To establish the procedure for Preventive and Predictive Maintenance of Equipment. This is applicable to all the machinery of Tata Ryerson Limited, Jamshedpur. Section 7.5.1.4 ISO/TS 16949: 2002(E) Nil 3 Chief of Business Jamshedpur Unit. Manager (Quality and Process Control) Dy. Manager (Maintenance) Dy. Manager (Materials) Management. Representative
AUTHORISED BY: Ravi Inder Singh DESIGNATION: SIGNATURE: DATE:30.10.2004 Chief of Business Unit
DOCUMENT: Procedure DIVISION: MMC, Jamshedpur DEPARTMENT: Production/Maintenance SECTION: 7. 5. 1. 4 TITLE : Preventive and Predictive Maintenance
7.0
7.1 7.2
Procedure
Deputy Manager (Maintenance) is responsible for the execution of this procedure. All the machines and other equipment are maintained at the shop-floor in a proper manner. The following types of maintenance activities are carried out at shop floor. Break-down maintenance Preventive maintenance Predictive maintenance
7.3
7.4
Preventive Maintenance
Preventive maintenance of the Equipments listed in the Annexure 1 are carried out as per schedule mentioned. The spares availability is planned and executed as per clause 7.3.
The Preventive maintenance is carried out as per the checklists. If the Check list compliance is less than 90% than it is not considered as the compliance to PM.For spare parts,procedure of clause 7.3 is followed.
DOCUMENT: Procedure DIVISION: MMC, Jamshedpur DEPARTMENT: Production/Maintenance SECTION: 7. 5. 1. 4 TITLE : Preventive and Predictive Maintenance
Cranes Chain Pulley Blocks Fortklift 3 - TON Hydraulic Power Packs Power Transformers Pressure Vessels Electrical Earth Pits Major Gear Boxes
NA
NA
Yearly
NA
NA
NA
Note Vibration monitoring is done with a small metal stick. The basis of basis for monitoring is daily observation and the persons experience.
DOCUMENT: Procedure DIVISION: MMC, Jamshedpur DEPARTMENT: Production/Maintenance SECTION: 7. 5. 1. 4 TITLE : Preventive and Predictive Maintenance