DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
AREA BREAKDOWN
EQUIPMENT IDENTIFICATION
PROCESS FLOW DIAGRAMS
PIPING AND INSTRUMENT DIAGRAMS
DISTRIBUTION
Doc. no.
DOCUMENT CONTROL
Rev
Date REMARKS Prep. Issued Check Approved
no.
0 26 Jan 2007 For Information JCQ JCQ EJP MAF
1 27.Mar.2007 Included Area Code JCQ JCQ EJP MAF
2 10.Apr.2007 General Revision JCQ JCQ EJP MAF
3 14. May.2007 General Revision JCQ JCQ EJP MAF
4 23. Oct.2007 General Revision JCQ JCQ EJP MAF
5 26. Apr 2008 General Revision FAO FAO JQC EJP
6 29. Mai 2008 General Revision FAO FAO JQC EJP
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
5 1.0 BACKGROUND
Area breakdown and procedures for the identification of equipment are fundamental requirements for the
preparation of PFD’s, C&ID’s, Single line Diagrams and P&ID’s.
Anglo Base Metals (ABM) has defined specific policies for asset management and optimisation of the
operations, which require these procedures and structures to be in line and compatible with the software
currently used by ABM (Ellipse).
These structures and procedures may also be used for the development of the cost structure and schedule
for the project.
2.0 OBJECTIVES
This document defines the relevant criteria and procedures to be applied in the process engineering activities
during the feasibility study.
As the study progress it is likely that this document will be modified to accommodate the up-dates and the
contributions from the engineering contractor.
5 3.0 STRUCTURE
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
Area Breakdown
The project is divided into physical areas according to the following structure, which is based on the following
criteria:
1. The breakdown is primarily based on the concept of “physical area”, as universally accepted
2. For these cases with parallel lines, the above concept may be superseded by the “line concept”,
which is a Ellipse requirement as to properly account for individual cost for a given line
3. The breakdown includes three levels in order to accommodate the comments from SL-Miner
4. Exceptions are applicable to the Mine, where functional criteria replaces the physical area
concept
5. Other exceptions have been introduced as to facilitate the common use of the area breakdown
structure in the work breakdown structure (WBS)
