Académique Documents
Professionnel Documents
Culture Documents
Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.
Material Rate for Budget
Name of the Project : All Project
SI
No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
Unit
Bag
Cft
Cft
Cft
Cft
Cft
Pcs
Pcs
Cft
Cft
Kg
Kg
Bag
Bag
Sft
Sft
Sft
Sft
Sft
Sft
Rft
Rft
Sft
Sft
Bag
Gallon
Gallon
Gallon
Gallon
Gallon
Kg
Sft
Sft
Sft
Sft
Present
Rate
385.00
29.00
10.00
8.00
75.00
112.00
6.20
6.20
55.00
35.00
60.00
60.00
800.00
800.00
38.00
38.00
58.00
105.00
105.00
58.00
560.00
280.00
675.00
155.00
500.00
352.00
700.00
450.00
730.00
920.00
2800.00
265.00
265.00
265.00
105.00
Projected
Projected
Rate
Rate
Add 10%
404.25
30.45
10.50
8.40
78.75
117.60
6.51
6.51
57.75
36.75
63.00
63.00
840.00
840.00
39.90
39.90
60.90
110.25
110.25
60.90
588.00
294.00
708.75
162.75
525.00
369.60
735.00
472.50
766.50
966.00
2940.00
278.25
278.25
278.25
110.25
Approved
385.00
29.00
10.00
8.00
75.00
112.00
6.20
6.20
55.00
35.00
60.00
60.00
800.00
800.00
38.00
38.00
58.00
105.00
105.00
58.00
560.00
280.00
675.00
155.00
500.00
352.00
700.00
450.00
730.00
920.00
2800.00
265.00
265.00
265.00
105.00
36
37
38
39
40
Window Grill
Ver Grill
Stair Railing
Stone Lime
Ver Railing
Sft
Sft
Sft
Bag
Sft
95.00
120.00
165.00
500.00
165.00
99.75
126.00
173.25
525.00
173.25
95.00
120.00
165.00
500.00
165.00
TD
oy Nagar, Dhaka-1000.
Remarks
Name of Item
No
Unit
Quantity
Rate
Amount
(Tk.)
(Tk.)
B.
Cost of Materials :
a Cost of Viti Sand . (F.M 0.8)
TotalA)
Cost of Labour :
a Labour cost for filling, levelling, compaction etc.
Total(B)
Cft
130.00
8.00
1040.00
1040.00
Cft
130.00
1.00
130.00
130.00
Total(A+B)
Cost Per Cft Tk=
A.
B.
1170.00
11.70
300.00
5.00
6.20
8.00
1860.00
40.00
1900.00
100.00
0.65
65.00
65.00
1965.00
900.00
45.00
12.00
6.20
10.00
385.00
5580.00
450.00
4620.00
10650.00
900.00
90.00
45.00
900.00
45.00
0.25
100.00
100.00
0.30
1.00
0.75
0.15
1.00
160.00
11.00
1.00
270.00
90.00
33.75
135.00
45.00
40.00
1100.00
100.00
1813.75
12463.75
124.64
Name of Item
No
A
a.
b.
c.
e
B
a
b
c
d
e
f
g
h
Rate
Amount
(Tk.)
(Tk.)
860.00
22.50
22.50
18.00
6.20
29.00
10.00
385.00
5332.00
652.50
225.00
6930.00
13139.50
860.00
86.00
45.00
860.00
45.00
0.25
100.00
100.00
0.30
1.00
0.75
0.15
1.00
160.00
8.25
1.00
258.00
86.00
33.75
129.00
45.00
40.00
825.00
100.00
1516.75
Unit
Quantity
Nos
Cft.
Cft.
Bag
Nos
Cft.
Cft.
Nos
Cft.
Nos
Cft.
Cft.
Total (A+B)
Cost Per Cft
14656.25
146.56
Cost of Materials :
a. Stone Chips
b. Sylhet Sand (F.M. 2.5)
c Cement
Cft.
Cft.
Bag
82.00
41.00
22.00
112.00
29.00
385.00
9184.00
1189.00
8470.00
18843.00
Cft.
Cft.
Cft.
Cft.
Nos
Cft.
Cft.
82.00
41.00
82.00
41.00
0.25
100.00
100.00
1.00
0.75
1.25
1.00
160.00
5.85
1.00
82.00
30.75
102.50
41.00
40.00
585.00
100.00
981.25
Total of (A)
B.
a
b
c
d
e
f
g
Cost of Labour :
Labour charge for Screening (Stone Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Stone Chips)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)
Total (A+B)
Cost Per Cft
19824.25
198.24
Item
Name of Item
No
Unit
Quantity
Rate
Amount
(Tk.)
(Tk.)
Cost of Materials :
a. Stone Chips
b. Sylhet Sand (F.M. 2.5)
c Cement
Cft.
Cft.
Bag
82.00
41.00
22.00
112.00
29.00
385.00
9184.00
1189.00
8470.00
18843.00
Cft.
Cft.
Cft.
Cft.
Nos
Cft.
Cft.
82.00
41.00
82.00
41.00
0.25
100.00
100.00
1.00
0.75
1.25
1.00
160.00
7.10
1.00
82.00
30.75
102.50
41.00
40.00
710.00
100.00
1106.25
Total of (A)
B.
a
b
c
d
e
f
g
Cost of Labour :
Labour charge for Screening (Stone Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Stone Chips)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)
Total (A+B)
Cost Per Cft
19949.25
199.49
Cost of Materials :
Stone Chips
Sylhet Sand (F.M. 2.5)
Local Sand (F.M. 1.5)
Cement
Cft.
Cft.
Cft.
Bag
86.00
22.50
22.50
18.00
112.00
29.00
10.00
385.00
9632.00
652.50
225.00
6930.00
17439.50
Cft.
Cft.
Cft.
Cft.
Nos
Cft.
Cft.
86.00
45.00
86.00
45.00
0.25
100.00
100.00
1.00
0.75
1.25
1.00
160.00
5.85
1.00
86.00
33.75
107.50
45.00
40.00
585.00
100.00
997.25
Total of (A)
B.
a
b
c
d
e
f
g
Cost of Labour :
Labour charge for Screening (Stone Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Stone Chips)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)
Total(A+B)
Cost Per Cft
18436.75
184.37
Item
Name of Item
No
Unit
Quantity
Rate
Amount
(Tk.)
(Tk.)
Cost of Materials :
Stone Chips
Sylhet Sand (F.M. 2.5)
Local Sand (F.M. 1.5)
Cement
Cft.
Cft.
Cft.
Bag
86.00
22.50
22.50
18.00
112.00
29.00
10.00
385.00
9632.00
652.50
225.00
6930.00
17439.50
Cft.
Cft.
Cft.
Cft.
Nos
Cft.
Cft.
86.00
45.00
86.00
45.00
0.25
100.00
100.00
1.00
0.75
1.25
1.00
160.00
7.10
1.00
86.00
33.75
107.50
45.00
40.00
710.00
100.00
1122.25
Total of (A)
B.
a
b
c
d
e
f
g
Cost of Labour :
Labour charge for Screening (Stone Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Stone Chips)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)
Total(A+B)
Cost Per Cft
18561.75
185.62
Cost of Materials :
Picket
Sylhet Sand (F.M. 2.5)
Local Sand (F.M. 1.5)
Cement
Total of (A)
Cost of Labour :
Breaking cost of Picket
Labour charge for Screening (Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Picket)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)
Nos
Cft.
Cft.
Bag
820.00
20.50
20.50
22.00
6.20
29.00
10.00
385.00
5084.00
594.50
205.00
8470.00
14353.50
Nos
Cft.
Cft.
Nos
Cft.
Nos
Cft.
Cft.
820.00
86.00
41.00
820.00
41.00
0.25
100.00
100.00
0.30
1.00
0.75
0.15
1.00
160.00
5.85
1.00
246.00
86.00
30.75
123.00
41.00
40.00
585.00
100.00
1251.75
Total(A+B)
Cost Per Cft
15605.25
156.05
Item
Name of Item
No
Unit
Quantity
Rate
Amount
(Tk.)
(Tk.)
Cost of Materials :
Picket
Sylhet Sand (F.M. 2.5)
Local Sand (F.M. 1.5)
Cement
Total of (A)
Cost of Labour :
Breaking cost of Picket
Labour charge for Screening (Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Picket)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)
Nos
Cft.
Cft.
Bag
820.00
20.50
20.50
22.00
6.20
29.00
10.00
385.00
5084.00
594.50
205.00
8470.00
14353.50
Nos
Cft.
Cft.
Nos
Cft.
Nos
Cft.
Cft.
820.00
86.00
41.00
820.00
41.00
0.25
100.00
100.00
0.30
1.00
0.75
0.15
1.00
160.00
7.10
1.00
246.00
86.00
30.75
123.00
41.00
40.00
710.00
100.00
1376.75
Total(A+B)
Cost Per Cft
15730.25
157.30
Cost of Materials :
Picket
Sylhet Sand (F.M. 2.5)
Local Sand (F.M. 1.5)
Cement
Total of (A)
Cost of Labour :
Breaking cost of Picket
Labour charge for Screening (Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Picket)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)
Total(A+B)
Nos
Cft.
Cft.
Bag
860.00
22.50
22.50
18.00
6.20
29.00
10.00
385.00
5332.00
652.50
225.00
6930.00
13139.50
Nos
Cft.
Cft.
Nos
Cft.
Nos
Cft.
Cft.
860.00
86.00
45.00
860.00
45.00
0.25
100.00
100.00
0.30
1.00
0.75
0.15
1.00
160.00
5.85
1.00
258.00
86.00
33.75
129.00
45.00
40.00
585.00
100.00
1276.75
14416.25
Item
144.16
Name of Item
No
Unit
Quantity
Rate
Amount
(Tk.)
(Tk.)
Cost of Materials :
Picket
Sylhet Sand (F.M. 2.5)
Local Sand (F.M. 1.5)
Cement
Nos
Cft.
Cft.
Bag
860.00
22.50
22.50
18.00
6.20
29.00
10.00
385.00
5332.00
652.50
225.00
6930.00
13139.50
Nos
Cft.
Cft.
Nos
Cft.
Nos
Cft.
Cft.
860.00
86.00
45.00
860.00
45.00
0.25
100.00
100.00
0.30
1.00
0.75
0.15
1.00
160.00
7.10
1.00
Total (B)
258.00
86.00
33.75
129.00
45.00
40.00
710.00
100.00
1401.75
Total(A+B)
14541.25
Total of (A)
B
a
b
c
d
e
f
g
h
Cost of Labour :
Breaking cost of Picket
Labour charge for Screening (Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Picket)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
145.41
Cost of Materials :
Picket
Sylhet Sand (F.M. 2.5)
Local Sand (F.M. 1.5)
Cement
Total of (A)
Cost of Labour :
Breaking cost of Picket
Labour charge for Screening (Chips)
Labour charge for Screening (Sand)
Labour charge for local carrying (Picket)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Casting
Cost for Mixing & Vibratoring Machine
Total (B)
Nos
Cft.
Cft.
Bag
860.00
22.50
22.50
18.00
6.20
29.00
10.00
385.00
5332.00
652.50
225.00
6930.00
13139.50
Nos
Cft.
Cft.
Nos
Cft.
Nos
Cft.
Cft.
860.00
86.00
45.00
860.00
45.00
0.25
100.00
100.00
0.30
1.00
0.75
0.15
1.00
160.00
12.00
1.00
258.00
86.00
33.75
129.00
45.00
40.00
1200.00
100.00
1891.75
Total(A+B)
Cost Per Cft
Item
Name of Item
No
A
a.
b.
c.
e
B
a
b
c
d
e
f
g
h
15031.25
150.31
Unit
Quantity
Rate
Amount
(Tk.)
(Tk.)
A.
a.
b.
c.
B.
a
b
c
d
e
15031.25
150.31
Nos.
Cft
Bag
1150.00
36.00
4.00
6.20
10.00
385.00
7130.00
360.00
1540.00
9030.00
Cft.
Nos
Cft.
Nos
Cft.
36.00
1150.00
36.00
0.25
100.00
0.75
0.15
1.00
160.00
4.00
27.00
172.50
36.00
40.00
400.00
675.50
Total(A+B)
9705.50
97.06
Item
Name of Item
No
A.
a.
b.
c.
B.
a
b
c
d
e
A.
Rate
Amount
(Tk.)
(Tk.)
1150.00
36.00
4.00
6.20
10.00
385.00
7130.00
360.00
1540.00
9030.00
36.00
1150.00
36.00
0.25
100.00
0.75
0.15
1.00
160.00
4.70
27.00
172.50
36.00
40.00
470.00
745.50
Unit
Quantity
Nos.
Cft
Bag
Cft.
Nos
Cft.
Nos
Cft.
Total (A+B)
9775.50
97.76
Nos.
Cft
Bag
500.00
17.00
2.60
6.20
10.00
385.00
3100.00
170.00
1001.00
4271.00
Cft.
Nos
Cft.
Nos
Cft.
17.00
500.00
17.00
0.25
100.00
0.75
0.15
1.00
160.00
3.00
12.75
75.00
17.00
40.00
300.00
444.75
4715.75
Nos.
Cft
Bag
500.00
17.00
2.60
6.20
10.00
385.00
3100.00
170.00
1001.00
4271.00
Cft.
