390

4224.50

3747.38

3985.94

c Weather coat

Sft

0.1092

0.6774

1085.45

961.91

1023.68

d Enamel

Sft

0.0416

0.2581

413.50

366.50

390.00

e White washing

Sft

0.0180

0.1121

178.92

159.18

169.05

f French Polish

Sft

0.0303

0.1880

301.18

266.96

284.07

Rft

0.0018

0.0110

17.89

15.62

16.76

b Internal Door Frame

Rft

0.0062

0.0384

61.63

54.53

58.08

c Main Door shutter

Sft

0.0023

0.0140

22.86

19.88

21.37

d Flush Door shutter

Sft

0.0085

0.0524

84.49

74.41

79.45

e Plastic door with Shutter

Pcs

0.0006

0.0036

5.96

5.11

5.54

f Cat Door work

Pcs

0.0005

0.0028

4.97

3.98

4.47

Plastering Work:

Tiles Work:

Paint Work:

Door Frame & Door Shutter:


a Main Door Frame

Grill Work:
a Window grill

Sft

0.0151

0.0935

150.09

132.77

141.43

b Varandah safety grill

Sft

0.0165

0.1022

164.01

145.12

154.57

c Varandah railing

Sft

0.0092

0.0568

91.45

80.66

86.05

d Stair railing (Grill)

Sft

0.0028

0.0174

27.83

24.71

26.27

e Stair hand rest

Rft

0.0010

0.0062

9.94

8.80

9.37

a Aluminium Sliding window

Sft

0.0116

0.0721

115.30

102.38

108.84

b Aluminium fixed window

Sft

0.0100

0.0619

99.40

87.90

93.65

c Aluminium Sliding door

Sft

0.0107

0.0667

106.36

94.71

100.54

a Marble works

Sft

0.0024

0.0152

23.86

21.58

22.72

b Main Gate

Pcs

0.0001

0.0006

0.99

0.85

0.92

c Mortice type Door lock

Pcs

0.0007

0.0040

6.96

5.68

6.32

Aluminium Work:

Common Work:

SI

Description of work

No

Unit

Per Total

Per Floor

Cons Area

Area

Cons Area

Area

Average

Average

Average

Average

E) 4th Floor
1

0.00

0.00

0.00

0.00

Brick Work:
a 10" Thick brick work (1:6)

Cft

0.0160

0.0995

159.04

141.29

150.17

b 5" Thick brick work (1:4)

Sft

0.2305

1.4302

2291.17

2030.88

2161.03

a 25 mm Thick Plaster (1:5) B/W (in side)

Sft

0.4255

2.6424

4229.47

3752.21

3990.84

b 20 mm Thick Plaster (1:5) B/W (out side)

Sft

0.1092

0.6774

1085.45

961.91

1023.68

c 20 mm Thick Plaster (1:4) on Concrete

Sft

0.2054

1.2738

2041.68

1808.80

1925.24

a Tiles work in Lobby & Stair

Sft

0.0148

0.0918

147.11

130.36

138.73

b Tiles work in Floor

Sft

0.1224

0.7595

1216.66

1078.49

1147.57

c Tiles work in Skirting

Sft

0.0146

0.0904

145.12

128.37

136.75

d Tiles work in Toilet Floor

Sft

0.0136

0.0844

135.18

119.85

127.52

e Tiles work in Toilet wall

Sft

0.0751

0.4664

746.49

662.29

704.39

0.00

0.00

0.00

a Ceiling

Sft

0.2054

1.2738

2041.68

1808.80

1925.24

b Wall

Sft

0.4250

2.6390

4224.50

3747.38

3985.94

c Weather coat

Sft

0.1092

0.6774

1085.45

961.91

1023.68

d Enamel

Sft

0.0416

0.2581

413.50

366.50

390.00

e White washing

Sft

0.0180

0.1121

178.92

159.18

169.05

f French Polish

Sft

0.0303

0.1880

301.18

266.96

284.07

Rft

0.0018

0.0110

17.89

15.62

16.76

b Internal Door Frame

Rft

0.0062

0.0384

61.63

54.53

58.08

c Main Door shutter

Sft

0.0023

0.0140

22.86

19.88

21.37

d Flush Door shutter

Sft

0.0085

0.0524

84.49

74.41

79.45

e Plastic door with Shutter

Pcs

0.0006

0.0036

5.96

5.11

5.54

f Cat Door work

Pcs

0.0005

0.0028

4.97

3.98

4.47

Plastering Work:

Tiles Work:

Paint Work:

Door Frame & Door Shutter:


a Main Door Frame

Per Total Per Floor

Grill Work:
a Window grill

Sft

0.0151

0.0935

150.09

132.77

141.43

b Varandah safety grill

Sft

0.0165

0.1022

164.01

145.12

154.57

c Varandah railing

Sft

0.0092

0.0568

91.45

80.66

86.05

d Stair railing (Grill)

Sft

0.0028

0.0174

27.83

24.71

26.27

e Stair hand rest

Rft

0.0010

0.0062

9.94

8.80

9.37

a Aluminium Sliding window

Sft

0.0116

0.0721

115.30

102.38

108.84

b Aluminium fixed window

Sft

0.0100

0.0619

99.40

87.90

93.65

c Aluminium Sliding door

Sft

0.0107

0.0667

106.36

94.71

100.54

a Marble works

Sft

0.0024

0.0152

23.86

21.58

22.72

b Main Gate

Pcs

0.0001

0.0006

0.99

0.85

0.92

c Mortice type Door lock

Pcs

0.0007

0.0040

6.96

5.68

6.32

Aluminium Work:

Common Work:

SI

Description of work

No

Unit

Per Total

Per Floor

Cons Area

Area

Cons Area

Area

Average

Average

Average

Average

F) 5th Floor
1

0.00

0.00

0.00

0.00

Brick Work:
a 10" Thick brick work (1:6)

Cft

0.0160

0.0995

159.04

141.29

150.17

b 5" Thick brick work (1:4)

Sft

0.2305

1.4302

2291.17

2030.88

2161.03

a 25 mm Thick Plaster (1:5) B/W (in side)

Sft

0.4255

2.6424

4229.47

3752.21

3990.84

b 20 mm Thick Plaster (1:5) B/W (out side)

Sft

0.1092

0.6774

1085.45

961.91

1023.68

c 20 mm Thick Plaster (1:4) on Concrete

Sft

0.2054

1.2738

2041.68

1808.80

1925.24

a Tiles work in Lobby & Stair

Sft

0.0148

0.0918

147.11

130.36

138.73

b Tiles work in Floor

Sft

0.1224

0.7595

1216.66

1078.49

1147.57

c Tiles work in Skirting

Sft

0.0146

0.0904

145.12

128.37

136.75

d Tiles work in Toilet Floor

Sft

0.0136

0.0844

135.18

119.85

127.52

e Tiles work in Toilet wall

Sft

0.0751

0.4664

746.49

662.29

704.39

0.00

0.00

0.00

a Ceiling

Sft

0.2054

1.2738

2041.68

1808.80

1925.24

b Wall

Sft

0.4250

2.6390

4224.50

3747.38

3985.94

c Weather coat

Sft

0.1092

0.6774

1085.45

961.91

1023.68

d Enamel

Sft

0.0416

0.2581

413.50

366.50

390.00

e White washing

Sft

0.0180

0.1121

178.92

159.18

169.05

f French Polish

Sft

0.0303

0.1880

301.18

266.96

284.07

Rft

0.0018

0.0110

17.89

15.62

16.76

b Internal Door Frame

Rft

0.0062

0.0384

61.63

54.53

58.08

c Main Door shutter

Sft

0.0023

0.0140

22.86

19.88

21.37

d Flush Door shutter

Sft

0.0085

0.0524

84.49

74.41

79.45

e Plastic door with Shutter

Pcs

0.0006

0.0036

5.96

5.11

5.54

f Cat Door work

Pcs

0.0005

0.0028

4.97

3.98

4.47

Plastering Work:

Tiles Work:

Paint Work:

Door Frame & Door Shutter:


a Main Door Frame

Per Total Per Floor

Grill Work:
a Window grill

Sft

0.0151

0.0935

150.09

132.77

141.43

b Varandah safety grill

Sft

0.0165

0.1022

164.01

145.12

154.57

c Varandah railing

Sft

0.0092

0.0568

91.45

80.66

86.05

d Stair railing (Grill)

Sft

0.0028

0.0174

27.83

24.71

26.27

e Stair hand rest

Rft

0.0010

0.0062

9.94

8.80

9.37

a Aluminium Sliding window

Sft

0.0116

0.0721

115.30

102.38

108.84

b Aluminium fixed window

Sft

0.0100

0.0619

99.40

87.90

93.65

c Aluminium Sliding door

Sft

0.0107

0.0667

106.36

94.71

100.54

a Marble works

Sft

0.0024

0.0152

23.86

21.58

22.72

b Main Gate

Pcs

0.0001

0.0006

0.99

0.85

0.92

c Mortice type Door lock

Pcs

0.0007

0.0040

6.96

5.68

6.32

Aluminium Work:

Common Work:

SI

Description of work

No

Unit

Per Total

Per Floor

Cons Area

Area

Cons Area

Area

Average

Average

Average

Average

G) Top Floor
1

Per Total Per Floor


0.00

0.00

0.00

0.00

Brick Work:
a 10" Thick brick work (1:6)

