Beity Plant Extension Project No.

: 1607-P1-b

ScenarioofsitesMechanicalWorks
Firefightingnetworkinstallations

Storagearea(B03)
1 Thecontractorwillaskedtheownerbeforestartinghisworkswith4daysto evacuatetheworkingareabetweentheracksandtheupperlevelofitin ordertobeabletowork 2 Thestorageareawillbedividedintothreepartsinthestoragearea. 3 Thecontractorwillstartinstallationofscaffoldingineachareafromthe groundtoupasshowninthe(fig1.)otherwiseovertheracksifaccepted.

Redarrows:Scaffolding Blackarrows:Labors&Materials

(Fig1)
GAMAForTrading&Contracting 1

Beity Plant Extension Project No.: 1607-P1-b 4 Theaccesspassagetotheworkingareaisdescribedbelowasshownin (Fig2.)Showingtheentrance&theexitofthematerials&labors.

(Fig2) 5 Thelocutionofpowersupplypanelforeclectictoolsisshowing(fig3.) WhereonlythedrillingM/C&thecuttingM/Cwellbeused

(Fig3) 6Thenumberoflaborswhichwillworkatetchareaitwillbespecifiedindaily report&willnotbelessthan45workers/eacharea


GAMAForTrading&Contracting 2

Beity Plant Extension Project No.: 1607-P1-b 7 Paintingofthepipeswiththetwolayersofprimercoatwillbeoutsidethe site&thefinishlayerwillbeinsite. 8Thefabricationofpipesitswillbeinourworkshopyardoutsidetheworking areaasshowing(Fig4)

(Fig4) 9installationoffirefightingpipessupports(usingEquipmentDrillonlyand thereisnohotworks) 10Usingfixedscaffoldingabovetheracksortendenciesfloorsandmoving scaffoldingatflatfloorandcorridorstoInstallationofsupportsandpipes 11Transferpipeswithsmalldiameters(Lessthan2.5")byworkersmanually fromtheworkshoptotheplaceofinstallationandlargediameters(largerthan 2.5")transportitbyhandvehicletotheplacesofinstallation. 12Liftingpipeswithlargediametersfromthegroundtotheinstallationplaces byBlancoandliftingpipeswithsmalldiameterstotheplaceofinstallationby Handrollerspull 13Afterfinishingoftheinstallationworkandinstallationofpipesthenwater pressuretestforpipeswillbedone 14Afterthepressuretests,installationofsprinklers.

GAMAForTrading&Contracting 3

Beity Plant Extension Project No.: 1607-P1-b

AirConditioninginstallations:
1 Stepsforinstallationoffans(rooftopfans)
1 Identifyingtheplacesofthefansaccordingtotheapproveddrawing 2Thecontractorwillstartinstallationofscaffoldingineachareafromthe Groundtoupasshowninthe(fig1.)otherwiseovertheracksifaccepted

(Fig1) 3Thelocationofpowersupplypanelforeclectictoolsisshowing(fig2) WhereonlythedrillingM/C&thecuttingM/Cwellbeused

GAMAForTrading&Contracting

Beity Plant Extension Project No.: 1607-P1-b

(Fig2) 4Theaccesspassagetotheworkingareaisdescribedbelowasshownin (Fig3)showingtheentrance&theexitofthematerials

(Fig3) 5Makethenecessarystrengtheningintheinternalceilingforthesteel structureaccordingtoapproveddrawings.


GAMAForTrading&Contracting 5

Beity Plant Extension Project No.: 1607-P1-b

6Installtheframewherethefanswillbeinstalledon 7Makeopeningsinthecorditesheetmetalwhichwillbefrominsidethe building 8Installation&fixingthecurbfromabovethesteelstructure 9Liftingthefansbycranes&fixingitabovetothecurb 10Supplying&installationelectriccablesfromthefanstotheelectrical board


6

GAMAForTrading&Contracting

Beity Plant Extension Project No.: 1607-P1-b

Firefightingnetworkinstallations

Processingarea(B03groundfloor)
1 Thecontractorwillaskedtheownerbeforestartinghisworkswith4daysto evacuatetheworkingareabetweentheracksandtheupperlevelofitinorder tobeabletowork 2 Thecontractorwillstartinstallationofscaffoldingineachareafromthe groundtoupasshowninthe(fig1.)

Fig1
GAMAForTrading&Contracting 7

Beity Plant Extension Project No.: 1607-P1-b 3 Theaccesspassagetotheworkingareaisdescribedbelowasshownin (Fig2.)Showingtheentrance&theexitofthematerials

(Fig2) 4 Thelocationofpowersupplypanelforeclectictools(fig3.)

Fig3
GAMAForTrading&Contracting 8

Beity Plant Extension Project No.: 1607-P1-b 5Thenumberoflaborswhichwillworkatetchareaitwillbespecifiedindaily report&willnotbelessthan45workers/eacharea 6Thefabricationofpipesitswillbeinoutsideattheworkshoparea(fig4.)

