Académique Documents
Professionnel Documents
Culture Documents
PROJECT ATTRIBUTES
Project Brief:
Spike Technologies is a software company situated on Whitefield - Bangalore. M/s Equis India is the project management consultants and M/s KNK Swamy and Co. is the contractors for the building project.
38
Total quantity of work = Duration in days x Unit Manpower Output -------- (3.1)
39
Total quantity of work Manpower required per day = Duration in days x Unit Manpower Output ----- (3.2)
Based on the total quantities (obtained from BOQ/drawings), total duration (as per schedule) and output constants, manpower required have been computed for various activities as shown in table 3.2. The following example illustrates the computations carried out for these activities. Similarly, the quantities have been computed and presented in table 3.2. Example computations: The example has been carried out for footing. 1167 12 x1.5 60 10 x0.2 100 10 x0.2 192 10 x6 18.36 10 x 0.2
Unskilled =
Unskilled =
Unskilled
Carpenters =
Barbenders =
40
Table 3.2. Quantities for various activities Sl.No. 1 Activity Footing Excavation(5) PCC(6) Carpenters(8) Barbenders(7) Concrete(9) Columns up to Plinth Level Carpenters(11) Barbenders(10) Concrete(12) Plinth Beams Size Stone Masonry(13) Carpenters(15) Barbenders(14) Concrete(16) Columns up to GF slab Carpenters(18) Barbenders(17) Concrete(19) PCC below floor(21) Ground Floor Slab Carpenters(22) Barbenders(23) 7 Columns up to FF Slab Carpenters(28) Barbenders(27) Concrete29) First Floor Slab Carpenters(30) Barbenders(31) Columns up to SF Slab Carpenters(36) Barbenders(35) Concrete(37) 10 Second Floor Slab 41 1655.64 51.2 M2 MT 10 10 6.0 M2 0.2 MT 28 26 75.71 579 20.92 56.61 M3 M2 MT M3 8 7 7 7 0.9 M3 6.0 M2 0.2 MT 0.2 M3 11 14 16 40 1167 60 192 18.36 100 M3 M3 M2 MT M3 12 10 10 10 10 1.5 M3 0.2 M3 6.0 M2 0.2 MT 0.2 M3 65 30 4 10 50 Total Quantity Unit Duration in Manpower Days Output Manpower Required
210.96 9.86 24
M2 MT M3
9 9 9
4 6 14
5 6
M2 MT M3 M3
10 7 10 12
6 10 17 68
M2 MT M3 M2 MT
7 7 7 10 10
8 10 24 34 28
289.69 11.8 34
M2 MT M3
6 6 6
8 10 28
Carpenters(38) Barbenders(39) 11 OHT Carpenters(43) Barbenders(43) Concrete(43) 12 Lift Machine Room Carpenters(44) Barbenders(44) Concrete(44) 13 Masonry Work Ground Floor(48) First Floor(49) Second Floor(50) Terrace(45) 14 15 Terrace Water Proofing(46) Wall Plastering (Internal) Ground Floor(52) First Floor(53) Second Floor(54) External Wall Plastering(56) Paint(57) UG sump Carpenters(58) Barbenders(58) Concrete(58) Toilet water proofing 19 coat(62)
1643.89 51.8
M2 MT
10 10
6.0 M2 0.2 MT
28 26
M2 MT M3 M2 MT M3
15 15 15 15 15 15
2 2 4 2 2 5
M2 M2 M2 M2 M2
15 15 10 5 12
10 12 14 6 16
M2 M2 M2 M2 M2
16 16 10 17 15
14 16 20 22 52
16 17 18
M2 MT M3 M2
25 25 25 10
2 2 2 2
Note: The numbers shown in bracket in above table refers the activity number presented in the schedule
42
3.4 Cost:
The total cost of the project has been divided into two types namely, direct cost and indirect cost. The direct cost and indirect cost of the project are shown in table 3.3.
43
From the fig.3.3, it has been observed that there is a gradual increase in the indirect cost mainly due to providing more number of facilities and maintenance/house keeping of site. When combined direct cost and indirect cost cumulatively, an S curve has been arrived with steep increase up to the 3rd month as shown in fig. 3.4.
Table 3.3. Direct Cost for various activities as per the site documents for the duration of the project. Sl. No. 1 Item Labour Skilled Semi Skilled Un Skilled 2 Equipments JCB & Tractors 3 Materials Cement Steel RMC Sand Aggregates Centering & Shuttering Blocks Transportation Miscellaneous (ATT, Shalitex board, PVC pipes, Diesel, Petrol, SSM, Bricks, Doors etc.) Total 286200 799807 644725 105390 169884 800000 150000 190800 4182126 1126312 122025 163416 1100000 90000 175000 159000 1005895 1122112 142500 64900 1500000 435600 150000 493800 165990 74008 504000 250000 150000 75000 109025 107220 44700 215075 123600 110000 194250 51120 87200 200200 63840 16900 February March April May
84000
104000
63000
127000
3450951
7702354
4975577
1970738
Table 3.4. Indirect Cost for various activities as per the site documents for 44
Sl.No. Item 1 2 3 4 5 6 7 8 Supervision Temporary Infrastructure Office expenditure Conveyance Water Accommodation Medical facilities Miscellaneous (Generator rent etc.) Total
February 107000 65000 45000 75000 80000 25000 2500 54000 453500
Table 3.5 Direct Cost of project interms of percentage for corresponding month. Sl.No. 1 2 3 Item Labour Equipments Materials February 7.56% 4.35% 88.09% March 5.83% 94.17% April 6.68% 93.32% May 14.25% 3.81% 81.94%
45
The direct cost and indirect cost fig.s are shown below.
6000 000 5000 000 4000 000 3000 000 2000 000 1000 000 0 0 1 2
T e (M n s im o th )
1000000 800000
Cost (Rs)
46
The cumulative cost is shown in following table 3.6. Table 3.6 cumulative cost of the project
Time(Months) Cumulative Cost(Rs.) 0 0 1 3809051 2 11284305 3 18139882 4 20713120
47
Further, the total cost on monthly basis and also cumulative basis is shown in table 3.7 and the same has been plotted in fig. 3.5 to compare the effect of monthly costs on cumulative cost. The values of cost/month and cumulative is shown in following table.3.7. Table 3.7 cost/month and cumulative cost.
Month Cost/Month Cumulative Cost Feb.'04 3809051 3809051 Mar.'04 7475254 11284305 Apr.'04 6855577 18139882 May.'04 2573238 20713120
Cost(Rs)
20713120 18139882
M ar .'1 1
Duration(Months)
48
M ay .'1 1
Ap r.' 1
.'1