Cft

0.0050

0.0310

49.70

44.02

46.86

b 5" Thick brick work (1:4)

Sft

0.0609

0.3779

605.35

536.62

570.98

a 25 mm Thick Plaster (1:5) B/W (in side)

Sft

0.0626

0.3882

622.24

551.24

586.74

b 20 mm Thick Plaster (1:5) B/W (out side)

Sft

0.1382

0.8573

1373.71

1217.37

1295.54

c 20 mm Thick Plaster (1:4) on Concrete

Sft

0.0245

0.1518

243.53

215.56

229.54

a Tiles work in Lobby & Stair

Sft

0.0005

0.0031

4.97

4.40

4.69

b Tiles work in Floor

Sft

0.0101

0.0623

100.39

88.47

94.43

c Tiles work in Skirting

Sft

0.0019

0.0118

18.89

16.76

17.82

d Tiles work in Toilet Floor

Sft

0.0010

0.0059

9.94

8.38

9.16

e Tiles work in Toilet wall

Sft

0.0056

0.0349

55.66

49.56

52.61

0.00

0.00

0.00

a Ceiling

Sft

0.0245

0.1518

243.53

215.56

229.54

b Wall

Sft

0.0626

0.3882

622.24

551.24

586.74

c Weather coat

Sft

0.1382

0.8573

1373.71

1217.37

1295.54

d Enamel

Sft

0.0005

0.0031

4.97

4.40

4.69

e White washing

Sft

0.0000

0.0000

0.00

0.00

0.00

f French Polish

Sft

0.0000

0.0000

0.00

0.00

0.00

a MS Door Frame

Pcs

0.0001

0.0006

0.99

0.85

0.92

b MS Door shutter

Sft

0.0011

0.0068

10.93

9.66

10.30

c Plastic door

Pcs

0.0000

0.0000

0.00

0.00

0.00

d Cat Door work

Pcs

0.0000

0.0000

0.00

0.00

0.00

Plastering Work:

Tiles Work:

Paint Work:

Door Frame & Door Shutter:

Grill Work:
a Window grill

Sft

0.0000

0.0000

0.00

0.00

0.00

b Varandah safety grill

Sft

0.0000

0.0000

0.00

0.00

0.00

c Varandah railing

Sft

0.0000

0.0000

0.00

0.00

0.00

d Stair railing (Grill)

Sft

0.0005

0.0030

4.97

4.26

4.62

e Stair hand rest

Rft

0.0002

0.0012

1.99

1.70

1.85

a Aluminium Sliding window

Sft

0.0000

0.0000

0.00

0.00

0.00

b Aluminium fixed window

Sft

0.0000

0.0000

0.00

0.00

0.00

c Aluminium Sliding door

Sft

0.0000

0.0000

0.00

0.00

0.00

a Marble works

Sft

0.0000

0.0000

0.00

0.00

0.00

b Main Door lock

Pcs

0.0000

0.0000

0.00

0.00

0.00

c Mortice type Door lock

Pcs

0.0000

0.0000

0.00

0.00

0.00

d Lime terracing (4" thick.)

Cft.

0.0302

0.1876

300.19

266.39

283.29

e Ground Floor Decoration & Finishing

Sft

0.1570

0.9752

1560.58

1384.78

1472.68

f Roofing with Fibre glass sheet & MS Truss

Sft

0.0736

0.4551

731.58

646.24

688.91

g NCF in OHWT

Sft

0.0293

0.1816

291.24

257.87

274.56

h False Ceiling with Gypsum board

Sft

0.0299

0.1856

297.21

263.55

280.38

Aluminium Work:

Common Work:

TD

Nagar, Dhaka-1000.
9940
1420

r Cons.area

Remarks

Remarks

Remarks

Remarks

Remarks

Remarks

Remarks

Remarks

Remarks

Remarks

Remarks

Remarks

Remarks

Remarks

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

Bill of Quantity (BOQ)

Name of the Project

Location

Nos of floor

Nos

Nos of Flat

Nos

Nos of Car Perking

Nos

Completion Time

27

Month

Per Floor Area

1420

Sft

Total construction Area

9940

Sft

SI

Description

No

Kaizuddin Tower ( 7th floor), 176 Shahid


Nazrul Islam Sharani, Bijoy Nagar, Dhaka-

Unit

Amount

Date: 13 April, 2010

Per Sft Cost

Sub-Structure

Tk

1089320.00

109.59

Super-Structure (Structure work)

Tk

3870528.00

389.39

Super-Structure (Finishing work)

Tk

4788508.00

481.74

Total Civil work (A+B+C)

Tk

9748356.00

980.72

r, Dhaka-1000.

loor), 176 Shahid

Bijoy Nagar, Dhaka-

e: 13 April, 2010

Remarks

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.
Date: 13 April, 2010

Civil Contractor Bill


Sl
No

Description

Unit

Qty

Rate

Foundation Upto PL

Sft

1420

70.00

99400.00

Ground Floor

Sft

1420

113.00

160460.00

1st Floor

Sft

1420

119.78

170087.60

2nd Floor

Sft

1420

126.56

179715.20

3rd Floor

Sft

1420

133.34

189342.80

4th Floor

Sft

1420

140.12

198970.40

5th Floor

Sft

1420

146.90

208598.00

6th Floor

Sft

1420

153.68

218225.60

Top Floor

Sft

1420

56.50

80230.00

TOTAL

Amount

1505029.60

Remarks

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

Bill of Quantity (BOQ)

Name of the Project

Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul


Islam Sharani, Bijoy Nagar, Dhaka-1000.

Location

Nos of floor

Nos

Nos of Flat

Nos

Nos of Car Perking

Nos

Completion Time

27

Month

Per Floor Area

1420

Sft

Total construction Area

9940

Sft

SI
No

Date: 13 April, 2010

Unit

Amount

A Sub-Structure

Tk

1089320.00

109.59

Super-Structure (Structure work)

Tk

3870528.00

389.39

Super-Structure (Finishing work)

Tk

4788508.00

481.74

Total Civil work (A+B+C)

Tk

9748356.00

980.72

Description

Per Sft Cost

Remarks

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.
Bill of Quantity (Civil Work)

A. Sub-Structure
Name of the Project :
SI
No
1 Lay-out

Description of work

Unit

Quantity

Rate

Amount

LS

1887.04

0.50

944.00

Earth Excavation

Cft

9033.61

2.00

18067.00

Earth filling

Cft

3011.32

1.00

3011.00

Sand filling

Cft

3774.01

11.70

44156.00

3" thick C.C work (1:3:6) BC,MS

Cft

194.97

124.64

24301.00

4" thick C.C work (1:2:4) BC,50% CS

Cft

912.07

146.56

133672.00

Dressing & Leveling

Sft

2485.14

1.00

2485.00

One Layer Brick flat soling

Sft

2666.05

19.65

52388.00

Polythene sheel laying (Double layer)

Sft

2653.55

3.25

8624.00

Rft

0.00

0.00

0.00

a) Footing (1:1:3) SC,50% CS

Cft

1153.68

198.24

228705.00

b) Column upto PL (1:1:3) SC,50% CS

Cft

156.27

198.24

30979.00

c) Lift wall (1:1:3) SC,50% CS

Cft

50.48

198.24

10007.00

d) U.G.W.R (1:1:3) BC,50% CS

Cft

162.31

198.24

32176.00

e) Grade Beam (1:2:4) BC,50% CS

Cft

182.83

156.05

28530.00

f) U.G.W.R Top Slab (1:2:4) BC,50% CS

Cft

42.17

156.05

6581.00

g) Pile (1:1:3) Shingless ,50% CS

Cft

0.00

0.00

0.00

a) Footing

Kg

2100.68

b) Column upto PL

Kg

1297.31

62.90

429497.00

10 Pile boring
11 R.C.C work :

12 Re-Bar work (60 Grade)

c) Lift wall

Kg

184.25

d) U.G.W.R

Kg

1139.65

e) Grade Beam

Kg

1907.48

g) Pile

Kg

0.00

Kg

6629.36

Kg

6828.24

a) Footing & C.C

Sft

557.92

b) Column upto PL

Sft

482.45

c) Lift wall

Sft

97.41

d) U.G.W.R

Sft

518.44

e) Grade Beam

Sft

580.92

Total (a+g)
in/c 3% wastage
13 Form work (M+L)

Sft

2237.14

12.50

27964.00

14 12 mm Plaster with NCF (1:6)

Total (a+e)