17.00
0.75
12.75
Total (A)
B.
a
b
c
d
e
Cost of Labour :
Labour charge for Screening (Sand)
Labour charge for local carrying (Picket)
Labour charge for local carrying (Sand)
Curing
Labour Cost of Brick work
A.
B.
Total (B)
Total(A+B)
47.16
b
c
d
e
Nos
Cft.
Nos
Cft.
500.00
17.00
0.25
100.00
0.15
1.00
160.00
3.50
Total (B)
Total(A+B)
A
a.
c.
B
a
b
c
d
e
4765.75
47.66
Name of Item
No
75.00
17.00
40.00
350.00
494.75
Rate
Amount
(Tk.)
(Tk.)
Unit
Quantity
Cft.
Bag
10.42
1.67
10.00
385.00
104.20
642.95
747.15
Cft.
Cft.
Cft.
Sft
Nos
10.42
10.42
10.42
100.00
0.25
0.75
0.75
1.00
3.15
160.00
7.82
7.82
10.42
315.00
40.00
381.05
Total(A+B)
1128.20
11.28
10.42
1.67
10.00
385.00
104.20
642.95
747.15
10.42
10.42
10.42
100.00
0.25
0.75
0.75
1.00
3.65
160.00
7.82
7.82
10.42
365.00
40.00
431.05
1178.20
7.81
1.25
10.00
385.00
78.10
481.25
559.35
7.81
7.81
0.75
0.75
5.86
5.86
Item
A
a.
c.
B
a
b
c
d
e
A
a.
c.
B
a
b
c
d
e
A
a.
c.
B
a
b
c
7.81
100.00
0.25
1.00
3.60
160.00
Total (B)
7.81
360.00
40.00
419.53
Total(A+B)
978.88
9.79
Name of Item
No
Cft.
Sft
Nos
Unit
Quantity
Rate
Amount
(Tk.)
(Tk.)
10.00
385.00
78.10
481.25
559.35
0.75
0.75
1.00
4.20
160.00
5.86
5.86
7.81
420.00
40.00
479.53
1038.88
10.00
385.00
75.00
577.50
652.50
0.75
0.75
1.00
3.60
160.00
5.63
5.63
7.50
360.00
40.00
418.75
1071.25
10.00
385.00
75.00
577.50
652.50
0.75
0.75
1.00
5.63
5.63
7.50
Sft
Nos
100.00
0.25
4.10
160.00
Total (B)
Total(A+B)
Item
A.
B.
11.21
Name of Item
No
Unit
A.
a.
b.
c.
B.
a
b
c
d
e
f
Quantity
Rate
Amount
(Tk.)
(Tk.)
5.00
1.00
0.50
10.00
385.00
385.00
50.00
385.00
192.50
627.50
100.00
100.00
5.00
5.00
5.00
0.25
3.60
1.00
0.75
0.75
1.00
160.00
360.00
100.00
3.75
3.75
5.00
40.00
512.50
Total (A+B)
1140.00
11.40
410.00
40.00
468.75
1121.25
Total (A+B)
5.00
1.00
0.50
10.00
385.00
385.00
50.00
385.00
192.50
627.50
100.00
100.00
5.00
5.00
5.00
0.25
4.10
1.00
0.75
0.75
1.00
160.00
410.00
100.00
3.75
3.75
5.00
40.00
562.50
1190.00
11.90
Item
Name of Item
No
A
a
b
B
a.
c.
C
a
b
c
d
A
a
b
B
a.
c.
C
a
b
c
d
Unit
Quantity
Rate
Amount
(Tk.)
(Tk.)
105.00
100.00
58.00
1.00
6090.00
100.00
6190.00
9.37
2.50
10.00
385.00
93.70
962.50
1056.20
100.00
9.37
9.37
0.25
10.00
0.75
1.00
160.00
1000.00
7.03
9.37
40.00
1056.40
8302.60
105.00
100.00
58.00
1.00
6090.00
100.00
6190.00
9.37
2.50
10.00
385.00
93.70
962.50
1056.20
100.00
9.37
9.37
0.25
10.00
0.75
1.00
160.00
1000.00
7.03
9.37
40.00
1056.40
8302.60
83.03
Item
Name of Item
No
B
a.
c.
C
a
b
c
d
Total (A)
"Thick Bsase materials (cenent morter) (1:2)
Local Sand (1.5 F.M.)
Cement .in bag
Total (B)
Cost of Labour :
Labour cost per Sft. (Tiles)
Labour charge for Screening (Sand)
Labour charge for local carrying (Sand)
Curing
Total (C)
Rate
Amount
(Tk.)
(Tk.)
Unit
Quantity
Sft
Sft
105.00
100.00
38.00
1.00
3990.00
100.00
4090.00
Cft.
Bag
6.25
2.50
10.00
385.00
62.50
962.50
1025.00
Sft
Cft.
Cft.
Nos
100.00
6.25
6.25
0.25
10.00
0.75
1.00
160.00
1000.00
4.69
6.25
40.00
1050.94
Total (A+B+C)
B
a.
c.
C
a
b
c
d
6165.94
61.66
Total (A)
"Thick Bsase materials (cenent morter) (1:2)
Local Sand (1.5 F.M.)
Cement .in bag
Total (B)
Cost of Labour :
Labour cost per Sft. (Tiles)
Labour charge for Screening (Sand)
Labour charge for local carrying (Sand)
Curing
Total (C)
Total (A+B+C)
Sft
Sft
105.00
100.00
38.00
1.00
3990.00
100.00
4090.00
Cft.
Bag
6.25
2.50
10.00
385.00
62.50
962.50
1025.00
Sft
Cft.
Cft.
Nos
100.00
6.25
6.25
0.25
10.00
0.75
1.00
160.00
1000.00
4.69
6.25
40.00
1050.94
6165.94
Item
No
A.
61.66
Name of Item
Analysis for 100 Sft. (All Floor)
Stair & Lobby Tiles (N.G.Hom 16"x16")
Cost of Materials :
a N.G.Hom Tiles (16"x16") i/c 5% wastage
b Pointing Materials and curring
Amount
(Tk.)
(Tk.)
105.00
100.00
105.00
1.00
11025.00
100.00
11125.00
9.37
2.50
10.00
385.00
93.70
962.50
1056.20
100.00
9.37
9.37
0.25
10.00
0.75
1.00
160.00
1000.00
7.03
9.37
40.00
1056.40
13237.60
Quantity
Sft
Sft
Total (A)
1"Thick Bsase materials (cenent morter) (1:3)
a. Local Sand (1.5 F.M.)
Cft.
c. Cement .in bag
Bag
Total (B)
Cost of Labour :
a Labour cost per Sft. (Tiles)
Sft
b Labour charge for Screening (Sand)
Cft.
c Labour charge for local carrying (Sand)
Cft.
d Curing
Nos
Total (C)
Total (A+B+C)
So, Cost per Sft.
132.38
Analysis for 1 Cwt. (Ground Floor)
Fabrication of M.S. rod in (40 Grade)
Cost of Materials :
a. Cost of Material M.S. rod
b. Material wastage 1.5%
Rate
Unit
Cwt
1.00
3000.00
3000.00
45.00
3045.00
Cwt
Cwt
1.00
1.00
90.00
10.00
90.00
10.00
100.00
3145.00
1.00
3000.00
3000.00
45.00
Total (A)
B.
Cost of Labour :
a. Labour charge for fabrication binding
b. Labour charge for local carrying (Rod)
Total(B)
Total(A+B)
A.
Cost Per Kg
Analysis for 1 Cwt. (1st Floor to 6th Floor)
Fabrication of M.S. rod in (40 Grade)
Cost of Materials :
a. Cost of Material M.S. rod
b. Material wastage 1.5%
62.90
Cwt
Total (A)
B.
Cost of Labour :
a. Labour charge for fabrication binding
b. Labour charge for local carrying (Rod)
3045.00
Cwt
Cwt
1.00
1.00
105.00
10.00
Total(B)
Total(A+B)
Cost Per Kg
Item
A.
3160.00
63.20
Name of Item
No
Rate
Amount
(Tk.)
(Tk.)
Unit
Quantity
Cwt
1.00
3000.00
3000.00
45.00
3045.00
Cwt
Cwt
1.00
1.00
90.00
10.00
90.00
10.00
100.00
Total (A)
B.
Cost of Labour :
a. Labour charge for fabrication binding
b. Labour charge for local carrying (Rod)
Total(B)
Total(A+B)
Cost Per Kg
A.
a.
b.
B.
a.
b.
3145.00
62.90
Cwt
1.00
3000.00
3000.00
45.00
3045.00
Cwt
Cwt
1.00
1.00
105.00
10.00
105.00
10.00
115.00
Total(A+B)
Cost Per Kg
A.
3160.00
63.20
Sft
Sft
100.00
100.00
95.00
2.00
9500.00
200.00
9700.00
Sft
100.00
3.50
350.00
Total (A)
B
105.00
10.00
115.00
Cost of Labour :
a Labour cost for fitting
Total (A)
350.00
Total (A+B)
10050.00
Item
No
A.
100.50
Name of Item
Analysis for 100 Sft. (All Floor)
Varandah safety grill
Cost of Materials :
a Steel Grill as per Design
b Fitting Materials
Rate
Amount
(Tk.)
(Tk.)
Unit
Quantity
Sft
Sft
100.00
100.00
95.00
2.00
9500.00
200.00
9700.00
Sft
100.00
3.50
350.00
350.00
Total (A)
B
Cost of Labour :
a Labour cost for fitting
Total (A)
Total (A+B)
So, Cost per Sft. Tk.
A.
10050.00
100.50
Sft
Sft
100.00
100.00
165.00
2.00
16500.00
200.00
16700.00
Sft
100.00
3.50
Total (B)
350.00
350.00
Total (A+B)
17050.00
Total (A)
B
Cost of Labour :
a Labour cost for fitting
A.
170.50
Sft
Sft
100.00
100.00
165.00
2.00
16500.00
200.00
16700.00
Sft
100.00
4.40
440.00
440.00
Total (A+B)
So, Cost per Sft. Tk.
Item
No
A.
17140.00
171.40
Name of Item
Rate
Amount
(Tk.)
(Tk.)
Unit
Quantity
Mond
Sft
1.00
1000.00
500.00
0.02
500.00
20.00
520.00
Sft
1000.00
0.20
Total (B)
200.00
200.00
Total (A+B)
720.00
A.
Cost of Labour :
a. Labour cost for 1000 Sft. .
Sft.
1.05
200.00
200.00
450.00
0.60
0.30
472.50
120.00
60.00
652.50
200.00
1.50
300.00
300.00
Total (B)
Total (A+B)
So, Cost per Sft. Tk.
A.
952.50
4.76
1.50
200.00
200.00
700.00
0.60
0.30
1050.00
120.00
60.00
1230.00
Cost of Labour :
a. Labour Cost for Pastic Paint
Sft.
Total (B)
350.00
350.00
Total (A+B)
1580.00
Item
A.
Unit
B
a
b
Quantity
Rate
Amount
(Tk.)
(Tk.)
1.05
200.00
200.00
920.00
0.60
0.30
966.00
120.00
60.00
1146.00
200.00
2.00
Total (B)
400.00
400.00
Total (A+B)
1546.00
Cost of Labour :
a. Labour Cost for Weather coat
a
b
1.75
7.9
Name of Item
No
200.00
Sft.
100.00
100.00
560.00
5.50
56000.00
550.00
56550.00
100.00
100.00
5.00
4.00
500.00
400.00
900.00
Total (A+B)
57450.00
574.50
Sft
Nos
100.00
100.00
475.00
15.00
47500.00
1500.00
49000.00
Sft
100.00
10.00
1000.00
total
B
b. Cost of Labour :
Labour charge for fitting
50000
So, cost per Sft.
Item
Name of Item
No
500.00
Rate
Amount
(Tk.)
(Tk.)
Unit
Quantity
Sft.
Sft.
100.00
100.00
155.00
3.00
15500.00
300.00
15800.00
Sft.
100.00
6.00
600.00
600.00
16400.00
Sft
Nos
100.00
100.00
145.00
15.00
14500.00
1500.00
16000.00
Sft
100.00
10.00
1000.00
17000.00
100.00
100.00
125.00
100.00
165.00
70.00
15.00
5.00
16500.00
7000.00
1875.00
500.00
25875.00
Total (B)
Total (A+B)
164.00
Total (A)
B
Cost of Labour :
Labour charge for fitting
Total (B)
Total (A+B)
A.
a.
b
c
d
170.00
Rft.
Rft.
Rft.
Rft.
Total (A)
So, Cost per Rft. Tk.
258.75
Analysis for 100 Cft.
4" Thick finished lime terracing (2:2:7)
A.
a
b
c
d
e
Cost of Materials :
I. 1st class Brick
Breaking cost
ii. Stone Lime
iii. 1st class Surki
iv. Chitagur, Garlic, Meti, Khoar
Pcs
Nos
Mond
Cft
LS
900.00
900.00
12.50
27.00
6.20
0.30
500.00
35.00
5580.00
270.00
6250.00
945.00
50.00
13095.00
Sft
100.00
7.50
750.00
13845.00
Total (A)
B.
Cost of Labour :
a Lime terracing With chipping
Total (B)
Tk.
