Académique Documents
Professionnel Documents
Culture Documents
Activity ID Activity Description Orig Rem % Dur Dur Comp Actual/ Forecast Start Actual/ Forecast Finish Total Float Planned Start Planned Finish
2010 2011 2012 2013
N D J F M AM J J A S O N D J F MAM J J A S ON D J F M AM J J A S O N D J F MA
Milestone
Milestone
Milestone
General Milestone MM010171 MM010178 MM010179 MM010181 MM012200 MM010164 MM010174 MM012401 MM015180 MECHANICAL COMPLETION FIRST COMMERCIAL PRODUCTION PROVISIONAL ACCEPTANCE ACHIEVED Taking Over of Whole Plant COMPLETE ERECTION OF REFORMER STEAM PRODUCTION BY BOILER First Feed to Reformer PROVISIONAL ACCEPTANCE CERTIFICATE COMPLETION OF PERFORMANCE TEST 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25-JAN-13 26-MAR-13 26-MAR-13 30-SEP-12 15-SEP-12 27-NOV-12 26-MAR-13 26-MAR-13 26-NOV-12 0 0 0 0 0 0 0 27-NOV-12 0 0 26-MAR-13 26-MAR-13 26-NOV-12 25-JAN-13 26-MAR-13 26-MAR-13 28-APR-12 30-JUL-12 CM
MECHANICAL COMPLETION FIRST COMMERCIAL PRODUCTIO PROVISIONAL ACCEPTANCE ACHIEVE Taking Over of Whole Plan
Construction Milestone
COMPLETE ERECTION OF REFORME
Precom. / Commissioning
STEAM PRODUCTION BY BOILE First Feed to Reforme PROVISIONAL ACCEPTANCE CERTIFICAT COMPLETION OF PERFORMANCE TES
250 245
4 15
94 89
12-JUL-11A 16-NOV-11A
03-SEP-12 14-SEP-12
0 0
Insulation
Piping C1N91529 10 Unit - Piping Insulation ( Ammonia Recovery ) 49 49 0 04-SEP-12 30-OCT-12 0 02-JUN-12 15-NOV-12
10 Unit - Piping Insulation ( Ammonia Recovery
Pre-commissioning
Unit 01: NG Desulphurization & Compression Unit C1NP0102A S-01-1: Natural Gas Compressor System Unit 10 : Ammonia Recovery Unit C1NP2302A S-10-1: Ammonia Recovery System 84 12 25 15-JUN-12A 15-SEP-12 0 92 22 26 11-JUN-12A 21-SEP-12 0
REVISION BOX Date Revision 31-AUG-12 Issue for Approval 13-APR-11 Issue for Approval_Rev.07 10-NOV-10 Issue for Approval_Rev.06
F08D
Checked H.C. Kim H.C.Kim H.R.DO Approved Y. Kim Y. Kim Y. Kim
Sheet 2 of 4
Activity ID Activity Description Orig Rem % Dur Dur Comp Actual/ Forecast Start Actual/ Forecast Finish Total Float Planned Start Planned Finish
2010 2011 2012 2013
N D J F M AM J J A S O N D J F MAM J J A S ON D J F M AM J J A S O N D J F MA
Urea
Steel Structure
S201 Structure C2N31504 C2N31505 C2N31506 Alignment Grating Roof Panel 42 33 15 3 5 15 99 99 0 04-SEP-11A 21-JAN-12A 02-SEP-12 02-SEP-12 04-SEP-12 16-SEP-12 0 0 0
Piping Installation
A/G Piping Shop Fabrication C2N51501 C2N51503 C2N52001 Shop Fabrication - C.S. line Shop Fabrication - S.S. Line Urea Main Pipe Rack 260 165 201 10 10 4 99 99 98 21-MAY-11A 25-JUN-11A 27-AUG-11A 11-SEP-12 11-SEP-12 04-SEP-12 0 02-APR-11 0 02-AUG-11 0 28-AUG-11 30-OCT-11 31-DEC-11 14-JAN-12
Shop Fabrication - C.S. line Shop Fabrication - S.S. Line
Pre-commissioning