000 GENERAL
010 Camp Contractors
011 Camp Contractors
012 Contractors Provisory Installation
020 Harmonic Filter, Thyristors and Main Generator Station
021 Harmonic Filters Station
022 Control Room and Thyristors Station
023 Main Generator Station
024 Kilns and Dryers Generator Station
030 Vehicles
031 Vehicles – Administration Area
032 Vehicles – Maintenance Area
033 Vehicles – Operational Area
040 Freight
041 Freight
050 TBA
060 Waste recycling storage
061 Waste recycling storage Rev.04
070 Land Acquisition
071 Land Acquisition
080 TBA
090 Multiple Application Packages
091 Multiple Application Packages
100 INFRASTRUCTURE
110 Water Supply and Distribution
111 Water Pumping Station – Dos Patos River
112 Raw Water Pipeline
113 TBA
114 Water Treatment Plant
115 Process Water Storage and Distribution
116 Water Cooling System
117 Potable Water Storage and Distribution
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
400 CALCINING
410 Rotary Kiln
411 Rotary Kiln - Line I
412 Rotary Kiln- Line II
420 Cold Calcine Storage Area Cancelled
421 Cold Calcine Storage and Reclamation Area Cancelled
430 Pelletising Plant
431 Dust Storage and Distribution Rev.3
432 Disk Pelletisers
433 Pellets storage and handling
434 Pellets Drying
440 KILN Off-Gas Plant
441 Off-Gas Treatment Circuit – Line I Rev.3
442 Off-Gas Treatment Circuit – Line II Rev.3
480 Unit Substation
481 Unit Substation Kiln – Line I
482 Unit Substation Kiln – Line II
483 Area MCC Kiln – Line I
484 Area MCC Kiln – Line II
490 Area PLC
491 PLC Kiln - Line I Area
492 PLC Kiln – Line II Area
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
600 REFINERY
610 Ladle Furnace
611 Ladle furnace - Line I
612 Ladle Furnace – Line II
620 Metal granulation
621 Metal Granulation Plant
630 Slag Treatment
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
810 Offices
811 Main Office
812 Change House
813 Canteen
814 First Aid/SHE/Quality
815 Training Centre
816 Mine and Geology Office
817 Bank
818 Reception
819 Contractors Support Facilities
820 Laboratory
821 Main Laboratory
822 Geology Laboratory
823
824 Effluent Neutralisation Plant
830 Workshops
831 Workshop Mechanical /Electrical /Instrument.
832 Earthmoving Vehicles
833 Wash and Lub Bay
834 Effluent treatment Plant
840 Main Stores
841 Main Store
842 Refuelling Station
850 Storage, Handling and Dispatch
851 Storage
852 Packaging and Dispatch
860 Main Gate
861 Main Gate
862 Secondary gate
863 Road scale
870 Production Office
871 Production Office
880 Unit Substation
881 Offices Unit substation
882 Workshop Unit substation
883 Offices – MCC Area
884 Workshop – MCC Area
890 Area PLC
891 PLC - Storage, Handling and Dispatch Rev.2
900 INDIRECTS
910 Project Management
911 Owner’s Cost
912 EPCM
920 Pre Production & First Fill
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
This structure is made of 9 positions and it is applicable for mechanical equipments in the PFD files.
EQUIPMENT IDENTIFICATION
- - -
The identification of the equipment, its components and peripheral items will be made according to the
following criteria:
SEQUENCE – sequential numbering within a given area and a given type of equipment
SUF – suffix “A” is applied for the main unit and “R” is applied to the spare unit
EXAMPLES OF APPLICATION
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
This structure is made of 17 positions and it is applicable for mechanical and electrical equipment in the P&ID
or C&ID files.
EQUIPMENT IDENTIFICATION
- - - - -
The identification of the equipment, its components and peripheral items will be made according to the
following criteria:
SEQUENCE 1 – sequential numbering within a given area and a given type of equipment
SUF – suffix “A” is applied for the main unit and “R” is applied to the spare unit
Notes:
• All manual valves installed on pipelines or process intake (pressure gauges block valves, pressure
switch block valves and etc) will not be tagged at P&ID.
• Manual or automatic valves installed on the silos discharge and ducts shall be considered as
mechanical equipments, and will be tagged according examples number 6.
• Automatic valves that don’t fill the above requirements, i.e instrumentation valves such as shut-off
valves, control valves, pilot valves and inline solenoid valves, should be tagged according examples
number 4.
EXAMPLES OF APPLICATION
Example 1 – The level switch high installed on the second conveyor belt in the Primary Crushing
3 2 1 - T C - 0 0 2 - - L S H - 0 0 1
Example 2 – The emergency switch of the second conveyor belt in the Primary Crushing
3 2 1 - T C - 0 0 2 - - H S S - 0 0 1
Example 3 – Differential pressure alarm high high of the filter in the Electrical Furnace
5 1 1 - F L - 0 0 1 - - P D A H H - 0 0 1
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
Example 4 – Flow Control Valve in the Cooling Water Circuit of Electrical Furnace
5 1 1 - S L - 0 0 1 - - F V - 0 0 1
Example 5 – Flow Control Valve open limit switch related to the valve of example 4
5 1 1 - S L - 0 0 1 - - Z S H - 0 0 1
Example 8 – Control panel number one from Ladle Furnace 1 that interfaces with DCS
6 1 1 - F P - 0 0 1 - - P C - 0 0 1
6 9 1 - L O - 0 0 1 - - -
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
This structure is made of 9 positions and it is applicable for electrical equipments in the Single Line Diagram
files.
EQUIPMENT IDENTIFICATION
- - - - -
The identification of the equipment, its components and peripheral items will be made according to the
following criteria:
SEQUENCE – sequential numbering within a given area and a given type of equipment
SEQUENCE 2 – sequential numbering within a given area and a given type of equipment
EXAMPLES OF APPLICATION
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
The identification of the pipelines in the P&ID’s follows similar procedure as for the equipment items.
This identification will be compulsorily associated with the isometrics prepared for each line.