138.45
Description
4
5
Unit
Rate
L.S
Sft
6000.00
0.50
Cft
Cft
2.00
2.25
Cft
Cft
Sft
1.00
11.70
19.65
Cft
Cft
124.64
146.56
Cft
Cft
Cft
Cft
Cft
Cft
Cft
Cft
Cft
Cft
198.24
199.49
184.37
185.62
156.05
157.30
144.16
145.41
150.31
150.31
Cft
Cft
Sft
Sft
97.06
97.76
47.16
47.66
a
b
c
d
Site Mobilization
Site cleaning
Lay-out work
Earth Excavition
Earth work up to 7-6"
Earth work above 7-6"
Filling Work
Earth fill/sand fill
Sand fill with Royalty
One layer BFS
C.C Work
3'' CC (1:3:6)-BC,MS
4'' CC (1:2:4)-BC 50% CS
RCC Works:
RCC (1:1:3),SC 50% CS (Ground Floor)
RCC (1:1:3),SC 50% CS (1st Floor to 6th Floor)
RCC (1:2:4),SC 50% CS (Ground Floor)
RCC (1:2:4),SC 50% CS (1st Floor to 6th Floor)
RCC (1:1:3),BC 50% CS (Ground Floor)
RCC (1:1:3),BC 50% CS (1st Floor to 6th Floor)
RCC (1:2:4),BC 50% CS (Ground Floor)
RCC (1:2:4),BC 50% CS (1st Floor to 6th Floor)
RCC (1:2:4),BC 50% CS (Ground Floor),Lintel
RCC (1:2:4),BC 50% CS (1st Floor to 6th Floor) False Slab
Brick Work
10"Thick Brick work(1:6) (Ground Floor)
10"Thick Brick work(1:6) (1st Floor to 6th Floor)
5" Thick Brick work (1:4) (Ground Floor)
5" Thick Brick work (1:4) (1st Floor to 6th Floor)
a
b
c
d
e
f
g
h
Plaster Work
25 mm Plaster-(1:5)-Brick walls in side (Ground Floor)
25 mm Plaster-(1:5)-Brick walls in side (1st Floor to 6th Floor)
20 mm Plaster-(1:5)-Brick walls out side (Ground Floor)
20 mm Plaster-(1:5)-Brick walls out side (1st Floor to 6th Floor)
20 mm Plaster-(1:4)-on R.C.C Surfaces (Ground Floor)
20 mm Plaster-(1:4)-on R.C.C Surfaces (1st Floor to 6th Floor)
Plaster with NCF (Ground Floor)
Plaster with NCF (1st Floor to 6th Floor)
Sft
Sft
Sft
Sft
Sft
Sft
Sft
Sft
11.28
11.78
9.79
10.39
10.71
11.21
11.40
11.90
a
b
c
d
Tiles Work
Floor Tiles (Homogeneous 12" x 12")
Floor Tiles (Ceramic 12" x 12")
Wall Tiles (Ceramic 8'' x 12")
Wall Tiles (Ceramic 10 x 13")
Sft
Sft
Sft
Sft
83.03
83.03
61.66
61.66
a
b
a
b
a
b
a
b
c
d
e
f
g
h
i
j
Sft
132.38
Description
Unit
Rate
Sl No
10
11
12
13
14
15
16
17
18
a
b
c
d
Re-Bar Work
Re-Bar 40 Grade
Re-Bar 40 Grade
Re-Bar 60 Grade
Re-Bar 60 Grade
a
b
From work
Materials & Labour (Ground Floor)
Materials & Labour (1st Floor to 6th Floor)
(Ground Floor)
(1st Floor to 6th Floor)
(Ground Floor)
(1st Floor to 6th Floor)
Grill Work
Window grill
Ver Safety grill
Ver railing
Stair Box railing
Paint Work
White wash
Distempering
Plastic paint
Weather coat
Main Door Frame
Door Farme (6" x 2" )
a
b
c
d
a
b
c
d
Door Shutter
Door Shutter
Partex Door Shutter
Partex Door Shutter
Stair Hand Rest
Stair Hand rest Teak Chamble (3"x 2" )
Aluminium works
3" Section Sliding Aluminium Door Window Fixed works
Lime Terracing
4" Thick finished lime terracing (2:2:7)
a
a
a
Kg
Kg
Kg
Kg
62.90
63.20
62.90
63.20
Sft
Sft
20.00
22.00
Sft
Sft
Sft
Sft
100.50
100.50
170.50
171.40
Sft
Sft
Sft
Sft
0.72
4.76
7.90
7.73
Rft
574.50
Rft
574.50
Sft
500.00
Sft
164.00
Sft
258.75
Sft
253.00
Sft
138.45
Remarks
Remarks
Construction Area
0.00
Average BOQ Qty Per Total Cons.area and Per Floor Cons.area
SI
Description of work
No
Unit
Per Total
Per Floor
Cons Area
Area
Cons Area
Area
Average
Average
Average
Average
Lay-out
LS
0.2013
1.2487
Earth Excavation
Cft
0.9639
Earth filling
Cft
0.3213
Sand filling
Cft
Cft
10
Pile boring
11
R.C.C work :
2000.92
1773.15
1887.04
5.9761
9581.17
8486.06
9033.61
1.9922
3193.72
2828.92
3011.32
0.4026
2.4973
4001.84
3546.17
3774.01
0.0208
0.1290
206.75
183.18
194.97
Cft
0.0974
0.6028
968.16
855.98
912.07
Sft
0.2652
1.6438
2636.09
2334.20
2485.14
Sft
0.2844
1.7642
2826.94
2505.16
2666.05
Sft
0.2831
1.7557
2814.01
2493.09
2653.55
Rft
0.0000
0.0000
0.00
0.00
0.00
0.00
0.00
0.00
Cft
0.1231
0.7632
1223.61
1083.74
1153.68
Cft
0.0167
0.1032
166.00
146.54
156.27
Cft
0.0054
0.0333
53.68
47.29
50.48
Cft
0.0173
0.1075
171.96
152.65
162.31
Cft
0.0195
0.1210
193.83
171.82
182.83
Cft
0.0045
0.0279
44.73
39.62
42.17
Cft
0.0000
0.0000
0.00
0.00
0.00
0.00
0.00
0.00
a) Footing
Kg
0.2242
1.3893
2228.55
1972.81
2100.68
b) Column upto PL
Kg
0.1384
0.8584
1375.70
1218.93
1297.31
c) Lift wall
Kg
0.0196
0.1223
194.82
173.67
184.25
d) U.G.W.R
Kg
0.0662
0.4102
658.03
582.48
620.26
e) Grade Beam
Kg
0.0986
0.6112
980.08
867.90
923.99
g) Pile
Kg
0.0000
0.0000
0.00
0.00
0.00
0.00
0.00
0.00
12
13
Sft
0.0595
0.3693
591.43
524.41
557.92
b) Column upto PL
Sft
0.0515
0.3190
511.91
452.98
482.45
c) Lift wall
Sft
0.0104
0.0644
103.38
91.45
97.41
d) U.G.W.R
Sft
0.0553
0.3431
549.68
487.20
518.44
Sft
0.0620
0.3842
616.28
545.56
580.92
0.00
0.00
0.00
e) Grade Beam
Total (a+e)
Sft
14
Sft
0.0352
0.2186
349.89
310.41
330.15
15
Sft
0.0081
0.0501
80.51
71.14
75.83
16
Rft
0.0027
0.0166
26.84
23.57
25.21
SI
No
Description of work
Unit
Per Total
Per Floor
Cons Area
Area
Cons Area
Average
Average
Average
Average
0.00
X) R.C.C work :
0.00
0.00
0.00
A) Ground Floor
0.00
0.00
0.00
Cft
0.0168
0.1040
166.99
147.68
157.34
Cft
0.0000
0.0000
0.00
0.00
0.00
Cft
0.0206
0.1277
204.76
181.33
193.05
Cft
0.0703
0.4359
698.78
618.98
658.88
Cft
0.0052
0.0320
51.69
45.44
48.56
Cft
0.0006
0.0037
5.96
5.25
5.61
Cft
0.0004
0.0025
3.98
3.55
3.76
Cft
0.0004
0.0025
3.98
3.55
3.76
0.00
0.00
0.00
Cft
0.0160
0.0992
159.04
140.86
149.95
Cft
0.0000
0.0000
0.00
0.00
0.00
Cft
0.0211
0.1308
209.73
185.74
197.74
Cft
0.0703
0.4359
698.78
618.98
658.88
Cft
0.0052
0.0320
51.69
45.44
48.56
Cft
0.0022
0.0133
21.87
18.89
20.38
Cft
0.0039
0.0241
38.77
34.22
36.49
Cft
0.0033
0.0204
32.80
28.97
30.89
0.00
0.00
0.00
B) First Floor
C) 2nd Floor
a) Column (1:1:3) SC,50% CS
Cft
0.0160
0.0992
159.04
140.86
149.95
Cft
0.0000
0.0000
0.00
0.00
0.00
Cft
0.0211
0.1308
209.73
185.74
197.74
Cft
0.0703
0.4359
698.78
618.98
658.88
Cft
0.0052
0.0320
51.69
45.44
48.56
Cft
0.0022
0.0133
21.87
18.89
20.38
Cft
0.0039
0.0241
38.77
34.22
36.49
Cft
0.0033
0.0204
32.80
28.97
30.89
0.00
0.00
0.00
D) 3rd Floor
a) Column (1:1:3) SC,50% CS
Cft
0.0160
0.0992
159.04
140.86
149.95
Cft
0.0000
0.0000
0.00
0.00
0.00
Cft
0.0211
0.1308
209.73
185.74
197.74
Cft
0.0703
0.4359
698.78
618.98
658.88
Cft
0.0052
0.0320
51.69
45.44
48.56
Cft
0.0022
0.0133
21.87
18.89
20.38
Cft
0.0039
0.0241
38.77
34.22
36.49
Cft
0.0033
0.0204
32.80
28.97
30.89
SI
No
Description of work
Unit
Per Total
Per Floor
Cons Area
Area
Cons Area
Area
Average
Average
Average
Average
E) 4th Floor
0.00
0.00
0.00
159.04
140.86
149.95
Cft
0.0160
0.0992
Cft
0.0000
0.0000
0.00
0.00
0.00
Cft
0.0211
0.1308
209.73
185.74
197.74
Cft
0.0703
0.4359
698.78
618.98
658.88
Cft
0.0052
0.0320
51.69
45.44
48.56
Cft
0.0022
0.0133
21.87
18.89
20.38
Cft
0.0039
0.0241
38.77
34.22
36.49
Cft
0.0033
0.0204
32.80
28.97
30.89
0.00
0.00
0.00
F) 5th Floor
a) Column (1:1:3) SC,50% CS
Cft
0.0160
0.0992
159.04
140.86
149.95
Cft
0.0000
0.0000
0.00
0.00
0.00
Cft
0.0211
0.1308
209.73
185.74
197.74
Cft
0.0703
0.4359
698.78
618.98
658.88
Cft
0.0052
0.0320
51.69
45.44
48.56
Cft
0.0022
0.0133
21.87
18.89
20.38
Cft
0.0039
0.0241
38.77
34.22
36.49
Cft
0.0033
0.0204
32.80
28.97
30.89
0.00
0.00
0.00
Cft
0.0033
0.0205
32.80
29.11
30.96
Cft
0.0058
0.0360
57.65
51.12
54.39
Cft
0.0000
0.0000
0.00
0.00
0.00
Cft
0.0000
0.0000
0.00
0.00
0.00
Cft
0.0000
0.0000
0.00
0.00
0.00
Cft
0.0000
0.0000
0.00
0.00
0.00
Cft
0.0000
0.0000
0.00
0.00
0.00
Cft
0.0000
0.0000
0.00
0.00
0.00
Cft
0.0146
0.0907
145.12
128.79
136.96
SI
No
Description of work
Unit
Per Total
Per Floor
Cons Area
Area
Cons Area
Average
Average
Average
Average
0.00
0.00
0.00
0.00
A) Ground Floor
0.00
0.00
0.00
Kg
0.1421
0.8806
1412.47
1250.45
1331.46
Kg
0.0000
0.0000
0.00
0.00
0.00
Kg
0.1352
0.8395
1343.89
1192.09
1267.99
Kg
0.2031
1.2602
2018.81
1789.48
1904.15
Kg
0.0195
0.1207
193.83
171.39
182.61
Kg
0.0038
0.0237
37.77
33.65
35.71
Kg
0.0024
0.0147
23.86
20.87
22.37
Kg
0.0025
0.0155
24.85
22.01
23.43
0.00
0.00
0.00
B) First Floor
a) Column (60 Grade) in/c 3% wastage
Kg
0.1317
0.8167
1309.10
1159.71
1234.41
Kg
0.0000
0.0000
0.00
0.00
0.00
Kg
0.1352
0.8395
1343.89
1192.09
1267.99
Kg
0.2031
1.2602
2018.81
1789.48
1904.15
Kg
0.0195
0.1207
193.83
171.39
182.61
Kg
0.0164
0.1012
163.02
143.70
153.36
Kg
0.0142
0.0879
141.15
124.82
132.98
Kg
0.0122
0.0757
121.27
107.49
114.38
0.00
0.00
0.00
C) 2nd Floor
a) Column (60 Grade) in/c 3% wastage
Kg
0.1223
0.7585
1215.66
1077.07
1146.37
Kg
0.0000
0.0000
0.00
0.00