Sft

330.15

11.40

3764.00

15 Patent Stone with NCF

Sft

75.83

12.50

948.00

16 PVC water stopper 10"

Rft

25.21

100.00

2521.00
1089320.00

Remarks

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

B. Super-Structure (Structure work)


SI
No

Description of work

Unit

Quantity

Rate

Amount

X) R.C.C work :
A) Ground Floor
a) Column (1:1:3) SC,50% CS

Cft

157.34

198.24

31190.00

b) Lift wall (1:1:3) SC,50% CS

Cft

0.00

198.24

0.00

c) Beam (1:2:4) BC,50% CS

Cft

193.05

144.16

27830.00

d) Slab (1:2:4) BC,50% CS

Cft

658.88

144.16

94984.00

e) Stair (1:2:4) BC,50% CS

Cft

48.56

144.16

7001.00

f) Lintel (1:2:4) BC, MS

Cft

5.61

150.31

843.00

g) False Slab (1:2:4) BC, MS

Cft

3.76

150.31

566.00

Cft

3.76

150.31

566.00

a) Column (1:1:3) SC,50% CS

Cft

149.95

199.49

29914.00

b) Lift wall (1:1:3) SC,50% CS

Cft

0.00

199.49

0.00

c) Beam (1:2:4) BC,50% CS

Cft

197.74

145.41

28753.00

d) Slab (1:2:4) BC,50% CS

Cft

658.88

145.41

95808.00

e) Stair (1:2:4) BC,50% CS

Cft

48.56

145.41

7062.00

h) Sunshed & Drop wall (1:2:4) BC, MS


Sub-Total (a+h)
B) First Floor

f) Lintel (1:2:4) BC, MS

Cft

20.38

150.31

3063.00

g) False Slab (1:2:4) BC, MS

Cft

36.49

150.31

5485.00

h) Sunshed & Drop wall (1:2:4) BC, MS

Cft

30.89

150.31

4642.00

a) Column (1:1:3) SC,50% CS

Cft

149.95

199.49

29914.00

b) Lift wall (1:1:3) SC,50% CS

Cft

0.00

199.49

0.00

Sub-Total (a+h)
C) 2nd Floor

c) Beam (1:2:4) BC,50% CS

Cft

197.74

145.41

28753.00

d) Slab (1:2:4) BC,50% CS

Cft

658.88

145.41

95808.00

e) Stair (1:2:4) BC,50% CS

Cft

48.56

145.41

7062.00

f) Lintel (1:2:4) BC, MS

Cft

20.38

150.31

3063.00

g) False Slab (1:2:4) BC, MS

Cft

36.49

150.31

5485.00

h) Sunshed & Drop wall (1:2:4) BC, MS

Cft

30.89

150.31

4642.00

a) Column (1:1:3) SC,50% CS

Cft

149.95

199.49

29914.00

b) Lift wall (1:1:3) SC,50% CS

Cft

0.00

199.49

0.00

c) Beam (1:2:4) BC,50% CS

Cft

197.74

145.41

28753.00

d) Slab (1:2:4) BC,50% CS

Cft

658.88

145.41

95808.00

e) Stair (1:2:4) BC,50% CS

Cft

48.56

145.41

7062.00

f) Lintel (1:2:4) BC, MS

Cft

20.38

150.31

3063.00

g) False Slab (1:2:4) BC, MS

Cft

36.49

150.31

5485.00

Cft

30.89

150.31

4642.00

R.C.C work Sub-Total

687161.00

Sub-Total (a+h)
D) 3rd Floor

h) Sunshed & Drop wall (1:2:4) BC, MS


Sub-Total (a+h)

Remarks

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

B. Super-Structure (Structure work)


SI
No

Description of work

Unit

Quantity

E) 4th Floor

Rate

Amount

BF=

687161.00

149.95

199.49

29914.00

Cft

0.00

199.49

0.00

Cft

197.74

145.41

28753.00

d) Slab (1:2:4) BC,50% CS

Cft

658.88

145.41

95808.00

e) Stair (1:2:4) BC,50% CS

Cft

48.56

145.41

7062.00

f) Lintel (1:2:4) BC, MS

Cft

20.38

150.31

3063.00

g) False Slab (1:2:4) BC, MS

Cft

36.49

150.31

5485.00

h) Sunshed & Drop wall (1:2:4) BC, MS

Cft

30.89

150.31

4642.00

a) Column (1:1:3) SC,50% CS

Cft

149.95

199.49

29914.00

b) Lift wall (1:1:3) SC,50% CS

Cft

0.00

199.49

0.00

a) Column (1:1:3) SC,50% CS

Cft

b) Lift wall (1:1:3) SC,50% CS


c) Beam (1:2:4) BC,50% CS

Sub-Total (a+h)
F) 5th Floor

c) Beam (1:2:4) BC,50% CS

Cft

197.74

145.41

28753.00

d) Slab (1:2:4) BC,50% CS

Cft

658.88

145.41

95808.00

e) Stair (1:2:4) BC,50% CS

Cft

48.56

145.41

7062.00

f) Lintel (1:2:4) BC, MS

Cft

20.38

150.31

3063.00

g) False Slab (1:2:4) BC, MS

Cft

36.49

150.31

5485.00

Cft

30.89

150.31

4642.00

a) Column (1:1:3) SC,50% CS

Cft

149.95

199.49

29914.00

b) Lift wall (1:1:3) SC,50% CS

Cft

0.00

199.49

0.00

c) Beam (1:2:4) BC,50% CS

Cft

197.74

145.41

28753.00

d) Slab (1:2:4) BC,50% CS

Cft

658.88

145.41

95808.00

e) Stair (1:2:4) BC,50% CS

Cft

48.56

145.41

7062.00

f) Lintel (1:2:4) BC, MS

Cft

20.38

150.31

3063.00

g) False Slab (1:2:4) BC, MS

Cft

36.49

150.31

5485.00

Cft

30.89

150.31

4642.00

a) Column (1:1:3) SC,50% CS

Cft

30.96

199.49

6175.00

b) Lift M Room (1:1:3) SC,50% CS

Cft

54.39

199.49

10849.00

h) Sunshed & Drop wall (1:2:4) BC, MS


Sub-Total (a+h)
G) 6th Floor

h) Sunshed & Drop wall (1:2:4) BC, MS


Sub-Total (a+h)
H) 7th Floor (Top Floor)

c) Beam (1:2:4) BC,50% CS

Cft

0.00

145.41

0.00

d) Slab (1:1:3) SC,50% CS

Cft

0.00

145.41

0.00

e) Stair (1:2:4) BC,50% CS

Cft

0.00

145.41

0.00

f) Lintel (1:2:4) BC, MS

Cft

0.00

150.31

0.00

g) False Slab (1:2:4) BC, MS

Cft

0.00

150.31

0.00

h) Sunshed & Drop wall (1:2:4) BC, MS

Cft

0.00

150.31

0.00

Cft

136.96

121.64

16660.00

R.C.C work Total

1245026.00

j) OHWT (1:1:3) BC,50% CS


Sub-Total (a+j)

Remarks

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

B. Super-Structure (Structure work)


SI
No

Description of work

Unit

Quantity

Rate

Amount

Y) Re- bar work :


A) Ground Floor
a) Column (60 Grade) in/c 3% wastage

Kg

1331.46

62.90

83749.00

b) Lift wall (60 Grade) in/c 3% wastage

Kg

0.00

62.90

0.00

c) Beam (60 Grade) in/c 3% wastage

Kg

1267.99

62.90

79757.00

d) Slab (60 Grade) in/c 3% wastage

Kg

1904.15

62.90

119771.00

e) Stair (60 Grade) in/c 3% wastage

Kg

182.61

62.90

11486.00

f) Lintel (60 Grade) in/c 3% wastage

Kg

35.71

62.90

2246.00

g) False Slab (60 Grade) in/c 3% wastage

Kg

22.37

62.90

1407.00

h) Sunshed & Drop wall (60 Grade) in/c 3% wastage

Kg

23.43

62.90

1474.00

Kg

4767.72

a) Column (60 Grade) in/c 3% wastage

Kg

1234.41

63.20

78014.00

b) Lift wall (60 Grade) in/c 3% wastage

Kg

0.00

63.20

0.00

c) Beam (60 Grade) in/c 3% wastage

Kg

1267.99

63.20

80137.00

d) Slab (60 Grade) in/c 3% wastage

Kg

1904.15

63.20

120342.00

e) Stair (60 Grade) in/c 3% wastage

Kg

182.61

63.20

11541.00

f) Lintel (60 Grade) in/c 3% wastage

Kg

153.36

63.20

9692.00

g) False Slab (60 Grade) in/c 3% wastage

Kg

132.98

63.20

8405.00

h) Sunshed & Drop wall (60 Grade) in/c 3% wastage

Kg

114.38

63.20

7229.00

Kg

4989.88

a) Column (60 Grade) in/c 3% wastage

Kg

1146.37

63.20

72450.00

b) Lift wall (60 Grade) in/c 3% wastage

Kg

0.00

63.20

0.00

Sub-Total (a+h)
B) First Floor

Sub-Total (a+h)
C) 2nd Floor

c) Beam (60 Grade) in/c 3% wastage

Kg

1267.99

63.20

80137.00

d) Slab (60 Grade) in/c 3% wastage

Kg

1904.15

63.20

120342.00

e) Stair (60 Grade) in/c 3% wastage

Kg

182.61

63.20

11541.00

f) Lintel (60 Grade) in/c 3% wastage

Kg

153.36

63.20

9692.00

g) False Slab (60 Grade) in/c 3% wastage

Kg

132.98

63.20

8405.00

h) Sunshed & Drop wall (60 Grade) in/c 3% wastage

Kg

114.38

63.20

7229.00

Kg

4901.84

a) Column (60 Grade) in/c 3% wastage

Kg

1086.16

63.20

68645.00

b) Lift wall (60 Grade) in/c 3% wastage

Kg

0.00

63.20

0.00

c) Beam (60 Grade) in/c 3% wastage

Kg

1267.99

63.20

80137.00

d) Slab (60 Grade) in/c 3% wastage

Kg

1904.15

63.20

120342.00

e) Stair (60 Grade) in/c 3% wastage

Kg

182.61

63.20

11541.00

Sub-Total (a+h)
D) 3rd Floor

f) Lintel (60 Grade) in/c 3% wastage

Kg

153.36

63.20

9692.00

g) False Slab (60 Grade) in/c 3% wastage

Kg

132.98

63.20

8405.00

h) Sunshed & Drop wall (60 Grade) in/c 3% wastage

Kg

114.38

63.20

7229.00

Kg

4841.63

Re-Bar work Sub-Total

1231037.00

Sub-Total (a+h)