(Fig4) 7Installationoffirefightingpipessupports(usingEquipmentDrillonlyandthere isnohotworks) 8UsingfixedscaffoldinginFlooringleaningandmovingscaffoldingatflatfloor andcorridorstoInstallationofsupportsandpipes 9InstallandfixcantileversupportsinColumnsofsteelstructureformainloops andthreadedrodsforbranchespipesbyfixeditinpearlinessthatinupperfloor passagethroughthesandwichpanel 10Transferpipeswithsmalldiameters(Lessthan2.5")byworkersmanuallyfrom theworkshoptotheplaceofinstallationandlargediameters(largerthan2.5") transportitbyhandvehicletotheplacesofinstallation. 11Liftingpipeswithlargediametersfromthegroundtotheinstallationplacesby BlancoandliftingpipeswithsmalldiameterstotheplaceofinstallationbyHand rollerspull 12Afterfinishingoftheinstallationworkandinstallationofpipesthenwater pressuretestforpipeswillbedone 13Afterthepressuretests,installationofsprinklers.
GAMAForTrading&Contracting 9

Beity Plant Extension Project No.: 1607-P1-b

Firefightingnetworkinstallations

Juicepreparationarea(B02)
1 Thecontractorwillaskedtheownerbeforestartinghisworkswith48hours toevacuatetheworkingareabetweentheracksandtheupperlevelofitin ordertobeabletowork 2 Thecontractorwillstartinstallationofscaffoldinginetchareafromthe groundtoupasshowninthe(fig1.)Someareaswillbefixedscaffolding(above thetanksandM/C)andotherswillbemovingscaffolding

(fig1) 3 Theaccesspassagetotheworkingareaisdescribedbelowasshownin (Fig2.)Showingtheentrance&theexitofthematerials

GAMAForTrading&Contracting

10

Beity Plant Extension Project No.: 1607-P1-b

(Fig2) 4 Thereisnopathforpassageofcablestoworkinthisareaandtherefore sourceofelectricitywillbeusedfrominsidethebuilding,knowingthatthe toolsusedonlythedrillingM/C&thecuttingM/Cwillbeused 5 Thenumbersoflaborswhichwillworkatetchareaitwillbespecifiedindaily Report&willnotbelessthan45workers/eacharea 6 Paintingofthepipeswiththetwolayersofprimercoatwillbeoutsidethe Site&thefinishlayerwillbeonside. 7 Thefabricationofpipesitswillbeinourwork shopyardoutsidetheworkingareaasshowing(Fig

(Fig3) 8 installationoffirefightingpipessupports(usingEquipmentDrillonlyand thereisnohotworks) 9 Transferpipeswithsmalldiameters(Lessthan2.5")byworkersmanually fromtheworkshoptotheplaceofinstallationandlargediameters(larger than2.5")transportitbyhandvehicletotheplacesofinstallation. 10 Liftingpipeswithlargediametersfromthegroundtotheinstallationplaces byBlancoAndliftingpipeswithsmalldiameterstotheplaceofinstallationby Handrollerspull 11 Afterfinishingoftheinstallationworkandinstallationofpipesthenwater pressuretestforpipeswillbedone 12 Afterthepressuretests,installationofsprinklers.
GAMAForTrading&Contracting 11

Beity Plant Extension Project No.: 1607-P1-b

AirConditioninginstallations:
Airhandlingunit'sinstallation&ductconnection
1Identifyingthelocutionoftheunitsaccordingtotheapproveddrawing 2Theaccesspassagetotheworkingareaisdescribedbelowasshownin (Fig1.)Showingtheentrance&theexitofthematerials

(Fig1) 3Fabricatethebasesthattheunitswillbeinstalledonit 4Liftingtheunitfromoutsidethebuildingbycranes 5Makeopeningsinthesandwichpaneltopassagetheairduct Fromtheouttoinside 6Assemblytheductinoutsideareaintheworkshopandtransportitbyhand Vehicletothefeedpoints 7Connectionofpowercablefromtheunittothepowerdistributionpanel


GAMAForTrading&Contracting 12

Beity Plant Extension Project No.: 1607-P1-b

Proposed Scenario for work over the walk able ceiling areas
1Thefabricationofpipeswillbeinourworkshopyardoutsidetheworking Areaasshowing(Fig1)

(Fig1)
2Installationofsupportsforpipeswillbefixedbythreadedrodfromthebeamsandpurlins asshowingin(fig.2)

(Fig2)

GAMAForTrading&Contracting

13

Beity Plant Extension Project No.: 1607-P1-b


3Transferpipesfromtheworkshoptothearea(1)acrossthepathshowninattached drawing.

4 Liftingpipesmanuallybylaborsviathestairsandputitinthearea(1)

GAMAForTrading&Contracting 14

Beity Plant Extension Project No.: 1607-P1-b


5Transferepipesintothewalkableareabyworkersandputitinhangarsshowninthe abovefigure.

6Totalnumbersofworkersinthewalkableceilingareawillbe7workersatthesametime.

GAMAForTrading&Contracting

15

Beity Plant Extension Project No.: 1607-P1-b

Alternative Scenario for work over the walk able celling areas
After calculation of weights (workers & pipes) over the walk able ceiling it is found that we need another method of installation which is:
1Thefabricationofpipeswillbeinourworkshopyardoutsidetheworking Areaasshowing(Fig1)

(Fig1) 2Fabricationcantileversupportsshowingin(fig2)andfixeditinwallthatis Inwalkablesuspendedcelling


GAMAForTrading&Contracting 16

Beity Plant Extension Project No.: 1607-P1-b


3Transferpipesfromtheworkshoptothearea(1)&area(2)acrossthepathattachedin thefollowingfigure.

4Makeopeninginthewallbetweenthewalkablesuspendedceilingandthebesideroom Area(1)asshowninthefollowingfigure.

5Afterinstallthesupportsonthewallofthewalkablesuspendedceilingandworkwall openinginthesandwichpanelwillbepushthepipesthroughthesupportsasshowing. GAMAForTrading&Contracting 17

Beity Plant Extension Project No.: 1607-P1-b

6Totalnumbersofworkersinthewalkableceilingareawillbe4workersatthesame time.

GAMAForTrading&Contracting

18