0.00
Kg
0.1352
0.8395
1343.89
1192.09
1267.99
Kg
0.2031
1.2602
2018.81
1789.48
1904.15
Kg
0.0195
0.1207
193.83
171.39
182.61
Kg
0.0164
0.1012
163.02
143.70
153.36
Kg
0.0142
0.0879
141.15
124.82
132.98
Kg
0.0122
0.0757
121.27
107.49
114.38
0.00
0.00
0.00
Kg
0.1159
0.7185
1152.05
1020.27
1086.16
Kg
0.0000
0.0000
0.00
0.00
0.00
Kg
0.1352
0.8395
1343.89
1192.09
1267.99
Kg
0.2031
1.2602
2018.81
1789.48
1904.15
Kg
0.0195
0.1207
193.83
171.39
182.61
D) 3rd Floor
Kg
0.0164
0.1012
163.02
143.70
153.36
Kg
0.0142
0.0879
141.15
124.82
132.98
Kg
0.0122
0.0757
121.27
107.49
114.38
SI
No
Description of work
Unit
Per Total
Per Floor
Cons Area
Area
Cons Area
Area
Average
Average
Average
Average
E) 4th Floor
0.00
0.00
0.00
1097.38
972.42
1034.90
Kg
0.1104
0.6848
Kg
0.0000
0.0000
0.00
0.00
0.00
Kg
0.1352
0.8395
1343.89
1192.09
1267.99
Kg
0.2031
1.2602
2018.81
1789.48
1904.15
Kg
0.0195
0.1207
193.83
171.39
182.61
Kg
0.0164
0.1012
163.02
143.70
153.36
Kg
0.0142
0.0879
141.15
124.82
132.98
Kg
0.0122
0.0757
121.27
107.49
114.38
0.00
0.00
0.00
F) 5th Floor
a) Column (60 Grade) in/c 3% wastage
Kg
0.1093
0.6780
1086.44
962.76
1024.60
Kg
0.0000
0.0000
0.00
0.00
0.00
Kg
0.1352
0.8395
1343.89
1192.09
1267.99
Kg
0.2031
1.2602
2018.81
1789.48
1904.15
Kg
0.0195
0.1207
193.83
171.39
182.61
Kg
0.0164
0.1012
163.02
143.70
153.36
Kg
0.0142
0.0879
141.15
124.82
132.98
Kg
0.0122
0.0757
121.27
107.49
114.38
0.00
0.00
0.00
G) Top Floor
a) Column (60 Grade) in/c 3% wastage
Kg
0.0190
0.1175
188.86
166.85
177.86
Kg
0.0267
0.1653
265.40
234.73
250.06
Kg
0.0000
0.0000
0.00
0.00
0.00
Kg
0.0000
0.0000
0.00
0.00
0.00
Kg
0.0000
0.0000
0.00
0.00
0.00
Kg
0.0000
0.0000
0.00
0.00
0.00
Kg
0.0000
0.0000
0.00
0.00
0.00
Kg
0.0000
0.0000
0.00
0.00
0.00
Kg
0.0670
0.4158
665.98
590.44
628.21
SI
Description of work
No
Unit
Per Total
Per Floor
Cons Area
Area
Cons Area
Average
Average
Average
Average
0.00
Z) From work
0.00
0.00
0.00
A) Ground Floor
0.00
0.00
0.00
a) Column
Sft
0.0604
0.3743
600.38
531.51
565.94
b) Lift wall
Sft
0.0000
0.0000
0.00
0.00
0.00
c) Beam
Sft
0.0412
0.2554
409.53
362.67
386.10
d) Slab
Sft
0.1629
1.0107
1619.23
1435.19
1527.21
e) Stair
Sft
0.0161
0.0996
160.03
141.43
150.73
f) Lintel
Sft
0.0041
0.0251
40.75
35.64
38.20
g) False Slab
Sft
0.0018
0.0109
17.89
15.48
16.69
Sft
0.0035
0.0214
34.79
30.39
32.59
0.00
0.00
0.00
a) Column
Sft
0.0591
0.3661
587.45
519.86
553.66
b) Lift wall
Sft
0.0000
0.0000
0.00
0.00
0.00
c) Beam
Sft
0.0420
0.2608
417.48
370.34
393.91
d) Slab
Sft
0.1629
1.0107
1619.23
1435.19
1527.21
e) Stair
Sft
0.0161
0.0996
160.03
141.43
150.73
f) Lintel
Sft
0.0102
0.0636
101.39
90.31
95.85
g) False Slab
Sft
0.0149
0.0923
148.11
131.07
139.59
Sft
0.0186
0.1153
184.88
163.73
174.31
0.00
0.00
0.00
a) Column
Sft
0.0591
0.3661
587.45
519.86
553.66
b) Lift wall
Sft
0.0000
0.0000
0.00
0.00
0.00
c) Beam
Sft
0.1460
0.9006
1451.24
1278.85
1365.05
d) Slab
Sft
0.1629
1.0107
1619.23
1435.19
1527.21
e) Stair
Sft
0.0161
0.0996
160.03
141.43
150.73
f) Lintel
Sft
0.0130
0.0805
129.22
114.31
121.77
g) False Slab
Sft
0.0209
0.1294
207.75
183.75
195.75
Sft
0.0231
0.1434
229.61
203.63
216.62
0.00
0.00
0.00
B) First Floor
C) 2nd Floor
D) 3rd Floor
a) Column
Sft
0.0591
0.3661
587.45
519.86
553.66
b) Lift wall
Sft
0.0000
0.0000
0.00
0.00
0.00
c) Beam
Sft
0.1460
0.9006
1451.24
1278.85
1365.05
d) Slab
Sft
0.1629
1.0107
1619.23
1435.19
1527.21
e) Stair
Sft
0.0161
0.0996
160.03
141.43
150.73
f) Lintel
Sft
0.0130
0.0805
129.22
114.31
121.77
g) False Slab
Sft
0.0209
0.1294
207.75
183.75
195.75
Sft
0.0231
0.1434
229.61
203.63
216.62
SI
Description of work
No
Unit
Per Total
Per Floor
Cons Area
Area
Cons Area
Area
Average
Average
Average
Average
E) 4th Floor
0.00
0.00
0.00
587.45
519.86
553.66
a) Column
Sft
0.0591
0.3661
b) Lift wall
Sft
0.0000
0.0000
0.00
0.00
0.00
c) Beam
Sft
0.1460
0.9006
1451.24
1278.85
1365.05
d) Slab
Sft
0.1629
1.0107
1619.23
1435.19
1527.21
e) Stair
Sft
0.0161
0.0996
160.03
141.43
150.73
f) Lintel
Sft
0.0130
0.0805
129.22
114.31
121.77
g) False Slab
Sft
0.0209
0.1294
207.75
183.75
195.75
Sft
0.0231
0.1434
229.61
203.63
216.62
0.00
0.00
0.00
a) Column
Sft
0.0591
0.3661
587.45
519.86
553.66
b) Lift wall
Sft
0.0000
0.0000
0.00
0.00
0.00
c) Beam
Sft
0.1460
0.9006
1451.24
1278.85
1365.05
d) Slab
Sft
0.1629
1.0107
1619.23
1435.19
1527.21
e) Stair
Sft
0.0161
0.0996
160.03
141.43
150.73
f) Lintel
Sft
0.0130
0.0805
129.22
114.31
121.77
g) False Slab
Sft
0.0209
0.1294
207.75
183.75
195.75
Sft
0.0231
0.1434
229.61
203.63
216.62
0.00
0.00
0.00
F) 5th Floor
G) Top Floor
a) Column
Sft
0.0124
0.0766
123.26
108.77
116.01
b) Lift M Room
Sft
0.0151
0.0934
150.09
132.63
141.36
c) Beam
Sft
0.0000
0.0000
0.00
0.00
0.00
d) Slab
Sft
0.0000
0.0000
0.00
0.00
0.00
e) Stair
Sft
0.0000
0.0000
0.00
0.00
0.00
f) Lintel
Sft
0.0000
0.0000
0.00
0.00
0.00
g) False Slab
Sft
0.0000
0.0000
0.00
0.00
0.00
Sft
0.0000
0.0000
0.00
0.00
0.00
i) OHWT
Sft
0.0439
0.2720
436.37
386.24
411.30
SI
Description of work
No
Unit
Per Total
Per Floor
Cons Area
Area
Cons Area
Area
Average
Average
Average
Average
0.00
A) Ground Floor
1
0.00
0.00
0.00
Brick Work:
a 10" Thick brick work (1:6)
Cft
0.0015
0.0090
14.91
12.78
13.85
Sft
0.0952
0.5907
946.29
838.79
892.54
Sft
0.1904
1.1811
1892.58
1677.16
1784.87
Sft
0.2427
1.5053
2412.44
2137.53
2274.98
Sft
0.2754
1.7085
2737.48
2426.07
2581.77
Sft
0.0160
0.0993
159.04
141.01
150.02
Sft
0.0000
0.0000
0.00
0.00
0.00
Sft
0.0000
0.0000
0.00
0.00
0.00
Sft
0.0000
0.0000
0.00
0.00
0.00
Sft
0.0000
0.0000
0.00
0.00
0.00
0.00
0.00
0.00
Plastering Work:
Tiles Work:
Paint Work:
a Ceiling
Sft
0.2754
1.7085
2737.48
2426.07
2581.77
b Wall
Sft
0.1904
1.1811
1892.58
1677.16
1784.87
c Weather coat
Sft
0.2427
1.5053
2412.44
2137.53
2274.98
d Enamel
Sft
0.0018
0.0113
17.89
16.05
16.97
e White washing
Sft
0.0000
0.0000
0.00
0.00
0.00
f French Polish
Sft
0.0000
0.0000
0.00
0.00
0.00
Rft
0.0000
0.0000
0.00
0.00
0.00
Rft
0.0034
0.0212
33.80
30.10
31.95
Sft
0.0000
0.00
0.00
0.00
Sft
0.0034
0.0211
33.80
29.96
31.88
Pcs
0.0002
0.0012
1.99
1.70
1.85
Pcs
0.0002
0.0012
1.99
1.70
1.85
a Window grill
Sft
0.0037
0.0227
36.78
32.23
34.51
Sft
0.0000
0.0000
0.00
0.00
0.00
c Varandah railing
Sft
0.0000
0.0000
0.00
0.00
0.00
Sft
0.0028
0.0174
27.83
24.71
26.27
Rft
0.0010
0.0062
9.94
8.80
9.37
Sft
0.0000
0.0000
0.00
0.00
0.00
Sft
0.0037
0.0227
36.78
32.23
34.51
Sft
0.0000
0.0000
0.00
0.00
0.00
Grill Work:
Aluminium Work:
Common Work:
a Marble works
Sft
0.0057
0.0356
56.66
50.55
53.61
b Main Gate
Sft
0.0054
0.0332
53.68
47.14
50.41
Pcs
0.0002
0.0012
1.99
1.70
1.85
SI
Description of work
No
Unit
Per Total
Per Floor
Cons Area
Area
Cons Area
Average
Average
Average
Average
0.00
B) First Floor
1
Brick Work:
a 10" Thick brick work (1:6)
Cft
0.0160
0.0995
159.04
141.29
150.17
Sft
0.2305
1.4302
2291.17
2030.88
2161.03
Sft
0.4255
2.6424
4229.47
3752.21
3990.84
Sft
0.1092
0.6774
1085.45
961.91
1023.68
Sft
0.2054
1.2738
2041.68
1808.80
1925.24
Sft
0.0148
0.0918
147.11
130.36
138.73
Sft
0.1224
0.7595
1216.66
1078.49
1147.57
Sft
0.0146
0.0904
145.12
128.37
136.75
Sft
0.0136
0.0844
135.18
119.85
127.52
Sft
0.0751
0.4664
746.49
662.29
704.39
0.00
0.00
0.00
a Ceiling
Sft
0.2054
1.2738
2041.68
1808.80
1925.24
b Wall
Sft
0.4250
2.6390
4224.50
3747.38
3985.94
c Weather coat
Sft
0.1092
0.6774
1085.45
961.91
1023.68
d Enamel
Sft
0.0416
0.2581
413.50
366.50
390.00
e White washing
Sft
0.0180
0.1121
178.92
159.18
169.05
f French Polish
Sft
0.0303
0.1880
301.18
266.96
284.07
Rft
0.0018
0.0110
17.89
15.62
16.76
Rft
0.0062
0.0384
61.63
54.53
58.08
Sft
0.0023
0.0140
22.86
19.88
21.37
Sft
0.0085
0.0524
84.49
74.41
79.45
Pcs
0.0006
0.0036
5.96
5.11
5.54
Pcs
0.0005
0.0028
4.97
3.98
4.47
Plastering Work:
Tiles Work:
Paint Work:
Grill Work:
a Window grill
Sft
0.0151
0.0935
150.09
132.77
141.43
Sft
0.0165
0.1022
164.01
145.12
154.57
c Varandah railing
Sft
0.0092
0.0568
91.45
80.66
86.05
Sft
0.0028
0.0174
27.83
24.71
26.27
Rft
0.0010
0.0062
9.94
8.80
9.37
Sft
0.0116
0.0721
115.30
102.38
108.84
Sft
0.0100
0.0619
99.40
87.90
93.65
Sft
0.0107
0.0667
106.36
94.71
100.54
a Marble works
Sft
0.0024
0.0152
23.86
21.58
22.72
b Main Gate
Pcs
0.0001
0.0006
0.99
0.85
0.92
Pcs
0.0007
0.0040
6.96
5.68
6.32
Aluminium Work:
Common Work:
SI