PROSSIMO DEVELOPMENT LTD

Remarks

Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

B. Super-Structure (Structure work)


SI
No

Description of work

Unit

Quantity

Rate

E) 4th Floor

Amount

BF=

1231037.00

a) Column (60 Grade) in/c 3% wastage

Kg

1034.90

63.20

65405.00

b) Lift wall (60 Grade) in/c 3% wastage

Kg

0.00

63.20

0.00

c) Beam (60 Grade) in/c 3% wastage

Kg

1267.99

63.20

80137.00

d) Slab (60 Grade) in/c 3% wastage

Kg

1904.15

63.20

120342.00

e) Stair (60 Grade) in/c 3% wastage

Kg

182.61

63.20

11541.00

f) Lintel (60 Grade) in/c 3% wastage

Kg

153.36

63.20

9692.00

g) False Slab (60 Grade) in/c 3% wastage

Kg

132.98

63.20

8405.00

h) Sunshed & Drop wall (60 Grade) in/c 3% wastage

Kg

114.38

63.20

7229.00

Kg

4790.37

a) Column (60 Grade) in/c 3% wastage

Kg

1024.60

63.20

64755.00

b) Lift wall (60 Grade) in/c 3% wastage

Kg

0.00

63.20

0.00

c) Beam (60 Grade) in/c 3% wastage

Kg

1267.99

63.20

80137.00

d) Slab (60 Grade) in/c 3% wastage

Kg

1904.15

63.20

120342.00

e) Stair (60 Grade) in/c 3% wastage

Kg

182.61

63.20

11541.00

Sub-Total (a+h)
F) 5th Floor

f) Lintel (60 Grade) in/c 3% wastage

Kg

153.36

63.20

9692.00

g) False Slab (60 Grade) in/c 3% wastage

Kg

132.98

63.20

8405.00

h) Sunshed & Drop wall (60 Grade) in/c 3% wastage

Kg

114.38

63.20

7229.00

Kg

4780.08

a) Column (60 Grade) in/c 3% wastage

Kg

250.06

63.20

15804.00

b) Lift wall (60 Grade) in/c 3% wastage

Kg

0.00

63.20

0.00

c) Beam (60 Grade) in/c 3% wastage

Kg

1267.99

63.20

80137.00

d) Slab (60 Grade) in/c 3% wastage

Kg

1904.15

63.20

120342.00

e) Stair (60 Grade) in/c 3% wastage

Kg

182.61

63.20

11541.00

f) Lintel (60 Grade) in/c 3% wastage

Kg

153.36

63.20

9692.00

g) False Slab (60 Grade) in/c 3% wastage

Kg

132.98

63.20

8405.00

h) Sunshed & Drop wall (60 Grade) in/c 3% wastage

Kg

114.38

63.20

7229.00

Kg

4005.54

a) Column (60 Grade) in/c 3% wastage

Kg

177.86

63.20

11240.00

b) Lift M Room (60 Grade) in/c 3% wastage

Kg

250.06

63.20

15804.00

Sub-Total (a+h)
G) 6th Floor

Sub-Total (a+h)
H) Top Floor

c) Beam (60 Grade) in/c 3% wastage

Kg

0.00

63.20

0.00

d) Slab (60 Grade) in/c 3% wastage

Kg

0.00

63.20

0.00

e) Stair (60 Grade) in/c 3% wastage

Kg

0.00

63.20

0.00

f) Lintel (60 Grade) in/c 3% wastage

Kg

0.00

63.20

0.00

g) False Slab (60 Grade) in/c 3% wastage

Kg

0.00

63.20

0.00

h) Sunshed & Drop wall (60 Grade) in/c 3% wastage

Kg

0.00

63.20

0.00

Kg

628.21

63.20

39703.00

Re-Bar work Total

2155786.00

i) OHWT (60 Grade) in/c 3% wastage


Sub-Total (a+i)
Total Re-Bar 40 Grade + 60 Grade in/c 3% wastage

Kg

1056.13
40961.42

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

Remarks

B. Super-Structure (Structure work)


SI
No

Description of work

Unit

Quantity

Rate

Amount

Z) From work
A) Ground Floor
a) Column

Sft

565.94

b) Lift wall

Sft

0.00

c) Beam

Sft

386.10

d) Slab

Sft

1527.21

e) Stair

Sft

150.73

f) Lintel

Sft

38.20

g) False Slab

Sft

16.69

h) Sunshed & Drop wall

Sft

32.59

Sft

2717.45

a) Column

Sft

553.66

b) Lift wall

Sft

0.00

Sub-Total (a+h)

20.00

54349.00

22.00

66776.00

22.00

66776.00

22.00

66776.00

From work Sub-Total

254677.00

B) First Floor

c) Beam

Sft

393.91

d) Slab

Sft

1527.21

e) Stair

Sft

150.73

f) Lintel

Sft

95.85

g) False Slab

Sft

139.59

h) Sunshed & Drop wall

Sft

174.31

Sft

3035.25

a) Column

Sft

553.66

b) Lift wall

Sft

0.00

c) Beam

Sft

393.91

d) Slab

Sft

1527.21

e) Stair

Sft

150.73

Sub-Total (a+h)
C) 2nd Floor

f) Lintel

Sft

95.85

g) False Slab

Sft

139.59

h) Sunshed & Drop wall

Sft

174.31

Sft

3035.25

a) Column

Sft

553.66

b) Lift wall

Sft

0.00

Sub-Total (a+h)
D) 3rd Floor

c) Beam

Sft

393.91

d) Slab

Sft

1527.21

e) Stair

Sft

150.73

f) Lintel

Sft

95.85

g) False Slab

Sft

139.59

h) Sunshed & Drop wall

Sft

174.31

Sub-Total (a+h)

Sft

3035.25

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

B. Super-Structure (Structure work)

Remarks

SI
No

Description of work

Unit

Quantity

Rate

E) 4th Floor
a) Column

Sft

553.66

b) Lift wall

Sft

0.00

c) Beam

Sft

393.91

d) Slab

Sft

1527.21

e) Stair

Sft

150.73

f) Lintel

Sft

95.85

g) False Slab

Sft

139.59

h) Sunshed & Drop wall

Sft

174.31

Sft

3035.25

a) Column

Sft

553.66

b) Lift wall

Sft

0.00

c) Beam

Sft

393.91

d) Slab

Sft

1527.21

e) Stair

Sft

150.73

f) Lintel

Sft

95.85

g) False Slab

Sft

139.59

Sub-Total (a+h)

Amount

BF=

254677.00

22.00

66776.00

22.00

66776.00

22.00

66776.00

F) 5th Floor

h) Sunshed & Drop wall

Sft

174.31

Sft

3035.25

a) Column

Sft

553.66

b) Lift wall

Sft

0.00

c) Beam

Sft

393.91

d) Slab

Sft

1527.21

e) Stair

Sft

150.73

f) Lintel

Sft

95.85

g) False Slab

Sft

139.59

h) Sunshed & Drop wall

Sft

174.31

Sft

3035.25

a) Column

Sft

116.01

b) Lift M Room

Sft

141.36

Sub-Total (a+h)
G) 6th Floor

Sub-Total (a+h)
H) Top Floor

c) Beam

Sft

0.00

d) Slab

Sft

0.00

e) Stair

Sft

0.00

f) Lintel

Sft

0.00

g) False Slab

Sft

0.00

h) Sunshed & Drop wall

Sft

0.00

Sft

411.30

i) OHWT
Sub-Total (a+i)

Sft

22.00

14711.00

From work Total

668.68

469716.00

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

C. Super-Structure (Finishing work)

Remarks

SI
No

Description of work

Unit

Quantity

Rate

Amount

A) Ground Floor
1

10" Thick brick work (1:6)

Cft

13.85

97.06

1344.00

5" Thick brick work (1:4)

Sft

892.54

47.16

42092.00

25 mm Thick Plaster (1:5) B/W (in side)

Sft

1784.87

11.28

20133.00

20 mm Thick Plaster (1:5) B/W (out side)