Unit 21 : Ammonia Pumping Unit C2NP0302B S-21-1: Ammonia Pumping System Unit 22 : Urea Synthesis and Flare Unit C2NP0402B S-22-1: Urea Synthesis System Unit 27 : Granulation Unit C2NP1202 C2NP1602 S-27-2: Urea Granulation Auxiliary System S-28-1: Desorption and Hydrolysis System 102 110 50 29 1 3 22-MAY-12A 22-MAY-12A 24-OCT-12 15-OCT-12 0 17-SEP-12 0 15-SEP-12 01-NOV-12 15-NOV-12
S-27-2: Urea Granulation Auxiliary System
65 71
65 71
0 0
17-SEP-12 17-SEP-12
20-NOV-12 26-NOV-12
0 0
Utility
Instrument
Loop Test C3N76002 Loop Test 105 51 60 02-MAY-12A 29-OCT-12 0 01-JUL-12 17-NOV-12
Loop Test
Pre-commissioning
Unit 83: Auxiliary Boiler and Steam System C3NP0604 C3NP1002 S-83-3: Auxiliary Boiler System S-86-1: Nitrogen Import and Distribution 48 43 16 15 53 46 30-APR-12A 02-MAY-12A 09-OCT-12 17-SEP-12 0 0 18-MAR-12 29-APR-12 Unit 86: Inert Gas Unit
S-86-1: Nitrogen Import and Distributio
Offsite
Steel Structure
Transfer Tower CON32515 CON32516 T/T8 (Transfer Tower Str ) T/T9 (Transfer Tower Str ) 17 30 9 22 88 84 14-APR-12A 14-APR-12A 10-SEP-12 25-SEP-12 0 01-NOV-11 0 31-DEC-11
T/T8 (Transfer Tower Str
Pre-commissioning
Urea Product from TT-7 to TT-9 CONP2100 Urea Product from TT-7 to TT-9 8 8 0 30-OCT-12 07-NOV-12 0
Sheet 3 of 4
Activity ID Activity Description Orig Rem % Dur Dur Comp Actual/ Forecast Start 17-NOV-12 Actual/ Forecast Finish 26-NOV-12 Total Float Planned Start Planned Finish
2010 2011 2012 2013
N D J F M AM J J A S O N D J F MAM J J A S ON D J F M AM J J A S O N D J F MA
New Jetty Conveyor and Ship loader System CONP2102 New Jetty Conveyor and Ship loader System 9 9 0 0 01-SEP-12 31-OCT-12
New Jetty Conveyor and Ship loader System
Urea
Commissioning - Urea
Unit 20 : CO2 Compression Unit CXP3424 CXP3426 CXP3440 CXP3444 S-20-2: CO2 Compressor System S-21-1: Ammonia Pumping System S-27-2: Urea Granulation Auxiliary System S-28-1: Desorption and Hydrolysis System 42 56 79 87 42 56 79 87 0 0 0 0 08-DEC-12 21-NOV-12 25-OCT-12 16-OCT-12 24-JAN-13 24-JAN-13 24-JAN-13 24-JAN-13 0 0 0 0 Unit 21 : Ammonia Pumping Unit Unit 27 : Granulation Unit Unit 28: Desorption and Hydrolysis Unit
Utility
Commissioning _Utility/ Off Site
Unit 83: Auxiliary Boiler and Steam System CXP4014 CXP4020 CXP4026 S-83-3: Auxiliary Boiler System S-83-6: MP Steam Distribution System S-86-1: Nitrogen Import and Distribution 19 31 30 19 31 7 0 0 29 10-OCT-12 01-NOV-12 19-JUN-12A 31-OCT-12 06-DEC-12 26-SEP-12 0 0 0
Sheet 4 of 4
Activity ID Activity Description Orig Rem % Dur Dur Comp Actual/ Forecast Start Actual/ Forecast Finish Total Float Planned Start Planned Finish
2010 2011 2012 2013
N D J F M AM J J A S O N D J F MAM J J A S ON D J F M AM J J A S O N D J F MA
Performance Test
Performance Test
Performance Test CX4P0801 Performance Test of Ammonia & Urea plants 28 28 0 21-FEB-13 20-MAR-13 0 14-MAR-13 26-MAR-13
Performance Test of Ammonia & Urea plant