Description of work
No
Unit
Per Total
Per Floor
Cons Area
Area
Cons Area
Average
Average
Average
Average
0.00
C) 2nd Floor
1
Brick Work:
a 10" Thick brick work (1:6)
Cft
0.0160
0.0995
159.04
141.29
150.17
Sft
0.2305
1.4302
2291.17
2030.88
2161.03
Sft
0.4255
2.6424
4229.47
3752.21
3990.84
Sft
0.1092
0.6774
1085.45
961.91
1023.68
Sft
0.2054
1.2738
2041.68
1808.80
1925.24
Sft
0.0148
0.0918
147.11
130.36
138.73
Sft
0.1224
0.7595
1216.66
1078.49
1147.57
Sft
0.0146
0.0904
145.12
128.37
136.75
Sft
0.0136
0.0844
135.18
119.85
127.52
Sft
0.0751
0.4664
746.49
662.29
704.39
0.00
0.00
0.00
a Ceiling
Sft
0.2054
1.2738
2041.68
1808.80
1925.24
b Wall
Sft
0.4250
2.6390
4224.50
3747.38
3985.94
c Weather coat
Sft
0.1092
0.6774
1085.45
961.91
1023.68
d Enamel
Sft
0.0416
0.2581
413.50
366.50
390.00
e White washing
Sft
0.0180
0.1121
178.92
159.18
169.05
f French Polish
Sft
0.0303
0.1880
301.18
266.96
284.07
Rft
0.0018
0.0110
17.89
15.62
16.76
Rft
0.0062
0.0384
61.63
54.53
58.08
Sft
0.0023
0.0140
22.86
19.88
21.37
Sft
0.0085
0.0524
84.49
74.41
79.45
Pcs
0.0006
0.0036
5.96
5.11
5.54
Pcs
0.0005
0.0028
4.97
3.98
4.47
Plastering Work:
Tiles Work:
Paint Work:
Grill Work:
a Window grill
Sft
0.0151
0.0935
150.09
132.77
141.43
Sft
0.0165
0.1022
164.01
145.12
154.57
c Varandah railing
Sft
0.0092
0.0568
91.45
80.66
86.05
Sft
0.0028
0.0174
27.83
24.71
26.27
Rft
0.0010
0.0062
9.94
8.80
9.37
Sft
0.0116
0.0721
115.30
102.38
108.84
Sft
0.0100
0.0619
99.40
87.90
93.65
Sft
0.0107
0.0667
106.36
94.71
100.54
a Marble works
Sft
0.0024
0.0152
23.86
21.58
22.72
b Main Gate
Pcs
0.0001
0.0006
0.99
0.85
0.92
Pcs
0.0007
0.0040
6.96
5.68
6.32
Aluminium Work:
Common Work:
SI
Description of work
No
Unit
Per Total
Per Floor
Cons Area
Area
Cons Area
Average
Average
Average
Average
0.00
D) 3rd Floor
1
Brick Work:
a 10" Thick brick work (1:6)
Cft
0.0160
0.0995
159.04
141.29
150.17
Sft
0.2305
1.4302
2291.17
2030.88
2161.03
Sft
0.4255
2.6424
4229.47
3752.21
3990.84
Sft
0.1092
0.6774
1085.45
961.91
1023.68
Sft
0.2054
1.2738
2041.68
1808.80
1925.24
Sft
0.0148
0.0918
147.11
130.36
138.73
Sft
0.1224
0.7595
1216.66
1078.49
1147.57
Sft
0.0146
0.0904
145.12
128.37
136.75
Sft
0.0136
0.0844
135.18
119.85
127.52
Sft
0.0751
0.4664
746.49
662.29
704.39
0.00
0.00
0.00
a Ceiling
Sft
0.2054
1.2738
2041.68
1808.80
1925.24
b Wall
Sft
0.4250
2.6390
4224.50
3747.38
3985.94
c Weather coat
Sft
0.1092
0.6774
1085.45
961.91
1023.68
d Enamel
Sft
0.0416
0.2581
413.50
366.50
390.00
e White washing
Sft
0.0180
0.1121
178.92
159.18
169.05
f French Polish
Sft
0.0303
0.1880
301.18
266.96
284.07
Rft
0.0018
0.0110
17.89
15.62
16.76
Rft
0.0062
0.0384
61.63
54.53
58.08
Sft
0.0023
0.0140
22.86
19.88
21.37
Sft
0.0085
0.0524
84.49
74.41
79.45
Pcs
0.0006
0.0036
5.96
5.11
5.54
Pcs
0.0005
0.0028
4.97
3.98
4.47
Plastering Work:
Tiles Work:
Paint Work:
Grill Work:
a Window grill
Sft
0.0151
0.0935
150.09
132.77
141.43
Sft
0.0165
0.1022
164.01
145.12
154.57
c Varandah railing
Sft
0.0092
0.0568
91.45
80.66
86.05
Sft
0.0028
0.0174
27.83
24.71
26.27
Rft
0.0010
0.0062
9.94
8.80
9.37
Sft
0.0116
0.0721
115.30
102.38
108.84
Sft
0.0100
0.0619
99.40
87.90
93.65
Sft
0.0107
0.0667
106.36
94.71
100.54
a Marble works
Sft
0.0024
0.0152
23.86
21.58
22.72
b Main Gate
Pcs
0.0001
0.0006
0.99
0.85
0.92
Pcs
0.0007
0.0040
6.96
5.68
6.32
Aluminium Work:
Common Work:
SI
Description of work
No
Unit
Per Total
Per Floor
Cons Area
Area
Cons Area
Area
Average
Average
Average
Average
E) 4th Floor
1
0.00
0.00
0.00
0.00
Brick Work:
a 10" Thick brick work (1:6)
Cft
0.0160
0.0995
159.04
141.29
150.17
Sft
0.2305
1.4302
2291.17
2030.88
2161.03
Sft
0.4255
2.6424
4229.47
3752.21
3990.84
Sft
0.1092
0.6774
1085.45
961.91
1023.68
Sft
0.2054
1.2738
2041.68
1808.80
1925.24
Sft
0.0148
0.0918
147.11
130.36
138.73
Sft
0.1224
0.7595
1216.66
1078.49
1147.57
Sft
0.0146
0.0904
145.12
128.37
136.75
Sft
0.0136
0.0844
135.18
119.85
127.52
Sft
0.0751
0.4664
746.49
662.29
704.39
0.00
0.00
0.00
a Ceiling
Sft
0.2054
1.2738
2041.68
1808.80
1925.24
b Wall
Sft
0.4250
2.6390
4224.50
3747.38
3985.94
c Weather coat
Sft
0.1092
0.6774
1085.45
961.91
1023.68
d Enamel
Sft
0.0416
0.2581
413.50
366.50
390.00
e White washing
Sft
0.0180
0.1121
178.92
159.18
169.05
f French Polish
Sft
0.0303
0.1880
301.18
266.96
284.07
Rft
0.0018
0.0110
17.89
15.62
16.76
Rft
0.0062
0.0384
61.63
54.53
58.08
Sft
0.0023
0.0140
22.86
19.88
21.37
Sft
0.0085
0.0524
84.49
74.41
79.45
Pcs
0.0006
0.0036
5.96
5.11
5.54
Pcs
0.0005
0.0028
4.97
3.98
4.47
Plastering Work:
Tiles Work:
Paint Work:
Grill Work:
a Window grill
Sft
0.0151
0.0935
150.09
132.77
141.43
Sft
0.0165
0.1022
164.01
145.12
154.57
c Varandah railing
Sft
0.0092
0.0568
91.45
80.66
86.05
Sft
0.0028
0.0174
27.83
24.71
26.27
Rft
0.0010
0.0062
9.94
8.80
9.37
Sft
0.0116
0.0721
115.30
102.38
108.84
Sft
0.0100
0.0619
99.40
87.90
93.65
Sft
0.0107
0.0667
106.36
94.71
100.54
a Marble works
Sft
0.0024
0.0152
23.86
21.58
22.72
b Main Gate
Pcs
0.0001
0.0006
0.99
0.85
0.92
Pcs
0.0007
0.0040
6.96
5.68
6.32
Aluminium Work:
Common Work:
SI
Description of work
No
Unit
Per Total
Per Floor
Cons Area
Area
Cons Area
Area
Average
Average
Average
Average
F) 5th Floor
1
0.00
0.00
0.00
0.00
Brick Work:
a 10" Thick brick work (1:6)
Cft
0.0160
0.0995
159.04
141.29
150.17
Sft
0.2305
1.4302
2291.17
2030.88
2161.03
Sft
0.4255
2.6424
4229.47
3752.21
3990.84
Sft
0.1092
0.6774
1085.45
961.91
1023.68
Sft
0.2054
1.2738
2041.68
1808.80
1925.24
Sft
0.0148
0.0918
147.11
130.36
138.73
Sft
0.1224
0.7595
1216.66
1078.49
1147.57
Sft
0.0146
0.0904
145.12
128.37
136.75
Sft
0.0136
0.0844
135.18
119.85
127.52
Sft
0.0751
0.4664
746.49
662.29
704.39
0.00
0.00
0.00
a Ceiling
Sft
0.2054
1.2738
2041.68
1808.80
1925.24
b Wall
Sft
0.4250
2.6390
4224.50
3747.38
3985.94
c Weather coat
Sft
0.1092
0.6774
1085.45
961.91
1023.68
d Enamel
Sft
0.0416
0.2581
413.50
366.50
390.00
e White washing
Sft
0.0180
0.1121
178.92
159.18
169.05
f French Polish
Sft
0.0303
0.1880
301.18
266.96
284.07
Rft
0.0018
0.0110
17.89
15.62
16.76
Rft
0.0062
0.0384
61.63
54.53
58.08
Sft
0.0023
0.0140
22.86
19.88
21.37
Sft
0.0085
0.0524
84.49
74.41
79.45
Pcs
0.0006
0.0036
5.96
5.11
5.54
Pcs
0.0005
0.0028
4.97
3.98
4.47
Plastering Work:
Tiles Work:
Paint Work:
Grill Work:
a Window grill
Sft
0.0151
0.0935
150.09
132.77
141.43
Sft
0.0165
0.1022
164.01
145.12
154.57
c Varandah railing
Sft
0.0092
0.0568
91.45
80.66
86.05
Sft
0.0028
0.0174
27.83
24.71
26.27
Rft
0.0010
0.0062
9.94
8.80
9.37
Sft
0.0116
0.0721
115.30
102.38
108.84
Sft
0.0100
0.0619
99.40
87.90
93.65
Sft
0.0107
0.0667
106.36
94.71
100.54
a Marble works
Sft
0.0024
0.0152
23.86
21.58
22.72
b Main Gate
Pcs
0.0001
0.0006
0.99
0.85
0.92
Pcs
0.0007
0.0040
6.96
5.68
6.32
Aluminium Work:
Common Work:
SI
Description of work
No
Unit
Per Total
Per Floor
Cons Area
Area
Cons Area
Area
Average
Average
Average
Average
G) Top Floor
1
0.00
0.00
0.00
Brick Work:
a 10" Thick brick work (1:6)
Cft
0.0050
0.0310
49.70
44.02
46.86
Sft
0.0609
0.3779
605.35
536.62
570.98
Sft
0.0626
0.3882
622.24
551.24
586.74
Sft
0.1382
0.8573
1373.71
1217.37
1295.54
Sft
0.0245
0.1518
243.53
215.56
229.54
Sft
0.0005
0.0031
4.97
4.40
4.69
Sft
0.0101
0.0623
100.39
88.47
94.43
Sft
0.0019
0.0118
18.89
16.76
17.82
Sft
0.0010
0.0059
9.94
8.38
9.16
Sft
0.0056
0.0349
55.66
49.56
52.61
0.00
0.00
0.00
a Ceiling
Sft
0.0245
0.1518
243.53
215.56
229.54
b Wall
Sft
0.0626
0.3882
622.24
551.24
586.74
c Weather coat
Sft
0.1382
0.8573
1373.71
1217.37
1295.54
d Enamel
Sft
0.0005
0.0031
4.97
4.40
4.69
e White washing
Sft
0.0000
0.0000
0.00
0.00
0.00
f French Polish
Sft
0.0000
0.0000
0.00
0.00
0.00
a MS Door Frame
Pcs
0.0001
0.0006
0.99
0.85
0.92
b MS Door shutter
Sft
0.0011
0.0068
10.93
9.66
10.30
c Plastic door
Pcs
0.0000
0.0000
0.00
0.00
0.00
Pcs
0.0000
0.0000
0.00
0.00
0.00
Plastering Work:
Tiles Work:
Paint Work:
Grill Work:
a Window grill
Sft
0.0000
0.0000
0.00
0.00
0.00
Sft
0.0000
0.0000
0.00
0.00
0.00
c Varandah railing
Sft
0.0000
0.0000
0.00
0.00
0.00
Sft
0.0005
0.0030
4.97
4.26
4.62
Rft
0.0002
0.0012
1.99
1.70
1.85
Sft
0.0000
0.0000
0.00
0.00
0.00
Sft
0.0000
0.0000
0.00
0.00
0.00
Sft
0.0000
0.0000
0.00
0.00
0.00
a Marble works
Sft
0.0000
0.0000
0.00
0.00
0.00
Pcs
0.0000
0.0000
0.00
0.00
0.00
Pcs
0.0000
0.0000
0.00
0.00
0.00
Cft.