Sft

2274.98

9.79

22272.00

20 mm Thick Plaster (1:4) on Concrete

Sft

2581.77

10.71

27651.00

Tiles work in Lobby & Stair

Sft

150.02

132.38

19860.00

Tiles work in Floor

Sft

0.00

83.03

0.00

Tiles work in Skirting

Sft

0.00

83.03

0.00

Tiles work in Toilet Floor

Sft

0.00

83.03

0.00

Sft

0.00

61.66

0.00

10 Tiles work in Toilet wall


11 Paint work

0.00

a Ceiling

Sft

2581.77

7.90

20396.00

b Wall

Sft

1784.87

7.90

14100.00

c Weather coat

Sft

2274.98

7.73

17586.00

d Enamel

Sft

16.97

5.50

93.00

12 White washing

Sft

0.00

0.72

0.00

13 French Polish

Sft

0.00

18.00

0.00

14 Main Door Frame

Rft

0.00

574.50

0.00

15 Internal Door Frame

Rft

31.95

574.50

18355.00

16 Main Door shutter

Sft

0.00

500.00

0.00

17 Flush Door shutter

Sft

31.88

164.00

5228.00

18 Plastic door

Pcs

1.85 3600.00

6646.00

19 Window grill

Sft

34.51

100.50

3468.00

20 Varandah safety grill

Sft

0.00

100.50

0.00

21 Varandah railing

Sft

0.00

170.50

0.00

22 Stair railing (Grill)

Sft

26.27

171.40

4503.00

23 Stair hand rest

Rft

9.37

258.75

2425.00

24 Aluminium Sliding window

Sft

0.00

253.00

0.00

25 Aluminium fixed window

Sft

34.51

253.00

8730.00

26 Aluminium Sliding door

Sft

0.00

253.00

0.00

27 Cat Door work

Pcs

1.85

800.00

1477.00

28 Marble works

Sft

53.61

370.00

19834.00

29 Main Gate

Sft

50.41

250.00

12603.00

30 Mortice type Door lock

Pcs

1.85

450.00

831.00

Sub-Total Ground Floor

269627.00

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

C. Super-Structure (Finishing work)

Remarks

SI
No

Description of work

Unit

Quantity

Rate

Amount

B) First Floor
1

10" Thick brick work (1:6)

Cft

150.17

97.76

14680.00

5" Thick brick work (1:4)

Sft

2161.03

47.66

102995.00

25 mm Thick Plaster (1:5) B/W (in side)

Sft

3990.84

11.78

47012.00

20 mm Thick Plaster (1:5) B/W (out side)

Sft

1023.68

10.39

10636.00

20 mm Thick Plaster (1:4) on Concrete

Sft

1925.24

11.21

21582.00

Tiles work in Lobby & Stair

Sft

138.73

132.38

18366.00

Tiles work in Floor

Sft

1147.57

83.03

95283.00

Tiles work in Skirting

Sft

136.75

83.03

11354.00

Tiles work in Toilet Floor

Sft

127.52

83.03

10588.00

Sft

704.39

61.66

43433.00

10 Tiles work in Toilet wall


11 Paint work

0.00

a Ceiling

Sft

1925.24

7.90

15209.00

b Wall

Sft

3985.94

7.90

31489.00

c Weather coat

Sft

1023.68

7.73

7913.00

d Enamel

Sft

390.00

5.50

2145.00

12 White washing

Sft

169.05

0.72

122.00

13 French Polish

Sft

284.07

18.00

5113.00

14 Main Door Frame

Rft

17.75

574.50

10197.00

15 Internal Door Frame

Rft

134.91

574.50

77506.00

16 Main Door shutter

Sft

23.36

500.00

11680.00

17 Flush Door shutter

Sft

138.44

164.00

22704.00

18 Plastic door

Pcs

2.00 3600.00

7200.00

19 Window grill

Sft

141.43

100.50

14214.00

20 Varandah safety grill

Sft

154.57

100.50

15534.00

21 Varandah railing

Sft

86.05

170.50

14672.00

22 Stair railing (Grill)

Sft

26.27

171.40

4503.00

23 Stair hand rest

Rft

9.37

258.75

2425.00

24 Aluminium Sliding window

Sft

108.84

253.00

27537.00

25 Aluminium fixed window

Sft

93.65

253.00

23693.00

26 Aluminium Sliding door

Sft

100.54

253.00

25436.00

27 Cat Door work

Pcs

4.47

800.00

3578.00

28 Marble works

Sft

22.72

370.00

8406.00

29 Main Door lock

Pcs

0.92 2500.00

2308.00

30 Mortice type Door lock

Pcs

6.32

450.00

2844.00

Sub-Total 1st Floor

712357.00

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

C. Super-Structure (Finishing work)

Remarks

SI
No

Description of work

Unit

Quantity

Rate

Amount

C) 2nd Floor
1

10" Thick brick work (1:6)

Cft

150.17

97.76

14680.00

5" Thick brick work (1:4)

Sft

2161.03

47.66

102995.00

25 mm Thick Plaster (1:5) B/W (in side)

Sft

3990.84

11.78

47012.00

20 mm Thick Plaster (1:5) B/W (out side)

Sft

1023.68

10.39

10636.00

20 mm Thick Plaster (1:4) on Concrete

Sft

1925.24

11.21

21582.00

Tiles work in Lobby & Stair

Sft

138.73

132.38

18366.00

Tiles work in Floor

Sft

1147.57

83.03

95283.00

Tiles work in Skirting

Sft

136.75

83.03

11354.00

Tiles work in Toilet Floor

Sft

127.52

83.03

10588.00

Sft

704.39

61.66

43433.00

a Ceiling

Sft

1925.24

7.90

15209.00

b Wall

Sft

3985.94

7.90

31489.00

c Weather coat

Sft

1023.68

7.73

7913.00

d Enamel

Sft

390.00

5.50

2145.00

12 White washing

Sft

169.05

0.72

122.00

13 French Polish

Sft

284.07

18.00

5113.00

14 Main Door Frame

Rft

17.75

574.50

10197.00

15 Internal Door Frame

Rft

134.91

574.50

77506.00

16 Main Door shutter

Sft

23.36

500.00

11680.00

17 Flush Door shutter

Sft

138.44

164.00

22704.00

18 Plastic door

Pcs

2.00 3600.00

7200.00

19 Window grill

Sft

141.43

100.50

14214.00

20 Varandah safety grill

Sft

154.57

100.50

15534.00

21 Varandah railing

Sft

86.05

170.50

14672.00

22 Stair railing (Grill)

Sft

26.27

171.40

4503.00

23 Stair hand rest

Rft

9.37

258.75

2425.00

24 Aluminium Sliding window

Sft

108.84

253.00

27537.00

25 Aluminium fixed window

Sft

93.65

253.00

23693.00

26 Aluminium Sliding door

Sft

100.54

253.00

25436.00

27 Cat Door work

Pcs

4.47

800.00

3578.00

28 Marble works

Sft

22.72

370.00

8406.00

29 Main Door lock

Pcs

0.92 2500.00

2308.00

30 Mortice type Door lock

Pcs

6.32

450.00

2844.00

Sub-Total 2nd Floor

712357.00

10 Tiles work in Toilet wall


11 Paint work

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

C. Super-Structure (Finishing work)

Remarks

SI
No

Description of work

Unit

Quantity

Rate

Amount

D) 3rd Floor
1

10" Thick brick work (1:6)

Cft

150.17

97.76

14680.00

5" Thick brick work (1:4)

Sft

2161.03

47.66

102995.00

25 mm Thick Plaster (1:5) B/W (in side)

Sft

3990.84

11.78

47012.00

20 mm Thick Plaster (1:5) B/W (out side)

Sft

1023.68

10.39

10636.00

20 mm Thick Plaster (1:4) on Concrete

Sft

1925.24

11.21

21582.00

Tiles work in Lobby & Stair

Sft

138.73

132.38

18366.00

Tiles work in Floor

Sft

1147.57

83.03

95283.00

Tiles work in Skirting

Sft

136.75

83.03

11354.00

Tiles work in Toilet Floor

Sft

127.52

83.03

10588.00

Sft

704.39

61.66

43433.00

a Ceiling

Sft

1925.24

7.90

15209.00

b Wall

Sft

3985.94

7.90

31489.00

c Weather coat

Sft

1023.68

7.73

7913.00

d Enamel

Sft

390.00

5.50

2145.00

12 White washing

Sft

169.05

0.72

122.00

13 French Polish

Sft

284.07

18.00

5113.00

14 Main Door Frame

Rft

17.75

574.50

10197.00

15 Internal Door Frame

Rft

134.91

574.50

77506.00

16 Main Door shutter

Sft

23.36

500.00

11680.00

17 Flush Door shutter

Sft

138.44

164.00

22704.00

18 Plastic door

Pcs

2.00 3600.00

7200.00

19 Window grill

Sft

141.43

100.50

14214.00

20 Varandah safety grill

Sft

154.57

100.50

15534.00

21 Varandah railing

Sft

86.05

170.50

14672.00

22 Stair railing (Grill)

Sft

26.27

171.40

4503.00

23 Stair hand rest

Rft

9.37

258.75

2425.00

24 Aluminium Sliding window

Sft

108.84

253.00

27537.00

25 Aluminium fixed window

Sft

93.65

253.00

23693.00

26 Aluminium Sliding door

Sft

100.54

253.00

25436.00

27 Cat Door work

Pcs

4.47

800.00

3578.00

28 Marble works

Sft

22.72

370.00

8406.00

29 Main Door lock

Pcs

0.92 2500.00

2308.00

30 Mortice type Door lock

Pcs

6.32

450.00

2844.00

Sub-Total 3rd Floor

712357.00

10 Tiles work in Toilet wall


11 Paint work

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

C. Super-Structure (Finishing work)

Remarks

SI
No

Description of work

Unit

Quantity

Rate

Amount

E) 4th Floor
1

10" Thick brick work (1:6)