PIPELINE IDENTIFICATION
- - - -
FLUID – fluid inside the pipe according to Fluids Code – item 3.10
MATERIAL – material of the pipe according to Piping Material Code – item 3.11
EXAMPLES OF APPLICATION
Example 1 – Line of the raw water pump, with 800 mm, made of carbon steel and flanged:
1 1 1 - 8 0 0 - A B - A C - 0 3 2
Example 2 – Compressed air low pressure line of the Kiln area, mild steel, size 50 mm diameter:
4 3 0 - 5 0 - L A - A C - 0 0 8
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
E M Empilhadeira Stacker
E P Espessador / Clarificador Thickener / Clarifier
E S Equipamentos de segurança Safety equipment
E V Evaporador Evaporator
E X Exaustores Exhaust fans
E Z Estação (de oxigenio, de dessulfurisacao) (Oxigen, dessuphurisation) Station
F C Calcinadores Rotary Kilns
F E Forno elétrico Electric furnace
F L Filtro Filter / Bin Vent
F P Forno Panela Ladle Furnace
F S Fornos secadores rotativos Rotary Dryers
F Z Manta de revestimento de lagoa Pond liner
G A Garra hidráulica Clamshell
G F Grelha fixa / Basculante Fixed grizzly / Tipping grizzly
G L Guindaste de lança Jib crane
G V Grelha vibratória Vibrating grizzly
H C Hidrociclone Hydrocyclone
H M Talha móvel Monorail hoist
J E Junta de expansão Expansion joint
J I Jigs Jigs
K S Scanner Térmico Kiln Scanner
L A Equipamento de Laboratório Laboratory equipment
L S Suporte de Panela Laddle Support
M B Maquina de briquetagem Briquetting Machine
M G Moega Hopper
M N Manifold Manifold
M O Moinhos Mills
M S Mineral sizer Mineral sizer
M X Misturador \ Umidificador Mixer/Moisturiser
M Z Miscelâneas Miscelaneous
O C Isolation plate (blind)
O L Lança de oxigênio Oxygen lance
P A Pacote Package
P E Peneiras vibratórias Vibrating screens
P F Perfuratriz Drilling machine
P M Panela de metal Metal laddle
P N Peneiras de rolos Roller screens
P R Ponte rolante Over head crane
P S Panela de escoria Slag ladle
P T Precipitador eletrostático Electrostatic precipitator
Q U Queimadores Burners
R A Raspador Scraper
R E Retomadora Reclaimer
R H Rompedor hidráulico Rock breaker
S B Lavador de Gases Scrubber
S C Secadores Dryers
S D Sistema de dosagem Dosing system
S F Separador de fagulhas Spark separator
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
S I Silenciador Silencer
S L Silos, silos pulmão Silos, bins
S M Sistema agitação com gás Gas stirring system
T A Transportador de arraste Drag conveyor
T B Chute tipo tromba Spout,Tunck, Extendible chute
T C Transportador de correia Belt Conveyor
T E Trocador de calor Heat exchanger
T H Transportadores helicoidais Screw conveyors
T L Talha elétrica Electrical hoist
T M Tambor misturador / desaguador Dewatering / mixing drum
T N Talha manual Chain Block / Manual hoist
T O Trommels Trommels
T P Transportador pneumático Pneumatic screw pump
T Q Tanques Tanks
T R Torres de resfriamento Cooling towers
T S Calha transportadora Slide conveyor
T T Máquina de basculamento Tilting machine
T X Extrator de sucata Tramp iron extractor
T Z Maquina fechamento furo escória Slag stopper machine
U H Unidade hidráulica Hydraulic power unit
V A Tanques pressurizados Pressure vessels
V B Válvula de barras Bar valves
V C Conjunto de Valvulas Valve train
V D Válvula radial Radial valve
V E Ventiladores, sopradores Fans, blowers
V F Válvula Faca/Guilhotina Knife Valve /Guillotine Valve/ Slide valve
V G Válvula mangote Pinch valve
V M Válvula Borboleta Butterfly Valve
V P Válvula Pendular Pendullum Valve
V R Válvula rotativa Rotary valve
V T Vaso de transferência Transfer vessel
V X Vent de Segurança contra explosão Explosion Vent
V Y Cilindro pneumático Pneumatic cylinder
W H Guincho Winch
X V Válvula de Bloqueio Block Valve
X X Caixa / invólucro Housing / Enclosure
Z H Cilindro hidráulico Hydraulic cylinder
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
3.9 General
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
DATE
PBA-P-000-000-PD-210
6 29.Mai.2008
CODE D E S C R IC AO D E S C R IP T IO N