0.0302
0.1876
300.19
266.39
283.29
Sft
0.1570
0.9752
1560.58
1384.78
1472.68
Sft
0.0736
0.4551
731.58
646.24
688.91
g NCF in OHWT
Sft
0.0293
0.1816
291.24
257.87
274.56
Sft
0.0299
0.1856
297.21
263.55
280.38
Aluminium Work:
Common Work:
TD
Nagar, Dhaka-1000.
9940
1420
r Cons.area
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Location
Nos of floor
Nos
Nos of Flat
Nos
Nos
Completion Time
27
Month
1420
Sft
9940
Sft
SI
Description
No
Unit
Amount
Sub-Structure
Tk
1089320.00
109.59
Tk
3870528.00
389.39
Tk
4788508.00
481.74
Tk
9748356.00
980.72
r, Dhaka-1000.
e: 13 April, 2010
Remarks
Description
Unit
Qty
Rate
Foundation Upto PL
Sft
1420
70.00
99400.00
Ground Floor
Sft
1420
113.00
160460.00
1st Floor
Sft
1420
119.78
170087.60
2nd Floor
Sft
1420
126.56
179715.20
3rd Floor
Sft
1420
133.34
189342.80
4th Floor
Sft
1420
140.12
198970.40
5th Floor
Sft
1420
146.90
208598.00
6th Floor
Sft
1420
153.68
218225.60
Top Floor
Sft
1420
56.50
80230.00
TOTAL
Amount
1505029.60
Remarks
Location
Nos of floor
Nos
Nos of Flat
Nos
Nos
Completion Time
27
Month
1420
Sft
9940
Sft
SI
No
Unit
Amount
A Sub-Structure
Tk
1089320.00
109.59
Tk
3870528.00
389.39
Tk
4788508.00
481.74
Tk
9748356.00
980.72
Description
Remarks
A. Sub-Structure
Name of the Project :
SI
No
1 Lay-out
Description of work
Unit
Quantity
Rate
Amount
LS
1887.04
0.50
944.00
Earth Excavation
Cft
9033.61
2.00
18067.00
Earth filling
Cft
3011.32
1.00
3011.00
Sand filling
Cft
3774.01
11.70
44156.00
Cft
194.97
124.64
24301.00
Cft
912.07
146.56
133672.00
Sft
2485.14
1.00
2485.00
Sft
2666.05
19.65
52388.00
Sft
2653.55
3.25
8624.00
Rft
0.00
0.00
0.00
Cft
1153.68
198.24
228705.00
Cft
156.27
198.24
30979.00
Cft
50.48
198.24
10007.00
Cft
162.31
198.24
32176.00
Cft
182.83
156.05
28530.00
Cft
42.17
156.05
6581.00
Cft
0.00
0.00
0.00
a) Footing
Kg
2100.68
b) Column upto PL
Kg
1297.31
62.90
429497.00
10 Pile boring
11 R.C.C work :
c) Lift wall
Kg
184.25
d) U.G.W.R
Kg
1139.65
e) Grade Beam
Kg
1907.48
g) Pile
Kg
0.00
Kg
6629.36
Kg
6828.24
Sft
557.92
b) Column upto PL
Sft
482.45
c) Lift wall
Sft
97.41
d) U.G.W.R
Sft
518.44
e) Grade Beam
Sft
580.92
Total (a+g)
in/c 3% wastage
13 Form work (M+L)
Sft
2237.14
12.50
27964.00
Total (a+e)
Sft
330.15
11.40
3764.00
Sft
75.83
12.50
948.00
Rft
25.21
100.00
2521.00
1089320.00
Remarks
Description of work
Unit
Quantity
Rate
Amount
X) R.C.C work :
A) Ground Floor
a) Column (1:1:3) SC,50% CS
Cft
157.34
198.24
31190.00
Cft
0.00
198.24
0.00
Cft
193.05
144.16
27830.00
Cft
658.88
144.16
94984.00
Cft
48.56
144.16
7001.00
Cft
5.61
150.31
843.00
Cft
3.76
150.31
566.00
Cft
3.76
150.31
566.00
Cft
149.95
199.49
29914.00
Cft
0.00
199.49
0.00
Cft
197.74
145.41
28753.00
Cft
658.88
145.41
95808.00
Cft
48.56
145.41
7062.00
Cft
20.38
150.31
3063.00
Cft
36.49
150.31
5485.00
Cft
30.89
150.31
4642.00
Cft
149.95
199.49
29914.00
Cft
0.00
199.49
0.00
Sub-Total (a+h)
C) 2nd Floor
Cft
197.74
145.41
28753.00
Cft
658.88
145.41
95808.00
Cft
48.56
145.41
7062.00
Cft
20.38
150.31
3063.00
Cft
36.49
150.31
5485.00
Cft
30.89
150.31
4642.00
Cft
149.95
199.49
29914.00
Cft
0.00
199.49
0.00
Cft
197.74
145.41
28753.00
Cft
658.88
145.41
95808.00
Cft
48.56
145.41
7062.00
Cft
20.38
150.31
3063.00
Cft
36.49
150.31
5485.00
Cft
30.89
150.31
4642.00
687161.00
Sub-Total (a+h)
D) 3rd Floor
Remarks
Description of work
Unit
Quantity
E) 4th Floor
Rate
Amount
BF=
687161.00
149.95
199.49
29914.00
Cft
0.00
199.49
0.00
Cft
197.74
145.41
28753.00
Cft
658.88
145.41
95808.00
Cft
48.56
145.41
7062.00
Cft
20.38
150.31
3063.00
Cft
36.49
150.31
5485.00
Cft
30.89
150.31
4642.00
Cft
149.95
199.49
29914.00
Cft
0.00
199.49
0.00
Cft
Sub-Total (a+h)
F) 5th Floor
Cft
197.74
145.41
28753.00
Cft
658.88
145.41
95808.00
Cft
48.56
145.41
7062.00
Cft
20.38
150.31
3063.00
Cft
36.49
150.31
5485.00
Cft
30.89
150.31
4642.00
Cft
149.95
199.49
29914.00
Cft
0.00
199.49
0.00
Cft
197.74
145.41
28753.00
Cft
658.88
145.41
95808.00
Cft
48.56
145.41
7062.00
Cft
20.38
150.31
3063.00
Cft
36.49
150.31
5485.00
Cft
30.89
150.31
4642.00
Cft
30.96
199.49
6175.00
Cft
54.39
199.49
10849.00
Cft
0.00
145.41
0.00
Cft
0.00
145.41
0.00
Cft
0.00
145.41
0.00
Cft
0.00
150.31
0.00
Cft
0.00
150.31
0.00
Cft
0.00
150.31
0.00
Cft
136.96
121.64
16660.00
1245026.00
Remarks
Description of work
Unit
Quantity
Rate
Amount
Kg
1331.46
62.90
83749.00
Kg
0.00
62.90
0.00
Kg
1267.99
62.90
79757.00
Kg
1904.15
62.90
119771.00
Kg
182.61
62.90
11486.00
Kg
35.71
62.90
2246.00
Kg
22.37
62.90
1407.00
Kg
23.43
62.90
1474.00
Kg
4767.72
Kg
1234.41
63.20
78014.00
Kg
0.00
63.20
0.00
Kg
1267.99
63.20
80137.00
Kg
1904.15
63.20
120342.00
Kg
182.61
63.20
11541.00
Kg
153.36
63.20
9692.00
Kg
132.98
63.20
8405.00
Kg
114.38
63.20
7229.00
Kg
4989.88
Kg
1146.37
63.20
72450.00
Kg
0.00
63.20
0.00
Sub-Total (a+h)
B) First Floor
Sub-Total (a+h)
C) 2nd Floor
Kg
1267.99
63.20
80137.00
Kg
1904.15
63.20
120342.00
Kg
182.61
63.20
11541.00
Kg
153.36
63.20
9692.00
Kg
132.98
63.20
8405.00
Kg
114.38
63.20
7229.00
Kg
4901.84
Kg
1086.16
63.20
68645.00
Kg
0.00
63.20
0.00
Kg
1267.99
63.20
80137.00
Kg
1904.15
63.20
120342.00
Kg
182.61
63.20
11541.00
Sub-Total (a+h)
D) 3rd Floor
Kg
153.36
63.20
9692.00
Kg
132.98
63.20
8405.00
Kg
114.38
63.20
7229.00
Kg
4841.63
1231037.00
Sub-Total (a+h)
Remarks
Kaizuddin Tower ( 7th floor), 176 Shahid Nazrul Islam Sharani, Bijoy Nagar, Dhaka-1000.
Description of work
Unit
Quantity
Rate
E) 4th Floor
Amount
BF=
1231037.00
Kg
1034.90
63.20
65405.00
Kg
0.00
63.20
0.00
Kg
1267.99
63.20
80137.00
Kg
1904.15
63.20
120342.00
Kg
182.61
63.20
11541.00
Kg
153.36
63.20
9692.00
Kg
132.98
63.20
8405.00
Kg
114.38
63.20
7229.00
Kg
4790.37
Kg
1024.60
63.20
64755.00
Kg
0.00
63.20
0.00
Kg
1267.99
63.20
80137.00
Kg
1904.15
63.20
120342.00
Kg
182.61
63.20
11541.00
Sub-Total (a+h)
F) 5th Floor
Kg
153.36
63.20
9692.00
Kg
132.98
63.20
8405.00
Kg
114.38
63.20
7229.00
Kg
4780.08
Kg
250.06
63.20
15804.00
Kg
0.00
63.20
0.00
Kg
1267.99
63.20
80137.00
Kg
1904.15
63.20
120342.00
Kg
182.61
63.20
11541.00
Kg
153.36
63.20
9692.00
Kg
132.98
63.20
8405.00
Kg
114.38
63.20
7229.00
Kg
4005.54
Kg
177.86
63.20
11240.00
Kg
250.06
63.20
15804.00
Sub-Total (a+h)
G) 6th Floor
Sub-Total (a+h)
H) Top Floor
Kg
0.00
63.20
0.00
Kg
0.00
63.20
0.00
Kg
0.00
63.20
0.00
Kg
0.00
63.20
0.00
Kg
0.00
63.20
0.00
Kg
0.00
63.20
0.00
Kg
628.21
63.20
39703.00
2155786.00
Kg
1056.13
40961.42
Remarks
Description of work
Unit
Quantity
Rate
Amount
Z) From work
A) Ground Floor
a) Column
Sft
565.94
b) Lift wall
Sft
0.00
c) Beam
Sft
386.10
d) Slab
Sft
1527.21
e) Stair
Sft
150.73
f) Lintel
Sft
38.20
g) False Slab
Sft
16.69
Sft
32.59
Sft
2717.45
a) Column
Sft
553.66
b) Lift wall
Sft
0.00
Sub-Total (a+h)
20.00
54349.00
22.00
66776.00
22.00
66776.00
22.00
66776.00
254677.00
B) First Floor
c) Beam
Sft
393.91
d) Slab
Sft
1527.21
e) Stair
Sft
150.73
f) Lintel
Sft
95.85
g) False Slab
Sft
139.59
Sft
174.31
Sft
3035.25
a) Column
Sft
553.66
b) Lift wall
Sft
0.00
c) Beam
Sft
393.91
d) Slab
Sft
1527.21
e) Stair
Sft
150.73
Sub-Total (a+h)
C) 2nd Floor
f) Lintel
Sft
95.85
g) False Slab
Sft
139.59
Sft
174.31
Sft
3035.25
a) Column
Sft
553.66
b) Lift wall
Sft
0.00
Sub-Total (a+h)
D) 3rd Floor
c) Beam
Sft
393.91
d) Slab
Sft
1527.21
e) Stair
Sft
150.73
f) Lintel
Sft
95.85
g) False Slab
Sft
139.59
Sft
174.31
Sub-Total (a+h)
Sft
3035.25
Remarks
SI
No
Description of work
Unit
Quantity
Rate
E) 4th Floor
a) Column
Sft
553.66
b) Lift wall
Sft
0.00
c) Beam
Sft
393.91
d) Slab
Sft
1527.21
e) Stair
Sft
150.73
f) Lintel
Sft
95.85
g) False Slab
Sft
139.59
Sft
174.31
Sft
3035.25
a) Column
Sft
553.66
b) Lift wall
Sft
0.00
c) Beam
Sft
393.91
d) Slab
Sft
1527.21
e) Stair
Sft
150.73
f) Lintel
Sft
95.85
g) False Slab
Sft
139.59
Sub-Total (a+h)
Amount
BF=
254677.00
22.00
66776.00
22.00
66776.00
22.00
66776.00
F) 5th Floor
Sft
174.31
Sft
3035.25
a) Column
Sft
553.66
b) Lift wall
Sft
0.00
c) Beam
Sft
393.91
d) Slab
Sft
1527.21
e) Stair
Sft
150.73
f) Lintel
Sft
95.85
g) False Slab
Sft
139.59
Sft
174.31
Sft
3035.25
a) Column
Sft
116.01
b) Lift M Room
Sft
141.36
Sub-Total (a+h)
G) 6th Floor
Sub-Total (a+h)
H) Top Floor
c) Beam
Sft
0.00
d) Slab
Sft
0.00
e) Stair
Sft
0.00
f) Lintel
Sft
0.00
g) False Slab
Sft
0.00
Sft
0.00
Sft
411.30
i) OHWT
Sub-Total (a+i)
Sft
22.00
14711.00
668.68
469716.00
Remarks
SI
No
Description of work
Unit
Quantity
Rate
Amount
A) Ground Floor
1
Cft
13.85
97.06
1344.00
Sft
892.54
47.16
42092.00
Sft
1784.87
11.28
20133.00
Sft
2274.98