Cft

150.17

97.76

14680.00

5" Thick brick work (1:4)

Sft

2161.03

47.66

102995.00

25 mm Thick Plaster (1:5) B/W (in side)

Sft

3990.84

11.78

47012.00

20 mm Thick Plaster (1:5) B/W (out side)

Sft

1023.68

10.39

10636.00

20 mm Thick Plaster (1:4) on Concrete

Sft

1925.24

11.21

21582.00

Tiles work in Lobby & Stair

Sft

138.73

132.38

18366.00

Tiles work in Floor

Sft

1147.57

83.03

95283.00

Tiles work in Skirting

Sft

136.75

83.03

11354.00

Tiles work in Toilet Floor

Sft

127.52

83.03

10588.00

Sft

704.39

61.66

43433.00

a Ceiling

Sft

1925.24

7.90

15209.00

b Wall

Sft

3985.94

7.90

31489.00

c Weather coat

Sft

1023.68

7.73

7913.00

d Enamel

Sft

390.00

5.50

2145.00

12 White washing

Sft

169.05

0.72

122.00

13 French Polish

Sft

284.07

18.00

5113.00

14 Main Door Frame

Rft

17.75

574.50

10197.00

15 Internal Door Frame

Rft

134.91

574.50

77506.00

16 Main Door shutter

Sft

23.36

500.00

11680.00

17 Flush Door shutter

Sft

138.44

164.00

22704.00

18 Plastic door

Pcs

2.00 3600.00

7200.00

19 Window grill

Sft

141.43

100.50

14214.00

20 Varandah safety grill

Sft

154.57

100.50

15534.00

21 Varandah railing

Sft

86.05

170.50

14672.00

22 Stair railing (Grill)

Sft

26.27

171.40

4503.00

23 Stair hand rest

Rft

9.37

258.75

2425.00

24 Aluminium Sliding window

Sft

108.84

253.00

27537.00

25 Aluminium fixed window

Sft

93.65

253.00

23693.00

26 Aluminium Sliding door

Sft

100.54

253.00

25436.00

27 Cat Door work

Pcs

4.47

800.00

3578.00

28 Marble works

Sft

22.72

370.00

8406.00

29 Main Door lock

Pcs

0.92 2500.00

2308.00

30 Mortice type Door lock

Pcs

6.32

450.00

2844.00

Sub-Total 4th Floor

712357.00

10 Tiles work in Toilet wall


11 Paint work

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

C. Super-Structure (Finishing work)

Remarks

SI
No

Description of work

Unit

Quantity

Rate

Amount

F) 5th Floor
1

10" Thick brick work (1:6)

Cft

150.17

97.76

14680.00

5" Thick brick work (1:4)

Sft

2161.03

47.66

102995.00

25 mm Thick Plaster (1:5) B/W (in side)

Sft

3990.84

11.78

47012.00

20 mm Thick Plaster (1:5) B/W (out side)

Sft

1023.68

10.39

10636.00

20 mm Thick Plaster (1:4) on Concrete

Sft

1925.24

11.21

21582.00

Tiles work in Lobby & Stair

Sft

138.73

132.38

18366.00

Tiles work in Floor

Sft

1147.57

83.03

95283.00

Tiles work in Skirting

Sft

136.75

83.03

11354.00

Tiles work in Toilet Floor

Sft

127.52

83.03

10588.00

Sft

704.39

61.66

43433.00

a Ceiling

Sft

1925.24

7.90

15209.00

b Wall

Sft

3985.94

7.90

31489.00

c Weather coat

Sft

1023.68

7.73

7913.00

d Enamel

Sft

390.00

5.50

2145.00

12 White washing

Sft

169.05

0.72

122.00

13 French Polish

Sft

284.07

18.00

5113.00

14 Main Door Frame

Rft

17.75

574.50

10197.00

15 Internal Door Frame

Rft

134.91

574.50

77506.00

16 Main Door shutter

Sft

23.36

500.00

11680.00

17 Flush Door shutter

Sft

138.44

164.00

22704.00

18 Plastic door

Pcs

2.00 3600.00

7200.00

19 Window grill

Sft

141.43

100.50

14214.00

20 Varandah safety grill

Sft

154.57

100.50

15534.00

21 Varandah railing

Sft

86.05

170.50

14672.00

22 Stair railing (Grill)

Sft

26.27

171.40

4503.00

23 Stair hand rest

Rft

9.37

258.75

2425.00

24 Aluminium Sliding window

Sft

108.84

253.00

27537.00

25 Aluminium fixed window

Sft

93.65

253.00

23693.00

26 Aluminium Sliding door

Sft

100.54

253.00

25436.00

27 Cat Door work

Pcs

4.47

800.00

3578.00

28 Marble works

Sft

22.72

370.00

8406.00

29 Main Door lock

Pcs

0.92 2500.00

2308.00

30 Mortice type Door lock

Pcs

6.32

450.00

2844.00

Sub-Total 5th Floor

712357.00

10 Tiles work in Toilet wall


11 Paint work

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

C. Super-Structure (Finishing work)

Remarks

SI
No

Description of work

Unit

Quantity

Rate

Amount

G) 6th Floor
1

10" Thick brick work (1:6)

Cft

150.17

97.76

14680.00

5" Thick brick work (1:4)

Sft

2161.03

47.66

102995.00

25 mm Thick Plaster (1:5) B/W (in side)

Sft

3990.84

11.78

47012.00

20 mm Thick Plaster (1:5) B/W (out side)

Sft

1023.68

10.39

10636.00

20 mm Thick Plaster (1:4) on Concrete

Sft

1925.24

11.21

21582.00

Tiles work in Lobby & Stair

Sft

138.73

132.38

18366.00

Tiles work in Floor

Sft

1147.57

83.03

95283.00

Tiles work in Skirting

Sft

136.75

83.03

11354.00

Tiles work in Toilet Floor

Sft

127.52

83.03

10588.00

Sft

704.39

61.66

43433.00

a Ceiling

Sft

1925.24

7.90

15209.00

b Wall

Sft

3985.94

7.90

31489.00

c Weather coat

Sft

1023.68

7.73

7913.00

d Enamel

Sft

390.00

5.50

2145.00

12 White washing

Sft

169.05

0.72

122.00

13 French Polish

Sft

284.07

18.00

5113.00

14 Main Door Frame

Rft

17.75

574.50

10197.00

15 Internal Door Frame

Rft

134.91

574.50

77506.00

16 Main Door shutter

Sft

23.36

500.00

11680.00

17 Flush Door shutter

Sft

138.44

164.00

22704.00

18 Plastic door

Pcs

2.00 3600.00

7200.00

19 Window grill

Sft

141.43

100.50

14214.00

20 Varandah safety grill

Sft

154.57

100.50

15534.00

21 Varandah railing

Sft

86.05

170.50

14672.00

22 Stair railing (Grill)

Sft

26.27

171.40

4503.00

23 Stair hand rest

Rft

9.37

258.75

2425.00

24 Aluminium Sliding window

Sft

108.84

253.00

27537.00

25 Aluminium fixed window

Sft

93.65

253.00

23693.00

26 Aluminium Sliding door

Sft

100.54

253.00

25436.00

27 Cat Door work

Pcs

4.47

800.00

3578.00

28 Marble works

Sft

22.72

370.00

8406.00

29 Main Door lock

Pcs

0.92 2500.00

2308.00

30 Mortice type Door lock

Pcs

6.32

450.00

2844.00

Sub-Total 5th Floor

712357.00

10 Tiles work in Toilet wall


11 Paint work

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.

C. Super-Structure (Finishing work)

Remarks

SI
No

Description of work

Unit

Quantity

Rate

Amount

H) Top Floor
1

10" Thick brick work (1:6)

Cft

46.86

97.76

4581.00

5" Thick brick work (1:4)

Sft

570.98

47.66

27213.00

25 mm Thick Plaster (1:5) B/W (in side)

Sft

586.74

11.78

6912.00

20 mm Thick Plaster (1:5) B/W (out side)

Sft

1295.54

10.39

13461.00

20 mm Thick Plaster (1:4) on Concrete

Sft

229.54

11.21

2573.00

Tiles work in Lobby & Stair

Sft

4.69

132.38

620.00

Tiles work in Floor

Sft

94.43

83.03

7841.00

Tiles work in Skirting

Sft

17.82

83.03

1480.00

Tiles work in Toilet Floor

Sft

9.16

83.03

760.00

Sft

52.61

61.66

3244.00

a Ceiling

Sft

229.54

7.90

1813.00

b Wall

Sft

586.74

7.90

4635.00

c Weather coat

Sft

1295.54

7.73

10015.00

d Enamel

Sft

4.69

5.50

26.00

Sft

0.00

0.72

0.00

13 French Polish

Sft

0.00

18.00

0.00

14 MS Door Frame

Pcs

0.92 1250.00

1154.00

10 Tiles work in Toilet wall


11 Paint work

12 White washing

15 MS Door shutter

Sft

105.00

1081.00

16 Plastic door

Pcs

10.30

0.00 3600.00

0.00

17 Window grill

Sft

0.00

100.50

0.00

18 Varandah safety grill

Sft

0.00

100.50

0.00

19 Varandah railing

Sft

0.00

170.50

0.00

20 Stair railing (Grill)

Sft

4.62

171.40

791.00

21 Stair hand rest

Rft

1.85

258.75

478.00

22 Aluminium Sliding window

Sft

0.00

253.00

0.00

23 Aluminium fixed window

Sft

0.00

253.00

0.00

24 Aluminium Sliding door

Sft

0.00

253.00

0.00

25 Cat Door work

Pcs

0.00

800.00

0.00

26 Marble works

Sft

0.00

370.00

0.00

27 Main Door lock

Pcs

0.00 2500.00

0.00

28 Mortice type Door lock

Pcs

0.00

450.00

0.00

29 Lime terracing (4" thick.)

Cft.

283.29

95.95

27182.00

30 Ground Floor Decoration & Finishing work

Sft

1472.68

40.00

58907.00

31 Roofing with Fibre glass sheet & MS Truss

Sft

688.91

75.00

51668.00

32 12 mm Thick Plaster (1:4) with NCF in OHWT

Sft

274.56

10.50

2883.00

33 False Ceiling with Gypsum board & Aluminium

Sft

280.38

55.00

15421.00

Sub-Total Top Floor

244739.00

Sub-Structure

Total Amount

1089320.00

Super-Structure (Structure work)

Total Amount

3870528.00

Super-Structure (Finishing work)

Total Amount

4788508.00

Grand Total Civil work (A+B+C)

9748356.00

Remarks

PROSSIMO DEVELOPMENT LTD


Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.
Name of the Project :

FOUNDATION UPTO PL
Total Quantity
Item
no.

Material Consumption
Grey
Cement
Bag

Sylhet
Sand
Cft

Local
Sand
Cft

Stone
Chips
Cft

1st Class
Bricks
Pcs

1st Class
Picket
Pcs

Description

Unit

Total
Quantity

Single layer brick flat soling

Sft.

2666.05

One layer polythene

Sft.

2666.00

3 (a) C.C Work BC,50%,CS 3"thick

Cft

194.97

24.37

46.79

46.79

1754.69

3 (b) C.C Work BC,50%,CS 4"thick

Cft

912.07

164.17

205.21

205.21

7843.77

White
cement
Bag

Glazed
Wall
Tiles

N.G.H
Floor
Tiles

Plastic
paint
Liter

Chalk
powder
Kg

Snow
cem
Kg

Door
frame
Rft

Iternal
Door
frame
Rft

Alumin
ium
Sft

MS Rod
(60 G)
Kg

MS Rod
(40 G)
Kg

7998.15

R. C. C. casting work

a)

Column upto PL (1:1:3),SC 100%,CS

Cft.

156.27

34.38

64.07

b)

Footing (1:1:3),SC 50%,CS

Cft.

1153.68

253.81

236.50

236.50

c)

UGWR (1:1:3),BC 50%,CS

Cft.

162.31

35.71

33.27

33.27

d)

U.G.W.R Top Slab (1:2:4) BC,50% CS

Cft.

42.17

7.59

9.49

9.49

e)

Lift core (1:1:3),SC 50%,CS

Cft.

50.48

11.11

10.35

10.35

Cft.

182.83

32.91

41.14

41.14

Window
Grill
Sft

Varandah
Varandah
safety
railing Sft
grill Sft

Stair
railing
(Grill)
Sft

Stair
hand
rest Rft

Marble
Main
works Door lock
Sft
Pcs

133.30

128.14
946.02
1330.91
362.70
41.39

f)

Grade Beam (1:2:4),BC 50%,CS

Reinforcement work

a)

Column upto PL (60 Grade)

Kg

1336.23

1336.23

b)

Footing (60 Grade)

Kg

2163.70

2163.70

c)

UGWR (60 Grade)

Kg

1173.84

1173.84

d)

Lift core (60 Grade)

Kg

189.77

189.77

e)

Grade beam (60 Grade)

Kg

1964.70

1964.70

Plaster with padlo (UGWR)

Sft.

0.00

Sand filling

a)

Plinth

Cft.

3774.01

b)

Foundation, Lift pit & UGWR

Cft.

0.00

Total :

Cft.

3774.01

PVC water stopper 8"

Rft

25.21

0.00

Vity
Sand
Cft

1572.30

0.00

3774.01

10" to 20" Thik. Brick work

a)

On top of Grade beam (1:6)

Cft.

0.00

b)

Brick footing (1:6)

Cft.

0.00

Total :

Cft.

0.00

0.00

12

Patent Stone (UGWR) 1"

Sft.

75.83

1.71

13

Rough Plaster (L.S.)

Sft.

0.00

0.00

566.00

0.00
2.13

0.00

2.13

81.52

0.00

649.00

585.00

1116.00

7998.00

12946.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

6828.00

0.00

3907.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

GROUND FLOOR
Total Quantity
Item
no.

Description

Material Consumption

Unit

Total
Quantity

Grey
Cement
Bag

Sylhet
Sand
Cft

Local
Sand
Cft

Stone
Chips
Cft

White
1st Class
1st Class
cement
Bricks Pcs Picket Pcs
Bag

Glazed
Wall
Tiles

N.G.H
Floor
Tiles

Plastic
paint
Sft

Cat
Door
Pcs

Weather
coat
Sft

Main
Door
frame
Rft

Iternal
Door
frame
Rft

Alumin
ium
Sft

MS Rod
(60 G)
Kg

MS Rod
(40 G)
Kg

R. C. C. casting work

a)

Column (1:1:3),SC 100%,CS

Cft.

157.34

34.61

64.51

b)

Beam (1:2:4),BC 50%,CS

Cft.

193.05

34.75

43.44

43.44

1660.22

c)

Slab (1:2:4),BC 50%,CS

Cft.

658.88

118.60

148.25

148.25

5666.37

d)

Stair (1:2:4),BC 50%,CS

Cft.

48.56

8.74

10.93

10.93

417.65

R. C. C. casting work

a)

Lintel False Slab Sunshade Drop Wall


(1:2:4),BC ,MS

Cft.

13.14

2.36

5.91

112.96

Reinforcement work

a)

Column (60 Grade)

Kg

1331.46

1331.46

b)

Beam (60 Grade)

Kg

1267.99

1267.99

c)

Slab (40 Grade)

Kg

1904.15

1904.15

d)

Stair (40 Grade)

Kg

182.61

182.61

Lintel False Slab Sunshade Drop Wall (40


Grade)

Kg

81.51
13.85

0.55

4.98

159.22
4462.71

Vity
Sand
Cft

Window
Grill
Sft

Varandah
Varandah
safety
railing Sft
grill Sft

Stair
railing
(Grill)
Sft

Stair
hand
rest Rft

Marble
Main
works Door lock
Sft
Pcs

129.02

81.51

10" thick brick work (1:6)

5" Thick brick work (1:4)

Cft
Sft

892.54

23.21

151.73

25 mm thick Plaster on B/W in Side (1:5)

Sft

1784.87

29.81

185.98

20 mm thick Plaster on B/W out Side (1:5)

Sft

2274.98

28.44

177.68

Sft

2581.77

38.73

193.63

20 mm thick Plaster on R.C.C. (1:4)


Tiles work in Lobby & Stair {Moter 1" (1:3)}

Sft

150.02

3.75

14.06

0.15

157.52

10

Tiles work in Floor {Moter 1" (1:3)}

Sft

0.00

0.00

0.00

0.00

0.00

11

Tiles work in Skirting {Moter "(1:2)}

Sft

0.00

0.00

0.00

0.00

0.00

12

Tiles work in Toilet Floor {Moter 1" (1:3)}

Sft

0.00

0.00

0.00

0.00

13

Tiles work in Toilet wall {Moter "(1:2)}

Sft

0.00

0.00

0.00

0.00

14

Paint work (Plastic)

15

Ceiling

Sft

2581.77

2581.77

16

Wall

Sft

1784.87

1784.87

17

Weather coat

Sft

2274.98

18

Enamel

Sft

16.97

19

White washing

Sft

0.00

20

French Polish

Sft

0.00

21

Main Door Frame (1:1:3),BC 100%,CS

Rft

0.00

0.00

0.00

0.00

0.00

22

Internal Door Frame (1:1:3),BC 100%,CS

Rft

31.95

0.52

0.48

0.48

1.94

23

Main Door shutter

Sft

0.00

24

Flush Door shutter

Sft

31.88

25

Plastic door

Pcs

1.85

26

Window grill (1:1:3),BC 100%,CS

Sft

34.51

0.56

0.52

0.52

2.09

27

Varandah safety grill (1:1:3),BC 100%,CS

Sft

0.00

0.00

0.00

0.00

0.00

28

Varandah railing (1:1:3),BC 100%,CS

Sft

0.00

0.00

0.00

0.00

0.00

29

Stair railing (Grill) (1:1:3),BC 100%,CS

Sft

26.27

0.43

0.40

0.40

1.59

30

Stair hand rest

Rft

9.37

31

Aluminium Sliding window

Sft

0.00

0.00

32

Aluminium fixed window

Sft

34.51

34.51

33

Aluminium Sliding door

Sft

0.00

34

Cat Door work

Pcs

1.85

35

Marble works

Sft

53.61

1.34

36

Main Gate (1:1:3),BC 100%,CS

Sft

50.41

37

Mortice type Door lock

Pcs

1.85

38

D.P.C. 3" Thick

Rft.