9.79
22272.00
Sft
2581.77
10.71
27651.00
Sft
150.02
132.38
19860.00
Sft
0.00
83.03
0.00
Sft
0.00
83.03
0.00
Sft
0.00
83.03
0.00
Sft
0.00
61.66
0.00
0.00
a Ceiling
Sft
2581.77
7.90
20396.00
b Wall
Sft
1784.87
7.90
14100.00
c Weather coat
Sft
2274.98
7.73
17586.00
d Enamel
Sft
16.97
5.50
93.00
12 White washing
Sft
0.00
0.72
0.00
13 French Polish
Sft
0.00
18.00
0.00
Rft
0.00
574.50
0.00
Rft
31.95
574.50
18355.00
Sft
0.00
500.00
0.00
Sft
31.88
164.00
5228.00
18 Plastic door
Pcs
1.85 3600.00
6646.00
19 Window grill
Sft
34.51
100.50
3468.00
Sft
0.00
100.50
0.00
21 Varandah railing
Sft
0.00
170.50
0.00
Sft
26.27
171.40
4503.00
Rft
9.37
258.75
2425.00
Sft
0.00
253.00
0.00
Sft
34.51
253.00
8730.00
Sft
0.00
253.00
0.00
Pcs
1.85
800.00
1477.00
28 Marble works
Sft
53.61
370.00
19834.00
29 Main Gate
Sft
50.41
250.00
12603.00
Pcs
1.85
450.00
831.00
269627.00
Remarks
SI
No
Description of work
Unit
Quantity
Rate
Amount
B) First Floor
1
Cft
150.17
97.76
14680.00
Sft
2161.03
47.66
102995.00
Sft
3990.84
11.78
47012.00
Sft
1023.68
10.39
10636.00
Sft
1925.24
11.21
21582.00
Sft
138.73
132.38
18366.00
Sft
1147.57
83.03
95283.00
Sft
136.75
83.03
11354.00
Sft
127.52
83.03
10588.00
Sft
704.39
61.66
43433.00
0.00
a Ceiling
Sft
1925.24
7.90
15209.00
b Wall
Sft
3985.94
7.90
31489.00
c Weather coat
Sft
1023.68
7.73
7913.00
d Enamel
Sft
390.00
5.50
2145.00
12 White washing
Sft
169.05
0.72
122.00
13 French Polish
Sft
284.07
18.00
5113.00
Rft
17.75
574.50
10197.00
Rft
134.91
574.50
77506.00
Sft
23.36
500.00
11680.00
Sft
138.44
164.00
22704.00
18 Plastic door
Pcs
2.00 3600.00
7200.00
19 Window grill
Sft
141.43
100.50
14214.00
Sft
154.57
100.50
15534.00
21 Varandah railing
Sft
86.05
170.50
14672.00
Sft
26.27
171.40
4503.00
Rft
9.37
258.75
2425.00
Sft
108.84
253.00
27537.00
Sft
93.65
253.00
23693.00
Sft
100.54
253.00
25436.00
Pcs
4.47
800.00
3578.00
28 Marble works
Sft
22.72
370.00
8406.00
Pcs
0.92 2500.00
2308.00
Pcs
6.32
450.00
2844.00
712357.00
Remarks
SI
No
Description of work
Unit
Quantity
Rate
Amount
C) 2nd Floor
1
Cft
150.17
97.76
14680.00
Sft
2161.03
47.66
102995.00
Sft
3990.84
11.78
47012.00
Sft
1023.68
10.39
10636.00
Sft
1925.24
11.21
21582.00
Sft
138.73
132.38
18366.00
Sft
1147.57
83.03
95283.00
Sft
136.75
83.03
11354.00
Sft
127.52
83.03
10588.00
Sft
704.39
61.66
43433.00
a Ceiling
Sft
1925.24
7.90
15209.00
b Wall
Sft
3985.94
7.90
31489.00
c Weather coat
Sft
1023.68
7.73
7913.00
d Enamel
Sft
390.00
5.50
2145.00
12 White washing
Sft
169.05
0.72
122.00
13 French Polish
Sft
284.07
18.00
5113.00
Rft
17.75
574.50
10197.00
Rft
134.91
574.50
77506.00
Sft
23.36
500.00
11680.00
Sft
138.44
164.00
22704.00
18 Plastic door
Pcs
2.00 3600.00
7200.00
19 Window grill
Sft
141.43
100.50
14214.00
Sft
154.57
100.50
15534.00
21 Varandah railing
Sft
86.05
170.50
14672.00
Sft
26.27
171.40
4503.00
Rft
9.37
258.75
2425.00
Sft
108.84
253.00
27537.00
Sft
93.65
253.00
23693.00
Sft
100.54
253.00
25436.00
Pcs
4.47
800.00
3578.00
28 Marble works
Sft
22.72
370.00
8406.00
Pcs
0.92 2500.00
2308.00
Pcs
6.32
450.00
2844.00
712357.00
Remarks
SI
No
Description of work
Unit
Quantity
Rate
Amount
D) 3rd Floor
1
Cft
150.17
97.76
14680.00
Sft
2161.03
47.66
102995.00
Sft
3990.84
11.78
47012.00
Sft
1023.68
10.39
10636.00
Sft
1925.24
11.21
21582.00
Sft
138.73
132.38
18366.00
Sft
1147.57
83.03
95283.00
Sft
136.75
83.03
11354.00
Sft
127.52
83.03
10588.00
Sft
704.39
61.66
43433.00
a Ceiling
Sft
1925.24
7.90
15209.00
b Wall
Sft
3985.94
7.90
31489.00
c Weather coat
Sft
1023.68
7.73
7913.00
d Enamel
Sft
390.00
5.50
2145.00
12 White washing
Sft
169.05
0.72
122.00
13 French Polish
Sft
284.07
18.00
5113.00
Rft
17.75
574.50
10197.00
Rft
134.91
574.50
77506.00
Sft
23.36
500.00
11680.00
Sft
138.44
164.00
22704.00
18 Plastic door
Pcs
2.00 3600.00
7200.00
19 Window grill
Sft
141.43
100.50
14214.00
Sft
154.57
100.50
15534.00
21 Varandah railing
Sft
86.05
170.50
14672.00
Sft
26.27
171.40
4503.00
Rft
9.37
258.75
2425.00
Sft
108.84
253.00
27537.00
Sft
93.65
253.00
23693.00
Sft
100.54
253.00
25436.00
Pcs
4.47
800.00
3578.00
28 Marble works
Sft
22.72
370.00
8406.00
Pcs
0.92 2500.00
2308.00
Pcs
6.32
450.00
2844.00
712357.00
Remarks
SI
No
Description of work
Unit
Quantity
Rate
Amount
E) 4th Floor
1
Cft
150.17
97.76
14680.00
Sft
2161.03
47.66
102995.00
Sft
3990.84
11.78
47012.00
Sft
1023.68
10.39
10636.00
Sft
1925.24
11.21
21582.00
Sft
138.73
132.38
18366.00
Sft
1147.57
83.03
95283.00
Sft
136.75
83.03
11354.00
Sft
127.52
83.03
10588.00
Sft
704.39
61.66
43433.00
a Ceiling
Sft
1925.24
7.90
15209.00
b Wall
Sft
3985.94
7.90
31489.00
c Weather coat
Sft
1023.68
7.73
7913.00
d Enamel
Sft
390.00
5.50
2145.00
12 White washing
Sft
169.05
0.72
122.00
13 French Polish
Sft
284.07
18.00
5113.00
Rft
17.75
574.50
10197.00
Rft
134.91
574.50
77506.00
Sft
23.36
500.00
11680.00
Sft
138.44
164.00
22704.00
18 Plastic door
Pcs
2.00 3600.00
7200.00
19 Window grill
Sft
141.43
100.50
14214.00
Sft
154.57
100.50
15534.00
21 Varandah railing
Sft
86.05
170.50
14672.00
Sft
26.27
171.40
4503.00
Rft
9.37
258.75
2425.00
Sft
108.84
253.00
27537.00
Sft
93.65
253.00
23693.00
Sft
100.54
253.00
25436.00
Pcs
4.47
800.00
3578.00
28 Marble works
Sft
22.72
370.00
8406.00
Pcs
0.92 2500.00
2308.00
Pcs
6.32
450.00
2844.00
712357.00
Remarks
SI
No
Description of work
Unit
Quantity
Rate
Amount
F) 5th Floor
1
Cft
150.17
97.76
14680.00
Sft
2161.03
47.66
102995.00
Sft
3990.84
11.78
47012.00
Sft
1023.68
10.39
10636.00
Sft
1925.24
11.21
21582.00
Sft
138.73
132.38
18366.00
Sft
1147.57
83.03
95283.00
Sft
136.75
83.03
11354.00
Sft
127.52
83.03
10588.00
Sft
704.39
61.66
43433.00
a Ceiling
Sft
1925.24
7.90
15209.00
b Wall
Sft
3985.94
7.90
31489.00
c Weather coat
Sft
1023.68
7.73
7913.00
d Enamel
Sft
390.00
5.50
2145.00
12 White washing
Sft
169.05
0.72
122.00
13 French Polish
Sft
284.07
18.00
5113.00
Rft
17.75
574.50
10197.00
Rft
134.91
574.50
77506.00
Sft
23.36
500.00
11680.00
Sft
138.44
164.00
22704.00
18 Plastic door
Pcs
2.00 3600.00
7200.00
19 Window grill
Sft
141.43
100.50
14214.00
Sft
154.57
100.50
15534.00
21 Varandah railing
Sft
86.05
170.50
14672.00
Sft
26.27
171.40
4503.00
Rft
9.37
258.75
2425.00
Sft
108.84
253.00
27537.00
Sft
93.65
253.00
23693.00
Sft
100.54
253.00
25436.00
Pcs
4.47
800.00
3578.00
28 Marble works
Sft
22.72
370.00
8406.00
Pcs
0.92 2500.00
2308.00
Pcs
6.32
450.00
2844.00
712357.00
Remarks
SI
No
Description of work
Unit
Quantity
Rate
Amount
G) 6th Floor
1
Cft
150.17
97.76
14680.00
Sft
2161.03
47.66
102995.00
Sft
3990.84
11.78
47012.00
Sft
1023.68
10.39
10636.00
Sft
1925.24
11.21
21582.00
Sft
138.73
132.38
18366.00
Sft
1147.57
83.03
95283.00
Sft
136.75
83.03
11354.00
Sft
127.52
83.03
10588.00
Sft
704.39
61.66
43433.00
a Ceiling
Sft
1925.24
7.90
15209.00
b Wall
Sft
3985.94
7.90
31489.00
c Weather coat
Sft
1023.68
7.73
7913.00
d Enamel
Sft
390.00
5.50
2145.00
12 White washing
Sft
169.05
0.72
122.00
13 French Polish
Sft
284.07
18.00
5113.00
Rft
17.75
574.50
10197.00
Rft
134.91
574.50
77506.00
Sft
23.36
500.00
11680.00
Sft
138.44
164.00
22704.00
18 Plastic door
Pcs
2.00 3600.00
7200.00
19 Window grill
Sft
141.43
100.50
14214.00
Sft
154.57
100.50
15534.00
21 Varandah railing
Sft
86.05
170.50
14672.00
Sft
26.27
171.40
4503.00
Rft
9.37
258.75
2425.00
Sft
108.84
253.00
27537.00
Sft
93.65
253.00
23693.00
Sft
100.54
253.00
25436.00
Pcs
4.47
800.00
3578.00
28 Marble works
Sft
22.72
370.00
8406.00
Pcs
0.92 2500.00
2308.00
Pcs
6.32
450.00
2844.00
712357.00
Remarks
SI
No
Description of work
Unit
Quantity
Rate
Amount
H) Top Floor
1
Cft
46.86
97.76
4581.00
Sft
570.98
47.66
27213.00
Sft
586.74
11.78
6912.00
Sft
1295.54
10.39
13461.00
Sft
229.54
11.21
2573.00
Sft
4.69
132.38
620.00
Sft
94.43
83.03
7841.00
Sft
17.82
83.03
1480.00
Sft
9.16
83.03
760.00
Sft
52.61
61.66
3244.00
a Ceiling
Sft
229.54
7.90
1813.00
b Wall
Sft
586.74
7.90
4635.00
c Weather coat
Sft
1295.54
7.73
10015.00
d Enamel
Sft
4.69
5.50
26.00
Sft
0.00
0.72
0.00
13 French Polish
Sft
0.00
18.00
0.00
14 MS Door Frame
Pcs
0.92 1250.00
1154.00
12 White washing
15 MS Door shutter
Sft
105.00
1081.00
16 Plastic door
Pcs
10.30
0.00 3600.00
0.00
17 Window grill
Sft
0.00
100.50
0.00
Sft
0.00
100.50
0.00
19 Varandah railing
Sft
0.00
170.50
0.00
Sft
4.62
171.40
791.00
Rft
1.85
258.75
478.00
Sft
0.00
253.00
0.00
Sft
0.00
253.00
0.00
Sft
0.00
253.00
0.00
Pcs
0.00
800.00
0.00
26 Marble works
Sft
0.00
370.00
0.00
Pcs
0.00 2500.00
0.00
Pcs
0.00
450.00
0.00
Cft.