0.00

39

Column guard of m.s. angle

Rft.

0.00

40

MS steel gate at sub-station

Nos.

2.00

0.00
0.00

2274.98

0.00
31.95

34.51
0.00
0.00
26.27
9.37

0.00

0.03

0.03

0.03

0.82

0.76

0.76

3.06

0.00

0.00

0.00

0.00

1.85

0.11

53.61

5.02

0.03

0.03

0.03

327.00

269.00

944.00

129.00

4622.00

7866.00

0.00

0.00

158.00

4367.00

2.00

2275.00

0.00

32.00

35.00

2599.00

2168.00

0.00

35.00

0.00

0.00

26.00

9.00

54.00

0.00

TYPICAL FLOOR
Total Quantity
Item
no.

Description

Material Consumption

Unit

Total
Quantity

Grey
Cement
Bag

Sylhet
Sand
Cft

Local
Sand
Cft

Stone
Chips
Cft

White
1st Class
1st Class
cement
Bricks Pcs Picket Pcs
Bag

R. C. C. casting work

a)

Column (1:1:3),SC 100%,CS

Cft.

149.95

32.99

61.48

b)

Beam (1:2:4),BC 50%,CS

Cft.

197.74

35.59

44.49

44.49

1700.52

c)

Slab (1:2:4),BC 50%,CS

Cft.

658.88

118.60

148.25

148.25

5666.37

d)

Stair (1:2:4),BC 50%,CS

Cft.

48.56

8.74

10.93

10.93

417.65

R. C. C. casting work
Cft.

87.76

15.80

39.49

754.70

Glazed
Wall
Tiles

N.G.H
Floor
Tiles

Plastic
paint
Liter

Cat
Door
Pcs

Weather
coat
Sft

Door
frame
Rft

Iternal
Door
frame
Rft

Alumin
ium
Sft

MS Rod
(60 G)
Kg

MS Rod
(40 G)
Kg

3
a)

Column (60 Grade)

Kg

1234.41

1234.41

b)

Beam (60 Grade)

Kg

1267.99

1267.99

c)

Slab (40 Grade)

Kg

1904.15

1904.15

d)

Stair (40 Grade)

Kg

182.61

182.61

Kg

400.72
150.17

6.01

54.06

1726.90
10805.14

Lintel False Slab Sunshade Drop Wall (40


Grade)
10" thick brick work (1:6)

5" Thick brick work (1:4)

Cft
Sft

2161.03

56.19

367.37

25 mm thick Plaster on B/W in Side (1:5)

Sft

3990.84

66.65

415.85

20 mm thick Plaster on B/W out Side (1:5)

Sft

1023.68

12.80

79.95

20 mm thick Plaster on R.C.C. (1:4)

Sft

1925.24

28.88

144.39

e)

Window
Grill
Sft

Varandah
Varandah
safety
railing Sft
grill Sft

Stair
railing
(Grill)
Sft

Stair
hand
rest Rft

Marble
Main
works Door lock
Sft
Pcs

122.96

Lintel False Slab Sunshade Drop Wall


(1:2:4),BC 50%,CS
Reinforcement work

a)

Vity
Sand
Cft

400.72

Tiles work in Lobby & Stair {Moter 1" (1:3)}

Sft

138.73

3.47

13.00

0.14

145.67

10

Tiles work in Floor {Moter 1" (1:3)}

Sft

1147.57

28.69

107.53

1.15

1204.95

11

Tiles work in Skirting {Moter "(1:2)}

Sft

136.75

3.42

8.55

0.14

143.58

12

Tiles work in Toilet Floor {Moter 1" (1:3)}

Sft

127.52

3.19

11.95

0.13

13

Tiles work in Toilet wall {Moter "(1:2)}

Sft

704.39

17.61

44.02

0.70

14

Paint work

15

Ceiling

Sft

1925.24

1925.24

16

Wall

Sft

3985.94

3985.94

17

Weather coat

Sft

1023.68

18

Enamel

Sft

390.00

19

White washing

Sft

169.05

20

French Polish

Sft

284.07

21

Main Door Frame (1:1:3),BC 100%,CS

Rft

17.75

0.29

0.27

0.27

1.08

22

Internal Door Frame (1:1:3),BC 100%,CS

Rft

134.91

2.19

2.04

2.04

8.18

23

Main Door shutter

Sft

23.36

24

Flush Door shutter

Sft

138.44

25

Plastic door

Pcs

2.00

26

Window grill (1:1:3),BC 100%,CS

Sft

141.43

2.30

2.14

2.14

8.57

27

Varandah safety grill (1:1:3),BC 100%,CS

Sft

154.57

2.51

2.34

2.34

9.37

28

Varandah railing (1:1:3),BC 100%,CS

Sft

86.05

1.40

1.30

1.30

5.22

29

Stair railing (Grill) (1:1:3),BC 100%,CS

Sft

26.27

0.43

0.40

0.40

1.59

30

Stair hand rest

Rft

9.37

31

Aluminium Sliding window

Sft

108.84

32

Aluminium fixed window

Sft

93.65

93.65

33

Aluminium Sliding door

Sft

100.54

100.54

34

Cat Door work

Pcs

4.47

0.07

35

Marble works

Sft

22.72

0.57

36

Main Door lock

Pcs

0.92

37

Mortice type Door lock

Pcs

6.32

133.89
739.61

1023.68

17.75
134.91

141.43
154.57
86.05
26.27
9.37
108.84

0.07

0.07

4.47

0.27

22.72

2.13

0.92

448.00

274.00

1501.00

123.00

12532.00

8574.00

2.00

740.00

1628.00

5911.00

4.00

1024.00

18.00

135.00

303.00

2502.00

2487.00

0.00

141.00

155.00

86.00

26.00

9.00

23.00

1.00

TOP OF THE ROOF


Total Quantity
Item
no.

Description

Material Consumption

Unit

Total
Quantity

Grey
Cement
Bag

Sylhet
Sand
Cft

R.C.C. casting work

a)

Column (1:1:3),SC 100%,CS

Cft.

30.96

6.81

12.69

b)

Lift M Room (1:1:3),SC 50%,CS

Cft.

54.39

11.96

22.30

c)

OHWT (1:1:3),BC 50%,CS

Cft.

136.96

24.65

30.82

Local
Sand
Cft

Stone
Chips
Cft

White
1st Class
1st Class
cement
Bricks Pcs Picket Pcs
Bag

N.G.H
Floor
Tiles

Plastic
paint
Liter

Chalk Weather
powder
coat
Kg
Sft

Door
frame
Rft

Iternal
Door
frame
Rft

Alumin
ium
Sft

MS Rod
(60 G)
Kg

MS Rod
(40 G)
Kg

Vity
Sand
Cft

Window
Grill
Sft

Varandah
Varandah
safety
railing Sft
grill Sft

Stair
railing
(Grill)
Sft

Stair
hand
rest Rft

Marble
Main
works Door lock
Sft
Pcs

25.38
44.60
30.82

1177.85

Reinforcement work

a)

Column (60 Grade)

Kg

177.86

b)

Lift machine room (40 Grade)

Kg

250.06

c)

Over head water tank (40 Grade)

Kg

628.21

Total :

Kg

878.27

10" thick brick work

Cft.

46.86

1.87

16.87

538.89

5" Thick brick work

Sft.

570.98

14.85

97.07

2854.91

25 mm thick Plaster on B/W in Side (1:5)

Sft.

586.74

8.39

62.84

20 mm thick Plaster on B/W out Side (1:5)

Sft.

1295.54

19.43

97.17

20 mm thick Plaster on R.C.C. (1:4)

Sft.

229.54

2.30

11.48

Tiles work in Floor {Moter 1" (1:3)}

Sft.

108.28

2.71

10.15

0.54

Tiles work in Toilet wall {Moter "(1:2)}

Sft.

70.43

1.76

4.40

0.35

10

Patent Stone 1Thick (1:2:4),BC 50%,CS

Sft.

1472.68

33.14

11

12 mm thick Plaster with N.C.F.

Sft.

274.56

4.12

12

Door frame MS

Pcs

0.92

13

Door shutter MS

Sft.

10.30

14

Lime terracing (4" thk.)

Cft.

283.29

15

Plastic paint

Sft.

816.29

16

Weather coat

Sft.

1295.54

17

PVC water stopper

Rft.

100.00

18

Fibre glass sheet

Sft.

688.91

Total Matierials

Glazed
Wall
Tiles

177.86

878.27

41.42

41.42

113.69
73.95

165.68

15.10
0.92

2464.62
11.75

21.22
51.82

131.99

107.23

387.30

69.98

3393.80

3808.15

0.89

73.95

113.69

11.75

21.22

51.82

0.92

0.00

0.00

177.86

878.27

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

3264.99

2395.23

9421.30

1929.98

78673.80

67490.15

10.89

3773.95

8411.69

33933.75

43.22

7446.82

90.92

707.00

1550.00

22114.86

15481.27

3907.00

740.00

775.00

430.00

156.00

54.00

169.00

5.00

Total 60 Grade
Total 40 Grade
Total 60+40 Grade
Per Sft

Kg
Kg
Kg
Kg

22114.86
15481.27
37596.13
1.97

Mortice
type Door
lock Pcs

0.00

Mortice
type Door
lock Pcs

1.85

2.00

Vous aimerez peut-être aussi