283.29
95.95
27182.00
Sft
1472.68
40.00
58907.00
Sft
688.91
75.00
51668.00
Sft
274.56
10.50
2883.00
Sft
280.38
55.00
15421.00
244739.00
Sub-Structure
Total Amount
1089320.00
Total Amount
3870528.00
Total Amount
4788508.00
9748356.00
Remarks
FOUNDATION UPTO PL
Total Quantity
Item
no.
Material Consumption
Grey
Cement
Bag
Sylhet
Sand
Cft
Local
Sand
Cft
Stone
Chips
Cft
1st Class
Bricks
Pcs
1st Class
Picket
Pcs
Description
Unit
Total
Quantity
Sft.
2666.05
Sft.
2666.00
Cft
194.97
24.37
46.79
46.79
1754.69
Cft
912.07
164.17
205.21
205.21
7843.77
White
cement
Bag
Glazed
Wall
Tiles
N.G.H
Floor
Tiles
Plastic
paint
Liter
Chalk
powder
Kg
Snow
cem
Kg
Door
frame
Rft
Iternal
Door
frame
Rft
Alumin
ium
Sft
MS Rod
(60 G)
Kg
MS Rod
(40 G)
Kg
7998.15
R. C. C. casting work
a)
Cft.
156.27
34.38
64.07
b)
Cft.
1153.68
253.81
236.50
236.50
c)
Cft.
162.31
35.71
33.27
33.27
d)
Cft.
42.17
7.59
9.49
9.49
e)
Cft.
50.48
11.11
10.35
10.35
Cft.
182.83
32.91
41.14
41.14
Window
Grill
Sft
Varandah
Varandah
safety
railing Sft
grill Sft
Stair
railing
(Grill)
Sft
Stair
hand
rest Rft
Marble
Main
works Door lock
Sft
Pcs
133.30
128.14
946.02
1330.91
362.70
41.39
f)
Reinforcement work
a)
Kg
1336.23
1336.23
b)
Kg
2163.70
2163.70
c)
Kg
1173.84
1173.84
d)
Kg
189.77
189.77
e)
Kg
1964.70
1964.70
Sft.
0.00
Sand filling
a)
Plinth
Cft.
3774.01
b)
Cft.
0.00
Total :
Cft.
3774.01
Rft
25.21
0.00
Vity
Sand
Cft
1572.30
0.00
3774.01
a)
Cft.
0.00
b)
Cft.
0.00
Total :
Cft.
0.00
0.00
12
Sft.
75.83
1.71
13
Sft.
0.00
0.00
566.00
0.00
2.13
0.00
2.13
81.52
0.00
649.00
585.00
1116.00
7998.00
12946.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
6828.00
0.00
3907.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
GROUND FLOOR
Total Quantity
Item
no.
Description
Material Consumption
Unit
Total
Quantity
Grey
Cement
Bag
Sylhet
Sand
Cft
Local
Sand
Cft
Stone
Chips
Cft
White
1st Class
1st Class
cement
Bricks Pcs Picket Pcs
Bag
Glazed
Wall
Tiles
N.G.H
Floor
Tiles
Plastic
paint
Sft
Cat
Door
Pcs
Weather
coat
Sft
Main
Door
frame
Rft
Iternal
Door
frame
Rft
Alumin
ium
Sft
MS Rod
(60 G)
Kg
MS Rod
(40 G)
Kg
R. C. C. casting work
a)
Cft.
157.34
34.61
64.51
b)
Cft.
193.05
34.75
43.44
43.44
1660.22
c)
Cft.
658.88
118.60
148.25
148.25
5666.37
d)
Cft.
48.56
8.74
10.93
10.93
417.65
R. C. C. casting work
a)
Cft.
13.14
2.36
5.91
112.96
Reinforcement work
a)
Kg
1331.46
1331.46
b)
Kg
1267.99
1267.99
c)
Kg
1904.15
1904.15
d)
Kg
182.61
182.61
Kg
81.51
13.85
0.55
4.98
159.22
4462.71
Vity
Sand
Cft
Window
Grill
Sft
Varandah
Varandah
safety
railing Sft
grill Sft
Stair
railing
(Grill)
Sft
Stair
hand
rest Rft
Marble
Main
works Door lock
Sft
Pcs
129.02
81.51
Cft
Sft
892.54
23.21
151.73
Sft
1784.87
29.81
185.98
Sft
2274.98
28.44
177.68
Sft
2581.77
38.73
193.63
Sft
150.02
3.75
14.06
0.15
157.52
10
Sft
0.00
0.00
0.00
0.00
0.00
11
Sft
0.00
0.00
0.00
0.00
0.00
12
Sft
0.00
0.00
0.00
0.00
13
Sft
0.00
0.00
0.00
0.00
14
15
Ceiling
Sft
2581.77
2581.77
16
Wall
Sft
1784.87
1784.87
17
Weather coat
Sft
2274.98
18
Enamel
Sft
16.97
19
White washing
Sft
0.00
20
French Polish
Sft
0.00
21
Rft
0.00
0.00
0.00
0.00
0.00
22
Rft
31.95
0.52
0.48
0.48
1.94
23
Sft
0.00
24
Sft
31.88
25
Plastic door
Pcs
1.85
26
Sft
34.51
0.56
0.52
0.52
2.09
27
Sft
0.00
0.00
0.00
0.00
0.00
28
Sft
0.00
0.00
0.00
0.00
0.00
29
Sft
26.27
0.43
0.40
0.40
1.59
30
Rft
9.37
31
Sft
0.00
0.00
32
Sft
34.51
34.51
33
Sft
0.00
34
Pcs
1.85
35
Marble works
Sft
53.61
1.34
36
Sft
50.41
37
Pcs
1.85
38
Rft.
0.00
39
Rft.
0.00
40
Nos.
2.00
0.00
0.00
2274.98
0.00
31.95
34.51
0.00
0.00
26.27
9.37
0.00
0.03
0.03
0.03
0.82
0.76
0.76
3.06
0.00
0.00
0.00
0.00
1.85
0.11
53.61
5.02
0.03
0.03
0.03
327.00
269.00
944.00
129.00
4622.00
7866.00
0.00
0.00
158.00
4367.00
2.00
2275.00
0.00
32.00
35.00
2599.00
2168.00
0.00
35.00
0.00
0.00
26.00
9.00
54.00
0.00
TYPICAL FLOOR
Total Quantity
Item
no.
Description
Material Consumption
Unit
Total
Quantity
Grey
Cement
Bag
Sylhet
Sand
Cft
Local
Sand
Cft
Stone
Chips
Cft
White
1st Class
1st Class
cement
Bricks Pcs Picket Pcs
Bag
R. C. C. casting work
a)
Cft.
149.95
32.99
61.48
b)
Cft.
197.74
35.59
44.49
44.49
1700.52
c)
Cft.
658.88
118.60
148.25
148.25
5666.37
d)
Cft.
48.56
8.74
10.93
10.93
417.65
R. C. C. casting work
Cft.
87.76
15.80
39.49
754.70
Glazed
Wall
Tiles
N.G.H
Floor
Tiles
Plastic
paint
Liter
Cat
Door
Pcs
Weather
coat
Sft
Door
frame
Rft
Iternal
Door
frame
Rft
Alumin
ium
Sft
MS Rod
(60 G)
Kg
MS Rod
(40 G)
Kg
3
a)
Kg
1234.41
1234.41
b)
Kg
1267.99
1267.99
c)
Kg
1904.15
1904.15
d)
Kg
182.61
182.61
Kg
400.72
150.17
6.01
54.06
1726.90
10805.14
Cft
Sft
2161.03
56.19
367.37
Sft
3990.84
66.65
415.85
Sft
1023.68
12.80
79.95
Sft
1925.24
28.88
144.39
e)
Window
Grill
Sft
Varandah
Varandah
safety
railing Sft
grill Sft
Stair
railing
(Grill)
Sft
Stair
hand
rest Rft
Marble
Main
works Door lock
Sft
Pcs
122.96
a)
Vity
Sand
Cft
400.72
Sft
138.73
3.47
13.00
0.14
145.67
10
Sft
1147.57
28.69
107.53
1.15
1204.95
11
Sft
136.75
3.42
8.55
0.14
143.58
12
Sft
127.52
3.19
11.95
0.13
13
Sft
704.39
17.61
44.02
0.70
14
Paint work
15
Ceiling
Sft
1925.24
1925.24
16
Wall
Sft
3985.94
3985.94
17
Weather coat
Sft
1023.68
18
Enamel
Sft
390.00
19
White washing
Sft
169.05
20
French Polish
Sft
284.07
21
Rft
17.75
0.29
0.27
0.27
1.08
22
Rft
134.91
2.19
2.04
2.04
8.18
23
Sft
23.36
24
Sft
138.44
25
Plastic door
Pcs
2.00
26
Sft
141.43
2.30
2.14
2.14
8.57
27
Sft
154.57
2.51
2.34
2.34
9.37
28
Sft
86.05
1.40
1.30
1.30
5.22
29
Sft
26.27
0.43
0.40
0.40
1.59
30
Rft
9.37
31
Sft
108.84
32
Sft
93.65
93.65
33
Sft
100.54
100.54
34
Pcs
4.47
0.07
35
Marble works
Sft
22.72
0.57
36
Pcs
0.92
37
Pcs
6.32
133.89
739.61
1023.68
17.75
134.91
141.43
154.57
86.05
26.27
9.37
108.84
0.07
0.07
4.47
0.27
22.72
2.13
0.92
448.00
274.00
1501.00
123.00
12532.00
8574.00
2.00
740.00
1628.00
5911.00
4.00
1024.00
18.00
135.00
303.00
2502.00
2487.00
0.00
141.00
155.00
86.00
26.00
9.00
23.00
1.00
Description
Material Consumption
Unit
Total
Quantity
Grey
Cement
Bag
Sylhet
Sand
Cft
a)
Cft.
30.96
6.81
12.69
b)
Cft.
54.39
11.96
22.30
c)
Cft.
136.96
24.65
30.82
Local
Sand
Cft
Stone
Chips
Cft
White
1st Class
1st Class
cement
Bricks Pcs Picket Pcs
Bag
N.G.H
Floor
Tiles
Plastic
paint
Liter
Chalk Weather
powder
coat
Kg
Sft
Door
frame
Rft
Iternal
Door
frame
Rft
Alumin
ium
Sft
MS Rod
(60 G)
Kg
MS Rod
(40 G)
Kg
Vity
Sand
Cft
Window
Grill
Sft
Varandah
Varandah
safety
railing Sft
grill Sft
Stair
railing
(Grill)
Sft
Stair
hand
rest Rft
Marble
Main
works Door lock
Sft
Pcs
25.38
44.60
30.82
1177.85
Reinforcement work
a)
Kg
177.86
b)
Kg
250.06
c)
Kg
628.21
Total :
Kg
878.27
Cft.
46.86
1.87
16.87
538.89
Sft.
570.98
14.85
97.07
2854.91
Sft.
586.74
8.39
62.84
Sft.
1295.54
19.43
97.17
Sft.
229.54
2.30
11.48
Sft.
108.28
2.71
10.15
0.54
Sft.
70.43
1.76
4.40
0.35
10
Sft.
1472.68
33.14
11
Sft.
274.56
4.12
12
Door frame MS
Pcs
0.92
13
Door shutter MS
Sft.
10.30
14
Cft.
283.29
15
Plastic paint
Sft.
816.29
16
Weather coat
Sft.
1295.54
17
Rft.
100.00
18
Sft.
688.91
Total Matierials
Glazed
Wall
Tiles
177.86
878.27
41.42
41.42
113.69
73.95
165.68
15.10
0.92
2464.62
11.75
21.22
51.82
131.99
107.23
387.30
69.98
3393.80
3808.15
0.89
73.95
113.69
11.75
21.22
51.82
0.92
0.00
0.00
177.86
878.27
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
3264.99
2395.23
9421.30
1929.98
78673.80
67490.15
10.89
3773.95
8411.69
33933.75
43.22
7446.82
90.92
707.00
1550.00
22114.86
15481.27
3907.00
740.00
775.00
430.00
156.00
54.00
169.00
5.00
Total 60 Grade
Total 40 Grade
Total 60+40 Grade
Per Sft
Kg
Kg
Kg
Kg
22114.86
15481.27
37596.13
1.97
Mortice
type Door
lock Pcs
0.00
Mortice
type Door
lock Pcs
1.85
2.00